Documentos de Académico
Documentos de Profesional
Documentos de Cultura
“CREACION DEL SERVICIO DEL COMPLEJO DEPORTIVO EN EL BARRIO DE PATACANCHA DISTRITO DE HUACHOCOLPA - PROVINCIA DE HUANCAVELICA - DEPARTAMENTO
DE HUANCAVELICA "
ENTIDAD
MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA COSTO DIRECTO DEL PROYECTO S/ 236,255.22 DISTRITO : HUACHOCOLPA
EJECUTORA
MODALIDAD DE
CONTRATA PLAZO DE EJECUCION 80 DIAS CALENDARIOS PROVINCIA : HUACHOCOLPA
EJECUCION
AVANCES
PRESUPUESTO
ITEM DESCRIPCION JUNIO JULIO AGOSTO SETIEMBRE
Und. Metrado Precio (S/.) Parcial (S/.) 10 DIAS 31 DIAS 31 DIAS 8 DIAS
21/06/2022 - 30/06/2022 01/07/2022 - 31/07/2022 01/08/2022 - 31/08/2022 01/09/2022 - 08/09/2022
01 TRABAJOS PRELIMINARES 16,220.85
01.01 ALQUILER DE ALMACEN Y OFICINA mes 2.00 410.00 820.00 410.00 50.00% 410.00 50.00% 0.00 0.00% 0.00%
01.02 CARTEL DE IDENTIFICACION DE OBRA DE 2.40 X 3.60 m und 1.00 736.58 736.58 736.58 100% 0.00 0.00% 0.00 0.00% 0.00%
01.03 CERCO PERIMETRICO CON COSTALES DE YUTE m 180.00 6.37 1,146.60 1146.60 100% 0.00 0.00% 0.00 0.00% 0.00%
01.04 TANQUE DE PLASTICO PARA ALMACENAMIENTO DE AGUA, INC. A und 2.00 246.00 492.00 492.00 100% 0.00 0.00% 0.00 0.00% 0.00%
01.05 INSTALACION DE ENERGIA ELECTRICA PROVISIONAL, CONSUMO Y GLB 1.00 1,640.00 1,640.00 1640.00 100% 0.00 0.00% 0.00 0.00% 0.00%
01.06 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS GLB 1.00 8,814.67 8,814.67 4407.34 50% 4,407.34 50.00% 0.00 0.00% 0.00%
01.07 PLACA RECORDATORIA INC. INSTALACION und 1.00 82.00 82.00 0.00 0% 0.00 0.00% 82.00 100.00% 0.00%
01.08 TRAZO, NIVELES Y REPLANTEO PRELIMINAR m2 950.00 1.41 1,339.50 1339.50 100% 0.00 0.00% 0.00 0.00% 0.00%
01.09 TRAZO NIVEL Y REPLANTEO PRELIMINAR DURANTE EL PROCESO m2 950.00 1.21 1,149.50 191.18 17% 786.50 68.42% 171.82 14.95% 0.00%
02 MOVIMIENTO DE TIERRAS 11,562.81 0.00
02.01 CORTE DE TERRENO A NIVEL DE SUB RASANTE m3 2,109.33 2.25 4,745.99 0.00 0.00% 4,745.99 100.00% 0.00 0.00% 0.00%
02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO m3 243.02 6.29 1,528.60 0.00 0.00% 1,528.60 100.00% 0.00 0.00% 0.00%
02.03 PERFILADO Y COMPACTADO DE SUB RASANTE m2 950.00 1.22 1,159.00 0.00 0.00% 1,159.00 100.00% 0.00 0.00% 0.00%
02.04 ELIMINACION DE MATERIAL EXCEDENTE D= >1Km m3 2,332.89 1.77 4,129.22 0.00 0.00% 4,129.22 100.00% 0.00 0.00% 0.00%
03 SISTEMA DE DRENAJE 14,528.81 0.00
03.01 EXCAVACION MANUAL DE ZANJA PARA DRENAJE m3 39.38 19.78 778.94 0.00 0.00% 778.94 100.00% 0.00 0.00% 0.00%
03.02 RELLENO CON MATERIAL PROPIO m3 5.88 60.77 357.33 0.00 0.00% 357.33 100.00% 0.00 0.00% 0.00%
03.03 ELIMINACIÓN DE MATERIAL EXCEDENTE DIST= 30m m3 40.04 14.83 593.79 0.00 0.00% 593.79 100.00% 0.00 0.00% 0.00%
03.04 PIEDRA CHANCADA DE 1" m3 33.17 115.43 3,828.81 0.00 0.00% 3,828.81 100.00% 0.00 0.00% 0.00%
03.05 GRAVILLA DE 1/4" m3 2.81 112.59 316.38 0.00 0.00% 316.38 100.00% 0.00 0.00% 0.00%
03.06 TUBERIA PVC SAL DE 2" m 109.30 11.73 1,282.09 0.00 0.00% 1,282.09 100.00% 0.00 0.00% 0.00%
03.07 TUBERIA PVC SAL DE 4" m 41.80 17.66 738.19 0.00 0.00% 738.19 100.00% 0.00 0.00% 0.00%
03.08 CODO DE PVC SAL 2"X45° pza 12.00 57.62 691.44 0.00 0.00% 691.44 100.00% 0.00 0.00% 0.00%
03.09 GEOTEXTIL m2 294.69 14.64 4,314.26 0.00 0.00% 4,314.26 100.00% 0.00 0.00% 0.00%
03.10 BUZON STANDART H=1.40M und 1.00 1,627.58 1,627.58 0.00 0.00% 0.00 0.00% 1,627.58 100.00% 0.00%
04 CAMPO DE JUEGO 89,797.35 0.00
04.01 EXCAVACION MANUAL PARA SARDINEL m3 3.04 30.22 91.87 0.00 0.00% 0.00 0.00% 91.87 100.00% 0.00%
04.02 CONCRETO EN SARDINEL F'C=175 KG/CM2 m3 3.04 372.79 1,133.28 0.00 0.00% 0.00 0.00% 1,133.28 100.00% 0.00%
04.03 ENCOFRADO Y DESENCOFRADO NORMAL SARDINEL m2 25.33 28.48 721.40 0.00 0.00% 0.00 0.00% 721.40 100.00% 0.00%
04.04 TARRAJEO EN SARDINEL C:A 1:5, E= 1:5 cm m2 35.46 39.13 1,387.55 0.00 0.00% 0.00 0.00% 1,387.55 100.00% 0.00%
