VALORIZACION Nº 02

(PERIODO : DEL 01 JUNIO - 30 DE JUNIO 2022)

OBRA :
“MEJORAMIENTO Y AMPLIACION DEL SERVICIO EDUCATIVO DE LA II.EE. FE Y ALEGRIA N° 52, SECTOR PAMPA INALAMBRICA DISTRITO DE
ILO, PROVINCIA DE ILO DEPARTAMENTO DE MOQUEGUA” CUI N°2234866
UBICACIÓN : MOQUEGUA - ILO - ILO
SUB CONTRATISTA :
MES VALORIZADO : (PERIODO : DEL 01 JUNIO - 30 DE JUNIO 2022)

VALORIZACION
MONTO CONTRATO % AVANCE SALDO POR
DESCRIPCION
(S/IGV) ANTERIOR ACTUAL ACUMULADO ACUMULADO VALORIZAR

A: VALORIZACION CONTRACTUAL
001 - INFRAESTRUCTURA
1 - OBRAS PRELIMINARES 727,774.66 163,328.84 89,085.65 252,414.49 34.68% 475,360.17
2 - ESTRUCTURAS 6,488,433.84 1,306,622.30 970,005.25 2,276,627.55 35.09% 4,211,806.29
3 - ARQUITECTURA 6,028,098.79 0.00 0.00 0.00 0.00% 6,028,098.79
4 - INSTALACIONES SANITARIAS 809,028.62 0.00 0.00 0.00 0.00% 809,028.62
5 - INSTALACIONES ELECTRICAS Y MECANICAS 1,794,860.54 0.00 38,562.73 38,562.73 2.15% 1,756,297.81
6 - INSTALACIONES DE COMUNICACIONES 282,881.31 0.00 1,698.43 1,698.43 0.60% 281,182.89
7 - INSTALACIONES DE GAS 92,519.04 0.00 0.00 0.00 0.00% 92,519.04
8 - COVID - 19 113,122.11 23,748.51 8,662.40 32,410.91 28.65% 80,711.20

SUB TOTAL PARCIAL (5.1.2.) 16,336,718.90 1,493,699.65 1,108,014.45 2,601,714.10 13,735,004.80

AVANCE FISICO DE OBRA 9.14% 6.78% 15.93% 84.07%

B. DESCUENTOS POR MANO DE OBRA (PLANILLA)


MES DE MARZO 0.00 33,487.89 33,487.89
MES DE ABRIL 0.00 150,639.55 150,639.55
MES DE MAYO 205,857.29 205,857.29
MES DE JUNIO 302,034.09
TOTAL (B) 0.00 389,984.73 302,034.09 389,984.73

C. MATERIALES
MATERIALES MES DE MARZO Y ABRIL (INCLUYE 5% GASTOS LOGISTICOS) 1,796,640.47 1,796,640.47 11.00% 330,804.19
* AMORTIZACION DE ADELANTO EN MATERIALES 893,370.55 573,088.18 1,466,458.73
ENCOFRADO ALSINA (ALQUILER - VENTA) 34,350.24 66,357.47 100,707.71
TOTAL (C) 927,720.79 639,445.65 1,567,166.44 330,804.19

D VALORIZACION NETA VD=VA-(VB+VC) 175,994.13 166,534.71 644,562.93


MONTO A PAGAR AL CONTRATISTA
EN EFECTIVO 175,994.13 166,534.71 342,528.85
EN I.G.V. (18%*VN) 31,678.94 29,976.25 61,655.19
TOTAL (F) 207,673.07 196,510.96 404,184.04

RETENCION DEL 10% (5.2.1.) 10.00% -149,369.97 -110,801.45 -260,171.41

TOTAL COMPROMISO A SOLICITAR 58,303.11 85,709.52 144,012.63

SON : /100 SOLES

NOTA: * 5.3.1.(i) Se descontara en cada valorizacion el mismo porcentaje proporcional al adelanto otorgado, hasta la amortizacion del adelanto
RESUMEN DE MONTO CONTRATADO
(PERIODO : DEL 01 DE JUNIO AL 30 DE JUNIO 2022)

OBRA : “MEJORAMIENTO Y AMPLIACION DEL SERVICIO EDUCATIVO DE LA II.EE. FE Y ALEGRIA N° 52, SECTOR PAMPA INALAMBRICA DISTRITO DE ILO, PROVINCIA DE ILO DEPARTAMENTO DE MOQUEGUA” CUI N°2234866

UBICACIÓN : MOQUEGUA - ILO - ILO


SUB CONTRATISTA :

FECHA : Jun-22

01 INFRAESTRUCTURA

A B C D=A+B+C E F=E+D

GASTOS SUB TOTAL TOTAL PRESUP


FORMULA COSTO DIRECTO UTILIDAD 6 % IMPUESTO (IGV
GENERALES % PRESUP. BASE CONTRATO
18%)

OBRAS PRELIMINARES 637,029.77 52,523.10 38,221.79 727,774.66 130,999.44 858,774.10


ESTRUCTURAS 5,679,402.90 468,266.77 340,764.17 6,488,433.84 1,167,918.09 7,656,351.93
ARQUITECTURA 5,276,466.18 435,044.64 316,587.97 6,028,098.79 1,085,057.78 7,113,156.57
INST. SANITARIAS 708,152.32 58,387.16 42,489.14 809,028.62 145,625.15 954,653.77
INST. ELECTRICAS Y MECANICAS 1,571,062.66 129,534.12 94,263.76 1,794,860.54 323,074.90 2,117,935.43
INST. DE COMUNICAIONES 247,609.36 20,415.39 14,856.56 282,881.31 50,918.64 333,799.95
INST. DE GAS E II.MM. 80,983.01 6,677.05 4,858.98 92,519.04 16,653.43 109,172.47
COVID - 19 99,017.12 8,163.96 5,941.03 113,122.11 20,361.98 133,484.09

SUB TOTALES S/ 14,299,723.31 S/ 1,179,012.19 S/ 857,983.40 S/ 16,336,718.90 S/ 2,940,609.40 S/ 19,277,328.30

RESUMEN DE VALORIZACION N° 02

VALORIZACION ACTUAL

A B C D=A+B+C E F=(1+E)xD
GASTOS SUB TOTAL PRESUP. IMPUESTO (IGV
FORMULA COSTO DIRECTO UTILIDAD TOTALES
GENERALES BASE 18%)

01 INFRAESTRUCTURA
OBRAS PRELIMINARES 77,977.72 6,429.26 4,678.66 89,085.65 0.18 S/ 105,121.06
ESTRUCTURAS 849,057.07 70,004.76 50,943.42 970,005.25 0.18 S/ 1,144,606.19
ARQUITECTURA 0.00 0.00 0.00 0.00 0.18 S/ -
INST. SANITARIAS 0.00 0.00 0.00 0.00 0.18 S/ -
INST. ELECTRICAS Y MECANICAS 33,754.41 2,783.05 2,025.26 38,562.73 0.18 S/ 45,504.02
INST. DE COMUNICAIONES 0.00 983.05 715.38 1,698.43 0.18 S/ 2,004.14
INST. DE GAS E II.MM. 0.00 0.00 0.00 0.00 0.18 S/ -
COVID - 19 7,582.30 625.16 454.94 8,662.40 0.18 S/ 10,221.63

SUB TOTAL 968,371.50 80,825.28 58,817.67 1,108,014.45 S/ 1,108,014.45


IGV S/ 199,442.60
TOTAL S/ 1,307,457.05

RESUMEN DE VALORIZACION N° 01

VALORIZACION ACTUAL

A B C D=A+B+C E F=(1+E)xD
GASTOS SUB TOTAL PRESUP. IMPUESTO (IGV
FORMULA COSTO DIRECTO UTILIDAD TOTALES
GENERALES BASE 18%)

01 INFRAESTRUCTURA
OBRAS PRELIMINARES 142,963.67 11,787.35 8,577.82 163,328.84 0.18 S/ 192,728.03
ESTRUCTURAS 1,143,701.96 94,298.23 68,622.12 1,306,622.30 0.18 S/ 1,541,814.32
ARQUITECTURA 0.00 0.00 0.00 0.00 0.18 S/ -
INST. SANITARIAS 0.00 0.00 0.00 0.00 0.18 S/ -
INST. ELECTRICAS Y MECANICAS 0.00 0.00 0.00 0.00 0.18 S/ -
INST. DE COMUNICAIONES 0.00 0.00 0.00 0.00 0.18 S/ -
INST. DE GAS E II.MM. 0.00 0.00 0.00 0.00 0.18 S/ -
COVID - 19 20,787.35 1,713.92 1,247.24 23,748.51 0.18 S/ 28,023.24

SUB TOTAL 1,307,452.98 107,799.50 78,447.18 1,493,699.65 S/ 1,493,699.65


IGV S/ 268,865.94
TOTAL S/ 1,762,565.59

Resumen Metas Página 2


VALORIZACION DE OBRA Nº 02 OBRAS PRELIMINARES
(PERIODO : DEL 01 DE JUNIO AL 30 DE JUNIO 2022)

OBRA: “MEJORAMIENTO Y AMPLIACION DEL SERVICIO EDUCATIVO DE LA II.EE. FE Y ALEGRIA N° 52, SECTOR PAMPA INALAMBRICA DISTRITO DE ILO, PROVINCIA DE ILO DEPARTAMENTO DE MOQUEGUA” CUI N°2234866
UBICACIÓN: MOQUEGUA - ILO - ILO

AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
UND METRADO PRECIO UNITARIO PARCIAL Metrado Monto Metrado Monto % Metrado Monto % Metrado Monto

I. MODULOS
01 OBRAS PROVISIONALES, TRABAJOS PRELIMINARES , SEGURIDAD Y SALUD

01.01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES


01.01.02 INSTALACIONES PROVISIONALES
01.01.02.01 INSTALACIÓN PROVISIONAL DE AGUA Y DESAGUE__ mes 13.00 1,050.00 13,650.00 2.03 2,135.00 1.00 1,050.00 8.00% 3.03 3,185.00 23.00% 9.97 10,465.00
01.01.02.02 INSTALACION PROVISIONAL DE ENERGIA ELECTRICA Y CONSUMO mes 13.00 1,640.00 21,320.00 2.03 3,334.67 1.00 1,640.00 8.00% 3.03 4,974.67 23.00% 9.97 16,345.33
DURANTE LA OBRA__
01.01.03 TRABAJOS PRELIMINARES
01.01.03.01 LIMPIEZA PERMANENTE EN OBRA mes 13.00 4,200.00 54,600.00 2.03 8,540.00 1.00 4,200.00 8.00% 3.03 12,740.00 23.00% 9.97 41,860.00
01.01.03.02 LIMPIEZA FINAL DE OBRA und 1.00 4,540.67 4,540.67 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,540.67
01.01.04 ELIMINACION DE OBSTRUCCIONES
01.01.04.01 LIMPIEZA DE TERRENO EN ZONAS NO BOSCOSAS ha 1.00 1,008.03 1,008.03 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,008.03
01.01.05 TRANSPORTE VERTICAL Y HORIZONTAL
01.01.05.01 TRANSPORTE HORIZONTAL Y VERTICAL EN OBRA MES 11.00 15,427.12 169,698.32 1.53 23,654.92 1.00 15,427.12 9.00% 2.53 39,082.04 23.00% 8.47 130,616.28
01.01.07 MOVILIZACION Y DESMOBILIZACION
01.01.07.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 9,641.95 9,641.95 0.10 964.20 0.00 0.00% 0.10 964.20 10.00% 0.90 8,677.75
01.01.08 FLETE TERRESTRE
01.01.08.01 FLETE TERRESTRE LIMA A OBRA (ILO-FE ALEGRIA) 30Tn SEMITRAILER vje 2.00 7,380.00 14,760.00 2.00 14,760.00 0.00 0.00% 2.00 14,760.00 100.00% 0.00 0.00
01.01.08.02 FLETE TERRESTRE LIMA A OBRA (ILO-FE ALEGRIA) 10Tn FURGON 40 M3 vje 7.00 820.00 5,740.00 0.00 0.00 1.00 820.00 14.00% 1.00 820.00 14.00% 6.00 4,920.00
01.01.08.03 FLETE TERRESTRE AREQUIPA A OBRA (ILO-FE ALEGRIA) 30Tn vje 23.00 3,280.00 75,440.00 7.00 22,960.00 6.00 19,680.00 26.00% 13.00 42,640.00 57.00% 10.00 32,800.00
SEMITRAILER
01.01.08.04 FLETE TERRESTRE 30Tn SEMITRAILER PARA ALQUILER DE vje 6.00 8,200.00 49,200.00 4.00 32,800.00 2.00 16,400.00 33.00% 6.00 49,200.00 100.00% 0.00 0.00
ENCOFRADOS LIMA-ILO IDA
01.01.08.05 FLETE TERRESTRE 30Tn SEMITRAILER PARA ALQUILER DE vje 6.00 8,200.00 49,200.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 49,200.00
ENCOFRADOS ILO-LIMA RETORNO
01.01.08.06 FLETE TERRESTRE AREQUIPA A OBRA (ILO-FE ALEGRIA) 10Tn FURGON vje 4.00 2,050.00 8,200.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 8,200.00
40 M3
01.01.08.07 FLETE TERRESTRE AREQUIPA A OBRA (ILO-FE ALEGRIA) 5Tn 27 M3 vje 4.00 1,640.00 6,560.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 6,560.00
01.02 SEGURIDAD Y SALUD
01.02.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE glb 1.00 1,230.00 1,230.00 0.20 242.85 0.08 94.62 8.00% 0.27 337.46 27.00% 0.73 892.54
SEGURIDAD Y SALUD EN EL TRABAJO
01.02.02 EQUIPO DE PROTECCION INDIVIDUAL und 428.00 179.00 76,612.00 90.00 16,110.00 52.00 9,308.00 12.00% 142.00 25,418.00 33.00% 286.00 51,194.00
01.02.03 EXAMEN MEDICO OCUPACIONAL (Obreros, Staff) und 413.00 175.00 72,275.00 96.00 16,800.00 52.00 9,100.00 13.00% 148.00 25,900.00 36.00% 265.00 46,375.00
01.02.04 EQUIPO DE PROTECCION COLECTIVA glb 1.00 869.20 869.20 0.20 171.61 0.08 66.86 8.00% 0.27 238.47 27.00% 0.73 630.73
01.02.05 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 733.90 733.90 0.20 144.90 0.08 56.45 8.00% 0.27 201.35 27.00% 0.73 532.55
01.02.06 CAPACITACION EN SEGURIDAD Y SALUD glb 1.00 1,230.00 1,230.00 0.20 242.85 0.08 94.62 8.00% 0.27 337.46 27.00% 0.73 892.54
01.02.07 RECURSOS PARA RESPUESTAS ANTE EMERGENCIA glb 1.00 520.70 520.70 0.20 102.65 0.08 40.05 8.00% 0.27 142.70 27.00% 0.73 378.00
01.03 SERVICIO DE SEGURIDAD Y BIM

COSTO DIRECTO (OBRAS PRELIMINARES) 637,029.77 142,963.67 77,977.72 220,941.33 416,088.42


GASTOS GENERALES % 8.25% 52,523.10 11,787.35 6,429.26 18,216.61 34,306.49
UTILIDAD % 6.00% 38,221.79 8,577.82 4,678.66 13,256.48 24,965.31
SUBTOTAL (OBRAS PROVISIONALES, TRABAJOS PRELIMINARES Y SEGURIDAD Y SALUD) 727,774.66 163,328.84 89,085.65 12.24% 252,414.42 34.68% 475,360.22

Val_Prov Página 3
VALORIZACION DE OBRA Nº 02 ESTRUCTURAS
(PERIODO : DEL 01 DE JUNIO AL 30 DE JUNIO 2022)

OBRA: “MEJORAMIENTO Y AMPLIACION DEL SERVICIO EDUCATIVO DE LA II.EE. FE Y ALEGRIA N° 52, SECTOR PAMPA INALAMBRICA DISTRITO DE ILO, PROVINCIA DE ILO DEPARTAMENTO DE MOQUEGUA” CUI N°2234866
UBICACIÓN: MOQUEGUA - ILO - ILO

AVANCES
PRESUPUESTO
ANTERIOR ACTUAL
ITEM DESCRIPCION DE PARTIDA
UND METRADO PRECIO UNITARIO PARCIAL Metrado Monto Metrado Monto

I. MODULOS
02 ESTRUCTURAS
02.02 CONCRETO SIMPLE
02.02.01 CONCRETO f'c=100 kg/cm2 EN SOLADOS TIPO HS e=10 Cm. m2 2,189.12 33.02 72,284.74 1,063.37 35,112.48 533.52 17,616.83
02.02.02 CONCRETO SOBRECIMIENTOS MEZCLA 1:8 (100 kg/cm2)+ 20% P.M. m3 156.35 160.84 25,147.33 21.30 3,425.89 10.69 1,719.38
02.02.03 ENCOFRADO DE SOBRECIMIENTO CORRIDO m2 2,051.25 57.18 117,290.48 284.01 16,239.69 142.48 8,147.01
02.02.04 CONCRETO PARA FALSO PISO f'c= 175 Kg/cm2 TIPO HS, e= 4'' INCLUYE SARDIBEL INVERTIDO m2 3,267.69 40.77 133,223.72 - 0.00 0.00 0.00
02.02.05 CONCRETO PARA LOSA DE CIMENTACION (PATIOS EXTERIORES) f'c= 175 Kg/cm2 TIPO HS, e= 4'' INCLUYE SARDINEL INVERTIDO m2 4,697.86 48.86 229,537.44 - 0.00 0.00 0.00
02.02.06 CONCRETO PARA LOSA DE CIMENTACION (LOSA DEPORTIVA) f'c= 175 Kg/cm2 TIPO HS, e= 4'' INCLUYE SARDINEL INVERTIDO m2 626.05 48.86 30,588.80 - 0.00 0.00 0.00
02.02.07 CONCRETO PARA LOSA DE CIMENTACION (RAMPAS) f'c= 175 Kg/cm2 TIPO HS, e= 4'' INCLUYE SARDINEL INVERTIDO m2 463.55 55.37 25,666.76 - 0.00 0.00 0.00
02.02.08 CONCRETO PARA VEREDA (EXTERIOR) f'c= 175 Kg/cm2 TIPO HS, e= 4'' INCLUYE SARDINEL INVERTIDO m2 1,421.45 52.03 73,958.04 - 0.00 0.00 0.00
02.03 CONCRETO ARMADO
02.03.01 ZAPATAS
02.03.01.01 CONCRETO PREMEZCLADO F'C=315 KG/CM2 ZAPATAS__ m3 1,067.54 351.17 374,888.02 517.61 181,769.10 141.92 49,838.05
02.03.01.02 ENCOFRADO Y DESENCOFRADO NORMAL ZAPATAS m2 1,264.98 61.25 77,480.03 844.46 51,723.18 117.89 7,220.76
02.03.01.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 61,404.78 4.60 282,461.99 50,517.74 232,381.60 3,509.05 16,141.63
02.03.02 VIGAS DE CIMENTACION
02.03.02.01 CONCRETO EN VIGAS DE CIMENTACION f'c=315 kg/cm2 Tipo HS m3 143.03 371.02 53,066.99 110.01 40,815.91 26.70 9,906.23
02.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL VIGAS DE CIMENTACION m2 484.74 57.18 27,717.43 392.26 22,429.43 88.74 5,074.15
02.03.02.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 11,277.05 4.60 51,874.43 10,723.02 49,325.89 472.33 2,172.72
02.03.03 SOBRECIMIENTO REFORZADO
02.03.03.01 CONCRETO SOBRECIMIENTO REFORZADO f'c=315 kg/cm2 Tipo HS m3 17.27 378.36 6,534.28 4.26 1,611.81 0.00 0.00
02.03.03.02 ENCOFRADO Y DESENCOFRADO NORMAL SOBRECIMIENTO REFORZADO m2 230.22 57.18 13,163.98 97.30 5,563.61 0.00 0.00
02.03.03.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 711.98 4.60 3,275.11 296.84 1,365.46 0.00 0.00
02.03.04 CISTERNA
02.03.04.01 CONCRETO PREMEZCLADO DE CISTERNAS f'c=315 kg/cm2 Tipo HS m3 131.39 371.02 48,748.32 6.08 2,255.80 7.79 2,890.25
02.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA MURO DE CISTERNA m2 664.90 61.25 40,725.13 5.33 326.46 71.12 4,356.10
02.03.04.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 17,533.76 4.60 80,655.30 1,991.44 9,160.62 11,914.43 54,806.38
02.03.04.04 LADRILLO PARA TECHO 15x30x30 CM und 200.00 2.89 578.00 - 0.00 0.00 0.00
02.03.04.05 JUNTA WATER STOP 8" m 78.40 31.16 2,442.94 39.20 1,221.47 0.00 0.00
02.03.05 GRADERIAS
02.03.05.01 CONCRETO PREMEZCLADO f'c= 315 Kg/cm2 EN GRADERIAS- TIPO HS m3 62.27 371.02 23,103.42 - 0.00 0.00 0.00
02.03.05.02 ENCOFRADO DE GRADAS EN RELLENO m2 510.60 65.44 33,413.66 - 0.00 0.00 0.00
02.03.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 659.37 4.60 3,033.10 - 0.00 0.00 0.00
02.03.06 PUENTE
02.03.06.01 CONCRETO PREMEZCLADO EN PUENTE FC=210 KG/CM2 m3 37.17 351.17 13,052.99 - 0.00 0.00 0.00
02.03.06.02 ENCOFRADO Y DESENCOFRADO DE PUENTE m2 280.09 63.26 17,718.49 - 0.00 0.00 0.00
02.03.06.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 4,645.42 4.60 21,368.93 - 0.00 0.00 0.00
02.03.07 PEDESTAL
02.03.07.01 CONCRETO PREMEZCLADO EN PEDESTAL f'c=210 kg/cm2 m3 26.77 351.17 9,400.82 - 0.00 0.00 0.00
02.03.07.02 ENCOFRADO Y DESENCOFRADO DE PEDESTAL m2 184.14 52.64 9,693.13 - 0.00 0.00 0.00
02.03.07.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 2,789.84 4.60 12,833.26 687.12 3,160.75 136.47 627.76
02.03.08 MUROS DE CONTENCION
02.03.08.01 CONCRETO PREMEZCLADO MURO DE CONTENCION f'c=210 kg/cm2 m3 105.35 351.17 36,995.76 84.32 29,610.65 3.01 1,057.02
02.03.08.02 ENCOFRADO Y DESENCOFRADO MURO DE CONTENCION m2 1,154.80 66.19 76,436.21 949.85 62,870.57 0.00 0.00
02.03.08.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 7,591.81 4.60 34,922.33 5,897.87 27,130.20 0.00 0.00
02.03.09 PLACAS
02.03.09.01 CONCRETO PREMEZCLADO F'C=210 KG/CM2 MURO, PLACAS Y TABIQUES DE CONCRETO m3 423.12 379.61 160,620.58 99.73 37,858.51 101.24 38,431.72

Val_Estr Página 4
AVANCES
PRESUPUESTO
ANTERIOR ACTUAL
ITEM DESCRIPCION DE PARTIDA
UND METRADO PRECIO UNITARIO PARCIAL Metrado Monto Metrado Monto
02.03.09.02 ENCOFRADO Y DESENCOFRADO DE PLACAS m2 3,025.54 65.69 198,747.72 767.97 50,447.95 733.94 48,212.52
02.03.09.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 52,757.34 4.60 242,683.76 21,739.94 100,003.71 6,583.32 30,283.27
02.03.10 COLUMNAS
02.03.10.01 CONCRETO PREMEZCLADO COLUMNAS f'c=210 kg/cm2 m3 120.44 379.61 45,720.23 35.90 13,628.00 18.55 7,041.77
02.03.10.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 1,244.11 56.24 69,968.75 428.98 24,125.84 174.11 9,791.95
02.03.10.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 40,070.60 4.60 184,324.76 22,653.56 104,206.39 5,137.59 23,632.91
02.03.11 COLUMNETAS
02.03.11.01 CONCRETO COLUMNNETAS f'c=175 kg/cm2 m3 87.43 260.42 22,768.52 - 0.00 0.00 0.00
02.03.11.02 ENCOFRADO Y DESENCOFRADO DE COLUMNETAS m2 1,058.39 56.24 59,523.85 - 0.00 0.00 0.00
02.03.11.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 12,337.67 4.60 56,753.28 - 0.00 0.00 0.00
02.03.12 VIGAS
02.03.12.01 CONCRETO PREMEZCLADO F´C 210 kg/cm2 VIGAS__ m3 412.92 386.54 159,610.10 - 0.00 78.29 30,262.22
02.03.12.02 ENCOFRADO Y DESENCOFRADO DE VIGAS m2 2,806.93 63.26 177,566.39 - 0.00 1,009.76 63,877.42
02.03.12.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 55,125.42 4.60 253,576.93 1,479.56 6,805.98 21,078.61 96,961.61
02.03.13 VIGAS DE AMARRE
02.03.13.01 VIGAS DE AMARRE - CONCRETO 175 kg/cm2 m3 52.88 260.42 13,771.01 - 0.00 0.00 0.00
02.03.13.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGAS DE AMARRE m2 1,005.15 63.26 63,585.79 - 0.00 0.00 0.00
02.03.13.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 6,274.52 4.60 28,862.79 - 0.00 0.00 0.00
02.03.14 LOSA ALIGERADA
02.03.14.01 CONCRETO PREMEZCLADO LOSAS ALIGERADAS f'c=210 kg/cm2__ m3 342.30 371.02 127,000.15 - 0.00 67.73 25,129.18
02.03.14.02 ENCOFRADO Y DESENCOFRADO EN LOSAS ALIGERADAS m2 3,886.06 56.24 218,552.01 - 0.00 1,561.33 87,809.20
02.03.14.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 17,584.77 4.60 80,889.94 - 0.00 9,600.73 44,163.36
02.03.14.04 LADRILLO PARA TECHO 15x30x30 CM und 34,573.00 2.89 99,915.97 - 0.00 22,155.00 64,027.95
02.03.15 LOSA MACIZA
02.03.15.01 CONCRETO PREMEZCLADO LOSAS MACIZAS f'c=210 kg/cm2__ m3 134.03 288.25 38,634.15 - 0.00 11.87 3,421.53
02.03.15.02 ENCOFRADO Y DESENCOFRADO EN LOSAS MACIZAS m2 730.18 57.18 41,751.69 - 0.00 128.88 7,369.36
02.03.15.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 12,815.14 4.60 58,949.64 - 0.00 2,523.35 11,607.41
02.03.16 ESCALERAS
02.03.16.01 CONCRETO PREMEZCLADO ESCALERA f'c=210 kg/cm2__ m3 41.57 351.17 14,598.14 - 0.00 0.00 0.00
02.03.16.02 ENCOFRADO Y DESENCOFRADO EN ESCALERA m2 264.38 83.70 22,128.61 - 0.00 0.00 0.00
02.03.16.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 5,805.18 4.60 26,703.83 - 0.00 0.00 0.00
02.03.17 DINTELES PARA VANOS 0.00
02.03.17.01 CONCRETO EN DINTELES F'C=210 KG/CM2__ m3 6.12 351.17 2,149.16 - 0.00 0.00 0.00
02.03.17.02 ENCOFRADO Y DESENCOFRADO DINTELES m2 71.92 63.26 4,549.66 - 0.00 0.00 0.00
02.03.17.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 98.50 4.60 453.10 - 0.00 0.00 0.00
02.03.18 PORTICOS PARA COBERTURAS TENSIONADAS 0.00
02.03.18.01 CONCRETO PREMEZCLADO DE PORTICO PARA COBERTURA TENSIONADAS f'c=210 kg/cm2 m3 27.47 351.17 9,646.64 - 0.00 0.00 0.00
02.03.18.02 ENCOFRADO Y DESENCOFRADO PARA COBERTURA TENSIONADAS m2 255.57 65.45 16,727.06 - 0.00 0.00 0.00
02.03.18.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 6,121.89 4.60 28,160.69 - 0.00 0.00 0.00
02.03.19 VARIOS 0.00
02.03.19.01 PINTURA ASFALTICA EN CIMENTACIONES m2 2,725.72 11.72 31,945.44 1,352.73 15,854.00 206.63 2,421.70
02.04 ESTRUCTURAS METÁLICAS
02.04.01 SUMINISTRO E INSTALCION PARA COBERTURAS und 1.00 145,000.00 145,000.00 - 0.00 0.00 0.00
02.05 VARIOS 0.00
02.05.01 GEOSINTETICO MACLINE SDH 100 m2 2,486.30 43.95 109,272.89 - 0.00 0.00 0.00
02.05.02 CURADO DE CONCRETO CON ADITIVO CURADOR m2 18,232.82 3.31 60,350.63 3,770.16 12,479.23 4,028.25 13,333.51
02.06 REFORZAMIENTO ESTRUCTURAL
02.06.01 OBRAS PROVISIONALES
02.06.01.01 APUNTALAMIENTO DE LOSA ALIGERADAS EXISTENTES m2 661.90 24.77 16,395.26 - 0.00 198.57 4,918.58
02.06.01.02 APUNTALAMIENTO DE VIGAS EXISTENTES m 228.42 24.77 5,657.96 - 0.00 68.53 1,697.49
02.06.01.03 DEMOLICION LOSAS Y VIGAS CON EQUIPO m3 18.72 413.14 7,733.98 - 0.00 0.00 0.00
02.06.01.04 DEMOLICION PISO EXISTENTE PARA CIMENTACION m2 652.22 31.13 20,303.61 - 0.00 0.00 0.00
02.06.01.05 ESCARIFICADO DE COLUMNAS Y PLACAS m2 107.28 12.30 1,319.54 64.37 791.75 0.00 0.00
02.06.02 MOVIMIENTO DE TIERRAS
02.06.02.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 1,145.44 39.77 45,554.15 - 0.00 439.66 17,485.28
02.06.02.02 RELLENO COMPACTADO CON MATERIA PROPIO EN FORMA MANUAL m3 250.10 19.92 4,981.99 - 0.00 0.00 0.00

