PROYECTO: INSTALACION DEL SISTEMA DE RIEGO POR ASPERSION EN EL SECTOR CONCHARUMIYOC - ANCATIYANA, LOCALIDAD DE PUCA PUCA, DISTRITO DE CURAHUASI,
PROVINCIA DE ABANCAY - APURIMAC

COSTO MES 1 MES 2 MES 3


SUB SISTEMAS
ITEM DESCRIPCION TOTAL
CONCHARUMIYOC FISICO FISICO FISICO
ANCATIYANA S/.

1.00 OBRAS PRELIMINARES 1,591.50 1,591.50 0% 0.00 0% 0.00 0% 0.00


1.01 CARTEL DE OBRA EN BANNER 451.00 451.00 100% 451.00 0% 0.00 0% 0.00
1.02 CONSTRUCCION DE CAMPAMENTO 1,140.50 1,140.50 100% 1,140.50 0% 0.00 0% 0.00
02 CAMARA DE CARGA (02 UNID) 13,368.05 13,368.05 0% 0.00 0% 0.00 0% 0.00
02.01 TRABAJOS PRELIMINARES 8.20 8.20 0% 0.00 0% 0.00 0% 0.00
02.01.01 TRAZO Y REPLANTEO 8.20 8.20 100% 8.20 0% 0.00 0% 0.00
02.02 MOVIMIENTO DE TIERRAS 346.64 346.64 0% 0.00 0% 0.00
02.02.01 EXCAVACION MANUAL EN TERRENO SUELTO 159.82 159.82 100% 159.82 0% 0.00 0% 0.00
02.02.02 ELIMINACION DE MATERIAL EXCEDENTE 186.82 186.82 100% 186.82 0% 0.00 0% 0.00
02.03 OBRAS DE CONCRETO 13,013.21 13,013.21 0% 0.00 0% 0.00 0% 0.00
02.03.01 SOLADO DE CONCRETO 2" MEZCLA 1:12 C-H 193.25 193.25 0% 0.00 100% 193.25 0% 0.00
02.03.02 CONCRETO ARMADO F'C=175 KG/CM2. 3,857.10 3,857.10 0% 0.00 100% 3,857.10 0% 0.00
02.03.03 ENCOFRADO Y DESENCOFRADO NORMAL 1,712.39 1,712.39 0% 0.00 100% 1,712.39 0% 0.00
02.03.04 ACERO GRADO 60 1,867.02 1,867.02 0% 0.00 100% 1,867.02 0% 0.00
02.03.05 TARRAJEO CON CEMENTO-ARENA 996.31 996.31 0% 0.00 100% 996.31 0% 0.00
02.03.06 TARRAJEO CON IMPERMEABILIZANTES 888.08 888.08 0% 0.00 100% 888.08 0% 0.00
02.03.07 SUMINISTRO Y COLOC. DE ACCESORIOS Y VALVULAS 4" - CAMARA 1,892.10 1,892.10 0% 0.00 100% 1,892.10 0% 0.00
02.03.08 SUMINISTRO Y ACCESORIOS DE FILTRO ANILLO 1,117.43 1,117.43 0% 0.00 100% 1,117.43 0% 0.00
02.03.09 SUMINISTRO Y COLOC. DE TAPA METALICO 0.85 x 0.75 489.53 489.53 0% 0.00 50% 244.77 50% 244.77
03 CAMARA ROMPE PRESION (02 UNID) 9,384.60 9,384.60 0% 0.00 0% 0.00 0% 0.00
03.01 TRABAJOS PRELIMINARES 5.70 5.70 0% 0.00 0% 0.00 0% 0.00
03.01.01 TRAZO Y REPLANTEO 5.70 5.70 100% 5.70 0% 0.00 0% 0.00
03.02 MOVIMIENTO DE TIERRAS 178.54 178.54 0% 0.00 0% 0.00 0% 0.00
03.02.01 EXCAVACION MANUAL EN TERRENO SUELTO 82.33 82.33 100% 82.33 0% 0.00 0% 0.00
03.02.02 ELIMINACION DE MATERIAL EXCEDENTE 96.21 96.21 100% 96.21 0% 0.00 0% 0.00
03.03 OBRAS DE CONCRETO 9,200.36 9,200.36 0% 0.00 0% 0.00 0% 0.00
03.03.01 SOLADO DE CONCRETO SIMPLE 173.45 173.45 0% 0.00 100% 173.45 0% 0.00
03.03.02 CONCRETO ARMADO F'C=175 KG/CM2. 2,375.97 2,375.97 0% 0.00 100% 2,375.97 0% 0.00
03.03.03 ENCOFRADO Y DESENCOFRADO NORMAL 1,140.36 1,140.36 0% 0.00 100% 1,140.36 0% 0.00