04.05 RELLENO Y COMPACTADO CON MATERIAL AFIRMADO m3 56.25 89.16 5,015.25 0.00 0.00% 5,015.25 100.00% 0.00 0.00% 0.00%
04.06 GEOTEXTIL EN CAMPO DEPORTIVO m2 507.28 17.58 8,917.98 0.00 0.00% 8,917.98 100.00% 0.00 0.00% 0.00%
04.07 SUB BASE GRANULAR E= 0.05 M m2 28.12 14.55 409.15 0.00 0.00% 409.15 100.00% 0.00 0.00% 0.00%
04.08 SUMINISTRO E INSTALACION DE GRASS SINTETICO DE 60mm VERDEm2 562.49 121.36 68,263.79 0.00 0.00% 0.00 0.00% 68,263.79 100.00% 0.00%
04.09 SUMINISTRO E INSTALACION DE ARCO METALICOS und 2.00 1,688.18 3,376.36 0.00 0.00% 0.00 0.00% 3,376.36 100.00% 0.00%
04.10 EQUIPAMIENTO DEPORTIVO GLB 1.00 480.72 480.72 0.00 0.00% 0.00 0.00% 480.72 100.00% 0.00%
05 EDIFICACIONES (SS. HH.) 34,616.09 0.00 0.00%
05.01 ESTRUCTURAS 10,401.61 0.00 0.00%
05.01.01 MOVIMIENTO DE TIERRAS 248.13 0.00 0.00%
05.01.01.01 EXCAVACION MANUAL DE ZANJA PARA ZAPATAS m3 2.64 19.78 52.22 0.00 0.00% 52.22 100.00% 0.00 0.00% 0.00%
05.01.01.02 EXCAVACION MANUAL DE ZANJA PARA CIMENTACION m3 2.86 19.78 56.57 0.00 0.00% 56.57 100.00% 0.00 0.00% 0.00%
05.01.01.03 NIVELACIÓN Y COMPACTACIÓN CON EQUIPO LIVIANO m2 11.07 1.88 20.81 0.00 0.00% 20.81 100.00% 0.00 0.00% 0.00%
CRONOGRAMA ACTUALIZADO VALORIZADO DE OBRA
“CREACION DEL SERVICIO DEL COMPLEJO DEPORTIVO EN EL BARRIO DE PATACANCHA DISTRITO DE HUACHOCOLPA - PROVINCIA DE HUANCAVELICA - DEPARTAMENTO
DE HUANCAVELICA "
ENTIDAD
MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA COSTO DIRECTO DEL PROYECTO S/ 236,255.22 DISTRITO : HUACHOCOLPA
EJECUTORA
MODALIDAD DE
CONTRATA PLAZO DE EJECUCION 80 DIAS CALENDARIOS PROVINCIA : HUACHOCOLPA
EJECUCION
AVANCES
PRESUPUESTO
ITEM DESCRIPCION JUNIO JULIO AGOSTO SETIEMBRE
Und. Metrado Precio (S/.) Parcial (S/.) 10 DIAS 31 DIAS 31 DIAS 8 DIAS
05.01.01.04 RELLENO Y COMPACTACIÓN C/EQUIPO LIVIANO C/MATERIAL m3 1.42 14.94 21.21 0.00 0.00% 21.21 100.00% 0.00 0.00% 0.00%
05.01.01.05 ACARREO MANUAL DE MATERIAL EXCEDENTE HASTA UNA DISTm3 4.89 18.13 88.66 0.00 0.00% 88.66 100.00% 0.00 0.00% 0.00%
05.01.01.06 ELIMINACION DE MATERIAL EXCEDENTE D= >1Km m3 4.89 1.77 8.66 0.00 0.00% 8.66 100.00% 0.00 0.00% 0.00%
05.01.02 OBRAS DE CONCRETO SIMPLE 1,165.85 0.00
05.01.02.01 SOLADO DE CONCRETO C:H - 1:10 E=10CM EN ZAPATAS m2 2.40 22.42 53.81 0.00 0.00% 53.81 100.00% 0.00 0.00% 0.00%
05.01.02.02 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% m 2.82 200.57 565.61 0.00 0.00% 565.61 100.00% 0.00 0.00% 0.00%
05.01.02.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO. m2 12.58 28.48 358.28 0.00 0.00% 358.28 100.00% 0.00 0.00% 0.00%
05.01.02.04 CONCRETO EN SOBRECIMIENTOS C:H - 1:8 + 25% P.M. m3 0.93 202.31 188.15 0.00 0.00% 188.15 100.00% 0.00 0.00% 0.00%
05.01.03 OBRAS DE CONCRETO ARMADO 8,987.63 0.00
05.01.03.01 ZAPATAS 604.35 0.00
05.01.03.01.01 ACERO CORR. GRADO 60 F´y=4200Kg/cm2 kg 31.81 4.17 132.65 0.00 0.00% 132.65 100.00% 0.00 0.00% 0.00%
05.01.03.01.02 CONCRETO EN ZAPATAS F'C= 210 KG/CM2. m3 1.20 393.08 471.70 0.00 0.00% 471.70 100.00% 0.00% 0.00%
05.01.03.02 COLUMNAS 1,877.20 0.00
05.01.03.02.01 ACERO CORR. GRADO 60 F´y=4200Kg/cm2 kg 260.82 4.17 1,087.62 0.00 0.00% 1,087.62 100.00% 0.00% 0.00%
05.01.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS. m2 13.37 28.48 380.78 0.00 0.00% 380.78 100.00% 0.00% 0.00%
05.01.03.02.03 CONCRETO EN COLUMNAS f'c=210 kg/cm2. m3 1.04 393.08 408.80 0.00 0.00% 408.80 100.00% 0.00% 0.00%
05.01.03.03 VIGAS 1,617.08 0.00
05.01.03.03.01 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS. m2 18.89 28.48 537.99 0.00 0.00% 537.99 100.00% 0.00% 0.00%
05.01.03.03.02 ACERO CORR. GRADO 60 F´y=4200Kg/cm2 kg 153.20 4.17 638.84 0.00 0.00% 638.84 100.00% 0.00% 0.00%
05.01.03.03.03 CONCRETO EN VIGAS f'c=210 kg/cm2. m3 1.12 393.08 440.25 0.00 0.00% 440.25 100.00% 0.00% 0.00%
05.01.03.04 LOSA ALIGERADA 4,889.00