Val_Estr Página 5
AVANCES
PRESUPUESTO
ANTERIOR ACTUAL
ITEM DESCRIPCION DE PARTIDA
UND METRADO PRECIO UNITARIO PARCIAL Metrado Monto Metrado Monto
02.06.02.03 ELIMINACION DE MATERIAL EXCEDENTE INCL. ACARREO m3 1,163.98 28.69 33,394.59 - 0.00 444.66 12,757.30
02.06.03 CONCRETO SIMPLE
02.06.03.01 CONCRETO FALSA ZAPATAS f'c= 100 Kg/cm2 + 30% P.G. TIPO HS m3 199.63 219.10 43,738.93 - 0.00 104.27 22,845.56
02.06.04 CONCRETO ARMADO
02.06.04.01 ZAPATAS
02.06.04.01.01 CONCRETO PREMEZCLADO F'C=315 KG/CM2 ZAPATAS__ m3 428.58 341.02 146,154.35 - 0.00 0.00 0.00
02.06.04.01.02 ENCOFRADO Y DESENCOFRADO NORMAL ZAPATAS m2 470.30 61.25 28,805.88 - 0.00 0.00 0.00
02.06.04.01.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 31,240.41 4.60 143,705.89 - 0.00 0.00 0.00
02.06.04.02 COLUMNAS Y PLACAS 0.00
02.06.04.02.01 CONCRETO PREMEZCLADO COLUMNAS f'c=210 kg/cm2 m3 61.15 379.61 23,213.15 - 0.00 0.00 0.00
02.06.04.02.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS-PLACAS m2 595.77 56.24 33,506.10 - 0.00 0.00 0.00
02.06.04.02.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 14,398.90 4.60 66,234.94 - 0.00 0.00 0.00
02.06.04.03 VIGAS

02.06.04.03.01 CONCRETO PREMEZCLADO F´C 210 kg/cm2 VIGAS__ m3 22.77 379.61 8,643.72 - 0.00 0.00 0.00
02.06.04.03.02 ENCOFRADO Y DESENCOFRADO DE VIGAS m2 179.51 63.26 11,355.80 - 0.00 0.00 0.00
02.06.04.03.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 4,531.60 4.60 20,845.36 - 0.00 0.00 0.00
02.06.05 VARIOS
02.06.05.01 DOWELLS DE 3/8" und 5,120.00 5.74 29,388.80 - 0.00 0.00 0.00
02.06.05.02 DOWELLS DE 1/2" und 210.00 5.74 1,205.40 - 0.00 0.00 0.00
02.06.05.03 DOWELLS DE 3/4" und 102.00 5.74 585.48 - 0.00 0.00 0.00
02.06.05.04 PEGAMENTO EPOXICO P/UNION DE CONCRETO NUEVO-VIEJO m2 107.28 40.92 4,389.90 - 0.00 0.00 0.00
02.06.05.05 TRATAMIENTO DE SALITRE h=0.60m m 858.10 33.96 29,141.08 - 0.00 0.00 0.00
02.06.05.06 RESANE DE PATIO Y LOSA DEPORTIVA m2 457.20 31.50 14,401.80 - 0.00 0.00 0.00

COSTO DIRECTO (OBRAS ESTRUCTURAS) 5,679,402.90 1,143,701.96 849,057.07


GASTOS GENERALES % 8.25% 468,266.77 94,298.23 70,004.76
UTILIDAD % 6.00% 340,764.17 68,622.12 50,943.42
SUBTOTAL (OBRAS ESTRUCTURAS) 6,488,433.84 1,306,622.30 970,005.25

Val_Estr Página 6
ESTRUCTURAS
L 01 DE JUNIO AL 30 DE JUNIO 2022)

AMENTO DE MOQUEGUA” CUI N°2234866

AVANCES
SALDO
ACTUAL ACUMULADO
% Metrado Monto % Metrado Monto

24.00% 1,596.89 52,729.31 73.00% 592.23 19,555.43


7.00% 31.99 5,145.27 20.00% 124.36 20,002.06
7.00% 426.49 24,386.70 21.00% 1,624.76 92,903.78
0.00% 0.00 0.00 0.00% 3,267.69 133,223.72
0.00% 0.00 0.00 0.00% 4,697.86 229,537.44
0.00% 0.00 0.00 0.00% 626.05 30,588.80
0.00% 0.00 0.00 0.00% 463.55 25,666.76
0.00% 0.00 0.00 0.00% 1,421.45 73,958.04

13.00% 659.53 231,607.15 62.00% 408.01 143,280.87


9.00% 962.35 58,943.94 76.00% 302.63 18,536.09
6.00% 54,026.79 248,523.23 88.00% 7,377.99 33,938.76

19.00% 136.71 50,722.14 96.00% 6.32 2,344.85


18.00% 481.00 27,503.58 99.00% 3.74 213.85
4.00% 11,195.35 51,498.61 99.00% 81.70 375.82

0.00% 4.26 1,611.81 25.00% 13.01 4,922.47


0.00% 97.30 5,563.61 42.00% 132.92 7,600.37
0.00% 296.84 1,365.46 42.00% 415.14 1,909.65

6.00% 13.87 5,146.05 11.00% 117.52 43,602.27


11.00% 76.45 4,682.56 11.00% 588.45 36,042.57
68.00% 13,905.87 63,967.00 79.00% 3,627.89 16,688.30
0.00% 0.00 0.00 0.00% 200.00 578.00
0.00% 39.20 1,221.47 50.00% 39.20 1,221.47

0.00% 0.00 0.00 0.00% 62.27 23,103.42


0.00% 0.00 0.00 0.00% 510.60 33,413.66
0.00% 0.00 0.00 0.00% 659.37 3,033.10

0.00% 0.00 0.00 0.00% 37.17 13,052.99


0.00% 0.00 0.00 0.00% 280.09 17,718.49
0.00% 0.00 0.00 0.00% 4,645.42 21,368.93

0.00% 0.00 0.00 0.00% 26.77 9,400.82


0.00% 0.00 0.00 0.00% 184.14 9,693.13
5.00% 823.59 3,788.51 30.00% 1,966.25 9,044.75

3.00% 87.33 30,667.68 83.00% 18.02 6,328.08


0.00% 949.85 62,870.57 82.00% 204.95 13,565.64
0.00% 5,897.87 27,130.20 78.00% 1,693.94 7,792.13

24.00% 200.97 76,290.22 47.00% 222.15 84,330.36

Val_Estr Página 7
AVANCES
SALDO
ACTUAL ACUMULADO

% Metrado Monto % Metrado Monto

24.00% 1,501.91 98,660.47 50.00% 1,523.63 100,087.25


12.00% 28,323.26 130,286.98 54.00% 24,434.08 112,396.78

15.00% 54.45 20,669.76 45.00% 65.99 25,050.47


14.00% 603.09 33,917.78 48.00% 641.02 36,050.97
13.00% 27,791.15 127,839.31 69.00% 12,279.45 56,485.45

0.00% 0.00 0.00 0.00% 87.43 22,768.52


0.00% 0.00 0.00 0.00% 1,058.39 59,523.85
0.00% 0.00 0.00 0.00% 12,337.67 56,753.28

19.00% 78.29 30,262.22 19.00% 334.63 129,347.88


36.00% 1,009.76 63,877.42 36.00% 1,797.17 113,688.97
38.00% 22,558.17 103,767.58 41.00% 32,567.25 149,809.35

0.00% 0.00 0.00 0.00% 52.88 13,771.01


0.00% 0.00 0.00 0.00% 1,005.15 63,585.79
0.00% 0.00 0.00 0.00% 6,274.52 28,862.79

20.00% 67.73 25,129.18 20.00% 274.57 101,870.97


40.00% 1,561.33 87,809.20 40.00% 2,324.73 130,742.81
55.00% 9,600.73 44,163.36 55.00% 7,984.04 36,726.58
64.00% 22,155.00 64,027.95 64.00% 12,418.00 35,888.02

9.00% 11.87 3,421.53 9.00% 122.16 35,212.62


18.00% 128.88 7,369.36 18.00% 601.30 34,382.33
20.00% 2,523.35 11,607.41 20.00% 10,291.79 47,342.23

0.00% 0.00 0.00 0.00% 41.57 14,598.14


0.00% 0.00 0.00 0.00% 264.38 22,128.61
0.00% 0.00 0.00 0.00% 5,805.18 26,703.83

0.00% 0.00 0.00 0.00% 6.12 2,149.16


0.00% 0.00 0.00 0.00% 71.92 4,549.66
0.00% 0.00 0.00 0.00% 98.50 453.10

0.00% 0.00 0.00 0.00% 27.47 9,646.64


0.00% 0.00 0.00 0.00% 255.57 16,727.06
0.00% 0.00 0.00 0.00% 6,121.89 28,160.69

8.00% 1,559.36 18,275.70 57.00% 1,166.36 13,669.74

0.00% 0.00 0.00 0.00% 1.00 145,000.00

0.00% 0.00 0.00 0.00% 2,486.30 109,272.89


22.00% 7,798.41 25,812.74 43.00% 10,434.41 34,537.89

30.00% 198.57 4,918.58 30.00% 463.33 11,476.68


30.00% 68.53 1,697.49 30.00% 159.89 3,960.47
0.00% 0.00 0.00 0.00% 18.72 7,733.98
0.00% 0.00 0.00 0.00% 652.22 20,303.61
0.00% 64.37 791.75 60.00% 42.91 527.79

38.00% 439.66 17,485.28 38.00% 705.78 28,068.87


0.00% 0.00 0.00 0.00% 250.10 4,981.99

Val_Estr Página 8
AVANCES
SALDO
ACTUAL ACUMULADO

% Metrado Monto % Metrado Monto

38.00% 444.66 12,757.30 38.00% 719.32 20,637.29

52.00% 104.27 22,845.56 52.00% 95.36 20,893.37

0.00% 0.00 0.00 0.00% 428.58 146,154.35


0.00% 0.00 0.00 0.00% 470.30 28,805.88
0.00% 0.00 0.00 0.00% 31,240.41 143,705.89

0.00% 0.00 0.00 0.00% 61.15 23,213.15


0.00% 0.00 0.00 0.00% 595.77 33,506.10
0.00% 0.00 0.00 0.00% 14,398.90 66,234.94

0.00% 0.00 0.00 0.00% 22.77 8,643.72


0.00% 0.00 0.00 0.00% 179.51 11,355.80
0.00% 0.00 0.00 0.00% 4,531.60 20,845.36

0.00% 0.00 0.00 0.00% 5,120.00 29,388.80


0.00% 0.00 0.00 0.00% 210.00 1,205.40
0.00% 0.00 0.00 0.00% 102.00 585.48
0.00% 0.00 0.00 0.00% 107.28 4,389.90
0.00% 0.00 0.00 0.00% 858.10 29,141.08
0.00% 0.00 0.00 0.00% 457.20 14,401.80

1,992,758.95 3,686,643.90
164,302.98 303,963.79
119,565.54 221,198.63
14.95% 2,276,627.46 35.09% 4,211,806.32

Val_Estr Página 9
VALORIZACION DE OBRA Nº 02 ARQUITECTURA
(PERIODO : DEL 01 DE JUNIO AL 30 DE JUNIO 2022)

OBRA: “MEJORAMIENTO Y AMPLIACION DEL SERVICIO EDUCATIVO DE LA II.EE. FE Y ALEGRIA N° 52, SECTOR PAMPA INALAMBRICA DISTRITO DE ILO, PROVINCIA DE ILO DEPARTAMENTO DE MOQUEGUA” CUI N°2234866
UBICACIÓN: MOQUEGUA - ILO - ILO

AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
UND METRADO PRECIO UNITARIO PARCIAL Metrado Monto Metrado Monto % Metrado Monto % Metrado Monto

I. MODULOS
03 ARQUITECTURA
03.01 MUROS Y TABIQUES DE ALBAÑILERIA
03.01.01 MURO DE LADRILLO KK TIPO V, MEZCLA C:A 1:4 DE SOGA m2 5,228.03 92.00 480,978.76 - 0.00 0.00 0.00% 0.00 0.00 0.00% 5,228.03 480,978.76
03.01.02 MURO DE LADRILLO KK TIPO V, MEZCLA C:A 1:4 DE CABEZA m2 444.87 145.07 64,537.29 - 0.00 0.00 0.00% 0.00 0.00 0.00% 444.87 64,537.29
03.01.03 MURO DE LADRILLO KK TIPO V, MEZCLA C:A 1:4 DE CANTO m2 136.58 82.00 11,199.56 - 0.00 0.00 0.00% 0.00 0.00 0.00% 136.58 11,199.56
03.02 REVOQUES Y REVESTIMIENTOS
03.02.01 TARRAJEO PRIMARIO Y RAYADO MEZCLA C:A 1:5, e= 1.5cm m2 1,137.92 19.77 22,496.68 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1,137.92 22,496.68
03.02.02 TARRAJEO DE MUROS INTERIORES MEZC. C:A 1:5, E = 1.5 CM m2 6,302.03 18.46 116,335.47 - 0.00 0.00 0.00% 0.00 0.00 0.00% 6,302.03 116,335.47
03.02.03 TARRAJEO DE MUROS EXTERIORES MEZCLA C:A 1:5, e= 1.5cm m2 4,892.47 36.33 177,743.44 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4,892.47 177,743.44
03.02.04 TARRAJEO DE COLUMNAS MEZCLA C:A 1:5, e= 1.5cm m2 2,088.62 39.07 81,602.38 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2,088.62 81,602.38
03.02.05 TARRAJEO DE VIGAS MEZCLA C:A 1:5, e= 1.5cm m2 1,015.04 46.02 46,712.14 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1,015.04 46,712.14
03.02.06 VESTIDURA DERRAMES ANCHO = 0.15m MEZCLA C:A 1:5, E= 1.5 cm M 3,789.32 15.88 60,174.40 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3,789.32 60,174.40
03.02.07 TARRAJEO DE MUROS C/IMPERMEABILIZANTE MEZCLA C:A 1:5, e= 1.5cm m2 175.43 18.92 3,319.14 - 0.00 0.00 0.00% 0.00 0.00 0.00% 175.43 3,319.14
03.02.08 BRUÑAS INTERIORES (E=1 cm) M 4,534.33 4.00 18,137.32 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4,534.33 18,137.32
03.02.09 BRUÑAS EXTERIORES (E=1 cm) M 654.71 5.00 3,273.55 - 0.00 0.00 0.00% 0.00 0.00 0.00% 654.71 3,273.55
03.02.10 TARRAJEO EN FONDO DE ESCALERAS CON MEZCLA C:A 1:5 E=1.5cm m2 112.43 37.60 4,227.37 - 0.00 0.00 0.00% 0.00 0.00 0.00% 112.43 4,227.37
03.02.11 ACABADO DE PASO Y CONTRAPASO EN CEMENTO FROTACHADO m2 356.96 73.93 26,390.05 - 0.00 0.00 0.00% 0.00 0.00 0.00% 356.96 26,390.05
03.02.12 ACABADO DE DESCANSO EN CEMENTO FROTACHADO m2 45.77 22.33 1,022.04 - 0.00 0.00 0.00% 0.00 0.00 0.00% 45.77 1,022.04
03.02.13 SOLAQUEO DE DUCTOS m2 86.08 11.18 962.37 - 0.00 0.00 0.00% 0.00 0.00 0.00% 86.08 962.37
03.02.14 ACABADO DE CEMENTO EXPUESTO DE PORTADA YCOLUMNAS m2 437.43 30.13 13,179.77 - 0.00 0.00 0.00% 0.00 0.00 0.00% 437.43 13,179.77
03.03 TENSIONADA
CIELORRASOS
03.03.01 TARRAJEO DE CIELO RASO MEZCLA C:A 1:5, e= 1.5cm m2 5,965.14 38.84 231,686.04 - 0.00 0.00 0.00% 0.00 0.00 0.00% 5,965.14 231,686.04
03.03.02 FALSO CIELRO RASO CON BALDOSA DE FIBRA MINERAL DE 0.60X0.60X5/8" m2 46.51 95.65 4,448.68 - 0.00 0.00 0.00% 0.00 0.00 0.00% 46.51 4,448.68
03.03.03 FALSO CIELO RASO SISTEMA DE DRYWALL m2 97.04 83.17 8,070.82 - 0.00 0.00 0.00% 0.00 0.00 0.00% 97.04 8,070.82
03.03.04 FALSO CIELORASO CON BALDOSA CLEAN ROOM DE 0.60X0.60X5/8" m2 33.86 96.78 3,276.97 - 0.00 0.00 0.00% 0.00 0.00 0.00% 33.86 3,276.97
03.04 PISOS Y PAVIMENTOS
03.04.01 CONTRAPISOS e= 40mm MEZCLA C:A 1:4 m2 4,078.57 36.28 147,970.52 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4,078.57 147,970.52
03.04.02 PISO CEMENTO PULIDO CON IMPERMEABILIZANTE e=2" MEZCLA C.AA 1:4 m2 54.81 39.48 2,163.90 - 0.00 0.00 0.00% 0.00 0.00 0.00% 54.81 2,163.90
03.04.03 PISO DE CEMENTO PULIDO e=2" MEZCLA 1:4 m2 382.89 37.90 14,511.53 - 0.00 0.00 0.00% 0.00 0.00 0.00% 382.89 14,511.53
03.04.04 PISO DE CEMENTO SEMIPULIDO e=2" MEZCLA 1:4 m2 5,138.06 30.45 156,453.93 - 0.00 0.00 0.00% 0.00 0.00 0.00% 5,138.06 156,453.93
03.04.05 PISO DE CEMENTO SEMIPULIDO COLOR ROJO e=2" MEZCLA 1:4 m2 212.05 45.21 9,586.78 - 0.00 0.00 0.00% 0.00 0.00 0.00% 212.05 9,586.78
03.04.06 PISO DE PORCELANATO ANTIDESLIZANTE ALTO TRANSITO COLOR GRIS m2 3,225.85 86.73 279,777.97 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3,225.85 279,777.97
03.04.07 0.60PISO
x 0.60 m
CERAMICO DE ALTO TRANSITO COLOR GRIS 0.40x 0.40 m m2 680.15 51.40 34,959.71 - 0.00 0.00 0.00% 0.00 0.00 0.00% 680.15 34,959.71
03.04.08 PISO DE CAUCHO AMORTIGUANTE m2 122.50 125.99 15,433.78 - 0.00 0.00 0.00% 0.00 0.00 0.00% 122.50 15,433.78
03.04.09 PISO DE CEMENTO FROTACHADO Y BRUÑADO DE 1cmx 1cm, CADA 10 cm, m2 550.72 36.26 19,969.11 - 0.00 0.00 0.00% 0.00 0.00 0.00% 550.72 19,969.11
03.04.10 e= 2" MEZCLA 1:5 EN RAMPAS
RECUBRIMIENTO DE CEMENTO FROTACHADO E=2" EN GRADERIAS m2 60.52 25.10 1,519.05 - 0.00 0.00 0.00% 0.00 0.00 0.00% 60.52 1,519.05
03.04.11 LOSA MULTIUSO TIPO I m2 630.94 42.70 26,941.14 - 0.00 0.00 0.00% 0.00 0.00 0.00% 630.94 26,941.14
03.04.12 PISO DE GRAS BLOCK m2 50.25 77.81 3,909.95 - 0.00 0.00 0.00% 0.00 0.00 0.00% 50.25 3,909.95
03.05 ZOCALOS Y CONTRAZOCALES
03.05.01 ZOCALOS
03.05.01.01 ZOCALO DE CERAMICO 40X40 CM m2 1,198.59 53.18 63,741.02 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1,198.59 63,741.02
03.05.01.02 ZOCALO DE PORCELANATO 60 cm x 60 cm m2 13.03 66.88 871.45 - 0.00 0.00 0.00% 0.00 0.00 0.00% 13.03 871.45
03.05.02 CONTRAZOCALOS
03.05.02.01 CONTRAZOCALO DE CEMENTO PULIDO H=10CM M 2,446.93 9.80 23,979.91 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2,446.93 23,979.91
03.05.02.02 CONTRAZOCALO DE PORCELANATO 60 cm x 10 cm m 1,619.35 16.62 26,913.60 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1,619.35 26,913.60
03.05.02.03 CONTRAZOCALO CERAMICO 40x40 COLOR GRIS H=0.10M m 43.67 14.40 628.85 - 0.00 0.00 0.00% 0.00 0.00 0.00% 43.67 628.85
03.05.02.04 CONTRAZOCALO DE CEMENTO PULIDO h=0.30 m m 174.68 19.38 3,385.30 - 0.00 0.00 0.00% 0.00 0.00 0.00% 174.68 3,385.30
03.06 CUBIERTAS Y CERRAMIENTOS
03.06.01 CUBIERTA CON LADRILLO PASTELERO CON MORTERO CEMENTO ARENA m2 4,145.85 67.00 277,771.95 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4,145.85 277,771.95
03.06.02 + IMPERMEABILIZANTE DE TECHOSTENSIONADA
COBERTURA DE ESTRUCTURA m2 3,496.33 150.00 524,449.50 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3,496.33 524,449.50
03.06.03 CERCO TIPO AEROPUERTO m 341.43 976.55 333,423.47 - 0.00 0.00 0.00% 0.00 0.00 0.00% 341.43 333,423.47
03.06.04 CERCO TIPO AEROPUERTO MIXTO m 64.00 976.55 62,499.20 - 0.00 0.00 0.00% 0.00 0.00 0.00% 64.00 62,499.20
03.06.05 CERCO PREFABRICADO TIPO PERSIANA m 138.49 976.55 135,242.41 - 0.00 0.00 0.00% 0.00 0.00 0.00% 138.49 135,242.41
03.07 CARPINTERIA DE MADERA
03.07.01 MARCO Y PUERTA DE MADERA ACHIGUA INC. PINTURA BARNIZ + 1 und 4.00 1,565.15 6,260.60 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 6,260.60
03.07.02 REJILLA
MARCODE YMADERA
PUERTADE
DE90CM X 30CM
MADERA (P-1,P5-SA,
ACHIGUA INC. P4-SB)
PINTURA BARNIZ, + 1 und 15.00 1,447.67 21,715.05 - 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 21,715.05
03.07.03 REJILLA
MARCODE YMADERA
PUERTADE
DE60CM X 30 CM
MADERA (P6-Sa)INC. PINTURA BARNIZ + 1
ACHIGUA und 15.00 1,767.51 26,512.65 - 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 26,512.65
03.07.04 REJILLA
MARCODE YMADERA
PUERTADE
DE50CM X 30 CM
MADERA (P-2,P5-SB,
ACHIGUA P1-Sc) BARNIZ + 2
INC. PINTURA und 4.00 1,447.67 5,790.68 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 5,790.68
03.07.05 REJILLA
MARCODE YMADERA
PUERTADE
DE50CM X 30 CM
MADERA (P9'-Sa,
ACHIGUA P-3,P8-SB)
INC. PINTURA BARNIZ (P-4,P2- und 13.00 1,565.51 20,351.63 - 0.00 0.00 0.00% 0.00 0.00 0.00% 13.00 20,351.63
SA,P2-SB)