03.03.04 ACERO GRADO 60 1,355.81 1,355.81 0% 0.00 100% 1,355.81 0% 0.00
03.03.05 TARRAJEO CON IMPERMEABILIZANTES 585.85 585.85 0% 0.00 100% 585.85 0% 0.00
03.03.06 TARRAJEO CON CEMENTO-ARENA 753.16 753.16 0% 0.00 100% 753.16 0% 0.00
03.03.07 ACCESORIOS PARA CRP 4'' 2,021.84 2,021.84 0% 0.00 50% 1,010.92 50% 1,010.92
03.03.08 SUMINISTRO Y COLOC. DE TAPA METALICO 0.85 x 0.75 793.92 793.92 0% 0.00 50% 396.96 50% 396.96
04 LINEA DE CONDUCCION (2363.44 ML) 58,268.39 58,268.39 0% 0.00 0% 0.00 0% 0.00
04.01 TRABAJOS PRELIMINARES 2,529.45 2,529.45 0% 0.00 0% 0.00 0% 0.00
04.01.01 TRAZO Y REPLANTEO EN LINEA DE CONDUCCION 2,529.45 2,529.45 100% 2,529.45 0% 0.00 0% 0.00
04.02 MOVIMIENTO DE TIERRAS 14,842.27 14,842.27 0% 0.00 0% 0.00 0% 0.00
04.02.01 EXCAVACION MANUAL EN TERRENO SUELTO 10,179.07 10,179.07 0% 0.00 50% 5,089.54 50% 5,089.54
04.02.02 EXCAVACION DE ZANJA EN ROCA FIJA 4,663.20 4,663.20 0% 0.00 50% 2,331.60 50% 2,331.60
04.03 TENDIDO E INSTALACION DE TUBERIA 40,896.67 40,896.67 0% 0.00 0% 0.00 0% 0.00
04.03.01 REFINE NIVELACION Y COFINAMIENTO DE ZANJA 2,167.92 2,167.92 0% 0.00 50% 1,083.96 50% 1,083.96
04.03.02 COLOCACION Y COMPACTADO DE CAMA DE APOYO E = 0.10 M 13,369.95 13,369.95 0% 0.00 50% 6,684.98 50% 6,684.98
04.03.03 RELLENO DE ZANJAS CON MATERIAL PROPIO SELEC. DE LA ZONA 5,329.91 5,329.91 0% 0.00 50% 2,664.96 50% 2,664.96
04.03.07 TUBERIA PVC SAP 2" C-7.5 4,159.05 4,159.05 0% 0.00 0% 0.00 100% 4,159.05
04.03.08 TUBERIA PVC SAP 1 1/2" C-7.5 8,715.00 8,715.00 0% 0.00 0% 0.00 100% 8,715.00
04.03.09 TUBERIA PVC SAP 1" C-7.5 4,409.15 4,409.15 0% 0.00 0% 0.00 100% 4,409.15
04.03.10 ACCESORIOS COMPLEMENTARIOS A LA RED - Pucapuca 1,782.09 1,782.09 0% 0.00 0% 0.00 100% 1,782.09
04.03.11 PRUEBA HIDRAULICA 963.60 963.60 0% 0.00 0% 0.00 100% 963.60
05 LINEA DE DISTRIBUCION (1756.96 ML) 26,506.47 26,506.47 0% 0.00 0% 0.00 0% 0.00
05.01 TRABAJOS PRELIMINARES 1,583.16 1,583.16 0% 0.00 0% 0.00 0% 0.00
05.01.01 TRAZO Y REPLANTEO EN LINEA DE DISTRIBUCION 1,583.16 1,583.16 100% 1,583.16 0% 0.00 0% 0.00
05.02 MOVIMIENTO DE TIERRAS 17,414.71 17,414.71 0% 0.00 0% 0.00 0% 0.00
05.02.01 EXCAVACION MANUAL EN TERRENO SUELTO P/ ZANJA 6,088.36 6,088.36 0% 0.00 0% 0.00 0% 0.00
05.02.02 REFINE NIVELACION Y COFINAMIENTO DE ZANJA 1,356.99 1,356.99 0% 0.00 50% 3,044.18 50% 3,044.18
05.02.03 COLOCACION Y COMPACTADO DE CAMA DE APOYO E = 0.10 M 8,368.11 8,368.11 0% 0.00 50% 678.50 50% 678.50
05.02.04 RELLENO DE ZANJAS CON MATERIAL PROPIO SELEC. DE LA ZONA 1,601.25 1,601.25 0% 0.00 0% 0.00 100% 8,368.11
05.03 TUBERIA 7,508.60 7,508.60 0% 0.00 0% 0.00 0% 0.00
05.03.01 TUBERIA PVC SAP 3/4" C-10 6,747.26 6,747.26 0% 0.00 0% 0.00 100% 6,747.26