05.01.03.04.01 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSA ALIGERAD m2 19.45 28.48 553.94 0.00 0.00% 553.94 100.00% 0.00% 0.00%
05.01.03.04.02 ACERO CORR. GRADO 60 F´y=4200Kg/cm2 kg 93.98 4.17 391.90 0.00 0.00% 391.90 100.00% 0.00 0.00% 0.00%
05.01.03.04.03 CONCRETO EN LOSA ALIGERADA f'c=210 kg/cm2. m3 1.44 375.12 540.17 0.00 0.00% 540.17 100.00% 0.00 0.00% 0.00%
05.01.03.04.04 LADRILLO HUECO DE ARCILLA 15X30X30 CM PARA TECHO AL m2 106.51 31.95 3,402.99 0.00 0.00% 3,402.99 100.00% 0.00 0.00% 0.00%
05.02 ARQUITECTURA 12,449.51 0.00
05.02.01 MUROS Y TABIQUES DE ALBAÑILERIA 1,873.36 0.00
05.02.01.01 MURO DE LADRILLO CORRIENTE DE ARCILLA TIPO SOGA C:A-1:4m2 28.38 66.01 1,873.36 0.00 0.00% 1,873.36 100.00% 0.00% 0.00%
05.02.02 REVOQUES ENLUCIDOS Y MOLDURAS 3,659.57 0.00
05.02.02.01 TARRAJEO PRIMARIO RAYADO CON CEMENTO-ARENA m2 16.44 39.13 643.30 0.00 0.00% 0.00 0.00% 643.30 100.00% 0.00%
05.02.02.02 TARRAJEO MUROS INTERIORES MEZCLA C:A 1:5, E= 1:5 cm m2 20.47 39.13 800.99 0.00 0.00% 0.00 0.00% 800.99 100.00% 0.00%
05.02.02.03 TARRAJEO EN MUROS EXTERIORES C:A 1:5, E= 1:5 cm m2 18.68 39.13 730.95 0.00 0.00% 0.00 0.00% 730.95 100.00% 0.00%
05.02.02.04 TARRAJEO DE SUPERFICIE DE VIGAS Y VIGUETA m2 2.15 39.13 84.13 0.00 0.00% 0.00 0.00% 84.13 100.00% 0.00%
05.02.02.05 TARRAJEO DE SUPERFICIE DE COLUMNAS m2 9.55 39.13 373.69 0.00 0.00% 0.00 0.00% 373.69 100.00% 0.00%
05.02.02.06 VESTIDURA DE DERRAMES C:A 1:5. ANCHO 15 cm m 24.40 11.82 288.41 0.00 0.00% 0.00 0.00% 288.41 100.00% 0.00%
05.02.02.07 TARRAJEO EN CIELORRASO m2 13.18 39.13 515.73 0.00 0.00% 0.00 0.00% 515.73 100.00% 0.00%
05.02.02.08 BRUÑA DE 1.0 CM m 58.42 1.04 60.76 0.00 0.00% 0.00 0.00% 60.76 100.00% 0.00%
05.02.02.09 TARRAJEO VIGA BORDE CON C:A E IMPERMEABILIZANTE m2 4.13 39.13 161.61 0.00 0.00% 0.00 0.00% 161.61 100.00% 0.00%
05.02.03 PISOS Y PAVIMENTOS 1,685.44 0.00
05.02.03.01 FALSO PISO DE CONCRETO 1:12 DE E=4" m2 11.19 54.17 606.16 0.00 0.00% 0.00 0.00% 606.16 100.00% 0.00%
05.02.03.02 CONTRA PISO DE 48mm DE CONCRETO 1:10 m3 11.19 47.00 525.93 0.00 0.00% 0.00 0.00% 525.93 100.00% 0.00%
05.02.03.03 PISO CERAMICO DE 0.45 X 0.45 M m2 11.19 49.45 553.35 0.00 0.00% 0.00 0.00% 553.35 100.00% 0.00%
05.02.04 VEREDAS 1,692.80 0.00
05.02.04.01 ENCOFRADO Y DESENCOFRADO NORMAL EN VEREDA m2 1.98 28.48 56.39 0.00 0.00% 0.00 0.00% 56.39 100.00% 0.00%
CRONOGRAMA ACTUALIZADO VALORIZADO DE OBRA
“CREACION DEL SERVICIO DEL COMPLEJO DEPORTIVO EN EL BARRIO DE PATACANCHA DISTRITO DE HUACHOCOLPA - PROVINCIA DE HUANCAVELICA - DEPARTAMENTO
DE HUANCAVELICA "
ENTIDAD
MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA COSTO DIRECTO DEL PROYECTO S/ 236,255.22 DISTRITO : HUACHOCOLPA
EJECUTORA
MODALIDAD DE
CONTRATA PLAZO DE EJECUCION 80 DIAS CALENDARIOS PROVINCIA : HUACHOCOLPA
EJECUCION
AVANCES
PRESUPUESTO
ITEM DESCRIPCION JUNIO JULIO AGOSTO SETIEMBRE
Und. Metrado Precio (S/.) Parcial (S/.) 10 DIAS 31 DIAS 31 DIAS 8 DIAS
05.02.04.02 CONCRETO F'C=140 KG/CM2 E=4" PARA VEREDAS FROTACHAD m3 6.89 234.34 1,614.60 0.00 0.00% 0.00 0.00% 1,614.60 100.00% 0.00%
05.02.04.03 JUNTAS ASFALTICAS DE DILATACION E=1" PARA VEREDA m 1.30 16.78 21.81 0.00 0.00% 0.00 0.00% 21.81 100.00% 0.00%
05.02.05 ZOCALOS Y CONTRAZOCALOS 1,061.90 0.00
05.02.05.01 CONTRAZOCALO DE CEMENTO PULIDO h=0.30 m m 19.60 15.88 311.25 0.00 0.00% 0.00 0.00% 311.25 100.00% 0.00%
05.02.05.02 ZOCALO DE CERAMICA COLOR. H=1.20 m2 16.44 45.66 750.65 0.00 0.00% 0.00 0.00% 750.65 100.00% 0.00%
05.02.06 CARPINTERIA METALICA 1,789.14 0.00
05.02.06.01 PUERTA APANELADA DE MADERA TORNILLO SEGÚN DISEÑO IN m2 3.78 205.00 774.90 0.00 0.00% 0.00 0.00% 774.90 100.00% 0.00%
05.02.06.02 TABIQUERIA DE MELAMINE EN BAÑOS INCL. PUERTA Y CERROJOund 2.00 352.96 705.92 0.00 0.00% 0.00 0.00% 705.92 100.00% 0.00%
05.02.06.03 VENTANA DE ALUMINIO CON VIDRIO DOBLE S/DISEÑO Y INST. m2 1.88 164.00 308.32 0.00 0.00% 0.00 0.00% 308.32 100.00% 0.00%
