CRONOGRAMA DE AVANCE FISICO Y FINANCIERO

PROY: "CREACION DEL CAMPO DEPORTIVO DE GRASS SINTETICO EN LA LOCALIDAD DE CRUZPATA DEL DISTRITO DE IHUAYLLO, PROVINCIA DE AYMARAES, REGION APURIMAC"

FECHA: MAYO DEL 2023 AÑO 2023


MES 1 JUNIO MES 2 - JULIO MES 3 - AGOSTO

METRADO COSTO METRADO COSTO METRADO COSTO


Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) AVANCE % AVANCE % AVANCE % COSTO TOTAL
PARCIAL MENSUAL PARCIAL MENSUAL PARCIAL MENSUAL
1 OBRAS PROVISIONALES 4,783.35
1.01 TRABAJOS PRELIMINARES 3,512.16
1.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m (GIGANTOGRAu 1.00 744.15 744.15 100.00% 1.00 744.15 0.00% - - 0.00% - - 744.15 100%
1.01.02 LIMPIEZA DE TERRENO MANUAL m2 1,250.00 0.16 200.00 100.00% 1,250.00 200.00 0.00% - - 0.00% - - 200.00 100%
1.01.03 TRAZO NIVELES Y REPLANTEO m2 125.00 3.70 462.50 100.00% 125.00 462.50 0.00% - - 0.00% - - 462.50 100%
1.01.04 ALQUILER DE ALMACEN Y OFICINA mes 3.00 211.86 635.58 100.00% 3.00 635.58 0.00% - - 0.00% - - 635.58 100%
1.01.05 EQUIPAMIENTO DE PROTECCION PERSONAL u 1.00 1,016.94 1,016.94 100.00% 1.00 1,016.94 1,016.94 100%
1.01.06 EMERGENCIA SANITARIA COVID-19 BASICO glb 1.00 452.99 452.99 100.00% 1.00 452.99 452.99 100%
1.02 MOVILIZACION Y DESMOVILIZACIÓN 1,271.19
1.02.01 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIAS Y EQUIPOS glb 1.00 1,271.19 1,271.19 100.00% 1.00 1,271.19 0.00% - - 0.00% - - 1,271.19 100%
2 AREA DEPORTIVA 257,359.59
2.01 MOVIMIENTO DE TIERRAS 17,017.95
2.01.01 CORTE DE TERRENO NORMAL CON MAQUINARIA m3 393.14 14.74 5,794.88 100.00% 393.14 5,794.88 0.00% - - 0.00% - - 5,794.88 100%
2.01.02 REFINE, NIVELACION Y COMPACTACIÓN DE BASES m2 781.24 3.13 2,445.28 100.00% 781.24 2,445.28 0.00% - - 0.00% - - 2,445.28 100%
2.01.03 BASE GRANULAR COMPACTADO e=0.10M AL 95% PROCTOR MODIFICADOm2 676.40 7.00 4,734.80 100.00% 676.40 4,734.80 0.00% - - 0.00% - - 4,734.80 100%
2.01.04 ELIMINACION
OBRAS DE MATERIAL
DE CONCRETO EXCEDENTE CON EQUIPO D>100 m
SIMPLE m3 471.76 8.57 4,042.98 100.00% 471.76 4,042.98 0.00% - - 0.00% - - 4,042.98 100%
2.02 2,169.51
2.02.01 CONCRETO f'c=100 kg/cm2 h=4" PARA SOLADOS m3 3.11 424.40 1,319.88 100.00% 3.11 1,319.88 0.00% - - 0.00% - - 1,319.88 100%
2.02.02 CONCRETO f'c=140 kg/cm2 PARA SARDINEL m3 1.30 388.66 505.26 100.00% 1.30 505.26 0.00% - - 0.00% - - 505.26 100%
2.02.03 ENCOFRADO
OBRAS Y DESENCOFRADO
DE CONCRETO ARMADO NORMAL EN SARDINELES m2 13.00 26.49 344.37 100.00% 13.00 344.37 0.00% - - 0.00% - - 344.37 100%
2.03 177,652.53
2.03.01 ZAPATAS 7,159.51
2.03.01.01 CONCRETO EN ZAPATAS f'c=210 kg/cm2 m3 12.42 413.48 5,135.42 100.00% 12.42 5,135.42 0.00% - - 0.00% - - 5,135.42 100%
2.03.01.02 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 334.56 6.05 2,024.09 100.00% 334.56 2,024.09 0.00% - - 0.00% - - 2,024.09 100%
2.03.02 COLUMNAS 4,364.84
2.03.02.01 CONCRETO f'c=210 kg/cm2 PARA COLUMNAS m3 2.94 483.39 1,421.17 100.00% 2.94 1,421.17 0.00% - - 0.00% - - 1,421.17 100%
2.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 16.80 45.23 759.86 100.00% 16.80 759.86 0.00% - - 0.00% - - 759.86 100%