Val_Arq Página 10
AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
UND METRADO PRECIO UNITARIO PARCIAL Metrado Monto Metrado Monto % Metrado Monto % Metrado Monto
03.07.06 MARCO Y PUERTA DE MADERA ACHIGUA INC. PINTURA BARNIZ + REJILLA und 25.00 1,472.92 36,823.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 25.00 36,823.00
03.07.07 DE MADERA
MARCO YDE 50CM XDE
PUERTA 30MADERA
CM (P-5, P6-Sb;
ACHIGUAP7-Sa)
INC. PINTURA BARNIZ (P3-SA,P- und 8.00 1,447.67 11,581.36 - 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 11,581.36
03.07.08 6,P3-Sb)
MARCO Y PUERTA DE MADERA ACHIGUA INC. PINTURA BARNIZ + 1 und 15.00 1,447.67 21,715.05 - 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 21,715.05
03.07.09 REJILLA
MARCO DE YMADERA
PUERTADE
DE50CM X 30 CM
MADERA (P-8, ,P8-SA
ACHIGUA ,P7-SB, P2-Sc)
INC. PINTURA BARNIZ + und 37.00 1,565.51 57,923.87 - 0.00 0.00 0.00% 0.00 0.00 0.00% 37.00 57,923.87
03.07.10 CRISTAL
MARCOTEMPLADO
Y PUERTADEDE
6MM X18CMX56CM
MADERA ACHIGUA(P-9,P1-SA,P1-SB)
INC. PINTURA BARNIZ +2 und 1.00 1,565.51 1,565.51 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,565.51
03.07.11 REJILLA
MARCODE YMADERA
PUERTADE 60CM
DE X 30 CM
MADERA (P9-SA)INC. PINTURA BARNIZ + REJILLA
ACHIGUA und 1.00 1,565.51 1,565.51 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,565.51
03.07.12 DE MADERA
MARCO YDE 80CM XDE
PUERTA 30MADERA
CM (P5´-SA)
ACHIGUA INC. PINTURA BARNIZ + VISOR und 1.00 2,945.84 2,945.84 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,945.84
03.07.13 (PB1-SB)
MARCO Y PUERTA DE MADERA ACHIGUA INC. PINTURA BARNIZ (PB2-SB) und 2.00 2,945.84 5,891.68 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 5,891.68
03.07.14 MARCO Y PUERTA DE MADERA ACHIGUA INC. PINTURA BARNIZ + REJILLA und 1.00 1,565.51 1,565.51 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,565.51
03.07.15 DE MADERA
MARCO YDE 50CM XDE
PUERTA 30 MADERA
CM (P4'-SB)
ACHIGUA INC. PINTURA BARNIZ (P4-Sa) und 2.00 1,447.67 2,895.34 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 2,895.34
03.07.16 MARCO Y PUERTA DE MADERA ACHIGUA INC. PINTURA BARNIZ + REJILLA und 3.00 1,665.43 4,996.29 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 4,996.29
03.07.17 DE MADERA
MARCO YDE 50CM XDE
PUERTA 30MADERA
CM (P3-Sc)
ACHIGUA INC. PINTURA BARNIZ + 2 und 1.00 1,447.67 1,447.67 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,447.67
03.07.18 REJILLA
MARCODE YMADERA
PUERTADE
DE50CM X 30 CM
MADERA (P-8A)INC. PINTURA BARNIZ + 2
ACHIGUA und 4.00 1,447.67 5,790.68 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 5,790.68
03.07.19 REJILLA DE MADERA
PUERTA FORMADADE 50CM
POR X 30 CM
PLACAS (P-7, P10-SA,
LAMINADAS HPLP9-SB)
e=3MM PLEGADIZA und 1.00 2,945.84 2,945.84 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,945.84
03.07.20 (PP1-Sa,
PUERTAPP1'-Sa)
FORMADA POR PLACAS LAMINADAS HPL e=3MM PLEGADIZA und 5.00 2,945.84 14,729.20 - 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 14,729.20
03.07.21 (PP1-SB)
MUEBLE BAJO DE ATENCIÓN DE MELAMINE DE ANCHO = 0.60m CON m 4.17 1,051.67 4,385.46 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.17 4,385.46
03.07.22 TABLERO FENOLICO
MUEBLE BAJO DEFORRADO
ATENCIÓNCON ACERO SATINADO
DE MELAMINE E=0.012m.
DE ANCHO = 0.70 m CON m 2.28 1,051.67 2,397.81 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.28 2,397.81
03.07.23 TABLERO FENOLICO
MUEBLE BAJO DEFORRADO
ATENCIÓNCON ACERO SATINADO
DE MELAMINE E=0.012m.
DE ANCHO = 0.93m CON m 2.80 1,051.67 2,944.68 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.80 2,944.68
03.07.24 TABLERO FENOLICO
MUEBLE BAJO DEFORRADO
MELAMINECON ACERO SATINADO
DE ANCHO=0.55m CONE=0.012m.
TABLERO FENOLICO m 7.75 1,044.59 8,095.57 - 0.00 0.00 0.00% 0.00 0.00 0.00% 7.75 8,095.57
03.07.25 FORRADO
MUEBLECON ACERO
BAJO SATINADOE=0.012m
DE MELAMINE DE ANCHO = 0.44m CON TABLERO m 1.15 883.75 1,016.31 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.15 1,016.31
03.07.26 FENOLICO
MUEBLEFORRADO CON ACERO
BAJO DE MELAMINE DESATINADO
ANCHO =E=0.012m.
0.73m CON TABLERO m 27.81 1,088.78 30,278.97 - 0.00 0.00 0.00% 0.00 0.00 0.00% 27.81 30,278.97
03.07.27 FENOLICO
MUEBLEFORRADO
BAJO DE CON ACERODE
MELAMINE SATINADO E=0.012m.
ANCHO=0.60m CON TABLERO FENOLICO m 2.83 1,088.78 3,081.25 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.83 3,081.25
03.07.28 FORRADO
MUEBLECON ACERO
ALTO SATINADOE=0.012m
DE MELAMINE COLOR BLANCO DE H=0.60m m 4.16 795.38 3,308.78 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.16 3,308.78
03.07.29 MUEBLE ALTO DE MELAMINE COLOR BLANCO DE H=0.70m m 1.36 839.57 1,141.82 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.36 1,141.82
03.07.30 MUEBLE ALTO DE MELAMINE COLOR BLANCO DE H=1.20m m 1.04 1,060.50 1,102.92 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.04 1,102.92
03.07.31 MUEBLE ALTO DE MELAMINE COLOR BLANCO DE H=0.44 m m 1.22 751.19 916.45 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.22 916.45
03.07.32 MUEBLE BAJO DE ACERO INOXIDABLE ANCHO = 0.60 m DE TRABAJO m 22.82 574.86 13,118.31 - 0.00 0.00 0.00% 0.00 0.00 0.00% 22.82 13,118.31
03.07.33 MURAL
MUEBLE BAJO DE MELAMINE DE e=18mm CON TABLERO GRANITO E=2cm m 8.35 1,551.27 12,953.10 - 0.00 0.00 0.00% 0.00 0.00 0.00% 8.35 12,953.10
03.07.34 ANCHO =60 DE
REPISA CMACERO INOXIDABLE A=0.40M m 44.82 146.78 6,578.68 - 0.00 0.00 0.00% 0.00 0.00 0.00% 44.82 6,578.68
03.07.35 REPISA DE ACERO INOXIDABLE A=0.30M m 22.00 122.18 2,687.96 - 0.00 0.00 0.00% 0.00 0.00 0.00% 22.00 2,687.96
03.08 CARPINTERIA METALICA
03.08.01 PUERTA CON MARCO METÁLICO Y REJILLA DE VENTILACIÓN (PM2-SB) und 1.00 3,726.40 3,726.40 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,726.40
03.08.02 PUERTA CON MARCO METÁLICO Y REJILLA DE VENTILACIÓN (PM-1) und 3.00 3,726.40 11,179.20 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 11,179.20
03.08.03 PUERTA CON MARCO METÁLICO Y REJILLA DE VENTILACIÓN (PM-2,PM1- und 4.00 3,665.30 14,661.20 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 14,661.20
03.08.04 SA) PUERTA CON MARCO METÁLICO Y REJILLA DE VENTILACIÓN (PM1-SB) und 5.00 5,131.17 25,655.85 - 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 25,655.85
03.08.05 PUERTA METÁLICA INCLUYE CERRADURA ( R-1) und 1.00 2,206.95 2,206.95 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,206.95
03.08.06 PUERTA METÁLICA INCLUYE CERRADURA ( R-2) und 1.00 4,441.48 4,441.48 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,441.48
03.08.07 PUERTA METÁLICA INCLUYE CERRADURA ( PM2-Sa, R2-Sa) und 4.00 4,146.35 16,585.40 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 16,585.40
03.08.08 PUERTA METÁLICA INCLUYE CERRADURA ( R1-Sa) und 1.00 4,722.14 4,722.14 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,722.14
03.08.09 PUERTA METÁLICA INCLUYE CERRADURA ( R1-Sb) und 1.00 5,406.09 5,406.09 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 5,406.09
03.08.10 PUERTA DE REJA METÁLICA DE MALLA GALVANIZADA ( R2-Sb) und 1.00 3,194.28 3,194.28 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,194.28
03.08.11 PERSIANA DE PUERTA ENROLLABLE VQ1-SB und 1.00 1,777.28 1,777.28 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,777.28
03.08.12 PERSIANA DE PUERTA ENROLLABLE VQ2-SB und 1.00 1,715.64 1,715.64 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,715.64
03.08.13 PERSIANA DE PUERTA ENROLLABLE VQ1-SA und 1.00 2,732.80 2,732.80 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,732.80
03.08.14 PUERTA DE REJA METÁLICA INICIAL PG-1 und 1.00 10,119.03 10,119.03 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 10,119.03
03.08.15 PUERTA DE REJA METÁLICA PRIMARIA RG1-Sa und 1.00 5,017.21 5,017.21 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 5,017.21
03.08.16 PUERTA DE REJA METÁLICA PRIMARIA PG1-Sa und 1.00 7,487.52 7,487.52 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 7,487.52
03.08.17 PUERTA DE REJA METÁLICA SECUNDARIA -RG1-SB und 1.00 18,457.44 18,457.44 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 18,457.44
03.08.18 PUERTA METALICA CORREDIZA SECUNDARIA RG2-SB und 1.00 10,358.97 10,358.97 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 10,358.97
03.08.19 CLOSET DE MARCO Y PUERTA DE ACERO GALVANIZADO (CL1-Sa, CL1-Sb, und 21.00 1,128.71 23,702.91 - 0.00 0.00 0.00% 0.00 0.00 0.00% 21.00 23,702.91
03.08.20 CL1-Sc )
CLOSET DE MARCO Y PUERTA DE ACERO GAALVANIZADO (CL2-Sa) und 1.00 1,926.31 1,926.31 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,926.31
03.08.21 CLOSET DE MARCO Y PUERTA DE ACERO GAALVANIZADO (CL3-Sa) und 2.00 2,267.97 4,535.94 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 4,535.94
03.08.22 CLOSET DE MARCO Y PUERTA DE ACERO GAALVANIZADO (CL2-Sc) und 1.00 2,547.05 2,547.05 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,547.05
03.08.23 CLOSET DE MARCO Y PUERTA DE ACERO GAALVANIZADO (CL4-Sa) und 2.00 2,613.33 5,226.66 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 5,226.66
03.08.24 BARANDA METALICA (h=0.20m) m 660.11 99.01 65,357.49 - 0.00 0.00 0.00% 0.00 0.00 0.00% 660.11 65,357.49
03.08.25 BARANDA METALICA (h=1.00m) m 79.30 231.62 18,367.47 - 0.00 0.00 0.00% 0.00 0.00 0.00% 79.30 18,367.47
03.08.26 PASAMANO METALICO m 93.15 107.46 10,009.90 - 0.00 0.00 0.00% 0.00 0.00 0.00% 93.15 10,009.90
03.08.27 TAPAJUNTA PLANCHA DE ACERO INOXIDABLE A=10 CM m 12.33 54.31 669.64 - 0.00 0.00 0.00% 0.00 0.00 0.00% 12.33 669.64
03.08.28 CANTONERA METALICA ESTRIADA DE 5CMX5CM m 588.75 26.10 15,366.38 - 0.00 0.00 0.00% 0.00 0.00 0.00% 588.75 15,366.38
03.08.29 LETRA METALICA h=0.22m und 25.00 105.13 2,628.25 - 0.00 0.00 0.00% 0.00 0.00 0.00% 25.00 2,628.25
03.08.30 LETRA METALICA h=0.35m und 54.00 193.92 10,471.68 - 0.00 0.00 0.00% 0.00 0.00 0.00% 54.00 10,471.68
03.08.31 LOGO METALICO h=0.35m und 2.00 1,173.90 2,347.80 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 2,347.80
03.08.32 TAPAJUNTA DE ALUMINIO EN CAMBIO DE PISO m 217.50 23.76 5,167.80 - 0.00 0.00 0.00% 0.00 0.00 0.00% 217.50 5,167.80
03.08.33 ESCALERA DE GATO und 2.00 1,127.52 2,255.04 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 2,255.04
03.08.34 ESQUINERO DE ACERO INOXIDABLE DE 1"X1" ENBUTIDO EN MURO m 10.00 10.82 108.20 - 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 108.20
03.09 CERRAJERIA
03.09.01 BISAGRAS 3 1/2 X 3 1/2" ACERO INOXIDABLE und 474.00 20.70 9,811.80 - 0.00 0.00 0.00% 0.00 0.00 0.00% 474.00 9,811.80
03.09.02 CERRADURA CON MANILLA AMBOS LADOS CON LLAVE EXTERIOR Y und 102.00 271.73 27,716.46 - 0.00 0.00 0.00% 0.00 0.00 0.00% 102.00 27,716.46
03.09.03 SEGURO INTERIOR
CERRADURA CONCON BOTONLADOS PARA BAÑOS CON BOTON/RANUERA
A AMBOS und 62.00 174.88 10,842.56 - 0.00 0.00 0.00% 0.00 0.00 0.00% 62.00 10,842.56
DE EMERGENCIA
Val_Arq Página 11
AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
UND METRADO PRECIO UNITARIO PARCIAL Metrado Monto Metrado Monto % Metrado Monto % Metrado Monto
03.09.04 PICAPORTE SUPERIOR EN PUERTA INTERIOR DE 6" und 6.00 11.24 67.44 - 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 67.44
03.09.05 PICAPORTE SUPERIOR EN PUERTA DE SUM DE 12" und 6.00 31.03 186.18 - 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 186.18
03.09.06 TOPE MEDIA LUNA DE ALUMIO EN PISO PARA PUERTA und 158.00 21.55 3,404.90 - 0.00 0.00 0.00% 0.00 0.00 0.00% 158.00 3,404.90
03.10 VIDRIOS, CRISTALES Y SIMILARES
03.10.01 VENTANA DE CRISTAL TEMPLADO INCOLORO DE 6mm CON m2 4.56 355.18 1,619.62 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.56 1,619.62
03.10.02 PERFORACIONES DE 1/2" TEMPLADO INCOLORO DE 6mm
VENTANA DE CRISTAL m2 660.40 355.18 234,560.87 - 0.00 0.00 0.00% 0.00 0.00 0.00% 660.40 234,560.87
03.10.03 VENTANA DE CRISTAL TEMPLADO INCOLORO DE 6mm CON m2 161.80 427.08 69,101.54 - 0.00 0.00 0.00% 0.00 0.00 0.00% 161.80 69,101.54
03.10.04 RECOBRIMIENTO
MAMPARA DE UV
VIDRIO TEMPLADO INCOLORO DE 8mm m2 245.86 534.92 131,515.43 - 0.00 0.00 0.00% 0.00 0.00 0.00% 245.86 131,515.43
03.10.05 SC ESPEJO BISELADO DE 4mm CON BASTIDOR DE MADERA ½” X 2” m2 40.82 258.86 10,566.67 - 0.00 0.00 0.00% 0.00 0.00 0.00% 40.82 10,566.67
03.10.06 DIVISORES DE INODOROS, INCLUYE PUERTAS DE DUCHAS m 148.58 365.66 54,329.76 - 0.00 0.00 0.00% 0.00 0.00 0.00% 148.58 54,329.76
03.10.07 ESPEJO BISELADO DE 4mm de 60cm X 80cm CON INCLINACION DE 10° m2 2.00 446.66 893.32 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 893.32
03.10.08 SEPARADORES DE URINARIOS und 20.00 159.60 3,192.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 3,192.00
03.11 PINTURA
03.11.01 PINTURA LATEX EN MUROS INTERIORES m2 9,055.23 9.97 90,291.51 - 0.00 0.00 0.00% 0.00 0.00 0.00% 9,055.23 90,291.51
03.11.02 PINTURA LATEX EN MUROS EXTERIORES m2 4,892.47 10.22 49,987.34 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4,892.47 49,987.34
03.11.03 PINTURA LATEX EN CIELO RASO m2 6,966.04 11.37 79,170.44 - 0.00 0.00 0.00% 0.00 0.00 0.00% 6,966.04 79,170.44
03.11.04 PINTURA DE LINEAS EN LOSA m 603.08 25.84 15,583.59 - 0.00 0.00 0.00% 0.00 0.00 0.00% 603.08 15,583.59
03.11.05 PINTURA DE LINEAS EN PATIO m 113.10 25.84 2,922.50 - 0.00 0.00 0.00% 0.00 0.00 0.00% 113.10 2,922.50
03.11.06 PINTURA VIAL DISCAPACITADOS EN ESTACIONAMIENTO m 118.95 25.84 3,073.67 - 0.00 0.00 0.00% 0.00 0.00 0.00% 118.95 3,073.67
03.11.07 PINTURA VIAL DE SIMBOLO DE ESTACIONAMIENTOS m2 7.50 25.84 193.80 - 0.00 0.00 0.00% 0.00 0.00 0.00% 7.50 193.80
03.12 VARIOS, LIMPIEZA Y JARDINERIA
03.12.01 SARDINEL DE DUCHA ENCHAPADO EN CERÁMICO h= 0.15m M 32.55 43.60 1,419.18 - 0.00 0.00 0.00% 0.00 0.00 0.00% 32.55 1,419.18
03.12.02 BASE DE CONCRETO f'c= 140 Kg/cm2 de 4" ENCHAPADO CON CERAMICO m2 10.46 70.22 734.50 - 0.00 0.00 0.00% 0.00 0.00 0.00% 10.46 734.50
03.12.03 DE 0.45mX0.45mPARA
BASE DE CONCRETOINODOROS DE DISCAPACITADOS
f'c= 140 Kg/cm2 Y COCINAS
de 4" ENCHAPADO CON m2 23.66 111.77 2,644.48 - 0.00 0.00 0.00% 0.00 0.00 0.00% 23.66 2,644.48
03.12.04 PORCELANATO DE 0.60mX0.60mPARA
LOSA DE CONCRETO ENCHAPADO LABORATORIO
EN CERÁMICO Y
DETALLERES
40 X40 EN CTO DE m 11.68 86.66 1,012.19 - 0.00 0.00 0.00% 0.00 0.00 0.00% 11.68 1,012.19
03.12.05 LIMPIEZA
LOSA DE CONCRETO PARA LAVATORIO EN ACABADO PORCELANATO m 14.24 290.15 4,131.74 - 0.00 0.00 0.00% 0.00 0.00 0.00% 14.24 4,131.74
03.12.06 60X60,INICIAL
LOSA DE CONCRETO PARA LAVATORIO EN ACABADO PORCELANATO m 26.53 290.15 7,697.68 - 0.00 0.00 0.00% 0.00 0.00 0.00% 26.53 7,697.68
03.12.07 60X60,
LOSAPRIMARIA
DE CONCRETO PARA LAVATORIO EN ACABADO PORCELANATO m 21.37 290.15 6,200.51 - 0.00 0.00 0.00% 0.00 0.00 0.00% 21.37 6,200.51
03.12.08 60X60, SECUNDARIA
BANCA DE CONCRETO CON ACABADO EN CEMENTO PULIDO H=0.45 m m 85.41 299.85 25,610.19 - 0.00 0.00 0.00% 0.00 0.00 0.00% 85.41 25,610.19
03.12.09 DOBLE ASTA DE BANDERA TIPICO + BASE CONCRETO und 2.00 3,252.03 6,504.06 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 6,504.06
03.12.10 JUNTA DE DILATACION 1" CON RELLENO ASFALTICO m 87.30 22.04 1,924.09 - 0.00 0.00 0.00% 0.00 0.00 0.00% 87.30 1,924.09
03.12.11 JUNTA DE DILATACIÓN 1/2" CON SELLO ELASTOMERO m 129.40 15.89 2,056.17 - 0.00 0.00 0.00% 0.00 0.00 0.00% 129.40 2,056.17
03.12.12 SARDINEL DE CONCRETO F'c=210, DE ACABADO DE CEMENTO m 388.12 66.32 25,740.12 - 0.00 0.00 0.00% 0.00 0.00 0.00% 388.12 25,740.12
03.12.13 FROTACHADO Y DOBLE
COLOCACION OCHAVO DE
E INSTALACION DE 3/4" DE H=15CM
TESTIGOS DE CONCRETO DE E=10CM, m 212.66 9.82 2,088.32 - 0.00 0.00 0.00% 0.00 0.00 0.00% 212.66 2,088.32
03.12.14 H=15CM
BASE FLOTANTE ANTIVIBRATORIA PARA EQUIPOS MECANICOS H=0.15m m2 5.49 74.11 406.86 - 0.00 0.00 0.00% 0.00 0.00 0.00% 5.49 406.86
03.12.15 BASE DE CONCRETO IMPERMEABILIZADO DE CEMENTO PULIDO DE m2 2.80 60.56 169.57 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.80 169.57
03.12.16 H=0.10m PARADE
SARDINEL EQUIPOS DE EXTRACIÓN
CONCRETO DE CEMENTO PULIDO E IMPERMEABILIZADO m 46.71 38.62 1,803.94 - 0.00 0.00 0.00% 0.00 0.00 0.00% 46.71 1,803.94
03.12.17 H=0.15m Y E=0.10cm
TRATAMIENTO DEEN DUCTOMETALICAS
PUERTA DE VENTILACIÓN
EXISTENTES m2 10.96 29.46 322.88 - 0.00 0.00 0.00% 0.00 0.00 0.00% 10.96 322.88
03.12.18 TRATAMIENTO DE CERCO EXISTENTE ml 237.56 44.58 10,590.42 - 0.00 0.00 0.00% 0.00 0.00 0.00% 237.56 10,590.42
03.12.19 BLOQUE DE CONCRETO ARMADO 1.00X0.20X0.10 m und 51.00 54.79 2,794.29 - 0.00 0.00 0.00% 0.00 0.00 0.00% 51.00 2,794.29
03.12.20 SOL Y SOMBRA DE METAL A-36° m2 143.70 267.79 38,481.42 - 0.00 0.00 0.00% 0.00 0.00 0.00% 143.70 38,481.42
03.13 OTROS
03.13.01 PAISAJISMO
03.13.01.01 PREPARACION DE TERRENO PARA PASAJISMO m2 3,979.85 14.82 58,981.38 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3,979.85 58,981.38
03.13.01.02 ARBOL SCHINUS MOLLE "MOLLE COSTEÑO" und 22.00 35.39 778.58 - 0.00 0.00 0.00% 0.00 0.00 0.00% 22.00 778.58
03.13.01.03 ARBOL LUCUMO "ARBOL DE LOCUMA" und 4.00 44.24 176.96 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 176.96
03.13.01.04 ARBOL HUARANGO "PROPOSIS PALLIDA" und 6.00 5.66 33.96 - 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 33.96
03.13.01.05 ARBUSTO YUCA ELEPHANTIPES(YUCA FINA) und 59.00 26.10 1,539.90 - 0.00 0.00 0.00% 0.00 0.00 0.00% 59.00 1,539.90
03.13.01.06 ARBUSTO CARISSA MACROCARPA(CARISSA) m2 548.57 4.79 2,627.65 - 0.00 0.00 0.00% 0.00 0.00 0.00% 548.57 2,627.65
03.13.01.07 ARBUSTO PLUMBAGO AURICULATA (PLUMBAGO) m2 478.29 4.79 2,291.01 - 0.00 0.00 0.00% 0.00 0.00 0.00% 478.29 2,291.01
03.13.01.08 APTENIA CORDIFOLIA(APTENIA VERDE) m2 526.89 1.62 853.56 - 0.00 0.00 0.00% 0.00 0.00 0.00% 526.89 853.56
03.13.01.09 TRADESCANTIA SPATACEA VARIEGATA(RHOEO ROSADO) m2 625.64 1.62 1,013.54 - 0.00 0.00 0.00% 0.00 0.00 0.00% 625.64 1,013.54
03.13.01.10 CARPOBROTUS EDULLS (CLAVEL CHINO) m2 683.23 1.62 1,106.83 - 0.00 0.00 0.00% 0.00 0.00 0.00% 683.23 1,106.83
03.13.01.11 SENECIO CINERARIA"SENECIO BLANCO" m2 478.76 1.84 880.92 - 0.00 0.00 0.00% 0.00 0.00 0.00% 478.76 880.92
03.13.01.12 CHLOROPHYTUM COMOSUM,CINTA DE NOVIA m2 533.40 1.62 864.11 - 0.00 0.00 0.00% 0.00 0.00 0.00% 533.40 864.11
03.13.01.13 TIERRA RASTILLADA m2 863.73 17.48 15,098.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 863.73 15,098.00
03.13.01.14 TIERRA DE CHACRA CON SUTRATOS m2 105.07 13.12 1,378.52 - 0.00 0.00 0.00% 0.00 0.00 0.00% 105.07 1,378.52
03.13.01.15 TIERRA COMPACTADA m2 1,343.14 9.08 12,195.71 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1,343.14 12,195.71
03.14 SEÑALETICA Y EQUIPOS
03.14.01 SALIDA (DIRECCION IZQUIERDA) und 30.00 20.38 611.40 - 0.00 0.00 0.00% 0.00 0.00 0.00% 30.00 611.40
03.14.02 SALIDA( DIRECCION DERECHA) und 44.00 20.38 896.72 - 0.00 0.00 0.00% 0.00 0.00 0.00% 44.00 896.72
03.14.03 SALIDA und 107.00 20.38 2,180.66 - 0.00 0.00 0.00% 0.00 0.00 0.00% 107.00 2,180.66
03.14.04 ZONA SEGURA EN CASO DE SISMOS und 170.00 15.28 2,597.60 - 0.00 0.00 0.00% 0.00 0.00 0.00% 170.00 2,597.60
03.14.05 SEÑAL EXTINTOR und 38.00 9.89 375.82 - 0.00 0.00 0.00% 0.00 0.00 0.00% 38.00 375.82
03.14.06 AFORO und 36.00 12.37 445.32 - 0.00 0.00 0.00% 0.00 0.00 0.00% 36.00 445.32
03.14.07 AVISO SONORO und 21.00 20.38 427.98 - 0.00 0.00 0.00% 0.00 0.00 0.00% 21.00 427.98
03.14.08 RIESGO ELECTRICO und 19.00 10.91 207.29 - 0.00 0.00 0.00% 0.00 0.00 0.00% 19.00 207.29
03.14.09 PROHIBIDO FUMAR und 7.00 8.73 61.11 - 0.00 0.00 0.00% 0.00 0.00 0.00% 7.00 61.11
03.14.10 BOTIQUIN und 2.00 158.78 317.56 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 317.56
Val_Arq Página 12
AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
UND METRADO PRECIO UNITARIO PARCIAL Metrado Monto Metrado Monto % Metrado Monto % Metrado Monto
03.14.11 ESCALERA BAJA und 13.00 20.38 264.94 - 0.00 0.00 0.00% 0.00 0.00 0.00% 13.00 264.94
03.14.12 LUZ DE EMERGENCIA und 118.00 9.45 1,115.10 - 0.00 0.00 0.00% 0.00 0.00 0.00% 118.00 1,115.10
03.14.13 ESTACION MANUAL ALARMA DE FUEGO und 20.00 20.38 407.60 - 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 407.60
03.14.14 CARTEL PUNTO DE REUNION EN CASO DE EMERGENCIA und 22.00 21.36 469.92 - 0.00 0.00 0.00% 0.00 0.00 0.00% 22.00 469.92
03.14.15 EXTINTOR PQS DE 9 KG und 33.00 139.13 4,591.29 - 0.00 0.00 0.00% 0.00 0.00 0.00% 33.00 4,591.29
03.14.16 EXTINTOR ACE und 4.00 293.93 1,175.72 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 1,175.72
03.14.17 CARTEL N° PISO und 14.00 293.06 4,102.84 - 0.00 0.00 0.00% 0.00 0.00 0.00% 14.00 4,102.84

COSTO DIRECTO (OBRAS ARQUITECTURA) 5,276,466.18 0.00 0.00 0.00 5,276,466.18


GASTOS GENERALES % 8.25% 435,044.64 0.00 0.00 0.00 435,044.64
UTILIDAD % 6.00% 316,587.97 0.00 0.00 0.00 316,587.97
SUBTOTAL (OBRAS ARQUITECTURA) 6,028,098.79 0.00 0.00 0.00% 0.00 0.00% 6,028,098.79

Val_Arq Página 13
VALORIZACION DE OBRA Nº 02 INSTALACIONES SANITARIAS
(PERIODO : DEL 01 DE JUNIO AL 30 DE JUNIO 2022)

OBRA: “MEJORAMIENTO Y AMPLIACION DEL SERVICIO EDUCATIVO DE LA II.EE. FE Y ALEGRIA N° 52, SECTOR PAMPA INALAMBRICA DISTRITO DE ILO, PROVINCIA DE ILO DEPARTAMENTO DE MOQUEGUA” CUI N°2234866
UBICACIÓN: MOQUEGUA - ILO - ILO

AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
UND METRADO PRECIO UNITARIO PARCIAL Metrado Monto Metrado Monto % Metrado Monto % Metrado Monto

I. MODULOS
04 INSTALACIONES SANITARIAS
04.01 APARATOS SANITARIOS Y ACCESORIOS
04.01.01 SUMINISTRO DE ACCESORIOS
04.01.01.01 INODORO NOVARA FLUX COLOR BLANCO O SIMILAR und 38.00 410.98 15,617.24 - 0.00 0.00 0.00% 0.00 0.00 0.00% 38.00 15,617.24
04.01.01.02 INODORO RAPID JET PREMIUM CON SISTEMA DE PULSADOR ÚNICO, COLOR und 26.00 304.90 7,927.40 - 0.00 0.00 0.00% 0.00 0.00 0.00% 26.00 7,927.40
04.01.01.03 BLANCO O SIMILAR
INODORO NACIONAL BABY FREDH INTEGRADO CON TANQUE Y PULSADOR und 8.00 360.12 2,880.96 - 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 2,880.96
04.01.01.04 URINARIO CADET COLOR BLANCO O SIMILAR und 24.00 198.12 4,754.88 - 0.00 0.00 0.00% 0.00 0.00 0.00% 24.00 4,754.88
04.01.01.05 URINARIO BAMBI O SIMILAR und 6.00 143.88 863.28 - 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 863.28
04.01.01.06 DUCHA Y LAVAOJOS und 1.00 2,845.94 2,845.94 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,845.94
04.01.01.07 LAVATORIO MANANTIAL BLANCO O SIMILAR und 12.00 177.48 2,129.76 - 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 2,129.76
04.01.01.08 LAVATORIO ANCÓN BLANCO O SIMILAR und 3.00 222.26 666.78 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 666.78
04.01.01.09 LAVADERO 1 POZA CON ESCURRIDERO 94X49cm RECORD O SIMILAR und 3.00 299.09 897.27 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 897.27
04.01.01.10 LAVADERO DE ACERO INOXIDABLE DOS POZA CON ESCURRIDERO 116 cm TEKA und 2.00 409.52 819.04 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 819.04
04.01.01.11 O SIMILAR
LAVADERO TIPO ANCON EN PARED O SIMILAR und 2.00 222.26 444.52 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 444.52
04.01.01.12 LAVADERO CUBETA DE ACERO INOXIDABLE und 15.00 241.24 3,618.60 - 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 3,618.60
04.01.02 SUMINISTRO DE ACCESORIOS
04.01.02.01 GRIFERIA PARA INODORO FLUXOMETRO HELVEX O SIMILAR und 38.00 476.98 18,125.24 - 0.00 0.00 0.00% 0.00 0.00 0.00% 38.00 18,125.24
04.01.02.02 GRIFERIA PARA URINARIO FLUXOMETRO HELVEX O SIMILAR und 23.00 720.52 16,571.96 - 0.00 0.00 0.00% 0.00 0.00 0.00% 23.00 16,571.96
04.01.02.03 GRIFERIA TEMPORIZADA NEOPLUS O SIMILAR und 12.00 154.58 1,854.96 - 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 1,854.96
04.01.02.04 GRIFERIA LLAVE DE BRONCE DE 1/2" PARA URINARIO LINEA ECO und 4.00 70.53 282.12 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 282.12
04.01.02.05 GRIFERIA LAVATORIO CARTAGENA und 59.00 168.10 9,917.90 - 0.00 0.00 0.00% 0.00 0.00 0.00% 59.00 9,917.90
04.01.02.06 GRIFERIA LAVATORIO NEO und 14.00 60.52 847.28 - 0.00 0.00 0.00% 0.00 0.00 0.00% 14.00 847.28
04.01.02.07 GRIFERIA PARA LAVATORIO DISCAPACITADOS und 4.00 120.28 481.12 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 481.12
04.01.02.08 GRIFERIA MONOCOMANDO DEVON DE COCINA CROMO und 2.00 470.61 941.22 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 941.22
04.01.02.09 MEZCLADORA DE DUCHA P/ DISCAPACITADOS und 4.00 312.67 1,250.68 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 1,250.68
04.01.02.10 MEZCLADORA DE DUCHA LINEA ECO O SIMILAR und 19.00 121.03 2,299.57 - 0.00 0.00 0.00% 0.00 0.00 0.00% 19.00 2,299.57
04.01.02.11 GRIFO DE 1/2" und 3.00 8.67 26.01 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 26.01
04.01.02.12 GRIFERIA PARA LAVADERO AVANTE und 2.00 322.68 645.36 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 645.36
04.01.02.13 GRIFERIA MEZCLADORA PARA COCINA und 3.00 945.10 2,835.30 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 2,835.30
04.01.02.14 GRIFERIA PARA LAVADERO PARA KITCHENET und 3.00 877.12 2,631.36 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 2,631.36
04.01.02.15 GRIFERIA LLAVE COCINA A LA PARED BILBAO und 7.00 103.35 723.45 - 0.00 0.00 0.00% 0.00 0.00 0.00% 7.00 723.45
04.01.02.16 GRIFERIA PARA LABORATORIO TIPO CUELLO ANGULAR und 6.00 322.75 1,936.50 - 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 1,936.50
04.01.02.17 JABONERA DE LOSA TREBOL SOBREPONER BLANCA O SIMILAR und 12.00 20.17 242.04 - 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 242.04
04.01.02.18 DISPENSADOR DE PAPEL HIGIENICO MARCA LEEYES MOD.BSB-096F O SIMILAR und 5.00 143.62 718.10 - 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 718.10
04.01.02.19 DISPENSADOR JABON LIQUIDO DE PRESIONAR MARCA LEEYES PD-004 O und 61.00 54.27 3,310.47 - 0.00 0.00 0.00% 0.00 0.00 0.00% 61.00 3,310.47
04.01.02.20 SIMILAR
DISPENSADOR DE PAPEL TOALLA MARCA LEEYES MOD.SB-068H O SIMILAR und 41.00 359.00 14,719.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 41.00 14,719.00
04.01.02.21 DISPENSADOR DE PAPEL und 68.00 87.41 5,943.88 - 0.00 0.00 0.00% 0.00 0.00 0.00% 68.00 5,943.88
04.01.02.22 BARRA DE ACERO INOXIDABLE PARA INODOROS DISCAPACITADOS " TIPO "L" und 16.00 124.15 1,986.40 - 0.00 0.00 0.00% 0.00 0.00 0.00% 16.00 1,986.40
04.01.02.23 BARRA DE ACERO INOXIDABLE PARA DISCAPACITADOS EN DUCHA und 4.00 350.00 1,400.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 1,400.00
04.01.02.24 GANCHO DE ROPA und 30.00 2.42 72.60 - 0.00 0.00 0.00% 0.00 0.00 0.00% 30.00 72.60
04.01.02.25 ASIENTO DUCHA PARA DISCAPACITADOS und 2.00 457.25 914.50 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 914.50
04.01.02.26 GANCHOS DE MULETAS und 8.00 40.34 322.72 - 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 322.72
04.01.02.27 TACHO DE BASURA und 25.00 33.62 840.50 - 0.00 0.00 0.00% 0.00 0.00 0.00% 25.00 840.50
04.01.02.28 PAPELERA DE CABINA und 79.00 49.90 3,942.10 - 0.00 0.00 0.00% 0.00 0.00 0.00% 79.00 3,942.10
04.01.03 INSTALACION DE APARATOS (SOLO MANO DE OBRA)
04.01.03.01 COLOCACION DE APARATOS SANITARIOS und 140.00 117.60 16,464.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 140.00 16,464.00
04.01.03.02 COLOCACION DE ACCESORIOS SANITARIOS und 351.00 23.52 8,255.52 - 0.00 0.00 0.00% 0.00 0.00 0.00% 351.00 8,255.52
04.01.03.03 COLOCACION DE GRIFERIAS (FLUXOMETROS, TEMPORIZADOR, MEZCLADORAS) und 203.00 80.85 16,412.55 - 0.00 0.00 0.00% 0.00 0.00 0.00% 203.00 16,412.55
04.02 SISTEMA DE AGUA FRIA
04.02.01 SALIDAS DE AGUA FRIA
04.02.01.01 SALIDA DE AGUA FRIA PARA LAVADERO DE COCINA PPR-100 C-10 DE 1/2" pto 4.00 91.84 367.36 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 367.36
04.02.01.02 SALIDA DE AGUA FRIA PARA INODORO TUBERIA PPR-100 C-10 DE 1/2" pto 34.00 97.58 3,317.72 - 0.00 0.00 0.00% 0.00 0.00 0.00% 34.00 3,317.72
04.02.01.03 SALIDA DE AGUA FRIA PARA LIMPIEZA TUBERIA PPR-100 C-10 DE 1/2" pto 11.00 97.58 1,073.38 - 0.00 0.00 0.00% 0.00 0.00 0.00% 11.00 1,073.38
04.02.01.04 SALIDA DE AGUA FRIA PARA CALENTADOR ELECTRICO PPR-100 C-10 DE 1/2" pto 7.00 97.58 683.06 - 0.00 0.00 0.00% 0.00 0.00 0.00% 7.00 683.06
04.02.01.05 SALIDA DE AGUA FRIA PARA INODORO FLUXOMETRO TUBERIA PPR-100 C-10 DE pto 38.00 114.80 4,362.40 - 0.00 0.00 0.00% 0.00 0.00 0.00% 38.00 4,362.40
04.02.01.06 1 1/4"SALIDA DE AGUA FRIA PARA DUCHA PPR-100 C-10 DE 1/2" pto 22.00 97.58 2,146.76 - 0.00 0.00 0.00% 0.00 0.00 0.00% 22.00 2,146.76
04.02.01.07 SALIDA DE AGUA FRIA PARA URINARIO FLUXOMETRO PPR-100 C-10 DE 1" pto 23.00 123.00 2,829.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 23.00 2,829.00
04.02.01.08 SALIDA DE AGUA FRIA PARA LAVADERO TUBERIA PPR-100 C-10 DE 1/2" pto 100.00 97.58 9,758.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 100.00 9,758.00
04.02.01.09 "SALIDA DE AGUA FRIA PARA BEBEDERO DE 1/2" pto 12.00 97.58 1,170.96 - 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 1,170.96
Val_I_San Página 14
AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
UND METRADO PRECIO UNITARIO PARCIAL Metrado Monto Metrado Monto % Metrado Monto % Metrado Monto
04.02.01.10 SALIDA DE AGUA FRIA PARA DUCHA DE EMERGENCIA PPR-100 C-10 DE 1 1/4" pto 1.00 114.80 114.80 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 114.80
04.02.01.11 SALIDA DE AGUA FRIA PARA URINARIO PPR-100 C-10 DE 1/2" pto 7.00 97.58 683.06 - 0.00 0.00 0.00% 0.00 0.00 0.00% 7.00 683.06
04.02.01.12 SALIDA DE AGUA FRIA PARA CALENTADOR ELECTRICO PPR-100 C-10 DE 1" und 2.00 123.00 246.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 246.00
04.02.02 TUBERIA DE AGUA FRIA
04.02.02.01 EMPOTRADAS
04.02.02.01.01 TUBERIA CLASE-10 DE POLIPROPILENO PPR-100 DE 1/2" m 410.37 6.28 2,577.12 - 0.00 0.00 0.00% 0.00 0.00 0.00% 410.37 2,577.12
04.02.02.01.02 TUBERIA CLASE-10 DE POLIPROPILENO PPR-100 DE 3/4" m 219.62 6.32 1,388.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 219.62 1,388.00
04.02.02.01.03 TUBERIA CLASE-10 DE POLIPROPILENO PPR-100 DE 1" m 147.18 6.97 1,025.84 - 0.00 0.00 0.00% 0.00 0.00 0.00% 147.18 1,025.84
04.02.02.01.04 TUBERIA CLASE-10 DE POLIPROPILENO PPR-100 DE 1 1/4" m 96.21 7.77 747.55 - 0.00 0.00 0.00% 0.00 0.00 0.00% 96.21 747.55
04.02.02.01.05 TUBERIA CLASE-10 DE POLIPROPILENO PPR-100 DE 1 1/2" m 283.27 11.92 3,376.58 - 0.00 0.00 0.00% 0.00 0.00 0.00% 283.27 3,376.58
04.02.02.01.06 TUBERIA CLASE-10 DE POLIPROPILENO PPR-100 DE 2" m 181.10 11.70 2,118.87 - 0.00 0.00 0.00% 0.00 0.00 0.00% 181.10 2,118.87
04.02.02.01.07 TUBERIA CLASE-10 DE POLIPROPILENO PPR-100 DE 2 1/2" m 101.62 15.56 1,581.21 - 0.00 0.00 0.00% 0.00 0.00 0.00% 101.62 1,581.21
04.02.02.01.08 TUBERIA CLASE-10 DE POLIPROPILENO PPR-100 DE 3" m 16.74 18.23 305.17 - 0.00 0.00 0.00% 0.00 0.00 0.00% 16.74 305.17
04.02.02.01.09 TUBERIA CLASE-10 DE POLIPROPILENO PPR-100 DE 4" m 10.59 35.75 378.59 - 0.00 0.00 0.00% 0.00 0.00 0.00% 10.59 378.59
04.02.02.02 MONTANTES
04.02.02.02.01 TUBERIA CLASE-10 DE POLIPROPILENO PPR-100 DE 2 1/2" MONTANTE m 3.04 18.40 55.94 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3.04 55.94
04.02.02.03 ENTERRADAS
04.02.02.03.01 TUBERIA CLASE-10 DE POLIPROPILENO PPR-100 DE 1" ENTERRADA m 15.84 17.57 278.31 - 0.00 0.00 0.00% 0.00 0.00 0.00% 15.84 278.31
04.02.02.03.02 TUBERIA CLASE-10 DE POLIPROPILENO PPR-100 DE 1 1/2" ENTERRADA m 35.59 20.01 712.16 - 0.00 0.00 0.00% 0.00 0.00 0.00% 35.59 712.16
04.02.02.03.03 TUBERIA CLASE-10 DE POLIPROPILENO PPR-100 DE 2" ENTERRADA m 42.82 23.21 993.85 - 0.00 0.00 0.00% 0.00 0.00 0.00% 42.82 993.85
04.02.02.03.04 TUBERIA CLASE-10 DE POLIPROPILENO PPR-100 DE 2 1/2" ENTERRADA m 169.75 26.50 4,498.38 - 0.00 0.00 0.00% 0.00 0.00 0.00% 169.75 4,498.38
04.02.02.03.05 TUBERIA CLASE-10 DE POLIPROPILENO PPR-100 DE 3" ENTERRADA m 37.35 28.78 1,074.93 - 0.00 0.00 0.00% 0.00 0.00 0.00% 37.35 1,074.93
04.02.02.03.06 TUBERIA CLASE-10 DE POLIPROPILENO PPR-100 DE 4" ENTERRADA m 51.94 44.67 2,320.16 - 0.00 0.00 0.00% 0.00 0.00 0.00% 51.94 2,320.16
04.02.02.03.07 TUBO SCHE40 GALVANIZADO EN CALIENTE 2" AGUA FRIA m 1.37 69.20 94.80 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.37 94.80
04.02.02.03.08 TUBO SCHE40 GALVANIZADO EN CALIENTE 4" AGUA FRIA m 3.96 113.41 449.10 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3.96 449.10
04.02.02.03.09 TUBO SCHE40 GALVANIZADO EN CALIENTE 6" AGUA FRIA m 2.72 144.64 393.42 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.72 393.42
04.02.02.03.10 TUBO SCHE40 GALVANIZADO EN CALIENTE 2 1/2" AGUA FRIA m 9.35 85.94 803.54 - 0.00 0.00 0.00% 0.00 0.00 0.00% 9.35 803.54
04.02.02.03.11 TUBO SCHE40 GALVANIZADO EN CALIENTE 3" AGUA FRIA m 2.15 97.15 208.87 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.15 208.87
04.02.03 VALVULAS
04.02.03.01 VALVULA DE CONTROL DE 1/2" AGUA FRIA und 65.00 94.47 6,140.55 - 0.00 0.00 0.00% 0.00 0.00 0.00% 65.00 6,140.55
04.02.03.02 VALVULA DE CONTROL DE 3/4" AGUA FRIA und 28.00 113.96 3,190.88 - 0.00 0.00 0.00% 0.00 0.00 0.00% 28.00 3,190.88
04.02.03.03 VALVULA DE CONTROL DE 1" AGUA FRIA und 9.00 140.74 1,266.66 - 0.00 0.00 0.00% 0.00 0.00 0.00% 9.00 1,266.66
04.02.03.04 VALVULA DE CONTROL DE 1¼" AGUA FRIA und 9.00 184.01 1,656.09 - 0.00 0.00 0.00% 0.00 0.00 0.00% 9.00 1,656.09
04.02.03.05 VALVULA DE CONTROL DE 1½" AGUA FRIA und 26.00 262.53 6,825.78 - 0.00 0.00 0.00% 0.00 0.00 0.00% 26.00 6,825.78
04.02.03.06 VALVULA DE CONTROL DE 2" AGUA FRIA und 5.00 415.48 2,077.40 - 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 2,077.40
04.02.03.07 VALVULA DE CONTROL DE 2 1/2" AGUA FRIA und 5.00 616.66 3,083.30 - 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 3,083.30
04.02.03.08 VALVULA DE CONTROL DE 3" AGUA FRIA und 2.00 398.29 796.58 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 796.58
04.02.03.09 VALVULA DE CONTROL DE 4" AGUA FRIA und 7.00 553.74 3,876.18 - 0.00 0.00 0.00% 0.00 0.00 0.00% 7.00 3,876.18
04.02.03.10 VALVULA DE CONTROL DE 6" AGUA FRIA und 2.00 1,821.41 3,642.82 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 3,642.82
04.02.03.11 VALVULA CHECK 2" und 1.00 257.66 257.66 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 257.66
04.02.04 VARIOS
04.02.04.01 CAJA DE VALVULA DE CONTROL EN PISO und 3.00 248.98 746.94 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 746.94
04.02.04.02 CAJUELA TIPO NICHO PARA VALVULAS und 132.00 120.85 15,952.20 - 0.00 0.00 0.00% 0.00 0.00 0.00% 132.00 15,952.20
04.02.04.03 CAJUELA TIPO NICHO PARA VALVULAS EXTERNAS und 14.00 295.48 4,136.72 - 0.00 0.00 0.00% 0.00 0.00 0.00% 14.00 4,136.72
04.02.04.04 CONEXIÓN DOMICILIARIA AGUA - RED PÚBLICA und 2.00 152.33 304.66 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 304.66
04.03 SISTEMA DE AGUA CALIENTE
04.03.01 SALIDA DE PUNTO DE AGUA CALIENTE
04.03.01.01 SALIDA DE AGUA CALIENTE PARA DUCHA TUBERIA PPR-100 C-10 DE 1/2" pto 22.00 54.28 1,194.16 - 0.00 0.00 0.00% 0.00 0.00 0.00% 22.00 1,194.16
04.03.01.02 SALIDA DE AGUA CALIENTE PARA CALENTADOR ELECTRICO TUBERIA PPR-100 pto 7.00 91.41 639.87 - 0.00 0.00 0.00% 0.00 0.00 0.00% 7.00 639.87
04.03.01.03 C-10 DE 1/2" DE AGUA CALIENTE/LAVADERO TUBERIA PPR-100 C-10 DE 1/2"
SALIDA pto 3.00 51.09 153.27 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 153.27
04.03.01.04 SALIDA DE AGUA CALIENTE PARA CALENTADOR ELECTRICO TUBERIA PPR-100 pto 2.00 42.61 85.22 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 85.22
04.03.02 C-10TUBERIA
DE 1" DE AGUA CALIENTE

04.03.02.01 TUBERÍA PPR PN-16 / AGUA CALIENTE D = 1/2" m 69.98 12.64 884.55 - 0.00 0.00 0.00% 0.00 0.00 0.00% 69.98 884.55
04.03.02.02 TUBERÍA PPR PN-16 / AGUA CALIENTE D = 3/4" m 10.51 14.15 148.72 - 0.00 0.00 0.00% 0.00 0.00 0.00% 10.51 148.72
04.03.02.03 TUBERÍA PPR PN-16 / AGUA CALIENTE D = 1" m 16.10 15.51 249.71 - 0.00 0.00 0.00% 0.00 0.00 0.00% 16.10 249.71
04.03.03 VALVULAS
04.03.03.01 VALVULA DE PPR TIPO ESFERICA DE 1/2" und 14.00 37.43 524.02 - 0.00 0.00 0.00% 0.00 0.00 0.00% 14.00 524.02
04.03.03.02 VALVULA DE PPR TIPO ESFERICA DE 1" und 4.00 48.52 194.08 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 194.08
04.03.04 VARIOS
04.03.04.01 CAJUELA TIPO NICHO PARA VALVULAS und 14.00 118.90 1,664.60 - 0.00 0.00 0.00% 0.00 0.00 0.00% 14.00 1,664.60
04.03.04.02 CALENTADOR ELÉCTRICO 20 LT und 2.00 813.06 1,626.12 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 1,626.12
04.03.04.03 CALENTADOR ELECTRICO 50 LT und 3.00 798.76 2,396.28 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 2,396.28
04.03.04.04 CALENTADOR ELÉCTRICO 110 LT und 4.00 1,622.76 6,491.04 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 6,491.04
04.04 SISTEMA DE RIEGO
04.04.01 TUBERIA PVC SAP
04.04.01.01 TUBERIA PVC C-10 ENTERRADA 3/4" M 83.38 10.16 847.14 - 0.00 0.00 0.00% 0.00 0.00 0.00% 83.38 847.14
04.04.01.02 TUBERIA PVC C-10 ENTERRADA 1" M 316.13 15.25 4,820.98 - 0.00 0.00 0.00% 0.00 0.00 0.00% 316.13 4,820.98

Val_I_San Página 15
AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
UND METRADO PRECIO UNITARIO PARCIAL Metrado Monto Metrado Monto % Metrado Monto % Metrado Monto
04.04.01.03 TUBERIA PVC C-10 ENTERRADA 1.1/2" M 309.96 20.66 6,403.77 - 0.00 0.00 0.00% 0.00 0.00 0.00% 309.96 6,403.77
04.04.01.04 TUBERIA PVC C-10 ENTERRADA 2" M 394.63 16.95 6,688.98 - 0.00 0.00 0.00% 0.00 0.00 0.00% 394.63 6,688.98
04.04.02 VARIOS
04.04.02.01 ACOPLE RAPIDO DE 3/4" EN JARDINES und 35.00 107.41 3,759.35 - 0.00 0.00 0.00% 0.00 0.00 0.00% 35.00 3,759.35
04.04.02.02 VALVULA DE COMPUERTA DE BRONCE Ø2” und 2.00 531.96 1,063.92 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 1,063.92
04.04.02.03 TUBERIA CON GOTEROS m 318.40 9.73 3,098.03 - 0.00 0.00 0.00% 0.00 0.00 0.00% 318.40 3,098.03
04.04.02.04 VALVULA DE COMPUERTA DE BRONCE Ø1” und 2.00 139.12 278.24 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 278.24
04.04.02.05 CAJA DE VALVULA DE CONTROL EN PISO und 2.00 248.98 497.96 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 497.96
04.05 PRUEBAS HIDRAULICAS
04.05.01 PRUEBA HIDRAÚLICA Y DESINFECCION PARA AGUA FRIA m 1,842.58 3.57 6,578.01 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1,842.58 6,578.01
04.05.02 PRUEBA HIDRAÚLICA Y DESINFECCION PARA AGUA CALIENTE m 96.59 3.92 378.63 - 0.00 0.00 0.00% 0.00 0.00 0.00% 96.59 378.63
04.05.03 PRUEBA DE ESTANQUEDAD PARA DESAGUE M 747.77 1.76 1,316.08 - 0.00 0.00 0.00% 0.00 0.00 0.00% 747.77 1,316.08
04.06 SISTEMA DE DESAGUE Y VENTILACIÓN
04.06.01 SALIDA DE DESAGUE
04.06.01.01 SALIDA DE DESAGUE 4" PTO 74.00 99.28 7,346.72 - 0.00 0.00 0.00% 0.00 0.00 0.00% 74.00 7,346.72
04.06.01.02 SALIDA DE DESAGUE 2" PTO 125.00 84.45 10,556.25 - 0.00 0.00 0.00% 0.00 0.00 0.00% 125.00 10,556.25
04.06.01.03 SALIDA DE DESAGUE 4" C/ TRAMPA "P" PTO 2.00 129.55 259.10 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 259.10
04.06.01.04 SALIDA DE DESAGUE 3" C/ TRAMPA "P" pto 17.00 138.35 2,351.95 - 0.00 0.00 0.00% 0.00 0.00 0.00% 17.00 2,351.95
04.06.01.05 SALIDA DE DESAGUE 2" C/ TRAMPA "P" PTO 38.00 94.92 3,606.96 - 0.00 0.00 0.00% 0.00 0.00 0.00% 38.00 3,606.96
04.06.02 TUBERIA DE DESAGUE
04.06.02.01 COLGADAS
04.06.02.01.01 TUBERÍA COLGADA PVC DESAGÜE D= 4" M 49.27 35.39 1,743.67 - 0.00 0.00 0.00% 0.00 0.00 0.00% 49.27 1,743.67
04.06.02.01.02 TUBERÍA COLGADA PVC DESAGÜE D= 3" m 16.76 31.28 524.25 - 0.00 0.00 0.00% 0.00 0.00 0.00% 16.76 524.25
04.06.02.01.03 TUBERÍA COLGADA PVC DESAGÜE D= 2" M 12.61 25.95 327.23 - 0.00 0.00 0.00% 0.00 0.00 0.00% 12.61 327.23
04.06.02.02 MONTANTES
04.06.02.02.01 MONTANTE PVC SAP D=4" m 5.61 36.56 205.10 - 0.00 0.00 0.00% 0.00 0.00 0.00% 5.61 205.10
04.06.02.03 ENTERRADAS
04.06.02.03.01 TUBERÍA ENTERRADA PVC DESAGÜE D= 6" m 181.53 45.84 8,321.34 - 0.00 0.00 0.00% 0.00 0.00 0.00% 181.53 8,321.34
04.06.02.03.02 TUBERÍA ENTERRADA PVC DESAGÜE D= 4" m 396.35 31.08 12,318.56 - 0.00 0.00 0.00% 0.00 0.00 0.00% 396.35 12,318.56
04.06.02.03.03 TUBERÍA ENTERRADA PVC DESAGÜE D= 2" m 4.91 20.37 100.02 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.91 100.02
04.06.02.04 EMPOTRADA
04.06.02.04.01 TUBERÍA EMPOTRADA PVC DESAGÜE D= 4" m 373.89 45.17 16,888.61 - 0.00 0.00 0.00% 0.00 0.00 0.00% 373.89 16,888.61
04.06.02.04.02 TUBERÍA EMPOTRADA PVC DESAGÜE D= 3" m 62.83 23.43 1,472.11 - 0.00 0.00 0.00% 0.00 0.00 0.00% 62.83 1,472.11
04.06.02.04.03 TUBERÍA EMPOTRADA PVC DESAGÜE D= 2" m 237.81 15.06 3,581.42 - 0.00 0.00 0.00% 0.00 0.00 0.00% 237.81 3,581.42
04.06.03 TUBERIA DE VENTILACION
04.06.03.01 EMPOTRADA
04.06.03.01.01 TUBERÍA EMPOTRADA PVC DESAGÜE D= 4" m 3.96 31.53 124.86 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3.96 124.86
04.06.03.01.02 TUBERÍA EMPOTRADA PVC DESAGÜE D= 3" m 586.04 23.43 13,730.92 - 0.00 0.00 0.00% 0.00 0.00 0.00% 586.04 13,730.92
04.06.03.01.03 TUBERÍA EMPOTRADA PVC DESAGÜE D= 2" m 104.65 15.06 1,576.03 - 0.00 0.00 0.00% 0.00 0.00 0.00% 104.65 1,576.03
04.06.03.02 MONTANTE
04.06.03.02.01 MONTANTE PVC SAL D=4" - VENTILACIÓN m 24.03 21.73 522.17 - 0.00 0.00 0.00% 0.00 0.00 0.00% 24.03 522.17
04.06.03.02.02 MONTANTE PVC SAL D=3" - VENTILACIÓN m 4.47 16.56 74.02 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.47 74.02
04.06.04 PUNTOS DE VENTILACION
04.06.04.01 SALIDA DE VENTILACION 2" pto 169.00 16.65 2,813.85 - 0.00 0.00 0.00% 0.00 0.00 0.00% 169.00 2,813.85
04.06.04.02 COLGADA
04.06.04.02.01 COLGADA PVC D=4" - VENTILACIÓN m 103.13 60.62 6,251.74 - 0.00 0.00 0.00% 0.00 0.00 0.00% 103.13 6,251.74
04.06.04.02.02 COLGADA PVC D=3" - VENTILACIÓN m 101.48 51.03 5,178.52 - 0.00 0.00 0.00% 0.00 0.00 0.00% 101.48 5,178.52
04.06.04.02.03 COLGADA PVC D=2" - VENTILACIÓN m 93.26 47.52 4,431.72 - 0.00 0.00 0.00% 0.00 0.00 0.00% 93.26 4,431.72
04.06.05 TUBERIA PLUVIAL
04.06.05.01 EMPOTRADAS
04.06.05.01.01 TUBERÍA PVC DESAGUE D= 3" - PLUVIAL m 137.79 33.74 4,649.03 - 0.00 0.00 0.00% 0.00 0.00 0.00% 137.79 4,649.03
04.06.05.01.02 CANALETA PLUVIAL TIPO MEDIA CAÑA D= 4" m 444.18 14.46 6,422.84 - 0.00 0.00 0.00% 0.00 0.00 0.00% 444.18 6,422.84
04.06.05.01.03 TUBERÍA PVC DESAGUE D= 2" - PLUVIAL m 72.03 14.94 1,076.13 - 0.00 0.00 0.00% 0.00 0.00 0.00% 72.03 1,076.13
04.06.05.02 MONTANTES
04.06.05.02.01 MONTANTE PVC D=3" - PLUVIAL m 202.92 35.41 7,185.40 - 0.00 0.00 0.00% 0.00 0.00 0.00% 202.92 7,185.40
04.06.05.02.02 MONTANTE PVC D=4" - PLUVIAL m 75.63 38.34 2,899.65 - 0.00 0.00 0.00% 0.00 0.00 0.00% 75.63 2,899.65
04.06.05.03 POZO PERCOLADOR
04.06.05.03.01 POZO PARA DRENAJE PLUVIAL 0.60m und 15.00 65.60 984.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 984.00
04.06.05.04 REGISTROS
04.06.05.04.01 REGISTRO DE BRONCE TIPO RR ROSCA PISO 4" und 59.00 77.81 4,590.79 - 0.00 0.00 0.00% 0.00 0.00 0.00% 59.00 4,590.79
04.06.05.04.02 REGISTRO DE BRONCE TIPO RR ROSCA PISO 3" und 22.00 50.23 1,105.06 - 0.00 0.00 0.00% 0.00 0.00 0.00% 22.00 1,105.06
04.06.05.04.03 REGISTRO DE BRONCE TIPO RR ROSCA PISO 2" und 18.00 40.51 729.18 - 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 729.18
04.06.05.04.04 REGISTRO COLGADO 4" DESAGÜE und 13.00 77.81 1,011.53 - 0.00 0.00 0.00% 0.00 0.00 0.00% 13.00 1,011.53
04.06.05.04.05 REGISTRO COLGADO 3" DESAGÜE und 5.00 50.23 251.15 - 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 251.15
04.06.05.05 SUMIDEROS
04.06.05.05.01 SUMIDERO DE BRONCE DE 4" und 10.00 82.34 823.40 - 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 823.40
04.06.05.05.02 SUMIDERO DE BRONCE DE 3" und 36.00 44.43 1,599.48 - 0.00 0.00 0.00% 0.00 0.00 0.00% 36.00 1,599.48