05.02.07 PINTURA 687.30 0.00
05.02.07.01 PINTURA LATEX PARA CIELO RASO, VIGAS Y COLUMNAS m2 24.88 5.88 146.29 0.00 0.00% 0.00 0.00% 146.29 100.00% 0.00%
05.02.07.02 PINTURA EN MUROS INTERIORES C/LATEX m2 20.47 11.37 232.74 0.00 0.00% 0.00 0.00% 232.74 100.00% 0.00%
05.02.07.03 PINTURA EN MUROS EXTERIORES C/LATEX m2 20.87 11.37 237.29 0.00 0.00% 0.00% 237.29 100.00% 0.00%
05.02.07.04 PINTURA ESMALTE EN CONTRA ZACALO m2 5.58 12.72 70.98 0.00 0.00% 0.00% 70.98 100.00% 0.00%
05.03 INSTALACIONES SANITARIAS 9,267.43 0.00 0.00%
05.03.01 SISTEMA DE DESAGÜE DE AGUAS SERVIDAS 198.51 0.00 0.00%
05.03.01.01 RED DE DISTRIBUCION DE DESAGUE PVC SAL DE 4" m 4.80 12.85 61.68 0.00 0.00% 61.68 100.00% 0.00 0.00% 0.00%
05.03.01.02 RED DE DISTRIBUCION DE DESAGUE PVC SAL DE 2" m 7.53 9.08 68.37 0.00 0.00% 68.37 100.00% 0.00 0.00% 0.00%
05.03.01.03 RED DE VENTILACION PVC SAL DE 2" m 7.54 9.08 68.46 0.00 0.00% 68.46 100.00% 0.00 0.00% 0.00%
05.03.02 ACCESORIOS RED DE DESAGUE 297.00 0.00
05.03.02.01 SUMIDERO CROMADO DE 2" EN PISO CON TRAMPA "P" und 3.00 12.76 38.28 0.00 0.00% 0.00 0.00% 38.28 100.00% 0.00%
05.03.02.02 REGISTRO DE BRONCE CROMADO 4" und 2.00 15.14 30.28 0.00 0.00% 0.00 0.00% 30.28 100.00% 0.00%
05.03.02.03 YEE PVC SAL PARA DESAGUE 4"x4" pza 2.00 11.76 23.52 0.00 0.00% 23.52 100.00% 0.00 0.00% 0.00%
05.03.02.04 TEE PVC SAL Ø 4" und 2.00 11.76 23.52 0.00 0.00% 23.52 100.00% 0.00 0.00% 0.00%
05.03.02.05 CODO PVC-SAL 4" X 45º pza 2.00 11.76 23.52 0.00 0.00% 23.52 100.00% 0.00 0.00% 0.00%
05.03.02.06 YEE PVC SAL 2" pza 4.00 7.66 30.64 0.00 0.00% 30.64 100.00% 0.00 0.00% 0.00%
05.03.02.07 CODO CON REDUCCION DE 4" A 2" PVC-SAL pza 1.00 14.88 14.88 0.00 0.00% 14.88 100.00% 0.00 0.00% 0.00%
05.03.02.08 CODO PVC-SAL 2" X 45º pza 4.00 6.10 24.40 0.00 0.00% 24.40 100.00% 0.00 0.00% 0.00%
05.03.02.09 CODO PVC-SAL 2" X 90º pza 9.00 6.10 54.90 0.00 0.00% 54.90 100.00% 0.00 0.00% 0.00%
05.03.02.10 TEE PVC SAL Ø 2" und 1.00 11.02 11.02 0.00 0.00% 11.02 100.00% 0.00 0.00% 0.00%
05.03.02.11 SOMBRERO DE VENTILACION PVC SAL Ø 2" und 2.00 11.02 22.04 0.00 0.00% 22.04 100.00% 0.00 0.00% 0.00%
05.03.03 CAJAS DE REGISTRO DE DESAGUE 102.81 0.00
05.03.03.01 CAJA DE REGISTRO 30"*50" CON TAPA DE FIERRO FUNDIDO und 1.00 102.81 102.81 0.00 0.00% 0.00 0.00% 102.81 100.00% 0.00%
05.03.04 APARATOS Y ACCESORIOS SANITARIOS 1,233.05 0.00
05.03.04.01 INODORO TANQUE BAJO BLANCO INC/ACCESORIOS und 2.00 287.61 575.22 0.00 0.00% 0.00 0.00% 575.22 100.00% 0.00%
05.03.04.02 URINARIO DE LOSA DE PICO COLOR BLANCO (INC ACCESORIOSund 1.00 246.61 246.61 0.00 0.00% 0.00 0.00% 246.61 100.00% 0.00%
05.03.04.03 LAVATORIO DE MESA COLOR BLANCO (INC ACCESORIOS) und 2.00 205.61 411.22 0.00 0.00% 0.00 0.00% 411.22 100.00% 0.00%
05.03.05 SISTEMA DE AGUA FRIA 104.85 0.00
05.03.05.01 RED DE DISTRIBUCION PVC SAP DE 1/2" C-10 m 10.58 9.91 104.85 0.00 0.00% 104.85 100.00% 0.00 0.00% 0.00%
05.03.06 VÁLVULAS 55.44 0.00
05.03.06.01 VALVULA DE COMPUERTA DE BRONCE Ø 1/2" und 3.00 18.48 55.44 0.00 0.00% 0.00 0.00% 55.44 100.00% 0.00%
05.03.07 ACCESORIOS DE REDE DE AGUA FRIA 277.98 0.00
05.03.07.01 TEE PVC - SAP Ø 1/2" PARA AGUA pto 4.00 6.92 27.68 0.00 0.00% 27.68 100.00% 0.00 0.00% 0.00%
05.03.07.02 CODO PVC SAP Ø 1/2""X90º pza 25.00 6.92 173.00 0.00 0.00% 173.00 100.00% 0.00 0.00% 0.00%
CRONOGRAMA ACTUALIZADO VALORIZADO DE OBRA
“CREACION DEL SERVICIO DEL COMPLEJO DEPORTIVO EN EL BARRIO DE PATACANCHA DISTRITO DE HUACHOCOLPA - PROVINCIA DE HUANCAVELICA - DEPARTAMENTO
DE HUANCAVELICA "
ENTIDAD
MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA COSTO DIRECTO DEL PROYECTO S/ 236,255.22 DISTRITO : HUACHOCOLPA
EJECUTORA
MODALIDAD DE
CONTRATA PLAZO DE EJECUCION 80 DIAS CALENDARIOS PROVINCIA : HUACHOCOLPA
EJECUCION
AVANCES
PRESUPUESTO