2.03.02.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 360.96 6.05 2,183.81 100.00% 360.96 2,183.81 0.00% - - 0.00% - - 2,183.81 100%
2.03.03 CARPINTERIA METALICA Y COBERTURA 166,128.18
2.03.03.01 COLUMNA TUB. METALICA CIRC. SCHEDULE 40 Ø 6" x E= 7.11 mm. H=6 u 20.00 2,295.36 45,907.20 50.00% 10.00 22,953.60 50.00% 10.00 22,953.60 0.00% - - 45,907.20 100%
2.03.03.02 VIGA ARCO METALICO L=26.42 m. F=5.0 m. SUM. E INSTAL. u 10.00 5,270.08 52,700.80 50.00% 5.00 26,350.40 50.00% 5.00 26,350.40 0.00% - - 52,700.80 100%
2.03.03.03 VIGA DE AMARRE TIPO CERCHA METALICO H=0.50m. SUM. E INSTAL. m 64.80 73.77 4,780.30 0.00% - - 100.00% 64.80 4,780.30 0.00% - - 4,780.30 100%
2.03.03.04 CORREAS METALICAS CON TUBO RECTANGULAR 40mmX60mm e=2 mm m 907.20 25.37 23,015.66 0.00% - - 100.00% 907.20 23,015.66 0.00% - - 23,015.66 100%
2.03.03.05 COBERTURA DE TECHO CON CALAMINON TIPO TRAPEZOIDAL CURVO L= m2 899.76 37.18 33,453.08 0.00% - - 100.00% 899.76 33,453.08 33,453.08 100%
2.03.03.06 CANALETA PARA AGUAS DE LLUVIA PLANCHA 1/32" INCLUYE SOPORTEm 115.60 47.14 5,449.38 0.00% - - 0.00% - - 100.00% 115.60 5,449.38 5,449.38 100%
2.03.03.07 TEMPLADORES CON FIERRO LISO DE 3/8" Y TENSOR TIPO BOA DE 3/8" m 48.00 17.12 821.76 100.00% 48.00 821.76 821.76 100%
2.04 52,984.31
2.04.01 SUMINISTRO Y TENDIDO DE ARENA FINA E=5 CM m2 676.40 7.21 4,876.84 0.00% - - 0.00% - - 100.00% 676.40 4,876.84 4,876.84 100%
2.04.02 SUMINISTRO E INSTALACION DE GRASS SINTETICO FRANJEADO 50 MM, 1m2 676.40 59.62 40,326.97 0.00% - - 0.00% - - 100.00% 676.40 40,326.97 40,326.97 100%
2.04.03 MALLA SINTETICA ATRAPA BOLAS m2 1,436.21 3.49 5,012.37 0.00% - - 0.00% - - 100.00% 1,436.21 5,012.37 5,012.37 100%
2.04.04 EQUIPAMIENTO PARA LOSA m2 1.00 1,076.27 1,076.27 0.00% - - 0.00% - - 100.00% 1.00 1,076.27 1,076.27 100%
2.04.05 ARCO DE FULBITO CON RED
DRENAJES u 2.00 845.93 1,691.86 0.00% - - 0.00% - - 100.00% 2.00 1,691.86 1,691.86 100%
2.05 3,719.93
2.05.01 EXCAVACION MANUAL EN TERRENO COMPACTO m3 10.20 24.72 252.14 0.00% - - 0.00% - - 100.00% 10.20 252.14 252.14 100%
2.05.02 TUBERIA MONTANTE DE PVC SAL 4" INCL. ACCESORIOS u 4.00 204.85 819.40 0.00% - - 0.00% - - 100.00% 4.00 819.40 819.40 100%
2.05.03 DRENAJE CON TUBERIA Ø 160 mm. CRIBADO Y GRAVA DE 1/4" A 3/4" INC m 46.00 53.12 2,443.52 0.00% - - 0.00% - - 100.00% 46.00 2,443.52 2,443.52 100%
2.05.04 ELIMINACION DE MATERIAL EXCEDENTE D= 30m. m3 13.26 15.45 204.87 0.00% - - 0.00% - - 100.00% 13.26 204.87 204.87 100%
2.06 INSTALACIONES ELECTRICAS Y REFLECTORES 3,815.36
2.06.01 CABLE ELECTRICO
REFLECTOR DE 100THW-90
WATTS 12 AWG m 87.00 5.93 515.91 0.00% - - 0.00% - - 100.00% 87.00 515.91 515.91 100%
2.06.02 u 8.00 294.37 2,354.96 0.00% - - 0.00% - - 100.00% 8.00 2,354.96 2,354.96 100%
2.06.03 CIRCUITO Y TABLERO Y MEDIDOR ELECTRICO SUM. E INSTAL. jgo 1.00 944.49 944.49 0.00% - - 0.00% - - 100.00% 1.00 944.49 944.49 100%
3 CERCO PERIMETRICO 16,243.43
3.01 MOVIMIENTO DE TIERRAS 158.52
