MES 01 SALDO MES 02 SALDO MES 03 SALDO SALDO SALDO SALDO


PRESUPUESTO BASE (S/.)
Item Descripción Und.
Metrado Precio (S/.) Parcial (S/.) METRADO PARCIAL % METRADO METRADO PARCIAL % METRADO METRADO PARCIAL % METRADO METRADO METRADO %
01 OBRAS PROVISIONALES
01.01 CARTEL DE OBRA 2,40 x 3.60 M GLB 1.00 709.21 709.21 1.00 709.21 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
MOVILIZACION Y DESMOVILIZACION DE MAQUINARIAS - HERRAMIENTAS
01.02 GLB 0.25 10,000.00 2,500.00 0.25 2500.00 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
PARA LA OBRA
01.03 OFICINA, ALMACEN Y GUARDIANIA GLB 0.58 7,500.00 4,350.00 0.58 4350.00 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
01.04 CERCO PROVISIONAL DE OBRA GLB 0.58 2,410.26 1,397.95 0.58 1397.95 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
01.05 MEJORAMIENTO DEL SUELO M3 52.45 127.90 6,708.36 52.45 6708.36 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
02 SEGURIDAD EN OBRA
02.01 EQUIPO DE SEGURIDAD INDIVIDUAL UND 20.00 139.00 2,780.00 20.00 2780.00 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
02.02 EQUIPO DE SEGURIDAD COLECTIVA GLB 0.58 1,575.00 913.50 0.58 913.50 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
02.03 SEÑALIZACIÓN TEMPORAL DE SEGURIDAD GLB 0.58 1,000.00 580.00 0.58 580.00 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
03 PAVIMENTO RIGIDO REVESTIDO CON PIEDRAS DE LAJA
03.01 OBRAS PRELIMINARES
03.01.01 DEMOLICION DE PAVIMENTO DE CONCRETO M3 10.49 70.85 743.22 10.49 743.22 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
03.01.02 ACARREO DE MATERIAL EXCAVADO M3 14.69 18.87 277.20 14.69 277.20 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
03.01.03 ELIMINACION MASIVA DE MATERIAL CON CARGADOR + VOLQUETE D =5Km M3 14.69 54.50 800.61 14.69 800.61 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
03.01.04 LIMPIEZA DE TERRENO MANUAL M2 179.86 3.84 690.66 179.86 690.66 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
03.02 MOVIMIENTO DE TIERRAS
03.02.01 TRAZO Y REPLANTEO M2 468.94 4.26 1,997.68 468.94 1997.68 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
03.02.02 CORTE HASTA EL NIVEL DE SUBRASANTE M3 13.44 37.74 507.23 13.44 507.23 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
03.02.03 ACARREO DE MATERIAL EXCAVADO M3 17.47 18.87 329.66 17.47 329.66 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
03.02.04 ELIMINACION MASIVA DE MATERIAL CON CARGADOR + VOLQUETE D = 5 km M3 17.47 54.50 952.12 17.47 952.12 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
03.02.05 NIVELACION Y APISONADO M2 103.36 2.01 207.75 103.36 207.75 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
03.02.06 PERFILADO Y COMPACTACION SUB-RASANTES ZONAS CORTE M2 103.36 2.27 234.63 103.36 234.63 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
03.02.07 BASE GRANULAR DE 0.20 m M2 386.04 26.46 10,214.62 386.04 10214.62 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
03.03 CONCRETO SIMPLE
03.03.01 ENCOFRADO Y DESENCOFRADO EN PAVIMENTO M2 57.12 35.47 2,026.05 57.12 2026.05 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
03.03.02 CONCRETO f 'c=210 kg/cm2 PARA PAVIMENTO M3 84.13 423.54 35,632.42 84.13 35632.42 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