ITEM DESCRIPCION JUNIO JULIO AGOSTO SETIEMBRE
Und. Metrado Precio (S/.) Parcial (S/.) 10 DIAS 31 DIAS 31 DIAS 8 DIAS
05.03.07.03 UNION UNIVERSAL PVC DE 1/2" pza 3.00 6.92 20.76 0.00 0.00% 20.76 100.00% 0.00 0.00% 0.00%
05.03.07.04 CAJA DE REGISTRO PARA AGUA 12"*24" CON TAPA DE FIERRO und 1.00 56.54 56.54 0.00 0.00% 56.54 100.00% 0.00 0.00% 0.00%
05.03.08 SISTEMA DE RED PLUVIAL Y ACCESORIOS 107.79 0.00 0.00
05.03.08.01 TUBERÍA PVC SAL DE 3” m 6.36 7.25 46.11 0.00 0.00% 46.11 100.00% 0.00 0.00% 0.00%
05.03.08.02 CODO PVC SAL 3"X90° pza 4.00 10.28 41.12 0.00 0.00% 41.12 100.00% 0.00 0.00% 0.00%
05.03.08.03 CODO PVC SAL 3"X45° pza 2.00 10.28 20.56 0.00 0.00% 20.56 100.00% 0.00 0.00% 0.00%
05.03.09 INSTALACIONES SANITARIAS EXTERIORES 6,890.00 0.00 0.00
05.03.09.01 CONEXION DOMICILIARIA DE AGUA POTABLE GLB 1.00 1,640.00 1,640.00 0.00 0.00% 0.00 0.00% 0.00% 1640.00 100.00%
05.03.09.02 SISTEMA DE BIODIGESTOR GLB 1.00 5,250.00 5,250.00 0.00 0.00% 0.00 0.00% 0.00% 5250.00 100.00%
05.04 INSTALACIONES ELÉCTRICAS 2,497.54 0.00
05.04.01 INSTALACIONES ELÉCTRICAS 103.04 0.00 0.00%
05.04.01.01 SALIDA PARA - CENTRO DE LUZ pto 3.00 6.18 18.54 0.00 0.00% 18.54 100.00% 0.00 0.00% 0.00%
05.04.01.02 SALIDA PARA - TOMACORRIENTE pto 2.00 14.38 28.76 0.00 0.00% 28.76 100.00% 0.00 0.00% 0.00%
05.04.01.03 SALIDA PARA - INTERRUPTOR pto 3.00 18.58 55.74 0.00 0.00% 55.74 100.00% 0.00 0.00% 0.00%
05.04.02 CANALIZACION DE TUBERIAS 98.27 0.00 0.00% 0.00
05.04.02.01 TUBERIA ELECTRICA PVC-SEL 3/4" m 14.18 6.93 98.27 0.00 0.00% 98.27 100.00% 0.00 0.00% 0.00%
05.04.03 CONDUCTORES ELECTRICOS Y/O CABLES 41.27 0.00 0.00%
05.04.03.01 CABLE ELECTRICO TW AWG-MCM N° 12 - 4 MM2. m 3.82 2.91 11.12 0.00 0.00% 0.00 0.00% 11.12 100.00% 0.00%
05.04.03.02 CABLE ELECTRICO TW AWG-MCM N° 14 - 4 MM2. m 10.36 2.91 30.15 0.00 0.00% 0.00 0.00% 30.15 100.00% 0.00%
05.04.04 ARTEFACTOS ELECTRICOS 85.14 0.00 0.00%
05.04.04.01 ARTEFACTOS ELECTRICOS FLUORESCENTES und 2.00 42.57 85.14 0.00 0.00% 0.00 0.00% 85.14 100.00% 0.00%
05.04.05 INSTALACIONES ELÉCTRICAS EXTERIORES 2,169.82 0.00%
05.04.05.01 ARTEFACTOS DE ILUMINACION 921.44 0.00%
05.04.05.01.01 INSTALACION DE ACCESORIOS ELECTRICOS REFLECTORES und 6.00 85.24 511.44 0.00 0.00% 0.00 0.00% 0.00% 511.44 100.00%
05.04.05.01.02 INSTALACION ACOMETIDA und 1.00 410.00 410.00 0.00 0.00% 0.00 0.00% 0.00% 410.00 100.00%
05.04.05.02 CARPINTERIA METALICA 1,248.38 0.00%
05.04.05.02.01 POSTES PARA LUMINARIAS und 6.00 171.91 1,031.46 0.00 0.00% 0.00 0.00% 1,031.46 100.00% 0.00%
05.04.05.02.02 TABLERO GENERAL und 1.00 108.46 108.46 0.00 0.00% 0.00 0.00% 108.46 100.00% 0.00%
05.04.05.02.03 TABLERO DE DISTRIBUCION und 1.00 108.46 108.46 0.00 0.00% 0.00 0.00% 108.46 100.00% 0.00%
06 OBRAS EXTERIORES 1,854.32 0.00%
06.01 VEREDAS 768.45 0.00% 0.00% 0.00% 0.00%
06.01.01 CONFORMACION DE BASE GRANULAR E=10CM EN VEREDA m3 1.59 96.18 152.93 0.00 0.00% 0.00 0.00% 152.93 100.00% 0.00%
06.01.02 CONCRETO F'c=175 KG/CM2 EN VEREDA m3 1.59 372.79 592.74 0.00 0.00% 0.00 0.00% 592.74 100.00% 0.00%
06.01.03 ENCOFRADO Y DESENCOFRADO m2 0.80 28.48 22.78 0.00 0.00% 0.00 0.00% 22.78 100.00% 0.00%
06.02 OTROS 1,085.87 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00%
06.02.01 AREA DE CIRCULACION m3 15.17 71.58 1,085.87 0.00 0.00% 0.00 0.00% 0.00% 1085.87 100.00%
07 CERCO PERIMETRICO CON MALLA METALICA 57,958.30
07.01 MOVIMIENTO DE TIERRAS 994.66
07.01.01 EXCAVACION DE ZANJA EN MATERIAL SUELTO m3 19.76 19.78 390.85 390.85 100% 0.00 0.00% 0.00 0.00% 0.00%
07.01.02 EXCAVACION DE SANJA PARA CIMIENTO CORRIDO m3 25.65 19.78 507.36 424.28 83.63% 0.00 0.00% 83.08 16.37% 0.00%
07.01.03 ELIMINACION DE MATERIAL EXCEDENTE D= >1Km m3 54.49 1.77 96.45 87.53 90.75% 0.00 0.00% 8.92 9.25% 0.00%
07.02 OBRAS DE CONCRETO CICLOPEO 19,729.03
07.02.01 NIVELACION Y COMPACTACION DE ZANJA CON EQUIPO LIVIANO m2 44.60 1.88 83.85 83.85 100.00% 0.00 0.00% 0.00 0.00% 0.00%