Val_I_San Página 16
AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
UND METRADO PRECIO UNITARIO PARCIAL Metrado Monto Metrado Monto % Metrado Monto % Metrado Monto
04.06.05.05.03 SUMIDERO DE BRONCE DE 2" und 26.00 35.80 930.80 - 0.00 0.00 0.00% 0.00 0.00 0.00% 26.00 930.80
04.06.05.06 CAMARAS DE INSPECCIÓN
04.06.05.06.01 CAJA DE REGISTRO 12" x 24" und 73.00 301.81 22,032.13 - 0.00 0.00 0.00% 0.00 0.00 0.00% 73.00 22,032.13
04.06.05.06.02 CAJA DE REGISTRO 24" x 24" und 5.00 332.20 1,661.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 1,661.00
04.06.05.06.03 CAJA DE REGISTRO 12" x 24" CON REGISTRO DE 6'' und 2.00 406.43 812.86 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 812.86
04.06.05.06.04 CAJA DE REGISTRO 12" x 24" CON VALVULA ANTIRETORNO DE 6" und 4.00 539.37 2,157.48 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 2,157.48
04.06.05.06.05 CAJA DE REGISTRO 24" x 24" CON VALVULA ANTIRETORNO DE 6" und 1.00 539.37 539.37 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 539.37
04.06.06 VARIOS
04.06.06.01 SOMBRERETE DE PROTECCION FINAL 4'' und 11.00 4.58 50.38 - 0.00 0.00 0.00% 0.00 0.00 0.00% 11.00 50.38
04.06.06.02 SOMBRERETE DE PROTECCION FINAL 2'' und 27.00 3.06 82.62 - 0.00 0.00 0.00% 0.00 0.00 0.00% 27.00 82.62
04.06.06.03 TRAMPA DE GRASA TIPO HELVEX 40 O SIMILAR und 3.00 2,506.21 7,518.63 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 7,518.63
04.06.06.04 CONEXIÓN DOMICILIARIA DESAGUE - RED PÚBLICA und 4.00 77.06 308.24 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 308.24
04.06.06.05 DADO DE CONCRETO + CODO DE 3'' und 31.00 50.44 1,563.64 - 0.00 0.00 0.00% 0.00 0.00 0.00% 31.00 1,563.64
04.06.06.06 VALVULA ANTIRETORNO DE 6'' und 2.00 861.00 1,722.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 1,722.00
04.06.06.07 TRAMAPA DE GRASA DE CONCRETO(0.70mX1.40mX1.15m) und 4.00 1,221.92 4,887.68 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 4,887.68
04.06.06.08 DADO DE CONCRETO + CODO DE 2" und 22.00 40.86 898.92 - 0.00 0.00 0.00% 0.00 0.00 0.00% 22.00 898.92
04.06.06.09 SOMBRERETE DE PROTECCION FINAL 3" und 3.00 9.60 28.80 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 28.80
04.07 MOVIMIENTO DE TIERRAS
04.07.01 MOVIMIENTO DE TIERRAS
04.07.01.01 EXCAVACION DE ZANJAS m3 782.47 32.75 25,625.89 - 0.00 0.00 0.00% 0.00 0.00 0.00% 782.47 25,625.89
04.07.01.02 CAMA DE APOYO m3 149.76 13.71 2,053.21 - 0.00 0.00 0.00% 0.00 0.00 0.00% 149.76 2,053.21
04.07.01.03 RELLENO, COMPACTADO MATERIAL PROPIO PARA ZANJA 0.60 X 0.80 m 722.35 16.14 11,658.73 - 0.00 0.00 0.00% 0.00 0.00 0.00% 722.35 11,658.73
04.07.01.04 ELIMINACION DE MATERIAL EXCEDENTE INCL. ACARREO m3 782.47 27.43 21,463.15 - 0.00 0.00 0.00% 0.00 0.00 0.00% 782.47 21,463.15
04.08 SISTEMA DE PRESION CONSTANTE
04.08.01 SISTEMA DE PRESION CONSTANTE Y VELOCIDAD VARIABLE N°1 AGUA
POTABLE
04.08.01.01 EQUIPO DE BOMBEO PRINCIPALES und 1.00 15,681.38 15,681.38 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 15,681.38
04.08.01.02 TABLERO DE CONTROL und 1.00 10,276.46 10,276.46 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 10,276.46
04.08.01.03 MONTAJE DEL SISTEMA glb 1.00 26,659.58 26,659.58 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 26,659.58
04.08.02 SISTEMA DE PRESION CONSTANTE Y VELOCIDAD VARIABLE N°2 AGUA DE
04.08.02.01 RIEGOEQUIPO DE BOMBEO PRINCIPALES und 1.00 5,083.54 5,083.54 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 5,083.54
04.08.02.02 TABLERO DE CONTROL und 1.00 3,143.58 3,143.58 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,143.58
04.08.02.03 MONTAJE DEL SISTEMA glb 1.00 11,108.16 11,108.16 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 11,108.16
04.08.03 SISTEMA DE PRESION CONSTANTE Y VELOCIDAD VARIABLE N°3
04.08.03.01 EQUIPO DE BOMBEO PRINCIPALES und 1.00 8,834.63 8,834.63 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 8,834.63
04.08.03.02 TABLERO DE CONTROL und 1.00 4,101.25 4,101.25 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,101.25
04.08.03.03 MONTAJE DEL SISTEMA glb 1.00 21,846.05 21,846.05 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 21,846.05
04.08.04 SISTEMA DE PRESION CONSTANTE Y VELOCIDAD VARIABLE N°4
04.08.04.01 EQUIPO DE BOMBEO PRINCIPALES und 1.00 5,083.54 5,083.54 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 5,083.54
04.08.04.02 TABLERO DE CONTROL und 1.00 3,143.58 3,143.58 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,143.58
04.08.04.03 MONTAJE DEL SISTEMA glb 1.00 11,108.16 11,108.16 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 11,108.16

COSTO DIRECTO (INSTALACIONES SANITARIAS) 708,152.32 0.00 0.00 0.00 708,152.32


GASTOS GENERALES % 8.25% 58,387.16 0.00 0.00 0.00 58,387.16
UTILIDAD % 6.00% 42,489.14 0.00 0.00 0.00 42,489.14
SUBTOTAL (INSTALACIONES SANITARIAS) 809,028.62 0.00 0.00 0.00% 0.00 0.00% 809,028.62
0.00

Val_I_San Página 17
VALORIZACION DE OBRA Nº 02 INSTALACIONES ELECTRICAS
(PERIODO : DEL 01 DE JUNIO AL 30 DE JUNIO 2022)

OBRA: “MEJORAMIENTO Y AMPLIACION DEL SERVICIO EDUCATIVO DE LA II.EE. FE Y ALEGRIA N° 52, SECTOR PAMPA INALAMBRICA DISTRITO DE ILO, PROVINCIA DE ILO DEPARTAMENTO DE MOQUEGUA” CUI N°2234866
UBICACIÓN: MOQUEGUA - ILO - ILO

AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
UND METRADO PRECIO UNITARIO PARCIAL Metrado Monto Metrado Monto % Metrado Monto % Metrado

I. MODULOS
05 INSTALACIONES ELECTRICAS Y MECANICAS
05.01 INSTALACIONES ELECTRICAS
05.01.01 SALIDAS ELECTRICAS
05.01.01.01 SALIDAS PARA LUMINARIAS
05.01.01.01.01 SALIDA PARA CENTRO DE LUZ (EN TECHO) pto 972.00 65.00 63,180.00 - 0.00 183.00 11,895.00 19.00% 183.00 11,895.00 19.00% 789.00 51,285.00
05.01.01.01.02 SALIDA PARA CENTRO DE LUZ SUSPENDIDO (EN POLIDEPORTIVO) pto 17.00 65.00 1,105.00 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 17.00 1,105.00
05.01.01.01.03 SALIDA PARA LUMINARIA DE EMERGENCIA pto 120.00 65.00 7,800.00 - 0.00 2.00 130.00 2.00% 2.00 130.00 2.00% 118.00 7,670.00
05.01.01.01.04 SALIDA PARA FAROL pto 15.00 65.00 975.00 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 975.00
05.01.01.01.05 SALIDA PARA REFLECTORES pto 39.00 65.00 2,535.00 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 39.00 2,535.00
05.01.01.02 SALIDAS PARA TOMACORRIENTES -
05.01.01.02.01 SALIDA TOMACORRIENTE DOBLE C/LINEA DE TIERRA 3 EN LINEA (EN PARED) pto 523.00 132.62 69,360.26 - 0.00 58.00 7,691.96 11.00% 58.00 7,691.96 11.00% 465.00 61,668.30
05.01.01.02.02 SALIDA TOMACORRIENTE DOBLE C/LINEA DE TIERRA TIPO SCHUKO (EN PISO) pto 62.00 214.47 13,297.14 - 0.00 4.00 857.88 6.00% 4.00 857.88 6.00% 58.00 12,439.26
05.01.01.02.03 SALIDA TOMACORRIENTE DOBLE C/LINEA DE TIERRA TIPO SCHUKO (EN pto 8.00 137.16 1,097.28 - 0.00 2.00 274.32 25.00% 2.00 274.32 25.00% 6.00 822.96
05.01.01.02.04 TECHO)
SALIDA TOMACORRIENTE DOBLE C/LINEA DE TIERRA TIPO SCHUKO (EN pto 10.00 137.16 1,371.60 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 10.00 1,371.60
05.01.01.02.05 PARED)SALIDA TOMACORRIENTEA PRUEBA DE AGUA C/LINEA DE TIERRA(EN PARED) pto 14.00 214.47 3,002.58 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 14.00 3,002.58
05.01.01.02.06 SALIDA TOMACORRIENTE SIMPLE TIPO SCHUKO C/LINEA DE TIERRA (EN pto 1.00 111.54 111.54 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 111.54
05.01.01.02.07 PARED)SALIDA TOMACORRIENTE DOBLE C/LINEA DE TIERRA 3 EN LINEA C/TAPA pto 18.00 132.62 2,387.16 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 2,387.16
05.01.01.02.08 PROTECTORA (EN PARED) TOMACORRIENTE DOBLE C/LINEA DE TIERRA TIPO
SALIDA ESTABILIZADA pto 73.00 139.80 10,205.40 - 0.00 0.00 0.00% 0.00 0.00 0.00% 73.00 10,205.40
05.01.01.03 SCHUKO (EN PISO)
SALIDAS PARA INTERRUPTORES - 0.00
05.01.01.03.01 SALIDA PARA INTERRUPTOR SIMPLE pto 96.00 76.95 7,387.20 - 0.00 2.00 153.90 2.00% 2.00 153.90 2.00% 94.00 7,233.30
05.01.01.03.02 SALIDA PARA INTERRUPTOR DOBLE pto 41.00 92.02 3,772.82 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 41.00 3,772.82
05.01.01.03.03 SALIDA PARA INTERRUPTOR TRIPLE pto 4.00 106.58 426.32 - 0.00 1.00 106.58 25.00% 1.00 106.58 25.00% 3.00 319.74
05.01.01.03.04 SALIDA PARA INTERRUPTOR CONMUTACION 3 VIAS pto 45.00 73.87 3,324.15 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 45.00 3,324.15
05.01.01.03.05 SALIDA PARA INTERRUPTOR CONMUTACION 4 VIAS pto 8.00 112.01 896.08 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 896.08
05.01.01.04 SALIDA DE FUERZA -
05.01.01.04.01 SALIDA PARA EQUIPOS DE EXTRACCION CAMPANA pto 3.00 52.32 156.96 - 0.00 2.00 104.64 67.00% 2.00 104.64 67.00% 1.00 52.32
05.01.01.04.02 SALIDA PARA SENSOR DE MOVIMIENTO pto 40.00 52.32 2,092.80 - 0.00 10.00 523.20 25.00% 10.00 523.20 25.00% 30.00 1,569.60
05.01.01.04.03 SALIDA INTERRUPTOR + PLACA BIPOLAR 2x20A pto 11.00 52.32 575.52 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 11.00 575.52
05.01.01.04.04 SALIDA DE FUERZA EN BOMBAS 6HP pto 3.00 343.34 1,030.02 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 1,030.02
05.01.01.04.05 SALIDA DE FUERZA EN BOMBAS 2HP pto 2.00 274.81 549.62 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 549.62
05.01.01.04.06 SALIDA DE FUERZA EN BOMBAS 1.8HP pto 2.00 274.81 549.62 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 549.62
05.01.02 SUMINISTRO E INSTALACION DE CAJAS DE PASE -
05.01.02.01 CAJA DE PASE 150x150x100mm pza 114.00 32.58 3,714.12 - 0.00 15.00 488.70 13.00% 15.00 488.70 13.00% 99.00 3,225.42
05.01.02.02 CAJA DE PASE OCTOGONAL pza 108.00 14.54 1,570.32 - 0.00 10.00 145.40 9.00% 10.00 145.40 9.00% 98.00 1,424.92
05.01.02.03 CAJA DE PASE 200x200x100mm pza 2.00 45.94 91.88 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 91.88
05.01.02.04 CAJA DE REGISTRO und 12.00 42.10 505.20 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 505.20
05.01.03 SUMINISTRO E INSTALACION DE TUBERIAS - 0.00
05.01.03.01 TUBERIA CONDUIT EMT Ø 20mm m 213.07 14.40 3,068.21 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 213.07 3,068.21
05.01.03.02 TUBERIA PVC-P (ELECTRICA) Ø 20mm m 9,342.56 11.65 108,840.82 - 0.00 797.00 9,285.05 9.00% 797.00 9,285.05 9.00% 8,545.56 99,555.77
05.01.03.03 TUBERIA PVC-P (ELECTRICA) Ø 25mm m 1,673.55 12.77 21,371.23 - 0.00 156.00 1,992.12 9.00% 156.00 1,992.12 9.00% 1,517.55 19,379.11
05.01.03.04 TUBERIA PVC-P (ELECTRICA) Ø 35mm m 292.09 18.52 5,409.51 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 292.09 5,409.51
05.01.03.05 TUBERIA PVC-P (ELECTRICA) Ø 40mm m 314.91 26.45 8,329.37 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 314.91 8,329.37
05.01.03.06 TUBERIA PVC-P (ELECTRICA) Ø 50mm m 126.95 17.61 2,235.59 - 0.00 6.00 105.66 5.00% 6.00 105.66 5.00% 120.95 2,129.93
05.01.03.07 TUBERIA PVC-P (ELECTRICA) Ø 65mm m 127.22 28.00 3,562.16 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 127.22 3,562.16
05.01.03.08 TUBERIA PVC-P (ELECTRICAS) Ø 100mm m 74.63 32.00 2,388.16 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 74.63 2,388.16
05.01.04 SUMINISTRO E INSTALACION DE CABLES - 0.00
05.01.04.01 CABLE 3-1x185mm2 H07Z-R + 1x185mm2 (N) m 83.15 329.61 27,407.07 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 83.15 27,407.07
05.01.04.02 CABLE 3-1x70mm2 H07Z-R + 1x70mm2 (N) m 132.35 132.20 17,496.67 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 132.35 17,496.67
05.01.04.03 CABLE 3-1x50mm2 H07Z-R + 1x50mm2 (N) m 134.70 95.14 12,815.36 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 134.70 12,815.36
05.01.04.04 CABLE 3-1x35mm2 H07Z-R + 1x35mm2 (N) + 1x25mm2 (T) und 22.55 84.58 1,907.28 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 22.55 1,907.28
05.01.04.05 CABLE 3-1x35mm2 H07Z-R + 1x35mm2 (N) m 331.95 72.12 23,940.23 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 331.95 23,940.23
05.01.04.06 CABLE 3-1x25mm2 H07Z-R + 1x25mm2 (N) + 1x6mm2 (T) m 29.80 59.19 1,763.86 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 29.80 1,763.86

Val_I_Elec Página 18
AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
UND METRADO PRECIO UNITARIO PARCIAL Metrado Monto Metrado Monto % Metrado Monto % Metrado
05.01.04.07 CABLE 3-1x25mm2 H07Z-R + 1x25mm2 (N) m 71.55 55.64 3,981.04 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 71.55 3,981.04
05.01.04.08 CABLE 3-1x16mm2 H07Z-R + 1x16mm2 (N) + 1x6mm2 (T) m 8.20 43.56 357.19 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 8.20 357.19
05.01.04.09 CABLE 3-1x16mm2 H07Z-R + 1x16mm2 (N) m 205.40 40.01 8,218.05 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 205.40 8,218.05
05.01.04.10 CABLE 3-1x10mm2 H07Z-R + 1x10mm2 (N) + 1x10mm2 (T) m 26.45 30.35 802.76 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 26.45 802.76
05.01.04.11 CABLE 3-1x10mm2 H07Z-R + 1x10mm2 (N) + 1x6mm2 (T) m 57.25 28.57 1,635.63 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 57.25 1,635.63
05.01.04.12 CABLE 3-1x10mm2 H07Z-R + 1x10mm2 (N) m 251.80 25.02 6,300.04 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 251.80 6,300.04
05.01.04.13 CABLE 3-1x6mm2 H07Z-R + 1x6mm2 (N) + 1x10mm2 (T) m 30.60 23.24 711.14 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 30.60 711.14
05.01.04.14 CABLE 3-1x6mm2 H07Z-R + 1x6mm2 (N) + 1x6mm2 (T) m 96.60 23.95 2,313.57 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 96.60 2,313.57
05.01.04.15 CABLE 3-1x6mm2 H07Z-R + 1x6mm2 (N) + 1x4mm2 (T) m 56.50 19.87 1,122.66 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 56.50 1,122.66
05.01.04.16 CABLE 3-1x6mm2 H07Z-R + 1x6mm2 (N) m 608.55 20.40 12,414.42 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 608.55 12,414.42
05.01.04.17 CABLE 1-1x16mm2 H07Z-R + 1x16mm2 (N) m 17.70 16.97 300.37 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 17.70 300.37
05.01.04.18 CABLE 1-1x10mm2 H07Z-R + 1x10mm2 (N) + 1x6mm2 (T) m 15.90 18.79 298.76 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 15.90 298.76
05.01.04.19 CABLE 1-1x10mm2 H07Z-R + 1x10mm2 (N) m 11.00 14.38 158.18 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 11.00 158.18
05.01.04.20 CABLE 1-1x6mm2 H07Z-R + 1x6mm2 (N) + 1x6mm2 (T) m 523.60 15.62 8,178.63 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 523.60 8,178.63
05.01.04.21 CABLE 1-1x6mm2 H07Z-R + 1x6mm2 (N) + 1x4mm2 (T) m 128.25 12.77 1,637.75 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 128.25 1,637.75
05.01.04.22 CABLE 1-1x6mm2 H07Z-R + 1x6mm2 (N) m 95.25 11.44 1,089.66 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 95.25 1,089.66
05.01.04.23 CABLE 1x4mm2 H07Z-R + 1x4mm2 (N) + 1x4mm2 (T) m 12,333.56 9.78 120,622.22 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 12,333.56 120,622.22
05.01.04.24 CABLE 1x2.5mm2 H07Z-R + 1x2.5mm2 (N) + 1x2.5mm2 (T) m 1,002.25 7.34 7,356.52 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1,002.25 7,356.52
05.01.05 SUMINISTRO E INSTALACION DE TABLEROS ELECTRICOS - 0.00
05.01.05.01 TABLEROS GENERALES - 0.00
05.01.05.01.01 TABLERO GENERAL DE DISTRIBUCION TGI und 1.00 6,150.62 6,150.62 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 6,150.62
05.01.05.01.02 TABLERO TRANSFERENCIA AUTOMATICA TTA 9.4KW und 1.00 9,346.36 9,346.36 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 9,346.36
05.01.05.01.03 TABLERO GENERAL DE EMERGENCIA INICIAL TGEM und 1.00 7,181.82 7,181.82 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 7,181.82
05.01.05.01.04 TABLERO GENERAL DE BOMBAS TGB und 1.00 2,926.62 2,926.62 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,926.62
05.01.05.01.05 TABLERO GENERAL DE COLEGIO (TGG-COLEGIO) und 1.00 17,983.63 17,983.63 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 17,983.63
05.01.05.01.06 TABLERO DE TRANSFERENCIA AUTOMATICA TTA 53 KW und 1.00 9,872.10 9,872.10 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 9,872.10
05.01.05.01.07 TABLERO GENERAL DE EMERGENCIA (TGEM) und 1.00 5,833.62 5,833.62 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 5,833.62
05.01.05.01.08 TABLERO GENERAL DE BOMBAS TG-B und 1.00 2,811.42 2,811.42 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,811.42
05.01.06 TABLEROS DE DISTRIBUCION -
05.01.06.01 TABLERO DE DISTRIBUCION TDI-A und 1.00 3,405.82 3,405.82 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,405.82
05.01.06.02 TABLERO DE DISTRIBUCION TDI-C und 1.00 2,701.02 2,701.02 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,701.02
05.01.06.03 TABLERO DE DISTRIBUCION TDI-B und 1.00 2,805.02 2,805.02 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,805.02
05.01.06.04 TABLERO DE DISTRIBUCION TDI-D und 1.00 3,557.02 3,557.02 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,557.02
05.01.06.05 TABLERO DE DISTRIBUCION TDI-F und 1.00 1,331.31 1,331.31 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,331.31
05.01.06.06 TABLERO ELECTRICO DISTRIBUCION TEMI-COM und 1.00 4,028.22 4,028.22 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,028.22
05.01.06.07 TABLERO ELECTRICO DISTRIBUCION TDI-COC und 1.00 2,501.02 2,501.02 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,501.02
05.01.06.08 TABLERO ELECTRICO DISTRIBUCION TD-A1 und 1.00 6,312.91 6,312.91 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 6,312.91
05.01.06.09 TABLERO ELECTRICO DISTRIBUCION TD-A2 und 1.00 3,872.11 3,872.11 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,872.11
05.01.06.10 TABLERO ELECTRICO DISTRIBUCION TD-B1 und 1.00 3,542.80 3,542.80 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,542.80
05.01.06.11 TABLERO ELECTRICO DISTRIBUCION TD-C1 und 1.00 4,699.42 4,699.42 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,699.42
05.01.06.12 TABLERO ELECTRICO DISTRIBUCION TD-C2 und 1.00 4,604.22 4,604.22 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,604.22
05.01.06.13 TABLERO ELECTRICO DISTRIBUCION TD-D1 und 1.00 4,651.42 4,651.42 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,651.42
05.01.06.14 TABLERO DE DISTRIBUCION MODULO DE CONECTIVIDAD PRIMARIA TD MC P und 1.00 3,864.91 3,864.91 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,864.91
05.01.06.15 TABLERO DE DISTRIBUCION DE COCINA PRIMARIA TD-COCP und 1.00 4,286.97 4,286.97 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,286.97
05.01.06.16 TABLERO DE DISTRIBUCION QUIOSCO PRIMARIA TD-QUI.P und 1.00 1,360.11 1,360.11 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,360.11
05.01.06.17 TABLERO ELECTRICO DISTRIBUCION LOZA DEPORTIVA PRIMARIA TD-LD P und 1.00 3,697.82 3,697.82 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,697.82
05.01.06.18 TABLERO DE DISTRIBUCION TD-E1 und 1.00 4,118.51 4,118.51 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,118.51
05.01.06.19 TABLERO DE DISTRIBUCION TD-E2 und 1.00 6,112.91 6,112.91 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 6,112.91
05.01.06.20 TABLERO DE DISTRIBUCION TD-FA1 und 1.00 5,846.62 5,846.62 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 5,846.62
05.01.06.21 TABLERO DE DISTRIBUCION TD-FB1 und 1.00 5,473.82 5,473.82 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 5,473.82
05.01.06.22 TABLERO DE DISTRIBUCION TD-FA2 und 1.00 4,124.22 4,124.22 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,124.22
05.01.06.23 TABLERO DE DISTRIBUCION TD-FB2 und 1.00 5,352.64 5,352.64 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 5,352.64
05.01.06.24 TABLERO DE DISTRIBUCION TD-G1 und 1.00 4,509.02 4,509.02 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,509.02
05.01.06.25 TABLERO DE DISTRIBUCION MODULO DE CONECTIVIDAD SEGUNDARIA TD MCS und 1.00 3,691.31 3,691.31 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,691.31
05.01.06.26 TABLERO DE DISTRIBUCION COCINA SEGUNDARIA TD-COCS und 1.00 2,501.02 2,501.02 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,501.02
05.01.06.27 TABLERO ELECTRICO DISTRIBUCION QUIOSCO SECUNDARIA TD-QUI S und 1.00 1,384.11 1,384.11 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,384.11
05.01.06.28 TABLERO ELECTRICO DISTRIBUCION GUARDIANIA SECUNDARIA TD-GUARD S und 1.00 4,422.24 4,422.24 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,422.24
05.01.06.29 TABLERO DE EMERGENCIA TEM-A und 1.00 3,846.62 3,846.62 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,846.62
05.01.06.30 TABLERO DE EMERGENCIA TEM-B und 1.00 2,905.82 2,905.82 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,905.82
05.01.06.31 TABLERO DE EMERGENCIA TEM-C und 1.00 3,256.22 3,256.22 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,256.22
05.01.06.32 TABLERO DE EMERGENCIA TEM-D und 1.00 2,973.82 2,973.82 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,973.82

