CONSTRUCTORA ALPHAFORMA

PROYECTO: APARTAMENTOS

ARQUITECTA: ROSA MARIA RAMOS CHAVEZ


PROPIETARIO:
FECHA:

PRESUPUESTO INTEGRADO
PRECIO
No. DESCRIPCION CANTIDAD UNIDAD TOTAL
UNITARIO
1 PRELIMINARES 190.00 M2 Q 145.78 Q 27,698.00
CIMENTACION
2 ZAPATAS DE 1.30X1.30 T=0.30 19.00 UNIDAD Q 2,094.63 Q 39,798.00
3 VIGA CONECTORA DE CIMENTACION DIMENSIONES DE 0.60X0.30 125.00 ML Q 458.22 Q 57,277.00
4 COLUMNAS ESTRUCTURALES DIMENSIONES DE 0.40X0.40 114.00 ML Q 608.81 Q 69,404.50
5 LEVANTADO DE MUROS 154.00 M2 Q 388.43 Q 59,818.00
6 SOLERA INTERMEDIA DE DIMENSIONES DE 0.20X0.15 55.00 ML Q 201.80 Q 11,099.00
7 SOLERA CORONA DIMENSIONES DE 0.20X0.15 55.00 ML Q 201.80 Q 11,099.00
8 VIGA CON DIMENSIONES DE 0.40X0.20 125.00 ML Q 580.80 Q 72,600.00
9 LOSA TRADICIONAL T=12 190.00 M2 Q 695.34 Q 132,115.50
10 DIMENSIONES DE SISTERNA 2.00X3.00X1.00 CAPACIDAD DE 6,000LT + POZO 2.00 UNIDAD Q 5,170.00 Q 10,340.00
11 CONSCTRUCCION DE POZO 1.00 UNIDAD Q 9,955.00 Q 9,955.00
12 EQUIPO HIDRONEUMATICO 1.00 GLOBAL Q 6,600.00 Q 6,600.00
13 GRADAS T=10 1.00 UNIDAD Q 8,173.00 Q 8,173.00
14 INSTALACIONES DE ILUMINACION 38.00 ML Q 422.40 Q 16,051.20
15 INSTALACIONES DE FUERZA 8.00 ML Q 783.75 Q 6,270.00
16 INSTALACIONES DE HIDRAULICA 1.00 GLOBAL Q 14,135.00 Q 14,135.00
17 INSTALACIONES DE BAPS 1.00 GLOBAL Q 5,403.20 Q 5,403.20
18 INSTALACIONES DE SERVICIO SANITARIO "DRENAJES" 1.00 GLOBAL Q 8,795.60 Q 8,795.60
19 ACABADOS FINALES CERNIDO GRIS 546.00 M2 Q 38.78 Q 21,175.00
20 INSTALACION DE PUERTAS+ PORTON+ VENTANAS 11.85 ML Q 1,152.91 Q 13,662.00
21 PISO + TORTA DE CONCRETO 182.00 M2 Q 174.25 Q 31,713.00
TOTAL PRIMER NIVEL Q 633,182.00

2DO NIVEL
22 LEVANTADO DE MUROS 372.00 M2 Q 236.18 Q 87,859.64
23 COLUMNAS ESTRUCTURALES DIMENSIONES DE 0.40X0.40 114.00 ML Q 608.81 Q 69,404.50
24 SOLERA INTERMEDIA DE DIMENSIONES DE 0.20X0.15 Y DE 0.10X0.20 124.00 ML Q 154.00 Q 19,096.00
25 SOLERA CORONA DIMENSIONES DE 0.20X0.15 124.00 ML Q 191.74 Q 23,775.40
26 VIGA CON DIMENSIONES DE 0.40X0.20 125.00 ML Q 580.80 Q 72,600.00
27 LOSA TRADICIONAL T=12 190.00 M2 Q 695.34 Q 132,115.50
28 GRADAS T=10 1.00 UNIDAD Q 8,173.00 Q 8,173.00
29 INSTALACIONES DE ILUMINACION 37.00 UNIDAD Q 287.90 Q 10,652.40
30 INSTALACIONES DE FUERZA 40.00 UNIDAD Q 222.75 Q 8,910.00
31 INSTALACIONES DE HIDRAULICA 1.00 GLOBAL Q 17,490.00 Q 17,490.00
32 INSTALACIONES DE BAPS 1.00 GLOBAL Q 5,403.20 Q 5,403.20
33 INSTALACIONES DE SERVICIO SANITARIO "DRENAJES" 1.00 GLOBAL Q 5,715.60 Q 5,715.60
34 ACABADOS FINALES 579.00 M2 Q 68.40 Q 39,605.50
35 INSTALACION DE PUERTAS+ PORTON+ VENTANAS 1.00 GLOBAL Q 34,999.25 Q 34,999.25
36 PISO + TORTA DE CONCRETO 190.00 M2 Q 114.28 Q 21,714.00
TOTAL PRIMER NIVEL Q 557,513.99

TOTAL DE APARTAMENTOS Q 1,190,695.99