03.03.03 COLOCACION DE DOWELS UND 322.00 12.19 3,925.18 322.00 3925.18 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
03.03.04 REVESTIMIENTO DE PAVIMENTO CON PIEDRAS DE LAJA M2 1,541.08 231.75 357,145.29 231.16 53571.79 15% 1309.92 924.65 214287.17 60% 385.27 385.27 89286.32 25% 0.00 0.00 0.00 0%
03.03.05 CURADO CON AGUA M2 420.64 4.68 1,968.60 0.00 0.00 0% 420.64 0.00 0.00 0% 420.64 420.64 1968.60 100% 0.00 0.00 0.00 0%
03.03.06 LIMPIEZA DE PAVIMENTO M2 420.64 0.23 96.75 0.00 0.00 0% 420.64 0.00 0.00 0% 420.64 420.64 96.75 100% 0.00 0.00 0.00 0%
03.04 JUNTAS
03.04.01 JUNTA DE CONSTRUCCION LONGITUDINAL M 167.97 9.72 1,632.67 0.00 0.00 0% 167.97 0.00 0.00 0% 167.97 167.97 1632.67 100% 0.00 0.00 0.00 0%
03.04.02 JUNTA DE DILATACION M 8.69 7.66 66.57 0.00 0.00 0% 8.69 0.00 0.00 0% 8.69 8.69 66.57 100% 0.00 0.00 0.00 0%
03.04.03 JUNTA DE CONTRACCION M 263.50 7.66 2,018.41 0.00 0.00 0% 263.50 0.00 0.00 0% 263.50 263.50 2018.41 100% 0.00 0.00 0.00 0%
03.05 SEÑALIZACION
03.05.01 PINTURA DE TRAFICO M 167.40 13.42 2,246.51 0.00 0.00 0% 167.40 0.00 0.00 0% 167.40 167.40 2246.51 100% 0.00 0.00 0.00 0%
03.05.02 SEÑALIZACION VERTICAL UND 2.00 500.00 1,000.00 0.00 0.00 0% 2.00 0.00 0.00 0% 2.00 2.00 1000.00 100% 0.00 0.00 0.00 0%
03.05.03 LETRERO DE IDENTIFICACION DE CALLES UND 4.00 1,500.00 6,000.00 0.00 0.00 0% 4.00 0.00 0.00 0% 4.00 4.00 6000.00 100% 0.00 0.00 0.00 0%
03.06 REPOSICION DE SARDINELES AFECTADOS EN EL PERIMETRO DE LA PLAZA
03.06.01 EXCAVACION A MANO EN TERRENO NORMAL M3 41.09 28.30 1,162.85 0.00 0.00 0% 41.09 0.00 0.00 0% 41.09 41.09 1162.85 100% 0.00 0.00 0.00 0%
03.06.02 ACARREO DE MATERIAL EXCAVADO M3 57.52 18.87 1,085.40 0.00 0.00 0% 57.52 0.00 0.00 0% 57.52 57.52 1085.40 100% 0.00 0.00 0.00 0%
03.06.03 ENCOFRADO Y DESENCOFRADO M2 31.60 51.04 1,612.86 0.00 0.00 0% 31.60 0.00 0.00 0% 31.60 31.60 1612.86 100% 0.00 0.00 0.00 0%
03.06.04 CONCRETO f'c=175 kg/cm2 M3 30.81 358.31 11,039.53 0.00 0.00 0% 30.81 0.00 0.00 0% 30.81 30.81 11039.53 100% 0.00 0.00 0.00 0%
03.06.05 REVESTIMIENTO DE SARDINELES CON PIEDRAS LAJA M2 41.09 200.66 8,245.12 0.00 0.00 0% 41.09 0.00 0.00 0% 41.09 41.09 8245.12 100% 0.00 0.00 0.00 0%
04 SISTEMA DE ALCANTARILLADO
04.01 OBRAS PRELIMINARES
04.01.01 CORTE DE LOSA DE ALCANTARILLA M2 168.49 25.83 4,352.10 168.49 4352.10 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
04.01.02 DEMOLICION DE PAREDES Y LOSA DE FONDO DE ALCANTARILLA M3 67.40 150.07 10,114.72 67.40 10114.72 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
04.01.03 ACARREO DE MATERIAL EXCAVADO M3 94.36 18.87 1,780.57 94.36 1780.57 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
04.01.04 ELIMINACION MASIVA DE MATERIAL CON CARGADOR + VOLQUETE D = 5 km M3 94.36 54.50 5,142.62 94.36 5142.62 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
04.01.05 LIMPIEZA DE TERRENO MANUAL M2 168.49 3.84 647.00 168.49 647.00 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
04.02 ALCANTARILLADO PLUVIAL
CALENDARIO DE AVANCE PROGRAMADO DE OBRA VALORIZADO
OBRA "MEJORAMIENTO DE PAVIMENTO DEL PERIMETRO DE LA PLAZA DE LA CIUDAD DE HUARI, DEL DISTRITO DE HUARI, PROVINCIA DE HUARI - ANCASH"
ENTIDAD MUNICIPALIDAD PROVINCIAL DE HUARI
UBICACIÓN HUARI - HUARI - ANCASH
FECHA ABRIL DE 2015