Val_I_Elec Página 19
AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
UND METRADO PRECIO UNITARIO PARCIAL Metrado Monto Metrado Monto % Metrado Monto % Metrado
05.01.06.33 TABLERO DE EMERGENCIA GUARDIANIA INICIAL TEMI-E und 1.00 2,017.02 2,017.02 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,017.02
05.01.06.34 TABLERO DE EMERGENCIA TEM-A1 und 1.00 2,815.31 2,815.31 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,815.31
05.01.06.35 TABLERO DE EMERGENCIA TEM-A2 und 1.00 4,780.91 4,780.91 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,780.91
05.01.06.36 TABLERO DE EMERGENCIA TEM-B1 und 1.00 2,144.91 2,144.91 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,144.91
05.01.06.37 TABLERO DE EMERGENCIA TEM-C1 und 1.00 3,036.22 3,036.22 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,036.22
05.01.06.38 TABLERO DE EMERGENCIA TEM-C2 und 1.00 4,028.22 4,028.22 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,028.22
05.01.06.39 TABLERO DE EMERGENCIA TEM-D1 und 1.00 1,927.31 1,927.31 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,927.31
05.01.06.40 TABLERO DE EMERGENCIA TEM-E1 und 1.00 4,445.71 4,445.71 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,445.71
05.01.06.41 TABLERO DE EMERGENCIA TEM-E2 und 1.00 4,075.99 4,075.99 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,075.99
05.01.06.42 TABLERO DE EMERGENCIA TEM-FA1 und 1.00 2,441.82 2,441.82 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,441.82
05.01.06.43 TABLERO DE EMERGENCIA TEM-FB1 und 1.00 2,493.02 2,493.02 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,493.02
05.01.06.44 TABLERO DE EMERGENCIA TEM-FA2 und 1.00 3,721.71 3,721.71 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,721.71
05.01.06.45 TABLERO DE EMERGENCIA TEM-FB2 und 1.00 3,791.31 3,791.31 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,791.31
05.01.06.46 TABLERO DE EMERGENCIA GUARDIANIA SECUNDARIA TEM-GUARD S und 1.00 4,422.24 4,422.24 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,422.24
05.01.07 SISTEMA DE PUESTA A TIERRA -
05.01.07.01 SUMINISTRO E INSTALACION DE CABLES -
05.01.07.01.01 CABLE DESNUDO CU 70 mm2 m 56.80 41.53 2,358.90 - 0.00 0.00 0.00% 0.00 0.00 0.00% 56.80 2,358.90
05.01.07.01.02 CABLE DESNUDO CU 50 mm2 m 13.85 31.19 431.98 - 0.00 0.00 0.00% 0.00 0.00 0.00% 13.85 431.98
05.01.07.01.03 CABLE DESNUDO CU 25 mm2 m 54.60 20.18 1,101.83 - 0.00 0.00 0.00% 0.00 0.00 0.00% 54.60 1,101.83
05.01.07.01.04 CABLE DESNUDO CU 16 mm2 m 35.65 15.43 550.08 - 0.00 0.00 0.00% 0.00 0.00 0.00% 35.65 550.08
05.01.07.01.05 CABLE DESNUDO CU 10 mm2 m 127.70 12.22 1,560.49 - 0.00 0.00 0.00% 0.00 0.00 0.00% 127.70 1,560.49
05.01.07.01.06 CABLE DESNUDO CU 6 mm2 m 285.00 10.24 2,918.40 - 0.00 0.00 0.00% 0.00 0.00 0.00% 285.00 2,918.40
05.01.07.02 VARIOS -
05.01.07.02.01 POZO A TIERRA R = 25 OHM und 17.00 1,473.46 25,048.82 - 0.00 0.00 0.00% 0.00 0.00 0.00% 17.00 25,048.82
05.01.07.02.02 POZO A TIERRA R = 5 OHM und 9.00 1,600.00 14,400.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 9.00 14,400.00
05.01.08 SUMINISTRO E INSTALACIÓN DE ARTEFACTOS DE ILUMINACIÓN
05.01.08.01 L1 - LUMINARIA PANEL LED DE 2´X2´, PARA ADOSAR EN TECHO, CUERPO DE und 477.00 171.36 81,738.72 - 0.00 0.00 0.00% 0.00 0.00 0.00% 477.00 81,738.72
05.01.08.02 PLANCHA FABRICADA
L2 - LUMINARIA EN ACERO
PANEL LED DELAF, DISIPADOR
2´X2´, FABRICADO
PARA EMPOTRAR ENEN ALUMINIO
BALDOSA, CUERPO und 20.00 134.17 2,683.40 - 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 2,683.40
INYECTADO,
DE ALUMINIO, DIFUSOR
DISIPADORDE FABRICADO
POLICARBONATO, EQUIPADO CON MÓDULO LED DE
SMD
05.01.08.03 L3 - LUMINARIA
34W/3930 HERMÉTICA
lm/CRI>80/4000K/IP 40 PARAEN ALUMINIO
ADOSAR, CONINYECTADO, DIFUSOR
CUERPO FABRICADO EN und 227.00 148.34 33,673.18 - 0.00 0.00 0.00% 0.00 0.00 0.00% 227.00 33,673.18
POLICARBONATO,YEQUIPADO
POLICARBONATO CUBIERTA CON
DE MÓDULO
ÓPTICA DE LED SMD 34W/3930 OPALINA,
POLICARBONATO lm/CRI>80/4000K/IP
EQUIPADA 40
05.01.08.04 L4 - DOWNLIGHT CIRCULAR PARA ADOSAR EN TECHO, CUERPO DE PLANCHA und 17.00 143.03 2,431.51 - 0.00 0.00 0.00% 0.00 0.00 0.00% 17.00 2,431.51
CON MÓDULO
FABRICADA EN LED SMDLAF,
ACERO 40W/4745
CON lm/CRI>80/4000k/IP
CUERPO Y DISIPADOR 65 FABRICADO EN ALUMINIO
05.01.08.05 L5 - DOWNLIGHT CIRCULAR PARA EMPOTRAR EN FCR, CON CUERPO Y und 143.00 111.14 15,893.02 - 0.00 0.00 0.00% 0.00 0.00 0.00% 143.00 15,893.02
INYECTADO,FABRICADO
DISIPADOR DIFUSOR DE ENMETACRILATO
ALUMINIO OPAL, EQUIPADA
INYECTADO, DIFUSOR CON MÓDULO
DEDE LED SMD
METACRILATO
05.01.08.06 L6 - DOWNLIGHT CIRCULAR
14W/1357 ADOSAR EN TECHO, CUERPO PLANCHA OPAL, und 71.00 173.14 12,292.94 - 0.00 0.00 0.00% 0.00 0.00 0.00% 71.00 12,292.94
EQUIPADAlm/CRI>80/4000K/IP
FABRICADA CON MÓDULO
EN ACERO LED
LAF,
40SMD
CON 14W/1357
CUERPO lm/CRI>80/4000K/IP
Y DISIPADOR 40
FABRICADO
05.01.08.07 L7 - PROYECTOR SIMÉTRICO PARA EXTERIORES, CON CUERPO EN ALUMINIO
Y DISIPADOR und 33.00 500.24 16,507.92 - 0.00 0.00 0.00% 0.00 0.00 0.00% 33.00 16,507.92
INYECTADO,EN
FABRICADO DIFUSOR
ALUMINIODE METACRILATO
INYECTADO OPAL, EQUIPADA
Y EXTERIORES,
CUBIERTA DE CON CONDE
ÓPTICA MÓDULO
CRISTALLED SMD
05.01.08.08 L8 - PROYECTOR
22W/2204 SIMÉTRICO
lm/CRI>80/4000K/IP 40 PARA CUERPO Y DISIPADOR und 5.00 425.05 2,125.25 - 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 2,125.25
TEMPLADO,
FABRICADO EQUIPADA
EN ALUMINIO CON MÓDULO
INYECTADO LED SMD 200W/100
Y CUBIERTA lm/W/CRI>80/4000K/IP 66
05.01.08.09 L9 - LUMINARIA RECTANGULAR, PARA ADOSARDE ENÓPTICA
TECHO,DECONCRISTAL
CUERPO und 12.00 533.32 6,399.84 - 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 6,399.84
TEMPLADO, EQUIPADA
FABRICADO EN PLANCHA CONDEMÓDULO
ACERO LED CON
LAF, SMD CUBIERTA
100W/100 lm/W/CRI>80/4000K/IP
DE ÓPTICA 66 EN
05.01.08.10 L11 - LUMINARIA DE SECCIÓN RECTANGULAR PARA ADOSAR EN FABRICADA
EXTERIORES, und 35.00 688.20 24,087.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 35.00 24,087.00
POLIESTIRENO
CON L12
CUERPO DE ALTA
FABRICADO TRANSMITANCIA,
EN ALUMINIO EQUIPADO
INYECTADO CON MÓDULO
Y CUBIERTA LED SMD
DE ÓPTICA DE
05.01.08.11 - LUMINARIA DE ALUMBRADO
382/5121 lm/CRI>80/4000K/IP 40CON MODULOPÚBLICO 1X100W, CON CARCASA FABRICADA und 4.00 1,294.93 5,179.72 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 5,179.72
POLICARBONATO,
EN ALUMINIO EQUIPADA
INYECTADO A ALTA PRESIÓN, LED SMD
CON2X100W, 300W/3826
CUBIERTA lm/CRI>80/4000K/IP
DECARCASA
CRISTAL TEMPLADO,
05.01.08.12 65 L13 - LUMINARIA DE ALUMBRADO PÚBLICO CON FABRICADA und 11.00 1,436.06
EQUIPADA CON MÓDULO LED SMDPRESIÓN,
100W/11817 lm/CRI>80/4000K/IP 65 15,796.66 - 0.00 0.00 0.00% 0.00 0.00 0.00% 11.00 15,796.66
EN ALUMINIO INYECTADO A ALTA CON CUBIERTA DE CRISTAL TEMPLADO,
05.01.08.13 EQUIPADA CON MÓDULO
L15 - DOWNLIGHT LED SMDPARA
CIRCULAR 100W/11817 lm/CRI>80/4000K/IP
SUSPENDER 65
DESDE EL TECHO, CUERPO DE und 8.00 205.02 1,640.16 - 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 1,640.16
05.01.08.14 PLANCHA
L16 - FABRICADA
DOWNLIGHTEN ACERO LAF,
CIRCULAR PARACON CUERPO
ADOSAR EN Y DISIPADOR
TECHO, FABRICADO
CUERPO EN
DE PLANCHA und 4.00 206.94 827.76 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 827.76
ALUMINIO
FABRICADA INYECTADO,
EN ACERO DIFUSOR
LAF, CON DE METACRILATO
CUERPO Y OPAL,
DISIPADOR EQUIPADA
FABRICADO CON
EN MÓDULO
ALUMINIO
05.01.08.15 L17 -22W/2204
LED SMD DOWNLIGHT CIRCULAR PARA
lm/CRI>80/4000K/IP 40SUSPENDER DESDE EL TECHO, CUERPO DE und 4.00 220.96 883.84 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 883.84
INYECTADO,
PLANCHA DIFUSOR
FABRICADA DE METACRILATO
EN ACERO LAF, CONOPAL, EQUIPADA
CUERPO CON
Y DISIPADOR MÓDULO LED
FABRICADO SMD
05.01.08.16 L19 - lm/CRI>80/4000K/IP
40W/3754 LUMINARIA HERMÉTICA 40 DE PARA ADOSAR, CON CUERPO FABRICADO ENEN und 12.00 148.34 1,780.08 - 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 1,780.08
ALUMINIO INYECTADO,
POLICARBONATO DIFUSOR
Y CUBIERTA METACRILATO
DE ÓPTICA OPAL, EQUIPADA
DE POLICARBONATO CON EQUIPADA
OPALINA, MÓDULO
05.01.08.17 L20 -40W/3754
LED SMD LUMINARIA TIPO CRUZ,PARA
lm/CRI>80/4000K/IP SUSPENDER
40 CON CUERPO FABRICADO EN und 2.00 3,924.07 7,848.14 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 7,848.14
CON MÓDULO
PLANCHA LED SMD
DE ACERO TIPO 40W/4745 lm/CRI>80/4000k/IP
LAF YCRUZ,PARA
CUBIERTA DE 66
OPTICA FABRICADA EN POLIURETANO DE
05.01.08.18 L21 -LUMINARIA SUSPENDER CON CUERPO FABRICADO EN und 1.00 5,365.95 5,365.95 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 5,365.95
ALTA TRANSMITANCIA,EQUIPADA
PLANCHA DE ACERO LAF Y CONDE
CUBIERTA MODULO
OPTICA LED SMD 225W/20475
FABRICADA EN POLIURETANO DE
05.01.08.19 L22 -LUMINARIA TIPO CRUZ,PARA SUSPENDER
LM/CRI>80/4000K/IP40-CONFIGURACION 1 CON CUERPO FABRICADO EN und 1.00 3,443.44 3,443.44 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,443.44
ALTA TRANSMITANCIA,EQUIPADA
PLANCHA CON MODULO LED SMD 338W/30758
05.01.08.20 L23 - DE ACERO LAF
LUMINARIA TIPOY CRUZ,PARA
CUBIERTA DE
LM/CRI>80/4000K/IP40-CONFIGURACION 2
OPTICA FABRICADA
SUSPENDER CON CUERPO EN POLIURETANO
FABRICADO EN DE und 1.00 2,482.19 2,482.19 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,482.19
ALTA TRANSMITANCIA,EQUIPADA
PLANCHA DE ACERO CON
LAF Y CUBIERTA MODULO LED
DE OPTICADOBLE SMD
FABRICADA ENCON
POLIURETANO
05.01.08.21 ARTEFACTO DE EMERGENCIA, REFLECTOR
216W/19656LM/CRI>80/4000K/IP40-CONFIGURACION 3 SMD 2x100W BATERÍA DE und 120.00 171.76 20,611.20 - 0.00 0.00 0.00% 0.00 0.00 0.00% 120.00 20,611.20
ALTA TRANSMITANCIA,EQUIPADA
RECARGABLE (100x55x55mm) CON MODULO LED 190W / 17290 lm/CRI>80 /
05.01.08.22 4000KEQUIPO SENSOR DE MOVIMIENTO
/ IP40 - CONFIGURACION 4 und 40.00 87.33 3,493.20 - 0.00 0.00 0.00% 0.00 0.00 0.00% 40.00 3,493.20
05.01.08.23 POSTE C.A.C. 8.0/200/2/120/240 und 15.00 886.77 13,301.55 - 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 13,301.55
05.01.09 VARIOS -
05.01.09.01 GRUPO ELECTROGENO DE 9.40 KWh und 1.00 58,005.47 58,005.47 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 58,005.47
05.01.09.02 GRUPO ELECTROGENO DE 53.0 KWh und 1.00 75,112.31 75,112.31 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 75,112.31
05.01.09.03 EXCAVACION DE ZANJA DE H=0.65 Y A=0.50 m 524.25 10.06 5,273.96 - 0.00 0.00 0.00% 0.00 0.00 0.00% 524.25 5,273.96
05.01.09.04 EXCAVACION DE ZANJA DE H=0.35 Y A=0.40 m 287.80 10.06 2,895.27 - 0.00 0.00 0.00% 0.00 0.00 0.00% 287.80 2,895.27
05.01.09.05 RELLENO Y COMPACTADO, COLOCACIÓN DE LADRILLO Y CINTA SEÑALIZADORA m 524.25 49.35 25,871.74 - 0.00 0.00 0.00% 0.00 0.00 0.00% 524.25 25,871.74
05.01.09.06 DE H=0.65m
RELLENOY A=0.50
Y COMPACTADO, COLOCACIÓN DE LADRILLO Y CINTA SEÑALIZADORA m 287.80 38.93 11,204.05 - 0.00 0.00 0.00% 0.00 0.00 0.00% 287.80 11,204.05
05.01.09.07 DE H=0.35m Y A=0.40
ELIMINACIÓN DE MATERIAL DE PROCEDENTE DE TUBERIA ELECTRICA Y m3 137.12 15.09 2,069.14 - 0.00 0.00 0.00% 0.00 0.00 0.00% 137.12 2,069.14
05.01.09.08 BUZONETA
BUZONETA ELECTRICA 40 x 40cm und 8.00 26.90 215.20 - 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 215.20
05.01.09.09 BUZONETA ELECTRICA 60 x 60cm und 36.00 37.56 1,352.16 - 0.00 0.00 0.00% 0.00 0.00 0.00% 36.00 1,352.16
05.01.09.10 SUMINISTRO DE ELECTRICA EN BAJA TENSIÓN: INICIAL glb 1.00 20,208.84 20,208.84 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 20,208.84

Val_I_Elec Página 20
AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
UND METRADO PRECIO UNITARIO PARCIAL Metrado Monto Metrado Monto % Metrado Monto % Metrado
05.01.09.11 SUMINISTRO ELECTRICA EN MEDIA TENSIÓN: PRIMARIA - SECUNDARIA glb 1.00 99,843.44 99,843.44 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 99,843.44
05.01.09.12 (AMPLIACION DE MURO
PICADO DE POTENCIA
PARADETUBERIAS
SISTEMA DE UTILIZACION DE MEDIA TENSIÓN 10KV) m 152.50 57.40 8,753.50 - 0.00 0.00 0.00% 0.00 0.00 0.00% 152.50 8,753.50
05.01.09.13 UPS 3.0 KVA RACKEABLE und 5.00 4,513.75 22,568.75 - 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 22,568.75
05.01.09.14 UPS 1.0 KVA RACKEABLE und 4.00 2,398.26 9,593.04 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 9,593.04
05.01.09.15 UPS. 5kVA 220V, 60 Hz und 1.00 5,790.00 5,790.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 5,790.00
05.01.09.16 UPS. 6kVA 220V, 60 Hz und 1.00 5,790.00 5,790.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 5,790.00
05.01.09.17 UPS. 3kVA 220V, 60 Hz und 3.00 5,790.00 17,370.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 17,370.00
05.01.09.18 UPS. 8kVA 220V, 60 Hz und 1.00 5,790.00 5,790.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 5,790.00
05.01.09.19 TRANSFORMADOR DE AISLAMIENTO 6kVA und 1.00 1,900.00 1,900.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,900.00
05.01.09.20 TRANSFORMADOR DE AISLAMIENTO 8kVA und 1.00 3,200.00 3,200.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,200.00
05.01.09.21 TRANSFORMADOR DE AISLAMIENTO 3kVA und 3.00 1,235.00 3,705.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 3,705.00
05.01.09.22 TRANSFORMADOR DE AISLAMIENTO 10kVA und 1.00 3,400.00 3,400.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,400.00
05.01.10 PRUEBAS ELECTRICAS -
05.01.10.01 PRUEBAS ELECTRICAS glb 1.00 1,200.00 1,200.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,200.00

COSTO DIRECTO (INSTALACIONES ELECTRICAS) 1,571,062.66 0.00 33,754.41 33,754.41 1,537,308.24


GASTOS GENERALES % 8.25% 129,534.12 0.00 2,783.05 2,783.05 126,751.06
UTILIDAD % 6.00% 94,263.76 0.00 2,025.26 2,025.26 92,238.49
SUBTOTAL (INSTALACIONES ELECTRICAS) 1,794,860.54 0.00 38,562.73 2.15% 38,562.73 2.15% 1,756,297.80

Val_I_Elec Página 21
VALORIZACION DE OBRA Nº 02 INSTALACIONES DE COMUNICACIONES
(PERIODO : DEL 01 DE JUNIO AL 30 DE JUNIO 2022)

OBRA: “MEJORAMIENTO Y AMPLIACION DEL SERVICIO EDUCATIVO DE LA II.EE. FE Y ALEGRIA N° 52, SECTOR PAMPA INALAMBRICA DISTRITO DE ILO, PROVINCIA DE ILO DEPARTAMENTO DE MOQUEGUA” CUI N°2234866
UBICACIÓN: MOQUEGUA - ILO - ILO

AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
UND METRADO PRECIO UNITARIO PARCIAL Metrado Monto Metrado Monto % Metrado Monto % Metrado

I. MODULOS
06 INSTALACIONES DE COMUNICACIONES
06.01 SISTEMA DE COMUNICACIÓN DE VOZ Y DATOS
06.01.01 SISTEMA DE COMUNICACIONES
06.01.01.01 SALIDAS DEALARMA Y DETECCION
06.01.01.01.01 SALIDAS
06.01.01.01.01.01 SALIDA PARA DETECTOR DE HUMO EN TECHO pto 237.00 42.00 9,954.00 - 0.00 82.00 3,444.00 35.00% 82.00 3,444.00 35.00% 155.00 6,510.00
06.01.01.01.01.02 SALIDA PARA DETECTOR DE TEMPERATURA EN TECHO pto 3.00 42.00 126.00 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 126.00
06.01.01.01.01.03 SALIDA PARA ESTACION MANUAL CONTRA INCENDIOS pto 22.00 42.00 924.00 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 22.00 924.00
06.01.01.01.01.04 SALIDA PARA PARLANTE CON LUZ ESTROBOSCOPICA EN PARED pto 21.00 42.00 882.00 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 21.00 882.00
06.01.01.01.01.05 SALIDA DE DETECTOR MULTIPROPOSITOS EN TECHO pto 12.00 42.00 504.00 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 504.00
06.01.01.01.01.06 SALIDA DE PANEL DE CONTROL DE ALARMA DE INCENDIO pto 3.00 42.00 126.00 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 126.00
06.01.01.01.01.07 SALIDA DE SENSOR DE ANIEGO EN PISO pto 1.00 42.00 42.00 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 42.00
06.01.01.02 SALIDAS DE AUDIO Y PERIFONEO -
06.01.01.02.01 SALIDAS -
06.01.01.02.01.01 SALIDA DE PARLANTES DE 75W pto 12.00 42.00 504.00 - 0.00 8.00 336.00 67.00% 8.00 336.00 67.00% 4.00 168.00
06.01.01.02.01.02 SALIDA DE ALTAVOZ DE 150W pto 12.00 42.00 504.00 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 504.00
06.01.01.02.01.03 SALIDA DE FACEPLATE MULTIMEDIA pto 94.00 42.00 3,948.00 - 0.00 6.00 252.00 6.00% 6.00 252.00 6.00% 88.00 3,696.00
06.01.01.03 SALIDAS DE VOZ Y DATOS -
06.01.01.03.01 SALIDAS -
06.01.01.03.01.01 SALIDA SIMPLE PARA CAMARA FIJA TIPO BULLET pto 36.00 42.00 1,512.00 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 36.00 1,512.00
06.01.01.03.01.02 SALIDA DE ESTACION DE TRABAJO PARA CCTV pto 2.00 42.00 84.00 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 84.00
06.01.01.03.01.03 SALIDA DE LECTORA DE ASISTENCIA pto 2.00 42.00 84.00 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 84.00
06.01.01.03.01.04 SALIDA SIMPLE PARA DATOS EN PARED pto 14.00 42.00 588.00 - 0.00 4.00 168.00 29.00% 4.00 168.00 29.00% 10.00 420.00
06.01.01.03.01.05 SALIDA DOBLE PARA DATOS EN PARED pto 4.00 42.00 168.00 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 168.00
06.01.01.03.01.06 SALIDA SIMPLE PARA DATOS EN MUEBLES pto 46.00 42.00 1,932.00 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 46.00 1,932.00
06.01.01.03.01.07 SALIDA DOBLE PARA DATOS EN MUEBLES pto 3.00 42.00 126.00 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 126.00
06.01.01.03.01.08 SALIDA SIMPLE PARA DATOS EN TECHO pto 7.00 42.00 294.00 - 0.00 2.00 84.00 29.00% 2.00 84.00 29.00% 5.00 210.00
06.01.01.03.01.09 SALIDA PARA ACCESS POINT EN TECHO pto 21.00 42.00 882.00 - 0.00 2.00 84.00 10.00% 2.00 84.00 10.00% 19.00 798.00
06.01.01.03.01.10 SALIDA SIMPLE PARA CAMARA FIJA TIPO PTZ pto 3.00 42.00 126.00 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 126.00
06.01.01.03.01.11 SALIDA DOBLE PARA VOZ Y DATOS EN MUEBLE pto 7.00 42.00 294.00 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 7.00 294.00
06.01.01.03.02 TUBERIAS Y ACCESORIOS -
06.01.01.03.02.01 TUBERIA DE PVC-P DE Ø20mm m 1,517.99 11.65 17,684.58 - 0.00 465.00 5,417.25 31.00% 465.00 5,417.25 31.00% 1,052.99 12,267.33
06.01.01.03.02.02 TUBERIA DE PVC-P DE Ø25mm m 1,566.47 12.77 20,003.82 - 0.00 65.00 830.05 4.00% 65.00 830.05 4.00% 1,501.47 19,173.77
06.01.01.03.02.03 TUBERIA DE PVC-P DE Ø50mm m 1,233.99 17.61 21,730.56 - 0.00 60.00 1,056.60 5.00% 60.00 1,056.60 5.00% 1,173.99 20,673.96
06.01.01.03.02.04 TUBERIA DE PVC-P DE Ø75mm m 1,107.19 22.44 24,845.34 - 0.00 1.00 22.44 0.00% 1.00 22.44 0.00% 1,106.19 24,822.90
06.01.01.03.02.05 TUBERIA DE PVC-P DE Ø100mm m 131.53 32.00 4,208.96 - 0.00 1.00 32.00 1.00% 1.00 32.00 1.00% 130.53 4,176.96
06.01.01.03.02.06 TUBERIA CONDUIT EMT Ø25mm m 367.85 16.65 6,124.70 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 367.85 6,124.70
06.01.01.03.03 VARIOS -
06.01.01.03.03.01 CAJA DE PASE 150x150x100mm und 157.00 28.09 4,410.13 - 0.00 7.00 196.63 4.00% 7.00 196.63 4.00% 150.00 4,213.50
06.01.01.03.03.02 CAJA DE PASE 200x200x100mm und 27.00 33.50 904.50 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 27.00 904.50
06.01.01.03.03.03 CAJA DE PASE 300x300x100mm und 18.00 44.93 808.74 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 808.74
06.01.01.03.03.04 CAJA DE PASE 400x400x100mm und 21.00 56.58 1,188.18 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 21.00 1,188.18
06.01.01.03.03.05 CAJA DE PASE OCTOGONAL und 34.00 23.78 808.52 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 34.00 808.52
06.01.01.10 OBRAS CIVILES REDES EXTERIORES -
06.01.01.10.01 CONCRETO SOLADO e=0.05m, MEZCLA DE 1:8 CEMENTO - HORMIGON m2 457.87 17.00 7,783.79 - 0.00 0.00 0.00% 0.00 0.00 0.00% 457.87 7,783.79
06.01.01.10.02 BUZON CONCRETO TIPO 1 und 20.00 1,700.00 34,000.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 34,000.00
06.01.01.10.03 EXCAVACION DE BUZON DE CONCRETO m3 17.63 40.00 705.20 - 0.00 0.00 0.00% 0.00 0.00 0.00% 17.63 705.20
06.01.01.10.04 EXCAVACION DE ZANJA DE H=0.40 Y A=0.50 m 95.26 8.01 763.03 - 0.00 0.00 0.00% 0.00 0.00 0.00% 95.26 763.03
06.01.01.10.05 EXCAVACION DE ZANJA DE H=.60 Y A=0.50 m 805.15 11.68 9,404.15 - 0.00 0.00 0.00% 0.00 0.00 0.00% 805.15 9,404.15
06.01.01.10.06 ELIMINACION DE MATERIAL EXCEDENTE m3 265.20 27.43 7,274.44 - 0.00 0.00 0.00% 0.00 0.00 0.00% 265.20 7,274.44
06.01.01.10.07 RELLENO, COMPACTACION Y COLOCACION DE CINTA SEÑALIZADORA DE ZANJA m 95.26 14.65 1,395.56 - 0.00 0.00 0.00% 0.00 0.00 0.00% 95.26 1,395.56
06.01.01.10.08 H=0.40
RELLENO, COMPACTACION Y COLOCACION DE CINTA SEÑALIZADORA DE ZANJA m 820.48 16.73 13,726.63 - 0.00 0.00 0.00% 0.00 0.00 0.00% 820.48 13,726.63
H=0.60