05.03.02 ACCESORIOS COMPLEMENTARIOS A LA RED DE DISTRIBUCION 158.23 158.23 0% 0.00 0% 0.00 100% 158.23
05.03.03 PRUEBA HIDRAULICA 603.11 603.11 0% 0.00 0% 0.00 100% 603.11
06 VALVULAS DE PURGA Y CONTROL 4,262.25 4,262.25 0% 0.00 0% 0.00 0% 0.00
06.01 TRABAJOS PRELIMINARES 1.00 1.00 0% 0.00 0% 0.00 0% 0.00
06.01.01 TRAZO Y REPLANTEO 1.00 1.00 100% 1.00 0% 0.00 0% 0.00
06.02 MOVIMIENTO DE TIERRAS 12.07 12.07 0% 0.00 0% 0.00 0% 0.00
06.02.01 EXCAVACION PARA EXTRUCTURAS 7.40 7.40 0% 0.00 0% 0.00 100% 7.40
06.02.02 ELIMINACION DE MATERIAL EXCEDENTE 4.67 4.67 0% 0.00 0% 0.00 100% 4.67
06.03 VALVULAS DE PURGA Y CONTROL 4,249.18 4,249.18 0% 0.00 0% 0.00 0% 0.00
06.03.01 CAJA DE VALVULA DE 0.50 x 0.50 CON TAPA METALICA 1,247.88 1,247.88 0% 0.00 0% 0.00 100% 1,247.88
06.03.02 VALVULA DE PURGA ø 1 1/2" 1,860.64 1,860.64 0% 0.00 0% 0.00 100% 1,860.64
06.03.03 VALVULA DE CONTROL ø 4" 1,140.66 1,140.66 0% 0.00 0% 0.00 100% 1,140.66
07 HIDRANTES 21,345.46 21,345.46 0% 0.00 0% 0.00 0% 0.00
07.01 HIDRANTES (52 UNID) 10,567.71 10,567.71 0% 0.00 0% 0.00 0% 0.00
07.01.01 CAJA DE HIDRANTE DE 0.40 x 0.40 CON TAPA METALICA 6,591.48 6,591.48 0% 0.00 40% 2,636.59 60% 3,954.89
07.01.02 HIDRANTES DE ø 3/4" + Accesorios 3,263.88 3,263.88 0% 0.00 40% 1,305.55 60% 1,958.33
07.01.03 ACCESORIOS COMPLEMENTARIOS A LA RED - Pucapuca 712.35 712.35 0% 0.00 40% 284.94 60% 427.41
07.02 EQUIPO DE RIEGO 10,777.75 10,777.75 0% 0.00 0% 0.00 0% 0.00
07.02.01 EQUIPO DE RIEGO FAMILIAR - Aspersor Sect. Q=1.18m3/h 2,075.10 2,075.10 0% 0.00 0% 0.00 100% 2,075.10
07.02.02 EQUIPO DE RIEGO FAMILIAR - Aspersor Sect. Q=0.50m3/h 3,818.05 3,818.05 0% 0.00 0% 0.00 100% 3,818.05
07.02.03 EQUIPO DE RIEGO FAMILIAR - Aspersor Sect. Q=0.24m3/h 4,884.60 4,884.60 0% 0.00 0% 0.00 100% 4,884.60
08 TRANSPORTE DE MATERIALES 6,000.00 6,000.00 0% 0.00 0% 0.00 0% 0.00
08.01 TRANSPORTE RURAL 1,000.00 1,000.00 40% 400.00 30% 300.00 30% 300.00
08.02 TRANSPORTE DE MATERIALES - ABANCAY A OBRA 5,000.00 5,000.00 40% 2,000.00 30% 1,500.00 30% 1,500.00
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL COSTO DIRECTO 140,726.72 140,726.72 0.00 8,644.19 0.00 48,165.71 0.00 83,916.82
CAPACITACION Y MITIGACION 9,458.80 9,458.80 0.00 3,152.93 0.00 3,152.93 0.00 3,152.93
GASTOS GENERALES (17.40%) 33,791.74 33,791.74 0.00 11,263.91 0.00 11,263.91 0.00 11,263.91
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
UTILIDAD (10%) 15,018.55 15,018.55 0.00 5,006.18 0.00 5,006.18 0.00 5,006.18
TOTAL PRESUPUESTO DE OBRA 234,815.06 234,815.06 0.00 40,006.97 0.00 79,528.49 0.00 115,279.60
CRONOGRAMA DE EJECUCION FISICO FINANCIERO