07.02.02 CONCRETO CICLOPEO F'C=175 kg/cm2 +30% DE PG EN CIMIENTO m3 25.65 219.07 5,619.15 4,699.05 83.63% 920.09 16.37% 0.00 0.00% 0.00%
CRONOGRAMA ACTUALIZADO VALORIZADO DE OBRA
“CREACION DEL SERVICIO DEL COMPLEJO DEPORTIVO EN EL BARRIO DE PATACANCHA DISTRITO DE HUACHOCOLPA - PROVINCIA DE HUANCAVELICA - DEPARTAMENTO
DE HUANCAVELICA "
ENTIDAD
MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA COSTO DIRECTO DEL PROYECTO S/ 236,255.22 DISTRITO : HUACHOCOLPA
EJECUTORA
MODALIDAD DE
CONTRATA PLAZO DE EJECUCION 80 DIAS CALENDARIOS PROVINCIA : HUACHOCOLPA
EJECUCION
AVANCES
PRESUPUESTO
ITEM DESCRIPCION JUNIO JULIO AGOSTO SETIEMBRE
Und. Metrado Precio (S/.) Parcial (S/.) 10 DIAS 31 DIAS 31 DIAS 8 DIAS
07.02.03 CONCRETO CICLOPEO F'C=175 kg/cm2 +30% DE PG EN PLANTILL m3 39.12 219.07 8,570.02 4,604.85 53.73% 3,965.17 46.27% 0.00 0.00% 0.00%
07.02.04 ENCOFRADO Y DESENCOFRADO NORMAL m2 123.55 41.76 5,159.45 2,405.38 46.62% 2,754.07 53.38% 0.00 0.00% 0.00%
07.02.05 RELLENO CON MATERIAL PROPIO COMPACTADO POR CAPAS m3 19.85 14.94 296.56 0.00 0.00% 296.56 100.00% 0.00 0.00% 0.00%
07.03 OTROS 198.72
07.03.01 TUBERIA PVC SAL DE 3" PARA LLORONES m 54.00 3.68 198.72 0.00 0% 198.72 100.00% 0.00 0.00% 0.00%
7.04 ARQUITECTURA 32,949.61
07.04.01 CARPINTERIA METALICA 30,648.17
07.04.01.01 MALLA METÁLICA EN LOSA DEPORTIVA (OLIMPICA) 2*2 m2 207.14 95.71 19,825.37 0.00 0% 0.00 0.00% 19,825.37 100.00% 0.00%
07.04.01.02 TUBO NEGRO DE 2" X 2MM PARANTE m 194.90 55.53 10,822.80 0.00 0% 2,998.62 27.71% 7,824.18 72.29% 0.00%
07.04.02 PINTURA 608.90
07.04.02.01 PINTURA ESMALTE ANTICORROSIVO EN CERCO METALICO m2 90.88 6.70 608.90 0.00 0% 0.00 0.00% 608.90 100.00% 0.00%
07.04.03 VARIOS 1,692.54
07.04.03.01 ENMALLADO DE GRASS SINTETICO CON NYLON m2 275.21 6.15 1,692.54 0.00 0% 0.00 0.00% 1,692.54 100.00% 0.00%
07.04 PORTAL DE INGRESO 4,086.28
07.04.01 MOVIMIENTO DE TIERRAS 18.20 0.00
07.04.01.01 EXCAVACION MANUAL PARA ZAPATAS m3 0.92 19.78 18.20 0.00 0% 18.20 100.00% 0.00 0.00% 0.00%
07.04.02 OBRAS DE CONCRETO SIMPLE 5.16
07.04.02.01 SOLADO E= 10CM (f'c=140kg/cm2 m2 0.23 22.42 5.16 0.00 0% 5.16 100.00% 0.00 0.00% 0.00%
07.04.03 OBRAS DE CONCRETO ARMADO 1,381.35
07.04.03.01 CONCRETO PARA ZAPATAS F'C=210 KG/CM2 m3 1.02 393.08 400.94 0.00 0% 400.94 100.00% 0.00 0.00% 0.00%
07.04.03.02 ACERO CORR. GRADO 60 F´y=4200Kg/cm2 EN ZAPATAS kg 13.90 4.17 57.96 0.00 0% 57.96 100.00% 0.00 0.00% 0.00%
07.04.03.03 CONCRETO EN COLUMNAS f'c=210 kg/cm2. m3 0.88 393.08 345.91 0.00 0% 345.91 100.00% 0.00 0.00% 0.00%
07.04.03.04 ACERO CORR. GRADO 60 F´y=4200Kg/cm2 EN COLUMNAS kg 52.75 4.17 219.97 0.00 0% 219.97 100.00% 0.00 0.00% 0.00%
07.04.03.05 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS. m2 12.52 28.48 356.57 0.00 0% 356.57 100.00% 0.00 0.00% 0.00%
07.04.04 REVOQUES ENLUCIDOS Y MOLDURAS 525.91
07.04.04.01 TARRAJEO DE SUPERFICIE DE COLUMNAS m2 13.44 39.13 525.91 0.00 0% 0.00 0.00% 525.91 100.00% 0.00%
07.04.05 CARPINTERIA METALICA 1,666.88
07.04.05.01 TUBO NEGRO CUADRADO DE 2" X3" X 2MM m 5.00 39.53 197.65 0.00 0% 0.00 0.00% 197.65 100.00% 0.00%
07.04.05.02 TUBO NEGRO CUADRADO DE 2" X 2" X 2MM m 14.68 39.53 580.30 0.00 0% 0.00 0.00% 580.30 100.00% 0.00%
07.04.05.03 TUBO NEGRO CUADRADO DE 1" X 1" X 1.5MM m 28.80 27.23 784.22 0.00 0% 0.00 0.00% 784.22 100.00% 0.00%
07.04.05.04 PLANCHA DE F°G° E=2MM und 0.94 111.39 104.71 0.00 0% 0.00 0.00% 104.71 100.00% 0.00%
07.04.06 PINTURA 488.78
07.04.06.01 PINTURA ESMALTE ANTICORROSIVO EN PUERTA DE INGRESO GLB 1.00 488.78 488.78 0.00 0% 0.00% 488.78 100.00% 0.00%
08 FLETE 5,612.83
08.01 FLETE TERRESTRE GLB 1.00 5,612.83 5,612.83 5612.83 100% 0.00 0.00% 0.00 0.00% 0.00%
09 OTROS 820.00
09.01 TACHOS ECOLOGICOS 820.00 0.00 0.00% 0.00 0.00% 0.00%