Val_I_Comu Página 22
AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
UND METRADO PRECIO UNITARIO PARCIAL Metrado Monto Metrado Monto % Metrado Monto % Metrado
06.01.01.10.09 POSTE C.A.C. 8.0/200/2/120/240 und 2.00 650.00 1,300.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 1,300.00
06.01.01.10.10 BRAZO PARA CAMARAS TIPO BULLET und 37.00 90.00 3,330.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 37.00 3,330.00
06.01.01.10.11 PASTORAL PARA CAMARA TIPO PTZ und 2.00 130.00 260.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 260.00
06.01.01.11 CANALIZACIÓN -
06.01.01.11.01 TUBERIA PVC-P (ELECTRICA) Ø50mm ENTERRADA m 1,711.59 17.61 30,141.10 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1,711.59 30,141.10
06.01.01.11.02 TUBERIA PVC-P (ELECTRICA) Ø75mm ENTERRADA m 5.68 22.44 127.46 - 0.00 0.00 0.00% 0.00 0.00 0.00% 5.68 127.46
06.01.01.11.03 TUBERIA PVC-P (ELECTRICA) Ø100mm ENTERRADA m 406.01 27.28 11,075.95 - 0.00 0.00 0.00% 0.00 0.00 0.00% 406.01 11,075.95

COSTO DIRECTO (INSTALACIONES DE COMUNICACIONES ) 247,609.36 0.00 11,922.97 11,922.97 156,888.05


GASTOS GENERALES % 8.25% 20,415.39 0.00 983.05 983.05 12,935.42
UTILIDAD % 6.00% 14,856.56 0.00 715.38 715.38 9,413.28
SUBTOTAL (INSTALACIONES DE COMUNICACIONES) 282,881.31 0.00 13,621.40 4.82% 13,621.40 4.82% 179,236.75

Val_I_Comu Página 23
VALORIZACION DE OBRA Nº 02 INSTALACIONES DE GAS E II.MM
(PERIODO : DEL 01 DE JUNIO AL 30 DE JUNIO 2022)

OBRA: “MEJORAMIENTO Y AMPLIACION DEL SERVICIO EDUCATIVO DE LA II.EE. FE Y ALEGRIA N° 52, SECTOR PAMPA INALAMBRICA DISTRITO DE ILO, PROVINCIA DE ILO DEPARTAMENTO DE MOQUEGUA” CUI N°2234866
UBICACIÓN: MOQUEGUA - ILO - ILO

AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
UND METRADO PRECIO UNITARIO PARCIAL Metrado Monto Metrado Monto % Metrado Monto % Metrado

I. MODULOS
07 INSTALACIONES DE GAS E II.MM
07.01 INSTALACION DE GAS
07.01.01 SALIDAS
07.01.01.01 SALIDA EN MESAS DE LABORATORIO pto 6.00 24.60 147.60 - 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 147.60
07.01.01.02 SALIDA PARA COCINA A GAS pto 3.00 24.60 73.80 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 73.80
07.01.01.03 SALIDA DE COCINA EN MUEBLE pto 2.00 24.60 49.20 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 49.20
07.01.02 TUBERIAS -
07.01.02.01 TUBERIA DE Cu TIPO L DE 3/4" m 85.80 12.63 1,083.65 - 0.00 0.00 0.00% 0.00 0.00 0.00% 85.80 1,083.65
07.01.03 REGULADORES -
07.01.03.01 VALVULA DE CORTE 3/4" ADOSADOS PARA BALONES DE GAS DE 45 KG und 14.00 47.20 660.80 - 0.00 0.00 0.00% 0.00 0.00 0.00% 14.00 660.80
07.01.03.02 MANOMETRO DE 0 - 150 PSI ALT. 1.65 ADOSADO EN MURO und 4.00 51.59 206.36 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 206.36
07.01.03.03 MANOMETRO DE 0 - 30 PSI ALT. 1.70 ADOSADO EN MURO und 4.00 51.59 206.36 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 206.36
07.01.03.04 VALVULA DE CORTE 3/4" GENERAL ADOSADO EN MURO und 4.00 47.20 188.80 - 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 188.80
07.01.03.05 VALVULA DE CORTE 3/4" EMPOTRADA PARA COCINA und 3.00 47.20 141.60 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 141.60
07.01.03.06 VALVULA DE CORTE 3/4" ADOSADO PARA MESA DE LABORATORIO und 6.00 47.20 283.20 - 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 283.20
07.01.03.07 REGULADOR REGO 597FB ALT 1.60 ADOSADO EN MURO und 3.00 98.40 295.20 - 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 295.20
07.01.03.08 REGULADOR INTEGRAL 506/77 ALT 1.60m ADOSADO EN MURO und 1.00 114.80 114.80 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 114.80
07.01.04 VARIOS -
07.01.04.01 BALON DE GAS DE 10 KG und 2.00 99.77 199.54 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 199.54
07.01.04.02 BALON DE GAS DE 45 KG und 14.00 396.72 5,554.08 - 0.00 0.00 0.00% 0.00 0.00 0.00% 14.00 5,554.08
07.01.04.03 PRUEBAS Y PUESTA EN OPERACIONES DE LOS SISTEMAS glb 1.00 3,280.00 3,280.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,280.00
07.02 INSTALACIONES HVAC -
07.02.01 DUCTOS -
07.02.01.01 DUCTOS DE PLANCHA DE FIERRO GALVANIZADA -
07.02.01.01.01 FABRICACION, SUMINISTRO E INSTALACION DE DUCTOS METALICOS kg 613.86 82.00 50,336.52 - 0.00 0.00 0.00% 0.00 0.00 0.00% 613.86 50,336.52
07.02.01.01.02 SUMINISTRO E INSTALACION DE AISLAMIENTO DE LANA DE VÍDRIO m2 52.44 26.24 1,376.03 - 0.00 0.00 0.00% 0.00 0.00 0.00% 52.44 1,376.03
07.02.01.02 SUMINISTRO E INSTALACIÓN DE REJILLAS DE EXTRACCIÓN und 11.00 178.92 1,968.07 - 0.00 0.00 0.00% 0.00 0.00 0.00% 11.00 1,968.07
07.02.02 EQUIPOS -
07.02.02.01 SUMINISTRO E INSTALACION DE EXTRACTORES DE COCINA -
07.02.02.01.01 EXTRACTOR DE COCINA ECC-01 (PRIMARIA-141) und 1.00 738.00 738.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 738.00
07.02.02.01.02 EXTRACTOR DE COCINA ECC-02 (SECUNDARIA-121) und 1.00 836.40 836.40 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 836.40
07.02.02.01.03 EXTRACTOR DE COCINA ECC-01 (INICIAL-118) und 1.00 738.00 738.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 738.00
07.02.02.02 SUMINISTRO E INSTALACION DE EXTRACTORES EÓLICOS -
07.02.02.02.01 EXTRACTOR EOLICO 1 - 440 CFM und 1.00 1,763.00 1,763.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,763.00
07.02.02.02.02 EXTRACTOR EOLICO 2 - 470 CFM und 1.00 1,763.00 1,763.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,763.00
07.02.02.02.03 EXTRACTOR EOLICO 3 - 600 CFM und 2.00 1,763.00 3,526.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 3,526.00
07.02.02.02.04 EXTRACTOR EOLICO 4 - 2070 CFM und 1.00 1,763.00 1,763.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,763.00
07.02.02.02.05 PRUEBAS DE FUNCIONAMIENTO DE LOS SISTEMAS DE VENTILACIÓN glb 1.00 2,050.00 2,050.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,050.00
07.02.03 VARIOS -
07.02.03.01 ELIMINACION MATERIAL EXCEDENTE DESECHOS TOXICOS Gbl 1.00 1,640.00 1,640.00 - 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,640.00

COSTO DIRECTO (INSTALACIONES DE GAS E II.MM) 80,983.01 0.00 0.00 0.00 80,983.01
GASTOS GENERALES % 8.25% 6,677.05 0.00 0.00 0.00 6,677.05
UTILIDAD % 6.00% 4,858.98 0.00 0.00 0.00 4,858.98
SUBTOTAL (INSTALACIONES DE GAS E II.MM.) 92,519.04 0.00 0.00 0.00% 0.00 0.00% 92,519.04

Val_I_Gas Página 24
VALORIZACION DE OBRA Nº 02 COVID-19
(PERIODO : DEL 01 DE JUNIO AL 30 DE JUNIO 2022)

OBRA: “MEJORAMIENTO Y AMPLIACION DEL SERVICIO EDUCATIVO DE LA II.EE. FE Y ALEGRIA N° 52, SECTOR PAMPA INALAMBRICA DISTRITO DE ILO, PROVINCIA DE ILO DEPARTAMENTO DE MOQUEGUA” CUI N°2234866
UBICACIÓN: MOQUEGUA - ILO - ILO

AVANCES
PRESUPUESTO SALDO
ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION DE PARTIDA
UND METRADO PRECIO UNITARIO PARCIAL Metrado Monto Metrado Monto % Metrado Monto % Metrado

I. MODULOS
8 COVID -19
08.01 FUMIGACION POR DESINFECCION DE OFICINAS Y OBRAS mes 13.00 3,280.00 42,640.00 2.72 8,920.55 1.00 3,280.00 8.00% 3.72 12,200.55 29.00% 9.28 30,439.45
08.02 HIPOCLORITO DE SODIO gal 153.00 10.02 1,533.06 26.61 266.67 12.94 129.66 8.00% 39.55 396.33 26.00% 113.45 1,136.73
08.03 PAÑOS DE LIMPIEZA INDUSTRIAL und 240.00 10.69 2,565.60 50.65 541.44 18.57 198.51 8.00% 69.22 739.95 29.00% 170.78 1,825.65
08.04 PULVERIZADORES MANUALES DE 1LT DE PLASTICO und 50.00 1.95 97.50 8.00 15.60 0.00 0.00 0.00% 8.00 15.60 16.00% 42.00 81.90
08.05 PULVERIZADOR TIPO MOCHILA DE 20 LT und 6.00 80.62 483.72 2.00 161.24 0.00 0.00 0.00% 2.00 161.24 33.00% 4.00 322.48
08.06 BANDEJAS METALICAS PARA DESINFECCION DE CALZADO und 8.00 100.19 801.52 3.00 300.57 0.00 0.00 0.00% 3.00 300.57 38.00% 5.00 500.95
08.07 ALCOHOL ETILICO RECTIFICADO AL 70% gal 156.00 28.58 4,458.48 24.45 698.85 13.02 372.11 8.00% 37.47 1,070.96 24.00% 118.53 3,387.52
08.08 TERMOMETROS DIGITALES SIN CONTACTO und 4.00 100.79 403.16 3.00 302.37 0.00 0.00 0.00% 3.00 302.37 75.00% 1.00 100.79
08.09 APLICACIÓN DE PRUEBA SEROLOGICAS PARA COVID-19 und 413.00 20.17 8,330.21 96.00 1,936.32 54.00 1,089.18 13.00% 150.00 3,025.50 36.00% 263.00 5,304.71
08.10 PULSIOXIMETROS DIGITALES und 4.00 80.69 322.76 3.00 242.07 0.00 0.00 0.00% 3.00 242.07 75.00% 1.00 80.69
08.11 LAVADEROS PORTATILES und 6.00 123.00 738.00 6.00 738.00 0.00 0.00 0.00% 6.00 738.00 100.00% 0.00 0.00
08.12 DISPENSADORES DE ALCOHOL GEL 500 ML und 50.00 13.45 672.50 14.00 188.30 4.00 53.80 8.00% 18.00 242.10 36.00% 32.00 430.40
08.13 ALCOHOL GEL AL 70% gal 612.00 8.39 5,134.68 69.11 579.84 53.33 447.44 9.00% 122.44 1,027.28 20.00% 489.56 4,107.40
08.14 JABON LIQUIDO ANTIBACTERIAL gal 152.00 37.05 5,631.60 28.44 1,053.64 12.04 446.08 8.00% 40.48 1,499.72 27.00% 111.52 4,131.88
08.15 ROLLOS DE PAPEL TOALLA INDUSTRIAL und 444.00 3.29 1,460.76 78.08 256.88 36.85 121.24 8.00% 114.93 378.12 26.00% 329.07 1,082.64
08.16 MATERIALES PARA CAPACITACION und 1.00 16.80 16.80 0.28 4.65 0.08 1.34 8.00% 0.36 5.99 36.00% 0.64 10.81
08.17 SEÑALETICA DE SEGURIDAD und 180.00 6.66 1,198.80 40.16 267.47 13.70 91.24 8.00% 53.86 358.71 30.00% 126.14 840.09
08.18 MASCARILLAS QUIRURGICAS DE 3 PLIEGUES cja 1,770.00 10.02 17,735.40 162.00 1,623.24 113.00 1,132.26 6.00% 275.00 2,755.50 16.00% 1,495.00 14,979.90
08.19 CARETAS FACIALES und 30.00 1.68 50.40 8.30 13.94 2.22 3.73 7.00% 10.52 17.67 35.00% 19.48 32.73
08.20 CONTENEDOR DE DESECHO BIOCONTAMINADOS 120 L und 18.00 130.38 2,346.84 18.00 2,346.84 0.00 0.00 0.00% 18.00 2,346.84 100.00% 0.00 0.00
08.21 BOLSA DE PLASTICOS ROJAS pqt 609.00 3.03 1,845.27 76.35 231.36 54.54 165.26 9.00% 130.89 396.62 21.00% 478.11 1,448.65
08.22 ARMARIO 02 PUERTAS / GABINETE METALICO PARA GUARDAR INSUMOS pza 2.00 133.81 267.62 - 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 267.62
08.23 PANEL DE INFORMACION und 4.00 10.09 40.36 3.00 30.27 1.00 10.09 25.00% 4.00 40.36 100.00% 0.00 0.00
08.24 PANEL DE PREVENCION und 4.00 10.09 40.36 - 0.00 4.00 40.36 100.00% 4.00 40.36 100.00% 0.00 0.00
08.25 KIT DE EMERGENCIA (TRAJE DE PROTECCION BIOLOGICA und 6.00 33.62 201.72 2.00 67.24 0.00 0.00 0.00% 2.00 67.24 33.00% 4.00 134.48

COSTO DIRECTO (COVID) 99,017.12 20,787.35 7,582.30 28,369.65 70,647.47


GASTOS GENERALES % 8.25% 8,163.96 1,713.92 625.16 2,339.08 5,824.88
UTILIDAD % 6.00% 5,941.03 1,247.24 454.94 1,702.18 4,238.85
SUBTOTAL (COVID-19) 113,122.11 23,748.51 8,662.40 7.66% 32,410.91 28.65% 80,711.20

Val_Covid Página 25
COSTES PNLLA MAYO/ SCTR / VIDA LEY

SUBCONTRATISTAS REBISEQ

SEMANA 22-22 SEMANA 23-22


OT (30/05 A 05/06) (06/06 A 12/06)
Cantidad de Trabajadores 58 60
SALARIO 16,912.35 21,751.43
Descanso Medico
BUC 5,235.69 6,737.28
Movilidad 2,192.00 2,792.00
Dominical 2,818.72 3,625.24
Vacac. 10% 1,691.23 2,175.14
Indemn.CTS 15% 2,536.85 3,262.71
GRATIF. GRAV. 3,253.43 4,804.48
S/:H.E 60% 984.30 831.45
S/.H.E 100% 237.75
Asig Esc. 1,305.75 1,929.87
Bonificacion ley 292.81 432.40
Bono Altitud
BAE
Reintegro 896.62
Escolaridad
Adelantos
Bono Feriado
ESSALUD 2,509.21 3,160.86
AFP RIESGO 239.66 301.70
COSTO EMPRESA 41,106.37 51,804.56
SCTR PENSION Y SALUD - VIDA LEY
TOTAL COSTO A DESCONTAR ABRIL 2022 41,106.37 51,804.56
AYO/ SCTR / VIDA LEY

REBISEQ

SEMANA 24-22 SEMANA 25-22 SEMANA 26-22 TOTAL


(13/06 A 19/06) (20/06 A 26/06) (27/06 A 03/07)
64 77 94
22,962.14 27,926.94 34,367.23 123,920.09
0.00
7,121.49 8,653.92 10,658.92 38,407.30
2,928.00 3,584.00 3,768.00 15,264.00
3,827.02 4,654.49 5,727.87 20,653.34
2,296.21 2,792.69 3,436.72 12,391.99
3,444.32 4,189.04 5,155.08 18,588.00
5,012.04 6,123.61 7,566.16 26,759.72
1,293.50 2,575.20 2,424.30 8,108.75
58.45 571.11 2,866.06 3,733.37
1,862.28 1,815.35 2,011.24 8,924.49
451.08 551.12 680.95 2,408.36
0.00
16.72 16.72
896.62
0.00
0.00
0.00
3,380.30 4,245.70 6,224.69 19,520.76
323.08 414.51 489.66 1,768.61
54,959.91 68,097.68 85,393.60 301,362.12
671.97 671.97 PDTE DESCTO
54,959.91 68,097.68 86,065.57 302,034.09
CALCULO DE AMORTIZACION ADELANTO DE MATERIALES

Fecha 7/25/2022

PARTIDA DESCRIPCION

ACERO DE REFUERZO ACERO CORRUGADO FY=4200 kg/cm2 GRADO 60


20370146994 acero corrugado fy=4200 kg/cm2 grado 60CORPORACION ACEROS AREQUIPA
20370146994 acero corrugado fy=4200 kg/cm2 grado 60CORPORACION ACEROS AREQUIPA
20370146994 acero corrugado fy=4200 kg/cm2 grado 60CORPORACION ACEROS AREQUIPA
20370146994 acero corrugado fy=4200 kg/cm2 grado 60CORPORACION ACEROS AREQUIPA
20370146994 acero corrugado fy=4200 kg/cm2 grado 60CORPORACION ACEROS AREQUIPA
20370146994 acero corrugado fy=4200 kg/cm2 grado 60CORPORACION ACEROS AREQUIPA
20370146994 acero corrugado fy=4200 kg/cm2 grado 60CORPORACION ACEROS AREQUIPA
20370146994 acero corrugado fy=4200 kg/cm2 grado 60CORPORACION ACEROS AREQUIPA
20370146994 acero corrugado fy=4200 kg/cm2 grado 60CORPORACION ACEROS AREQUIPA
20370146994 acero corrugado fy=4200 kg/cm2 grado 60CORPORACION ACEROS AREQUIPA
20370146994 acero corrugado fy=4200 kg/cm2 grado 60CORPORACION ACEROS AREQUIPA
20370146994 acero corrugado fy=4200 kg/cm2 grado 60CORPORACION ACEROS AREQUIPA
20370146994 acero corrugado fy=4200 kg/cm2 grado 60CORPORACION ACEROS AREQUIPA
20370146994 acero corrugado fy=4200 kg/cm2 grado 60CORPORACION ACEROS AREQUIPA
20370146994 acero corrugado fy=4200 kg/cm2 grado 60CORPORACION ACEROS AREQUIPA
20370146994 acero corrugado fy=4200 kg/cm2 grado 60CORPORACION ACEROS AREQUIPA
20370146994 acero corrugado fy=4200 kg/cm2 grado 60CORPORACION ACEROS AREQUIPA
20370146994 acero corrugado fy=4200 kg/cm2 grado 60CORPORACION ACEROS AREQUIPA
20370146994 acero corrugado fy=4200 kg/cm2 grado 60CORPORACION ACEROS AREQUIPA
20370146995 acero corrugado fy=4200 kg/cm2 grado 60CORPORACION ACEROS AREQUIPA
20370146996 acero corrugado fy=4200 kg/cm2 grado 61CORPORACION ACEROS AREQUIPA
20370146997 acero corrugado fy=4200 kg/cm2 grado 62CORPORACION ACEROS AREQUIPA

ACERO DE REFUERZO ALAMBRE NEGRO Nro. 16


20370146994 alambre negro nro. 16 CORPORACION ACEROS AREQUIPA
20370146994 alambre negro nro. 16 CORPORACION ACEROS AREQUIPA

ENCOFRADOS ALAMBRE NEGRO Nro. 8


20370146994 alambre negro nro. 8 CORPORACION ACEROS AREQUIPA
20532521174 Liston 4x3x3m COMERCIAL MALDONADO ILO E.I.R.L

CONCRETO
CONCRETO CONCRETO PREMEZCLADO 100 Kg/Cm2, C. tipo HS
CONCRETO CONCRETO PREMEZCLADO 175 Kg/Cm2, C. tipo HS
CONCRETO CONCRETO PREMEZCLADO 210 Kg/Cm2, C. tipo HS
CONCRETO CONCRETO PREMEZCLADO 315 Kg/Cm2, C. tipo HS
CONCRETO SERVICIO DE BOMBA PARA CONCRETO PREMEZCLADO
20392965191 concreto premezclado 100 kg/cm2, c. tipo CONCRETOS SUPERMIX S.A.
20392965191 concreto premezclado 175 kg/cm2, c. tipo CONCRETOS SUPERMIX S.A.
20392965191 concreto premezclado 210 kg/cm2, c. tipo CONCRETOS SUPERMIX S.A.
20392965191 concreto premezclado 315 kg/cm2, c. tipo CONCRETOS SUPERMIX S.A.
20392965191 servicio de bomba para concreto premezclCONCRETOS SUPERMIX S.A.
20392965191 concreto premezclado 100 kg/cm2, c. tipo CONCRETOS SUPERMIX S.A.
20392965191 concreto premezclado 315 kg/cm2, c. tipo CONCRETOS SUPERMIX S.A.
20392965191 servicio de bomba para concreto premezclCONCRETOS SUPERMIX S.A.
20392965191 concreto premezclado 315 kg/cm2, c. tipo CONCRETOS SUPERMIX S.A.
20392965191 servicio de bomba para concreto premezclCONCRETOS SUPERMIX S.A.
20392965191 concreto premezclado 210 kg/cm2, c. tipo CONCRETOS SUPERMIX S.A.
20392965191 concreto premezclado 315 kg/cm2, c. tipo CONCRETOS SUPERMIX S.A.
20392965191 servicio de bomba para concreto premezclCONCRETOS SUPERMIX S.A.
20392965191 concreto premezclado 315 kg/cm2, c. tipo CONCRETOS SUPERMIX S.A.
20392965191 concreto premezclado 210 kg/cm2, c. tipo CONCRETOS SUPERMIX S.A.
20392965191 servicio de bomba para concreto premezclCONCRETOS SUPERMIX S.A.
20392965191 concreto premezclado 315 kg/cm2, c. tipo CONCRETOS SUPERMIX S.A.
20392965191 concreto premezclado 210 kg/cm2, c. tipo CONCRETOS SUPERMIX S.A.
20392965191 concreto premezclado 100 kg/cm2, c. tipo CONCRETOS SUPERMIX S.A.
20392965191 servicio de bomba para concreto premezclCONCRETOS SUPERMIX S.A.
20392965192 concreto premezclado 315 kg/cm2, c. tipo CONCRETOS SUPERMIX S.A.
20392965193 concreto premezclado 100 kg/cm2, c. tipo CONCRETOS SUPERMIX S.A.
20392965194 servicio de bomba para concreto premezclCONCRETOS SUPERMIX S.A.
20392965191 concreto premezclado 315 kg/cm2, c. ti CONCRETOS SUPERMIX S.A.
20392965191 concreto premezclado 210 kg/cm2, c. ti CONCRETOS SUPERMIX S.A.
20392965191 concreto premezclado 100 kg/cm2, c. ti CONCRETOS SUPERMIX S.A.
20392965191 servicio de bomba para concreto premeCONCRETOS SUPERMIX S.A.
20392965191 concreto premezclado 210 kg/cm2, c. ti CONCRETOS SUPERMIX S.A.