PROYECTO: INSTALACION DEL SISTEMA DE RIEGO POR ASPERSION EN EL SECTOR CONCHARUMIYOC - ANCATIYANA, LOCALIDAD DE PUCA PUCA, DISTRITO DE CURAHUASI,
PROVINCIA DE ABANCAY - APURIMAC

COSTO Dec-11 Jan-12 Feb-12


SUB SISTEMAS
ITEM TOTAL FINANC. FINANC. FINANC.
DESCRIPCION
CONCHARUMIYOC FISICO FISICO FISICO
S/. S/. S/. S/.
ANCATIYANA

01 OBRAS PRELIMINARES 1591.5 1,591.50


01.01 CARTEL DE OBRA EN BANNER 451 451.00 100% 451.00
01.02 CONSTRUCCION DE CAMPAMENTO 1140.5 1,140.50 100% 1,140.50
02 CAMARA DE CARGA (02 UNID) 13368.05 13,368.05
02.01 TRABAJOS PRELIMINARES 8.2 8.20
02.01.01 TRAZO Y REPLANTEO 8.2 8.20 100% 8.20
02.02 MOVIMIENTO DE TIERRAS 346.64 346.64
02.02.01 EXCAVACION MANUAL EN TERRENO SUELTO 159.82 159.82 100% 159.82
02.02.02 ELIMINACION DE MATERIAL EXCEDENTE 186.82 186.82 100% 186.82
02.03 OBRAS DE CONCRETO 13013.21 13,013.21
02.03.01 SOLADO DE CONCRETO 2" MEZCLA 1:12 C-H 193.25 193.25 100% 193.25
02.03.02 CONCRETO ARMADO F'C=175 KG/CM2. 3857.1 3,857.10 100% 3,857.10
02.03.03 ENCOFRADO Y DESENCOFRADO NORMAL 1712.39 1,712.39 100% 1,712.39
02.03.04 ACERO GRADO 60 1867.02 1,867.02 100% 1,867.02
02.03.05 TARRAJEO CON CEMENTO-ARENA 996.31 996.31 100% 996.31
02.03.06 TARRAJEO CON IMPERMEABILIZANTES 888.08 888.08 100% 888.08
02.03.07 SUMINISTRO Y COLOC. DE ACCESORIOS Y VALVULAS 4" - CAMARA 1892.1 1,892.10 100% 1,892.10
02.03.08 SUMINISTRO Y ACCESORIOS DE FILTRO ANILLO 1117.43 1,117.43 100% 1,117.43
02.03.09 SUMINISTRO Y COLOC. DE TAPA METALICO 0.85 x 0.75 489.53 489.53 50% 244.77 50% 244.77
03 CAMARA ROMPE PRESION (02 UNID) 9384.6 9,384.60
03.01 TRABAJOS PRELIMINARES 5.7 5.70
03.01.01 TRAZO Y REPLANTEO 5.7 5.70 100% 5.70
03.02 MOVIMIENTO DE TIERRAS 178.54 178.54
03.02.01 EXCAVACION MANUAL EN TERRENO SUELTO 82.33 82.33 100% 82.33
03.02.02 ELIMINACION DE MATERIAL EXCEDENTE 96.21 96.21 100% 96.21
03.03 OBRAS DE CONCRETO 9200.36 9,200.36
03.03.01 SOLADO DE CONCRETO SIMPLE 173.45 173.45 100% 173.45
03.03.02 CONCRETO ARMADO F'C=175 KG/CM2. 2375.97 2,375.97 100% 2,375.97
03.03.03 ENCOFRADO Y DESENCOFRADO NORMAL 1140.36 1,140.36 100% 1,140.36