3.01.01 EXCAVACION DE ZANJA EN TERRENO COMPACTO m3 3.60 24.72 88.99 0.00% - - 0.00% - - 100.00% 3.60 88.99 88.99 100%
3.01.02 ELIMINACION
OBRAS DE MATERIAL
DE CONCRETO SIMPLEEXCEDENTE D= 30m.
EN SARDINEL m3 4.50 15.45 69.53 0.00% - - 0.00% - - 100.00% 4.50 69.53 69.53 100%
3.02 1,435.15
3.02.01 CONCRETO 1:8+25% PM EN SARDINEL m3 4.80 254.84 1,223.23 0.00% - - 0.00% - - 100.00% 4.80 1,223.23 1,223.23 100%
3.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN SARDINELES m2 8.00 26.49 211.92 0.00% - - 0.00% - - 100.00% 8.00 211.92 211.92 100%
3.03 CERCO DE MALLA METALICA 14,649.76
3.03.01 CERCO DE MALLA METALICA POSTE Fº.N°. DE 2" C/MALLA Nº10 COCOS DEm 40.00 325.92 13,036.80 0.00% - - 0.00% - - 100.00% 40.00 13,036.80 13,036.80 100%
3.03.02 PUERTA C/MARCO DE TUBO F°.GVZDO DE 2" C/MALLA N°10 COCOS DE 2" u 1.00 1,155.36 1,155.36 0.00% - - 0.00% - - 100.00% 1.00 1,155.36 1,155.36 100%
3.03.03 PINTURA ESMALTE EN ESTRUCTURAS METALICAS m2 80.00 5.72 457.60 0.00% - - 0.00% - - 100.00% 80.00 457.60 457.60 100%
4 TRIBUNAS (GRADERIAS) 4,846.43
4.01 MOVIMIENTO DE TIERRAS 174.37
4.01.01 EXCAVACION MANUAL EN TERRENO COMPACTO m3 3.96 24.72 97.89 0.00% - - 0.00% - - 100.00% 3.96 97.89 97.89 100%
4.01.02 ELIMINACION DE MATERIAL EXCEDENTE D= 30m. m3 4.95 15.45 76.48 0.00% - - 0.00% - - 100.00% 4.95 76.48 76.48 100%
4.02 CONCRETO SIMPLE 3,882.18
4.02.01 ENCOFRADO Y DESENCOFRADO NORMAL EN GRADERIAS m2 14.70 40.39 593.73 0.00% - - 0.00% - - 100.00% 14.70 593.73 593.73 100%
4.02.02 CONCRETO 1:8 + 30% PG EN GRADERIAS m3 15.18 216.63 3,288.44 0.00% - - 0.00% - - 100.00% 15.18 3,288.44 3,288.44 100%
4.03 REVOQUES Y ENLUCIDOS 509.78
4.03.01 TARRAJEO EN EXTERIORES ACABADO CON CEMENTO-ARENA m2 26.40 19.31 509.78 0.00% - - 0.00% - - 100.00% 26.40 509.78 509.78 100%
4.04 PINTURA 280.10
4.04.01 PINTURA ESMALTE EN EXTERIORES m2 26.40 10.61 280.10 0.00% - - 0.00% - - 100.00% 26.40 280.10 280.10 100%
5 PRUEBAS DE ENSAYO DE LABORATORIOS 762.70
5.01 Diseño de Mezcla u 2.00 254.24 508.48 100.00% 2.00 508.48 0.00% - - 0.00% - - 508.48 100%
5.02 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) u 6.00 42.37 254.22 50.00% 3.00 127.11 50.00% 3.00 127.11 0.00% - - 254.22 100%
6 FLETE 2,542.37
6.01 FLETE TERRESTRE glb 1.00 2,542.37 2,542.37 100.00% 1.00 2,542.37 0.00% - - 0.00% - - 2,542.37 100%
7 IMPACTO AMBIENTAL 1,016.95
7.01 MITIGACION DE IMPACTO AMBIENTAL glb 1.00 1,016.95 1,016.95 100.00% 1.00 1,016.95 0.00% - - 0.00% - - 1,016.95 100%

COSTO DIRECTO 287,556.80 88,994.07 110,680.15 87,880.61 287,554.83 100%


GASTOS GENERALES 13.00% 37,382.38 11,569.23 14,388.42 11,424.48 37,382.38 100%
UTILIDAD 10.00% 28,755.68 8,899.41 11,068.01 8,788.06 28,755.68 100%
SUB TOTAL 353,694.86 109,462.70 136,136.58 108,093.15 353,694.86 100%
IMPUESTO IGV 18% 18.00% 63,665.07 19,703.29 24,504.58 19,456.77 63,665.07
LIQUIDACIÓN 0.00% - -
============ ============ ============ ============
PRESUPUESTO TOTAL 417,359.93 129,165.99 160,641.16 127,549.92 417,359.93
AVANCE PARCIAL MENSUAL 30.95% 38.49% 30.56%
AVANCE ACUMULADO MENSUAL 30.95% 69.44% 100.00%