MES 01 SALDO MES 02 SALDO MES 03 SALDO SALDO SALDO SALDO


PRESUPUESTO BASE (S/.)
Item Descripción Und.
Metrado Precio (S/.) Parcial (S/.) METRADO PARCIAL % METRADO METRADO PARCIAL % METRADO METRADO PARCIAL % METRADO METRADO METRADO %
04.02.01 TRAZO, NIVELES Y REPLANTEO M2 87.52 4.64 406.09 87.52 406.09 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
04.02.02 EXCAVACION DE ZANJAS M3 109.40 32.35 3,539.09 109.40 3539.09 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
04.02.03 NIVELACION INTERIOR Y APISONADO M2 87.52 1.90 166.29 87.52 166.29 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
04.02.04 ACARREO DE MATERIAL EXCAVADO M3 136.74 18.87 2,580.28 136.74 2580.28 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
04.02.05 ELIMINACION MASIVA DE MATERIAL CON CARGADOR + VOLQUETE D = 5 km M3 136.74 54.50 7,452.33 136.74 7452.33 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
04.02.06 RETIRO DE AGUA CON MOTOBOMBA GLB 0.69 946.44 653.04 0.58 551.00 84% 0.11 0.11 102.04 16% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
04.02.07 SOLADO f'c = 100Kg/cm2, e = 5cm M2 116.69 35.89 4,188.00 116.69 4188.00 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
04.02.08 ENCOFRADO Y DESENCOFRADO EN ALCANTARILLAS M2 106.69 50.07 5,341.97 106.69 5341.97 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
04.02.09 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 KG 2,008.81 4.83 9,702.55 1995.71 9639.29 99% 13.10 13.10 63.26 1% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
04.02.10 CONCRETO f 'c=210 Kg/cm2 (PARA ALCANTARILLAS) M3 64.53 423.54 27,331.04 0.00 0.00 0% 64.53 64.53 27331.04 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
04.02.11 REJILLA COLECTOR CON RIELES DE 25 Lbs. M 8.33 805.32 6,708.32 0.00 0.00 0% 8.33 8.33 6708.32 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
05 VEREDAS DE MAMPOSTERIA DE PIEDRA
05.01 OBRAS PRELIMINARES
05.01.01 LIMPIEZA DE TERRENO MANUAL M2 155.47 3.84 597.00 0.00 0.00 0% 155.47 155.47 597.00 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
05.01.02 TRAZO, NIVELES Y REPLANTEO M2 155.47 4.64 721.38 0.00 0.00 0% 155.47 155.47 721.38 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
05.02 MOVIMIENTO DE TIERRAS
05.02.01 RETIRO DE LAS PIEDRAS DE LAJAS DE LAS VEREDAS A DEMOLER M2 45.16 37.74 1,704.34 0.00 0.00 0% 45.16 22.02 830.87 49% 23.14 23.14 873.47 51% 0.00 0.00 0.00 0%
05.02.02 DEMOLICION DE CONCRETO EXISTENTE (COMBA Y PICO) M3 9.03 283.04 2,555.85 0.00 0.00 0% 9.03 0.00 0.00 0% 9.03 9.03 2555.85 100% 0.00 0.00 0.00 0%
05.02.03 RELLENO COMPACTADO MANUAL EN CAPAS CON MATERIAL DE PRESTAMO M3 32.65 100.19 3,271.20 0.00 0.00 0% 32.65 0.00 0.00 0% 32.65 32.65 3271.20 100% 0.00 0.00 0.00 0%
05.02.04 ACARREO DE MATERIAL EXCAVADO M3 12.64 18.87 238.52 0.00 0.00 0% 12.64 0.00 0.00 0% 12.64 12.64 238.52 100% 0.00 0.00 0.00 0%
05.02.05 ELIMINACION MASIVA DE MATERIAL CON CARGADOR + VOLQUETE D = 5 km M3 12.64 54.50 688.88 0.00 0.00 0% 12.64 0.00 0.00 0% 12.64 12.64 688.88 100% 0.00 0.00 0.00 0%
05.03 CONCRETO SIMPLE
05.03.01 CAMA DE PIEDRA DE 4" M3 15.55 207.40 3,225.07 0.00 0.00 0% 15.55 0.00 0.00 0% 15.55 15.55 3225.07 100% 0.00 0.00 0.00 0%
05.03.02 SARDINEL DE VEREDA CON BLOQUE DE PIEDRA M 207.42 132.78 27,541.23 0.00 0.00 0% 207.42 0.00 0.00 0% 207.42 207.42 27541.23 100% 0.00 0.00 0.00 0%
05.03.03 ENCOFRADO Y DESENCOFRADO DE VEREDAS M2 48.80 42.81 2,089.13 0.00 0.00 0% 48.80 0.00 0.00 0% 48.80 48.80 2089.13 100% 0.00 0.00 0.00 0%
05.03.04 CONCRETO f 'c=140 Kg/cm2 PARA VEREDAS M3 23.32 360.70 8,411.52 0.00 0.00 0% 23.32 0.00 0.00 0% 23.32 23.32 8411.52 100% 0.00 0.00 0.00 0%