03.03.04 ACERO GRADO 60 1355.81 1,355.81 100% 1,355.81
03.03.05 TARRAJEO CON IMPERMEABILIZANTES 585.85 585.85 100% 585.85
03.03.06 TARRAJEO CON CEMENTO-ARENA 753.16 753.16 100% 753.16
03.03.07 ACCESORIOS PARA CRP 4'' 2021.84 2,021.84 50% 1,010.92 50% 1,010.92
03.03.08 SUMINISTRO Y COLOC. DE TAPA METALICO 0.85 x 0.75 793.92 793.92 50% 396.96 50% 396.96
04 LINEA DE CONDUCCION (2363.44 ML) 58268.39 58,268.39
04.01 TRABAJOS PRELIMINARES 2529.45 2,529.45
04.01.01 TRAZO Y REPLANTEO EN LINEA DE CONDUCCION 2529.45 2,529.45 100% 2,529.45
04.02 MOVIMIENTO DE TIERRAS 14842.27 14,842.27
04.02.01 EXCAVACION MANUAL EN TERRENO SUELTO 10179.07 10,179.07 50% 5,089.54 50% 5,089.54
04.02.02 EXCAVACION DE ZANJA EN ROCA FIJA 4663.2 4,663.20 50% 2,331.60 50% 2,331.60
04.03 TENDIDO E INSTALACION DE TUBERIA 40896.67 40,896.67
04.03.01 REFINE NIVELACION Y COFINAMIENTO DE ZANJA 2167.92 2,167.92 50% 1,083.96 50% 1,083.96
04.03.02 COLOCACION Y COMPACTADO DE CAMA DE APOYO E = 0.10 M 13369.95 13,369.95 50% 6,684.98 50% 6,684.98
04.03.03 RELLENO DE ZANJAS CON MATERIAL PROPIO SELEC. DE LA ZONA 5329.91 5,329.91 50% 2,664.96 50% 2,664.96
04.03.07 TUBERIA PVC SAP 2" C-7.5 4159.05 4,159.05 100% 4,159.05
04.03.08 TUBERIA PVC SAP 1 1/2" C-7.5 8715 8,715.00 100% 8,715.00
04.03.09 TUBERIA PVC SAP 1" C-7.5 4409.15 4,409.15 100% 4,409.15
04.03.10 ACCESORIOS COMPLEMENTARIOS A LA RED - Pucapuca 1782.09 1,782.09 100% 1,782.09
04.03.11 PRUEBA HIDRAULICA 963.6 963.60 100% 963.60
05 LINEA DE DISTRIBUCION (1756.96 ML) 26506.47 26,506.47
05.01 TRABAJOS PRELIMINARES 1583.16 1,583.16
05.01.01 TRAZO Y REPLANTEO EN LINEA DE DISTRIBUCION 1583.16 1,583.16 100% 1,583.16
05.02 MOVIMIENTO DE TIERRAS 17414.71 17,414.71
05.02.01 EXCAVACION MANUAL EN TERRENO SUELTO P/ ZANJA 6088.36 6,088.36 50% 3,044.18 50% 3,044.18
05.02.02 REFINE NIVELACION Y COFINAMIENTO DE ZANJA 1356.99 1,356.99 50% 678.50 50% 678.50
05.02.03 COLOCACION Y COMPACTADO DE CAMA DE APOYO E = 0.10 M 8368.11 8,368.11 100% 8,368.11
05.02.04 RELLENO DE ZANJAS CON MATERIAL PROPIO SELEC. DE LA ZONA 1601.25 1,601.25 100% 1,601.25
05.03 TUBERIA 7508.6 7,508.60