09.01.01 INSTALACION DE TACHOS ECOLOGICOS DE TRES UNIDADES und 2.00 410.00 820.00 820.00 100% 0.00 0.00% 0.00 0.00% 0.00%
10 CAPACITACION SEGURIDAD Y SALUD EN EL TRABAJO 820.00
10.01 TALLER DE CAPACITACION A LA POBLACION GLB 1.00 410.00 410.00 0.00 0% 0.00 0.00% 0.00 0.00% 410.00 100.00%
10.02 ELABORACION DE PLAN DE SEGURIDAD Y SALUD GLB 1.00 410.00 410.00 410.00 100% 0.00 0.00% 0.00% 0.00%
11 ESTUDIO DE IMPACTO AMBIENTAL 2,463.86
CRONOGRAMA ACTUALIZADO VALORIZADO DE OBRA
“CREACION DEL SERVICIO DEL COMPLEJO DEPORTIVO EN EL BARRIO DE PATACANCHA DISTRITO DE HUACHOCOLPA - PROVINCIA DE HUANCAVELICA - DEPARTAMENTO
DE HUANCAVELICA "
ENTIDAD
MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA COSTO DIRECTO DEL PROYECTO S/ 236,255.22 DISTRITO : HUACHOCOLPA
EJECUTORA
MODALIDAD DE
CONTRATA PLAZO DE EJECUCION 80 DIAS CALENDARIOS PROVINCIA : HUACHOCOLPA
EJECUCION
AVANCES
PRESUPUESTO
ITEM DESCRIPCION JUNIO JULIO AGOSTO SETIEMBRE
Und. Metrado Precio (S/.) Parcial (S/.) 10 DIAS 31 DIAS 31 DIAS 8 DIAS
11.01 INSTALACION DE CONTENEDORES DE RESIDUOS SÓLIDOS und 1.00 1,066.42 1,066.42 1066.42 100% 0.00 0.00% 0.00 0.00% 0.00%
11.02 INSTALACION PROVISIONAL DE SERVICIOS HIGIENICOS und 2.00 82.00 164.00 164.00 100% 0.00 0.00% 0.00 0.00% 0.00%
11.03 CONSTRUCCION DE MICRORELLENO SANITARIO und 1.00 1,233.44 1,233.44 1233.44 100% 0.00 0.00% 0.00 0.00% 0.00%
% AVANCE EJECUTADO MENSUAL 45,728.19 13.70% 99,383.49 29.77% 175,534.04 52.59% 13149.93 3.94%
% AVANCE EJECUTADO ACUMULADO 45,728.19 13.70% 145,111.68 43.47% 320,645.72 96.06% 333,795.65 100.00%
ITEM DESCRIPCIÓN PARCIAL (S/.)
01 OBRAS EXTERIORES 1,244,181.57
02 CAMPO DEPORTIVO 913,953.88
03 CAFETIN 207,096.47
04 SERVICIO HIGIENICO 147,116.41
05 PORTADA DE INGRESO 145,724.56
06 CERCO PERIMETRICO 171,353.60
07 MUROS DE CONTENCION 613,568.92
08 TANQUE BIODIGESTOR DE 3000LTS 34,669.94
09 SISTEMA DE DRENAJE 150,511.00
10 TANQUE ELEVADO Y TANQUE CISTERNA 66,376.34
11 JUEGOS INFANTILES 41,450.00
TOTAL PRESUPUESTO 3,736,002.69
Recurso Unidad Cantidad Precio S/. Parcial S/.
MANO DE OBRA
CAPACITACION Y ASESORAMIENTO TECNICO EN USO DE EQUIPOS Y MOD MOD 1.0000 2,500.00 2,500.00
MATERIALES
PUERTA DE VIDRIO TEMPLADO 10mm SEGUN DISEÑO INCL. INSTALACION m2 28.7800 420.00 12,087.60
INODORO TQUE. BAJO NORMAL COLOR C/A. und 9.0000 261.00 2,349.00
SALIDA DE DUCHA ESPAÑOLA CON BRAZO CROMADO und 4.0000 89.00 356.00
LUZ AMBAR INTERMITENTE DE INSTALACION PROVISIONAL DE OBRA und 4.0000 12.72 50.88
CAJA DE PASE GALVANIZADA DE 4" X 4" X 2 1/2" pza 16.0000 14.35 229.60
CAJA RECTANGULAR GALVANIZADA DE 4" X 2 1/4" X 2 1/2" und 18.0000 9.18 165.24
CAJA RECTANGULAR DE PVC 4" x 2" x 2" und 14.0000 1.50 21.00
LAMPARA DE EMERGENCIA 7.5W 72LEDS (LD72SMD-ECO) HAGROY und 3.0000 126.00 378.00
PERFORMANCE, 4000K WT (INCLUYE EQUIPO COMPLETO CON ACCESORIOS) und 5.0000 559.20 2,796.00
TABLERO DE DISTRIB. METALICO DE 4 CIRCUITOS C/BARRA COBRE und 1.0000 27.90 27.90
LADRILLO KING KONG 18 HUECOS 9 X 12.5 X 23.2 cm und 7,719.7000 1.20 9,263.64
BANDA DE ADVERTENCIA DE PELIGRO DE MATERIAL PLASTICO REFLECTIVA rll 50.0000 10.50 525.00
MALLA FAENA, ROLLO DE 50YD 1M. (MALLA PROTECTORA DE SEGURIDAD). rll 2.0000 36.36 72.72
ARCO METALICO PARA FUTSAL SEGUN DISEÑO INCL. INSTALACION und 4.0000 1,250.00 5,000.00
POSTES DE VOLEY CON RED SEGUN DISEÑO INCL. INSTALACION und 1.0000 780.00 780.00
ESTRUCTURA METALICA PARA BASQUET SEGUN DISEÑO INCL. INSTALACION und 2.0000 18,500.00 37,000.00
FLETE TERRESTRE POR VIAJE (IDA Y VUELTA) GLB 3.0000 1,200.00 3,600.00
PAGO DE DERECHO DE CONEXION Y RECONEXCION DE SERVICIO DE AGUA Glb 1.0000 1,250.00 1,250.00
PAGO POR CONSUMO DE SERVICIO DE ENERGIA ELECTRICA Glb 7.0000 560.00 3,920.00
PAGO DE DERECHO DE CONEXION TRIFASICA DE SERVICIO DE ENERGIA ELECTRICA Glb 1.0000 1,600.00 1,600.00
PAGO POR DERECHO DE CONEXION MONOFASICO DE SERVICIO DE ENERGIA Glb 1.0000 3,200.00 3,200.00