05.03.05 REVESTIMIENTO DE VEREDAS CON PIEDRAS DE LAJA M2 240.25 116.66 28,027.57 0.00 0.00 0% 240.25 0.00 0.00 0% 240.25 240.25 28027.57 100% 0.00 0.00 0.00 0%
05.03.06 RAMPA DE CONCRETO PARA MINUSVALIDOS DE 0.80x0.80m M3 1.28 189.82 242.97 0.00 0.00 0% 1.28 0.00 0.00 0% 1.28 1.28 242.97 100% 0.00 0.00 0.00 0%
05.03.07 LIMPIEZA DE LAS VEREDAS M2 240.25 0.58 139.35 0.00 0.00 0% 240.25 0.00 0.00 0% 240.25 240.25 139.35 100% 0.00 0.00 0.00 0%
05.03.08 JUNTAS EN VEREDA M 3.00 9.48 28.44 0.00 0.00 0% 3.00 0.00 0.00 0% 3.00 3.00 28.44 100% 0.00 0.00 0.00 0%
06 OBRAS E INSTALACIONES PROVISIONALES
06.01 REPOSICION DE AGUA POTABLE
06.01.01 TRAZO Y REPLANTEO M2 53.00 3.01 159.53 53.00 159.53 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.01.02 EXCAVACION DE ZANJAS M3 50.88 32.35 1,645.97 50.88 1645.97 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.01.03 RETIRO DE TUBERIA EXISTENTE M 53.00 0.73 38.69 53.00 38.69 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.01.04 REFINE EN TERRENO NORMAL M 53.00 2.86 151.58 53.00 151.58 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.01.05 CAMA DE APOYO PARA TUBERIA M 53.00 3.57 189.21 53.00 189.21 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.01.06 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP CLASE 10 DE 2" M 53.00 6.89 365.17 53.00 365.17 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.01.07 ACCESORIOS DE INSTALACION GLB 1.00 500.00 500.00 1.00 500.00 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.01.08 CONEXIONES DOMICILIARIAS DE AGUA POTABLE DN 1/2" C-10, LP=4m UND 6.00 109.16 654.96 6.00 654.96 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.01.09 PRUEBA HIDRAULICA M 53.00 4.46 236.38 53.00 236.38 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.01.10 ACARREO DE MATERIAL EXCAVADO M3 63.60 18.87 1,200.13 63.60 1200.13 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.01.11 RELLENO Y COMPACTACION DE ZANJAS MANUAL M3 63.60 12.74 810.26 63.60 810.26 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.01.12 CAJA DE REGISTRO DOMICILIARIO - AGUA POTABLE UND 6.00 89.44 536.64 6.00 536.64 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.02 REPOSICION DEL SISTEMA DE DESAGUE
06.02.01 TRAZO Y REPLANTEO M2 102.00 3.01 307.02 102.00 307.02 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.02.02 EXCAVACION DE ZANJAS M3 114.24 32.35 3,695.66 114.24 3695.66 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.02.03 RETIRO DE TUBERIA EXISTENTE M 102.00 0.73 74.46 102.00 74.46 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.02.04 REFINE EN TERRENO NORMAL M 102.00 2.86 291.72 102.00 291.72 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.02.05 CAMA DE APOYO PARA TUBERIA M 102.00 3.57 364.14 102.00 364.14 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.02.06 SUMINISTRO Y COLOCACION DE TUBERIA PVC SAL 8" M 53.00 45.66 2,419.98 53.00 2419.98 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.02.07 CODO CACHIMBA UF 45º PVC ISO 4435 DN 110m, D=6" UND 6.00 48.62 291.72 6.00 291.72 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.02.08 RELLENO Y COMPACTACION DE ZANJAS MANUAL M3 142.80 12.74 1,819.27 142.80 1819.27 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
CALENDARIO DE AVANCE PROGRAMADO DE OBRA VALORIZADO
OBRA "MEJORAMIENTO DE PAVIMENTO DEL PERIMETRO DE LA PLAZA DE LA CIUDAD DE HUARI, DEL DISTRITO DE HUARI, PROVINCIA DE HUARI - ANCASH"
ENTIDAD MUNICIPALIDAD PROVINCIAL DE HUARI
UBICACIÓN HUARI - HUARI - ANCASH
FECHA ABRIL DE 2015