05.03.01 TUBERIA PVC SAP 3/4" C-10 6747.26 6,747.26 100% 6,747.26
05.03.02 ACCESORIOS COMPLEMENTARIOS A LA RED DE DISTRIBUCION 158.23 158.23 100% 158.23
05.03.03 PRUEBA HIDRAULICA 603.11 603.11 100% 603.11
06 VALVULAS DE PURGA Y CONTROL 4262.25 4,262.25
06.01 TRABAJOS PRELIMINARES 1 1.00
06.01.01 TRAZO Y REPLANTEO 1 1.00 100% 1.00
06.02 MOVIMIENTO DE TIERRAS 12.07 12.07
06.02.01 EXCAVACION PARA EXTRUCTURAS 7.4 7.40 100% 7.40
06.02.02 ELIMINACION DE MATERIAL EXCEDENTE 4.67 4.67 100% 4.67
06.03 VALVULAS DE PURGA Y CONTROL 4249.18 4,249.18
06.03.01 CAJA DE VALVULA DE 0.50 x 0.50 CON TAPA METALICA 1247.88 1,247.88 100% 1,247.88
06.03.02 VALVULA DE PURGA ø 1 1/2" 1860.64 1,860.64 100% 1,860.64
06.03.03 VALVULA DE CONTROL ø 4" 1140.66 1,140.66 100% 1,140.66
07 HIDRANTES 21345.46 21,345.46
07.01 HIDRANTES (52 UNID) 10567.71 10,567.71
07.01.01 CAJA DE HIDRANTE DE 0.40 x 0.40 CON TAPA METALICA 6591.48 6,591.48 40% 2,636.59 60% 3,954.89
07.01.02 HIDRANTES DE ø 3/4" + Accesorios 3263.88 3,263.88 40% 1,305.55 60% 1,958.33
07.01.03 ACCESORIOS COMPLEMENTARIOS A LA RED - Pucapuca 712.35 712.35 40% 284.94 60% 427.41
07.02 EQUIPO DE RIEGO 10777.75 10,777.75
07.02.01 EQUIPO DE RIEGO FAMILIAR - Aspersor Sect. Q=1.18m3/h 2075.1 2,075.10 100% 2,075.10
07.02.02 EQUIPO DE RIEGO FAMILIAR - Aspersor Sect. Q=0.50m3/h 3818.05 3,818.05 100% 3,818.05
07.02.03 EQUIPO DE RIEGO FAMILIAR - Aspersor Sect. Q=0.24m3/h 4884.6 4,884.60 100% 4,884.60
08 TRANSPORTE DE MATERIALES 6000 6,000.00
08.01 TRANSPORTE RURAL 1000 1,000.00 40% 400.00 30% 300.00 30% 300.00
08.02 TRANSPORTE DE MATERIALES - ABANCAY A OBRA 5000 5,000.00 40% 2,000.00 30% 1,500.00 30% 1,500.00
TOTAL COSTO DIRECTO 140,726.72 140,726.72 8,644.19 48,165.71 83,916.82

CAPACITACION Y MITIGACION 9,458.80 9,458.80 3,152.93 3,152.93 3,152.93

GASTOS GENERALES (17.40%) 33,791.74 33,791.74 11,263.91 11,263.91 11,263.91

UTILIDAD (10%) 15,018.55 15,018.55 5,006.18 5,006.18 5,006.18

IGV 35,819.25 35,819.25 11,939.75 11,939.75 11,939.75

TOTAL PRESUPUESTO DE OBRA 234,815.06 234,815.06 40,006.97 79,528.49 115,279.60