ELECTRICA
GASOLINA 84 OCTANOS gln 4.9965 14.50 72.45
COBERTURA DE POLICARBONATO CON PERFIL GRAN ONDA E=1.00mm (transparentes) und 109.2873 155.00 16,939.53
TACHOS DE BASURA SEGUN DISEÑO INCL. INSTALACION und 20.0000 150.00 3,000.00
VENTANA SISTEMA PROYECTANTE SEGUN DISEÑO INCL. INSTALACION m2 3.0975 275.00 851.81
VENTANA SISTEMA VITROVEN TIPO PERSIANA SEGUN DISEÑO m2 5.5440 210.00 1,164.24
TABIQUERIA DE MELAMINA CON ESTRUCTURA DE ALUMINIO SEGUN DISEÑO INCL. m2 23.1525 80.00 1,852.20
INSTALACION
VENTANA FLOTANTE CON MARCO DE ALUMINIO SEGUN DISEÑO INCL. INSTALACION m2 2.4800 275.00 682.00
CARTEL DE OBRA METALICO DE 4.40M X 5.60M INCL .INSTALACION Y TRANSP und 1.0000 750.00 750.00
SUMINISTRO E INSTALACION DE POSTES PARA REFLECTORES 9.5M GLB 14.0000 2,500.00 35,000.00
CLOSET DE MELAMINA Y MADERA SEGUN DISEÑO INCL. INST. und 2.0000 1,000.00 2,000.00
PUERTA APANELADA DE MADERA DE TORNILLO SEGUN DISEÑO INC INST m2 21.6300 250.00 5,407.50
GAVION TIPO CAJA DE MALLA DOBLE TORSION (TIPO "A" 5.00x1.50x1.00m) und 180.5100 125.00 22,563.75
GAVION TIPO CAJA DE MALLA DOBLE TORSION (TIPO "B" 5.00x1.00x1.00m) und 180.5100 100.00 18,051.00
GAVION TIPO COLCHON DOBLE TORSION (TIPO "C" 2.00x0..3x5.00m) und 180.5100 271.50 49,008.47
TAPA C/MARCO Fº Fº PARA DESAGUE DE 12" X 24" pza 1.0000 36.00 36.00
PUERTA METALICA EN PORTADA DE INGRESO SEGUN DISEÑO INCL INSTALACION m2 20.0000 350.00 7,000.00
PUERTA METALICA EN CERCO PERIMETRICO SEGUN DISEÑO INCL INSTALACION m2 21.6000 220.00 4,752.00
TEJA ANDINA ETERNIT DE 72 X 114 CM. E=5 MM. pza 193.4790 30.00 5,804.37
TAPON MACHO DE PVC SAP CL-10 D= 1 1/2" und 1.0000 1.90 1.90
TIRAFON 4" CON ARANDELA Y TAPA DE PLASTICO und 2,167.8000 1.00 2,167.80
TUB. PVC SAP PRESION P/AGUA C-10 R. 1/2" m 230.9055 8.00 1,847.24
TUB. PVC SAP PRESION P/AGUA C-10 R. 3/4" m 75.2850 14.00 1,053.99
TEE PVC SAP DE 1/2" PARA AGUA und 31.0000 3.90 120.90
TEE PVC SAP DE 1 1/2" PARA AGUA und 2.0000 13.70 27.40
TUB. PVC SEL P/INST. ELECT. DE 3/4" x 3 MTS. pza 24.3000 4.20 102.06
CODO PVC SAP 1 1/2" PARA AGUA und 6.0000 11.90 71.40
TUB. PVC SAL P/DESAGUE DE 2" X 3 MTS. und 6.1650 12.90 79.53
REDUCCION PVC-SAP DE 3/4" A 1/2" PARA AGUA pza 8.0000 3.00 24.00
RAMAL TEE SIMPLE PVC SAL DE 2" und 4.8700 5.80 28.25
CURVA PVC SEL P/INST. ELECT 3/4" und 62.0000 1.00 62.00
TAPON CEBADO DE PVC DE 1 1/2" PARA AGUA und 2.0000 8.60 17.20
CODO PVC-SAP 1/2" x 90° PARA AGUA pza 155.0000 1.00 155.00
CODO PVC-SAP 3/4" x 90° PARA AGUA pza 9.0000 1.80 16.20
CAJA OCTOGONAL PVC DE 4" X 4" X 2 1/2" pza 51.0000 1.50 76.50
CURVA PVC SAP P/INST. ELECTRICAS DE 3/4" pza 21.0000 2.50 52.50
CURVA PVC SAP P/INST. ELECTRICAS DE 1" pza 15.0000 1.00 15.00
VALVULA DE CONTROL DE BRONCE UNION ROSCADA DE 2"" pza 1.0000 155.90 155.90
VALVULA DE AIRE B.B. DOBLE ESFERA DE 2" und 1.0000 33.90 33.90
EQUIPOS
BOMBA CENTRIFUGA 1.1/2" X 1" 1.5HP 220V MONOFASICA pza 1.0000 1,200.00 1,200.00
SUBCONTRATOS
109,671.21
3,736,184.59
CUADRO DE NECESIDAD DE PERSONAL POR M
PERSONAL
INGRESE DATOS REQUERID MAN
O POR
HORAS DIA 8 CANTIDAD M1 M2
PERIODO
HH PERSONA PERSONA
DIAS DE EJECUCION 30 DE % %
L L
OPERADOR DE EQUIPO L HH 31.35 EJECUCION
1 1 100.00% 0.00%
OPERADOR DE EQUIPO P HH 99.80 1 1 100.00% 0.00%
TOPOGRAFO HH 13.80 1 1 100.00% 0.00%
OPERARIO HH 20,272.95 85 10 11.76% 10 11.76%
OFICIAL HH 10,396.12 44 6 13.64% 6 13.64%
PEON HH 31,797.31 133 30 22.56% 30 22.56%
265 49 18.49% 46 17.36%
6/21/2022
8/19/2022
DE PERSONAL POR MES
M3 M4 M5 M6
PERSONA PERSONA PERSONA PERSONA
% % % %
L L L L
0.00% 0.00% 0.00% 0.00% 1 0
0.00% 0.00% 0.00% 0.00% 1 0
0.00% 0.00% 0.00% 0.00% 1 0
15 17.65% 16 18.82% 17 20.00% 17 20.00% 85 0
6 13.64% 6 13.64% 10 22.73% 10 22.73% 44 0
30 22.56% 20 15.04% 12 9.02% 11 8.27% 133 0
51 19.25% 42 15.85% 39 14.72% 38 14.34% 265
CUADRO DE REQUERIMIENTO DE PERSONAL POR MES