MES 01 SALDO MES 02 SALDO MES 03 SALDO SALDO SALDO SALDO


PRESUPUESTO BASE (S/.)
Item Descripción Und.
Metrado Precio (S/.) Parcial (S/.) METRADO PARCIAL % METRADO METRADO PARCIAL % METRADO METRADO PARCIAL % METRADO METRADO METRADO %
06.02.09 CAJA DE REGISTRO DOMICILIARIO - DESAGUE UND 6.00 89.44 536.64 6.00 536.64 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.02.10 ACARREO DE MATERIAL EXCAVADO M3 142.80 18.87 2,694.64 142.80 2694.64 100% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
06.03 REPOSICION DE BUZONES
06.03.01 EXCAVACION DE ZANJAS M3 21.60 32.35 698.76 0.00 0.00 0% 21.60 13.50 436.73 63% 8.10 8.10 262.03 37% 0.00 0.00 0.00 0%
06.03.02 ACARREO DE MATERIAL EXCAVADO M3 30.24 18.87 570.63 0.00 0.00 0% 30.24 0.00 0.00 0% 30.24 30.24 570.63 100% 0.00 0.00 0.00 0%
06.03.03 ELIMINACION MASIVA DE MATERIAL CON CARGADOR + VOLQUETE D = 5 km M3 30.24 54.50 1,648.08 0.00 0.00 0% 30.24 0.00 0.00 0% 30.24 30.24 1648.08 100% 0.00 0.00 0.00 0%
06.03.04 SOLADO f'c = 100Kg/cm2, e = 5cm M2 18.00 34.64 623.52 0.00 0.00 0% 18.00 0.00 0.00 0% 18.00 18.00 623.52 100% 0.00 0.00 0.00 0%
06.03.05 ENCOFRADO Y DESENCOFRADO EN MUROS M2 57.60 43.12 2,483.71 0.00 0.00 0% 57.60 0.00 0.00 0% 57.60 57.60 2483.71 100% 0.00 0.00 0.00 0%
06.03.06 CONCRETO f 'c=210 kg/cm2 M3 11.52 421.06 4,850.61 0.00 0.00 0% 11.52 0.00 0.00 0% 11.52 11.52 4850.61 100% 0.00 0.00 0.00 0%
06.03.07 MARCO DE FºFº Y TAPA DE CONCRETO ARMADO UND 11.00 92.92 1,022.12 0.00 0.00 0% 11.00 0.00 0.00 0% 11.00 11.00 1022.12 100% 0.00 0.00 0.00 0%
06.03.08 TARRAJEO PULIDO EN MUROS INTERIORES 1:3, e=3cm M2 57.60 36.92 2,126.59 0.00 0.00 0% 57.60 0.00 0.00 0% 57.60 57.60 2126.59 100% 0.00 0.00 0.00 0%
06.03.09 CONCRETO f 'c=140 Kg/cm2 P/MEDIA CAÑA M3 2.04 323.64 660.23 0.00 0.00 0% 2.04 0.00 0.00 0% 2.04 2.04 660.23 100% 0.00 0.00 0.00 0%
06.03.10 TARRAJEO PULIDO EN MEDIA CAÑA M2 2.71 41.09 111.35 0.00 0.00 0% 2.71 0.00 0.00 0% 2.71 2.71 111.35 100% 0.00 0.00 0.00 0%
06.03.11 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 KG 436.20 4.83 2,106.85 0.00 0.00 0% 436.20 0.00 0.00 0% 436.20 436.20 2106.85 100% 0.00 0.00 0.00 0%
07 OBRAS COMPLEMENTARIAS
07.01 HIDRANTES CONTRA INCENDIOS GLB 1.00 4,540.22 4,540.22 0.00 0.00 0% 1.00 0.00 0.00 0% 1.00 1.00 4540.22 100% 0.00 0.00 0.00 0%
08 FLETE TERRESTRE
08.01 FLETE TERRESTRE GLB 1.00 68,265.81 68,265.81 0.33 22755.27 33% 0.67 0.67 45510.54 67% 0.00 0.00 0.00 0% 0.00 0.00 0.00 0%
09 CAPACITACION
09.01 CAPACITACION GLB 1.00 3,871.75 3,871.75 0.00 0.00 0% 1.00 0.00 0.00 0% 1.00 1.00 3871.75 100% 0.00 0.00 0.00 0%

COSTO DIRECTO 755,951.07 S/. 229,690.24 S/. 296,588.36 S/. 229,672.46


AVANCE MENSUAL(%) 30.38% 39.23% 30.38%
AVANCE ACUMULADO(%) 30.38% 69.62% 100.00%
CURVA S
AVANCE PROGRAMADO VS. EJECUTADO

OBRA REPARACION DE VIGAS LONGITUDINALESEN EL PUENTE DE ACCESO (55ML) Y VIGAS GUARDERAS EN EL MUELLE NORTE Y SUR

ENTIDAD SERVICIOS INDUSTRIALES DE LA MARINA S.A.


FECHA JUNIO DEL 2021

Curva S de Avance de Obra


120%

100.00%
100%
100.00%

80% 82.76%
68.61%
(%) AVANCE

60%

40%

20%

0.00%
0% 0.00%
INICIO (04 - MAYO) (DEL 04 AL 31 - MAYO 2021) (DEL 01 AL 17- JUNIO 2021)

TIEMPO
AVANNCE ACUMULADO EJCUTADO

VALORIZACIÓN
AVANCE DE AVANCE PORCENTUAL AVANCE PORCENTUAL SITUACIÓN DE LA
MES OBRA (S/.) MENSUAL (%) ACUMULADO (%) OBRA

INICIO DE OBRA INICIO (04 - MAYO)


PROGRAMADO 0.00 0.00% 0.00%
MES 0
EJECUTADO 0.00 0.00% 0.00%

VALORIZACION N°01 (DEL 04 AL 31 - MAYO 2021) ESTADO

PROGRAMADO 254,225.99 68.61% 68.61%


(DEL 04 AL 31 - MAYO 2021) NORMAL
EJECUTADO 306,641.01 82.76% 82.76%

VALORIZACION N°02 (DEL 01 AL 17- JUNIO 2021) ESTADO

PROGRAMADO 116,302.28 31.39% 100.00%


(DEL 01 AL 17- JUNIO 2021) CULMINADO
EJECUTADO 63,887.26 17.24% 100.00%