LADRILLO DE TECHO
20532830126 Ladrillo de Techo TRANSPORTES SAN CALIBU EIRL
20532830126 Ladrillo de Techo - Estiba TRANSPORTES SAN CALIBU EIRL
20532830126 Ladrillo de Techo TRANSPORTES SAN CALIBU EIRL
20532830126 Ladrillo de Techo - Estiba TRANSPORTES SAN CALIBU EIRL
20532830128 Ladrillo de Techo TRANSPORTES SAN CALIBU EIRL
20532830128 Ladrillo de Techo TRANSPORTES SAN CALIBU EIRL
20532830128 Ladrillo de Techo TRANSPORTES SAN CALIBU EIRL

ARQUITECTURA
ALBAÑILERIA
20532830127 Ladrillo para Muro TRANSPORTES SAN CALIBU EIRL

INSTALACIONES ELECTRICAS Y INSTALACION DE COMUNICACIONES


20603515014 Tuberia Electrica GRUPO INVERSIONES SOPHIE ESPERA
20603515015 Tuberia Electrica GRUPO INVERSIONES SOPHIE ESPERA
20471132021 Electricas cajas ortogonales rectangulares,INDUSTRIAS JORMEN SRL
20471132021 Electricas cajas ortogonales rectangulares,INDUSTRIAS JORMEN SRL
20100067839 Tuberia Electrica TUBOPLAST S.A
OP-TP-SST-COVID VARIOS (OP-TP-SST-COVID)
06 tachos de 120 lts, distribuidora fjj s.a.c 06 TACHOS DE 120 LTS, DISTRIBUIDORA FJJ S.A.C
abtao garcia jose luis - insumos de plan cov ABTAO GARCIA JOSE LUIS - INSUMOS
grupe s.a.c insumos de seguridad para obGRUPE S.A.C INSUMOS DE SEGURIDAD PARA OBRA
servimed san geronimo - 02 prueba y 02 SERVIMED SAN GERONIMO - 02 PRUE
ferret.carlitos ore s.r.l - instalacion de agu FERRET.CARLITOS ORE S.R.L - INSTA
ferret.carlitos ore s.r.l - cinta de señalizac FERRET.CARLITOS ORE S.R.L - CINTA
kallpa maquinarias e.i.r.l - instalacion electrKALLPA MAQUINARIAS E.I.R.L - INSTA
tecelec s.r.l - 03 seccionadores TECELEC S.R.L - 03 SECCIONADORES
estructura de acero para distribución de agESTRUCTURA DE ACERO PARA DISTRI
electro sur - instalacion acometida sector inELECTRO SUR - INSTALACION ACOMET
interruptor termomagnetico 3x50 INTERRUPTOR TERMOMAGNETICO 3X5
descuentos de señalizaciones 19/02 fact. DESCUENTOS DE SEÑALIZACIONES 19/0
descuentos de señalizaciones 19/02 fact. DESCUENTOS DE SEÑALIZACIONES 19/0
descuentos de señalizaciones fact. e001-5DESCUENTOS DE SEÑALIZACIONES FAC
recibo de luz 21/03/2022, recibo n° 300- RECIBO DE LUZ 21/03/2022, RECIBO N°
inst. electrica obras provisionales fe012308INST. ELECTRICA OBRAS PROVISIONAL
GERIATRIC MEDIC PERU S.A.C, COLLARIN,CAMILLA PVC,PULSIOXIMETRO,T.DIGITAL
Mascarillas MERCADO PAMPA JESSICA LILIAN
OTROS
20449438834 DIAMANTINA INGESERVICIOS S.A.C

SUB TOTAL BRUTO


Cargo 5% (condicion contractual, por adquisicion directa de SICE)
SUB TOTAL NETO
IGV 18%
TOTAL NETO
marzo - abril - mayo 2022

UNIDAD CANTIDAD
241,694.826
Kg
FE02-0275995 20-Mar 5/8 Kg 451 6,299.57
FE02-0275995 20-Mar 3/8 Kg 791 3,986.64
FE02-0275995 20-Mar 3/4 Kg 65 1,307.48
FE02-0275995 20-Mar 1/2 Kg 1,562 18,631.54
FE34-0023507 31-Mar 3/8 Kg 1,153 5,811.12
FE34-0023507 31-Mar 3/4 Kg 205 4,123.58
FE34-0023507 31-Mar 1 Kg 60 2,145.42
FE34-0023507 31-Mar 5/8 Kg 1,300 18,158.40
FE34-023702 31-Mar 3/8 Kg 478 2,409.12
FE34-023702 31-Mar 5/8 Kg 1,785 24,932.88
FE34-023702 31-Mar 1 Kg 39 1,394.52
FE34-023702 31-Mar 1/2 Kg 300 2,683.80
FE34-023713 31-Mar 3/8 Kg 2,912 14,676.48
FE34-023713 31-Mar 1 Kg 464 16,591.25
FE34-023703 31-Mar 5/8 Kg 2,250 31,428.00
FE02-0279285 9-Apr 3/4 Kg 835 16,796.03
FE02-0279285 9-Apr 5/8 Kg 893 12,473.42
FE02-282920 3-May 3/8 Kg 4,160 20,966.40
FE02-282920 3-May 1/2 Kg 812 7,264.15
FE02-0289626 14-Jun 6.00 Kg 1,349 2,671.02
FE02-0289626 14-Jun 3/8 Kg 3,574 18,012.96
FE02-0289626 14-Jun 3/4 Kg 444 8,931.06

Kg 4,000.00
FE65-0474584 9-Apr 16 Kg 2,000 2,000.00
FE65-0478960 3-May 16 Kg 2,000 2,000.00

Kg 1,000.00
FE02-282920 3-May 8 Kg 1,000 1,000.00
F001-000561 28-Jun und

m3 170.50
m3 7.00
m3 387.50
m3 962.00
m3 1,449.50
FA6A-40238 7-Apr 100 m3 90.0 90.00
FA6A-40238 7-Apr 175 m3 7.0 7.00
FA6A-40238 7-Apr 210 m3 40.0 40.00
FA6A-40238 7-Apr 315 m3 210.0 210.00
FA6A-40242 7-Apr m3 347.0 347.00
FA6A-40423 21-Apr 100 m3 21.0 21.00
FA6A-40423 21-Apr 315 m3 176.0 176.00
FA6A-40424 21-Apr m3 197.0 197.00
FA6A-40604 2-May 315 m3 142.0 142.00
FA6A-40605 2-May m3 142.0 142.00
FA6A-40726 10-May 210 m3 18.0 18.00
FA6A-40726 10-May 315 m3 115.0 115.00
FA6A-40727 10-May m3 133.0 133.00
FA6A-41142 31-May 315 m3 87.0 87.00
FA6A-41143 31-May 210 m3 73.5 73.50
FA6A-41189 31-May m3 117.5 117.50
FA6A-41597 27-Jun 315 m3 171 171.00
FA6A-41598 27-Jun 210 m3 72 72.00
FA6A-41599 27-Jun 100 m3 34 34.00
FA6A-41629 28-Jun m3 299 298.50
FA6A-41683 30-Jun 315 m3 21 20.50
FA6A-41684 30-Jun 100 m3 16 16.00
FA6A-41685 30-Jun m3 8 8.00
FA6A-41686 30-Jun 315 m3 40.5 40.50
FA6A-41687 30-Jun 210 m3 157 156.50
FA6A-41688 30-Jun 100 m3 10 9.50
FA6A-41689 30-Jun m3 207 206.50
FA6A-41690 30-Jun 210 m3 28 27.50

184
18,840.00
F002-000322 6-Jun PIRAMIDE 15 und 3,768.00
F002-000323 6-Jun und
F002-000324 6-Jun PIRAMIDE 15 und 3,768.00
F002-000325 6-Jun und
F002-000339 21-Jun PIRAMIDE 15 und 3,768.00
F002-000351 27-Jun PIRAMIDE 15 und 3,768.00
F002-000360 1-Jul PIRAMIDE 15 und 3,768.00

F002-000337 21-Jun INFES und 7,980.00

F001-003825 7-Jun glb


F001-003881 22-Jun glb
F011-0009915 13-Jun glb
F001-0009914 13-Jun glb
F001-0069735 23-Jun glb
Glb 1.00
STRIBUIDORA FJJ S.A.C
F001-2275
SEGURIDAD PARA OBRA 16/02
E001-3969
FE01-2134
FE02-1604
F001-2827
001-84
RH E001-9
003-2673
E001-1266
E001-491 19-Feb
E001-492 19-Feb
E001-501
300-628114
12308 31-Mar
METRO,T.DIGITAL
F001-00023 25-Jun

E001-585 4-Jul
- mayo 2022

P.U. S/
3.41
3.21 11.87 5,353.37 963.61
3.21 4.28 3,385.48 609.39
3.28 17.45 1,134.25 204.17
3.21 10.14 15,838.68 2,850.96
3.16 4.28 4,934.84 888.27
3.23 17.45 3,577.25 643.91
3.20 30.69 1,841.40 331.45
3.16 11.87 15,431.00 2,777.58
3.16 4.28 2,045.84 368.25
3.16 11.87 21,187.95 3,813.83
3.20 30.69 1,196.91 215.44
3.19 7.67 2,301.00 414.18
3.16 4.28 12,463.36 2,243.40
3.20 30.69 14,240.16 2,563.23
3.16 11.87 26,707.50 4,807.35
3.95 21.37 17,843.95 3,211.91
3.86 14.53 12,975.29 2,335.55
3.81 5.05 21,008.00 3,781.44
3.85 9.05 7,348.60 1,322.75
3.81 2.02 2,724.98 490.50
3.70 5.00 17,870.00 3,216.60
3.78 20.39 9,053.16 1,629.57

4.70
4.64 1.25 2,500.00 450.00
4.76 1.25 2,500.00 450.00

4.76
4.76 1.25 1,250.00 225.00

316.20
346.54
371.85
434.25
33.48
314.98 314.98004
346.54 346.53995
364.53 364.53008
433.06 433.05997
35.00 35
314.98 314.97982
433.06 433.06004
35.00 35
433.06 433.05998
35.00 35
364.530603
433.059912
35.000000
436.634483
368.033878
31.500000
436.634553
368.033781
318.484297
31.499986
436.634147
318.483581
31.500000
436.634553
368.033781
318.483581
31.500000
429.231000

2.66

2.66

2.71
2.71
2.71

1.32
12,449.04
PARCIAL S/

824,568.16
6,316.98 3.7760 20,214.33 3,638.58 23,852.90 20,214.33
3,994.87 3.7760 12,783.57 2,301.04 15,084.62 12,783.57
1,338.42 3.7760 4,282.93 770.93 5,053.86 4,282.93
18,689.64 3.7760 59,806.86 10,765.23 70,572.09 59,806.86
5,823.11 3.7240 18,377.34 3,307.92 21,685.27 18,377.34
4,221.16 3.7240 13,321.68 2,397.90 15,719.58 13,321.68
2,172.85 3.7240 6,857.37 1,234.33 8,091.70 6,857.37
18,208.58 3.7240 57,465.04 10,343.71 67,808.75 57,465.04
2,414.09 3.7240 7,618.71 1,371.37 8,990.08 7,618.71
25,001.78 3.7240 78,903.93 14,202.71 93,106.63 78,903.93
1,412.35 3.7240 4,457.29 802.31 5,259.61 4,457.29
2,715.18 3.7240 8,568.92 1,542.41 10,111.33 8,568.92
14,706.76 3.7240 46,413.55 8,354.44 54,767.99 46,413.55
16,803.39 3.7240 53,030.36 9,545.46 62,575.82 53,030.36
31,514.85 3.7240 99,458.73 17,902.57 117,361.30 99,458.73
21,055.86 3.7150 66,290.27 11,932.25 78,222.52 66,290.27
15,310.84 3.7150 48,203.20 8,676.58 56,879.78 48,203.20
24,789.44 3.8200 79,935.44 14,388.38 94,323.82 79,935.44
8,671.35 3.8200 27,961.42 5,033.06 32,994.48 27,961.42
3,215.48 3.7310 10,166.90 1,830.04 11,996.94 10,166.90
21,086.60 3.7310 66,672.97 12,001.13 78,674.10 66,672.97
10,682.73 3.7310 33,777.34 6,079.92 39,857.26 33,777.34

18,800.00
2,950.00 3.7150 9,287.50 1,671.75 10,959.25 9,287.50
2,950.00 3.8200 9,512.50 1,712.25 11,224.75 9,512.50

11,535.91
1,475.00 3.8200 4,756.25 856.13 5,612.38 4,756.25
6,779.66 1,220.34 8,000.00 6,779.66

53,912.58
2,425.78
144,092.80
417,743.98
48,525.75
28,348.20 5,102.68 33,450.88 28,348.20
2,425.78 436.64 2,862.42 2,425.78
14,581.20 2,624.62 17,205.82 14,581.20
90,942.59 16,369.67 107,312.26 90,942.59
12,145.00 2,186.10 14,331.10 12,145.00
6,614.58 1,190.62 7,805.20 6,614.58
76,218.57 13,719.34 89,937.91 76,218.57
6,895.00 1,241.10 8,136.10 6,895.00
61,494.52 11,069.01 72,563.53 61,494.52
4,970.00 894.60 5,864.60 4,970.00
6,561.55 1,181.08 7,742.63 6,561.55
49,801.89 8,964.34 58,766.23 49,801.89
4,655.00 837.90 5,492.90 4,655.00
37,987.20 6,837.70 44,824.90 37,987.20
27,050.49 4,869.09 31,919.58 27,050.49
3,701.25 666.23 4,367.48 3,701.25
74,664.51 13,439.61 88,104.12 74,664.51
26,498.43 4,769.72 31,268.15 26,498.43
10,828.47 1,949.12 12,777.59 10,828.47
9,402.75 1,692.49 11,095.24 9,402.75
8,951.00 1,611.18 10,562.18 8,951.00
5,095.74 917.23 6,012.97 5,095.74
252.00 45.36 297.36 252.00
17,683.70 3,183.07 20,866.77 17,683.70
57,597.28 10,367.51 67,964.79 57,597.28
3,025.59 544.61 3,570.20 3,025.6
6,504.75 1,170.86 7,675.61 6,504.75
11,803.84 2,124.69 13,928.53 11,803.84

51,113.90
10,010.75 1,801.94 11,812.69 10,010.75
212.03 38.17 250.20 212.03
10,010.75 1,801.94 11,812.69 10,010.75
212.03 38.17 250.20 212.03
10,222.78 1,840.10 12,062.88 10,222.78
10,222.78 1,840.10 12,062.88 10,222.78
10,222.78 1,840.10 12,062.88 10,222.78

10,533.60 1,896.05 12,429.65 10,533.60

115,977.49
5,438.89 979.00 6,417.89 5,438.89
4,192.20 980.00 5,172.20 4,192.20
4,634.42 834.20 5,468.62 4,634.42
8,601.07 1,548.19 10,149.26 8,601.07
93,110.91 16,759.96 109,870.87 93,110.91
12,449.04
1,612.80 290.30 1,903.10
254.24 45.76 300.00
2,998.10 539.66 3,537.76
338.98 61.02 400.00
324.66 58.44 383.10
59.32 10.68 70.00
173.73 31.27 205.00
966.10 173.90 1,140.00
680.00 0.00 680.00
931.44 167.66 1,099.10
46.61 8.39 55.00
423.73 76.27 500.00
423.73 76.27 500.00
42.37 7.63 50.00
459.75 82.76 542.51
181.27 32.63 213.90
593.22 106.7796 700.00
142.37 25.6266 168.00

1,796.61 323.3898 2120.00

1,711,678.97 308,205.22 2,019,884.19


5% 84,961.50
Total 1,796,640.47 323395.2846988 2,120,035.76

1,711,678.97
84,961.50
1,796,640.47
323,395.28
2,120,035.76

1181816.861438
529,862.11
CONTRATO
PRINCIPAL
Metrado % Amortizacion Amortizacion
Acumulado Utilización Total Acumulada Acumulada Amortizacion Saldo por
Reconocido de material S/ Anterior a Considerar Amortizar

176,942.97 73.21% 603,660.17 390,461.98 213,198.19 220,907.99


-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

-
8,847.15 100.00% 18,800.00 18,800.00 - - DISCRIMINADO FORZADO
-
-

269.41 100.00% 11,535.91 4,756.25 6,779.66 - DISCRIMINADO FORZADO

159.69 100.00% 53,912.58 33,494.03 20,418.55 - DISCRIMINADO FORZADO


- 0.00% - - - 2,425.78
413.31 100.00% 144,092.80 48,193.24 95,899.55 - DISCRIMINADO FORZADO
901.70 100.00% 417,743.98 313,098.26 104,645.72 - DISCRIMINADO FORZADO
100.00% 48,525.75 31,515.27 17,010.47 -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -

22,155.00 100.00% 51,113.90 - 51,113.90 -

0.00% - - - 10,533.60

45,677.38 30.00% 34,793.25 - 34,793.25 81,184.24


100.00% 12,449.04 10,510.06 1,938.98 -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

1,396,627.36 850,829.09 545,798.27 315,051.61


69,831.37 42,541.45 27,289.91 15,752.58
1,466,458.73 893,370.55 573,088.18 330,804.19
263,962.57 160,806.70 103,155.87 59,544.75
1,730,421.30 1,054,177.24 676,244.06 390,348.95
ISCRIMINADO FORZADO AL 100%

ISCRIMINADO FORZADO AL 100%

ISCRIMINADO FORZADO AL 100%

ISCRIMINADO FORZADO AL 100%


ISCRIMINADO FORZADO AL 100%
MEDICION A SUB CONTRATISTA

EJECUTOR SICE S.A. SUB CONTRATISTA:


SUB CONTRATISTA Rafael Caso Tirado
MEJORAMIENTO Y AMPLIACION DEL SERVICIO EDUCATIVO DE LA II.EE. FE Y ALEGRIA N° 52, SECTOR PAMPA INALAMBRICA DISTRITO DE ILO, PROVINCIA DE ILO DEPARTAMENTO DE MOQUEGUA” CUI
OBRA
N°2234866
LUGAR PAMPA INALAMBRICA - ILO - MOQUEGUA 001-0014281, 001-0014285 Entrega 1 del 25-Apr-22 al 31-May-22
818000004063-2 Entrega 2 del 28-Apr-22 al 31-May-22
818000004063-2 Entrega 3 del 10-May-22 al 31-May-22
818000004063-2 Entrega 4 del 25-May-22 al 31-May-22
818000004063-2 Entrega 5
818000004063-2 Entrega 6
818000004209 Entrega 7
818000004561 Entrega 8

VALORES EN SOLES MEDICION Nº 1.00 MES ; Jul-22 FECHA Monday, July 25, 2022

DATOS CONTRACTUALES ENTREGA 01 25-Apr-22 ENTREGA 02 28-Apr-22 ENTREGA 03 10-May-22 ENTREGA 04 25-May-22 ENTREGA 05 31-May-22 ENTREGA 06 6-Jun-22 ENTREGA 07 14-Jun-22 ENTREGA 08 17-Jun-22 ENTREGA 09 22-Jun-22 ENTREGA 10 24-Jun-22 ENTREGA ACUMULADA SALDO EN DEVOLUCION
ITEM DESCRIPCION ANEXO UNID
CANTIDAD PVP Precio/Dia MONTO TOTAL CANT. Total dias VALOR CANT. Total dias VALOR CANT. Total dias VALOR CANT. Total Dias VALOR CANT. Total Dias VALOR CANT. Total Dias VALOR CANT. Total Dias VALOR CANT. Total Dias VALOR CANT. Total Dias VALOR CANT. Total Dias VALOR CANT. VALOR CANT. VALOR

ALQUILER ENCOFRADOS ALSINA


REF.: 818000005748
27601 SOPANDA 4M. ST ALM ANEXO 1 Uni 356.00 584.68 0.3410 121.40 66 0.00 160.00 63 3,437.28 50 0.00 35 0.00 6.00 30 61.38 80.00 23 627.44 30.00 15 153.45 12 0.00 7 0.00 71.00 5 121.06 347.00 97% 4,400.61 9.00 202.55
27602 SOPANDA 3M. ST ALM ANEXO 1 Uni 493.00 449.95 0.2625 129.41 66 0.00 63 0.00 50 0.00 35 0.00 5.00 30 39.38 240.00 23 1,449.00 8.00 15 31.50 12 0.00 7 0.00 58.00 5 76.13 311.00 63% 1,596.00 182.00 3,153.15
27603 SOPANDA 2M. ST ALM ANEXO 1 Uni 184.00 320.28 0.1868 34.37 66 0.00 63 0.00 50 0.00 35 0.00 24.00 30 134.50 23 0.00 15 0.00 31.00 12 69.49 7 0.00 71.00 5 66.31 126.00 68% 270.30 58.00 715.07
27644 SOPANDA 1.50M. ST MECANOFLEX ANEXO 1 Uni 156.00 323.49 0.1887 29.44 66 0.00 63 0.00 50 0.00 35 0.00 156.00 30 883.12 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 156.00 100% 883.12 0.00 0.00
SOPANDA MIXTA 4M. ST ALM ANEXO 1 Uni 106.00 692.09 0.4037 42.79 66 0.00 63 0.00 50 0.00 35 0.00 6.00 30 72.67 23 0.00 20.00 15 121.11 12 0.00 7 0.00 14.00 5 28.26 40.00 38% 222.04 66.00 1,758.52
SOPANDA MIXTA 3M. ST ALM ANEXO 1 Uni 224.00 528.37 0.3082 69.04 66 0.00 63 0.00 50 0.00 35 0.00 48.00 30 443.81 80.00 23 567.09 16.00 15 73.97 12 0.00 7 0.00 62.00 5 95.54 206.00 92% 1,180.41 18.00 366.14
SOPANDA MIXTA 2M. ST ALM ANEXO 1 Uni 86.00 377.26 0.2201 18.93 66 0.00 63 0.00 50 0.00 35 0.00 6.00 30 39.62 80.00 23 404.98 15 0.00 135.00 12 356.56 7 0.00 6.00 5 6.60 227.00 264% 807.77 (141.00) (2,048.25)
SOPANDA MIXTA 1.50M. ST MECANO ANEXO 1 Uni 86.00 364.09 0.2124 18.27 66 0.00 63 0.00 50 0.00 35 0.00 86.00 30 547.99 23 0.00 15 0.00 80.00 12 203.90 7 0.00 5 0.00 166.00 193% 751.90 (80.00) (1,121.47)
PSP 4.00M FEM. 244 MECANOFLEX ANEXO 1 Uni 13.00 831.03 0.4847 6.30 66 0.00 63 0.00 50 0.00 35 0.00 3.00 30 43.62 23 0.00 10.00 15 72.71 12 0.00 7 0.00 5 0.00 13.00 100% 116.33 0.00 0.00
PSP 2.00M FEM. 244 MECANOFLEX ANEXO 1 Uni 424.00 427.97 0.2496 105.83 66 0.00 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 31.00 12 92.85 7 0.00 52.00 5 64.90 83.00 20% 157.75 341.00 5,617.50
PSP 1.50M FEM. 244 MECANOFLEX ANEXO 1 Uni 26.00 334.29 0.1950 5.07 66 0.00 63 0.00 50 0.00 35 0.00 26.00 30 152.10 23 0.00 15 0.00 11.00 12 25.74 7 0.00 32.00 5 31.20 69.00 265% 209.04 (43.00) (553.41)
PSP 1.00M FEM. 244 MECANOFLEX ANEXO 1 Uni 5.00 234.00 0.1365 0.68 66 0.00 63 0.00 50 0.00 35 0.00 5.00 30 20.48 23 0.00 15 0.00 11.00 12 18.02 7 0.00 5 0.00 16.00 320% 38.49 (11.00) (99.10)
PUNTAL HASTA 5M ALSINA C/R/ ANEXO 1 Uni 600.00 254.10 0.1482 88.92 66 0.00 63 0.00 50 0.00 300.00 35 1,556.10 500.00 30 2,223.00 23 0.00 100.00 15 222.30 200.00 12 355.68 7 0.00 5 0.00 1,100.00 183% 4,357.08 (500.00) (4,890.60)
SOPORTE PSP ALULOSAS ANEXO 1 Uni 202.00 48.69 0.0284 5.74 66 0.00 63 0.00 50 0.00 35 0.00 185.00 30 157.62 23 0.00 17.00 15 7.24 12 0.00 7 0.00 205.00 5 29.11 407.00 201% 193.97 (205.00) (384.25)
TRIPODE ALISAN ECO ANEXO 1 Uni 90.00 172.17 0.1004 9.04 66 0.00 63 0.00 50 0.00 35 0.00 50.00 30 150.60 23 0.00 40.00 15 60.24 12 0.00 7 0.00 5 0.00 90.00 100% 210.84 0.00 0.00
FONDO 157X30 VCM ANEXO 2 Uni 130.00 445.13 0.2888 37.54 66 0.00 63 0.00 50 0.00 130.00 35 1,314.04 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 130.00 100% 1,314.04 0.00 0.00
FONDO 109X30 VCM ANEXO 2 Uni 76.00 341.53 0.2216 16.84 66 0.00 63 0.00 50 0.00 35 0.00 76.00 30 505.25 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 76.00 100% 505.25 0.00 0.00
CLIP UNION VCM ANEXO 2 Uni 1,308.00 24.27 0.0157 20.54 66 0.00 63 0.00 50 0.00 722.00 35 396.74 30 0.00 23 0.00 600.00 15 141.30 12 0.00 7 0.00 5 0.00 1,322.00 101% 538.04 (14.00) (14.51)
VASTAGO PUNTAL VCM ANEXO 2 Uni 617.00 14.90 0.0097 5.98 66 0.00 63 0.00 50 0.00 617.00 35 209.47 30 0.00 23 0.00 35.00 15 5.09 12 0.00 7 0.00 5 0.00 652.00 106% 214.56 (35.00) (22.41)
ANGULO REMATE FONDO 30 VC ANEXO 2 Uni 78.00 16.20 0.0105 0.82 66 0.00 63 0.00 50 0.00 78.00 35 28.67 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 78.00 100% 28.67 0.00 0.00
TRIANGULO NIVELADOR CU=A VCM ANEXO 2 Uni 305.00 131.43 0.0853 26.02 66 0.00 63 0.00 50 0.00 200.00 35 597.10 30 0.00 23 0.00 105.00 15 134.35 12 0.00 7 0.00 5 0.00 305.00 100% 731.45 0.00 0.00
FONDO RECUPERACION 30 VCM ANEXO 2 Uni 508.00 155.63 0.1010 51.31 66 0.00 63 0.00 50 0.00 508.00 35 1,795.78 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 508.00 100% 1,795.78 0.00 0.00
VASTAGO PUNTAL VCM ANEXO 2 Uni 108.00 14.90 0.0097 1.05 66 0.00 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 73.00 15 10.62 12 0.00 7 0.00 5 0.00 73.00 68% 10.62 35.00 22.41
TABICA 157X48 VCM ANEXO 2 Uni 346.00 643.57 0.4175 144.46 66 0.00 63 0.00 50 0.00 20.00 35 292.25 240.00 30 3,006.00 23 0.00 86.00 15 538.58 12 0.00 7 0.00 5 0.00 346.00 100% 3,836.83 0.00 0.00
TABICA 157X20 VCM ANEXO 2 Uni 30.00 364.37 0.2364 7.09 66 0.00 63 0.00 50 0.00 30.00 35 248.22 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 30.00 100% 248.22 0.00 0.00
TABICA 109X48 VCM ANEXO 2 Uni 312.00 499.23 0.3239 101.06 66 0.00 63 0.00 50 0.00 108.00 35 1,224.34 160.00 30 1,554.72 23 0.00 44.00 15 213.77 12 0.00 7 0.00 5 0.00 312.00 100% 2,992.84 0.00 0.00
TABICA 109X20 VCM ANEXO 2 Uni 80.00 309.07 0.2005 16.04 66 0.00 63 0.00 50 0.00 60.00 35 421.05 30 0.00 23 0.00 20.00 15 60.15 12 0.00 7 0.00 5 0.00 80.00 100% 481.20 0.00 0.00
CLIP UNION VCM ANEXO 2 Uni 1,056.00 24.27 0.0157 16.58 66 0.00 63 0.00 50 0.00 992.00 35 545.10 30 0.00 23 0.00 50.00 15 11.78 12 0.00 7 0.00 5 0.00 1,042.00 99% 556.88 14.00 14.51
TORNILLO UNION TABICA-FONDO VCM ANEXO 2 Uni 2,068.00 17.00 0.0110 22.75 66 0.00 63 0.00 50 0.00 1,648.00 35 634.48 30 0.00 23 0.00 420.00 15 69.30 12 0.00 7 0.00 5 0.00 2,068.00 100% 703.78 0.00 0.00
BARRA DYWIDAG 0.75 M. ANEXO 2 Uni 818.00 25.54 0.0166 13.58 66 0.00 63 0.00 50 0.00 637.00 35 370.10 30 0.00 23 0.00 181.00 15 45.07 12 0.00 7 0.00 5 0.00 818.00 100% 415.17 0.00 0.00
ANGULO REMATE TABICA 48 VCM ANEXO 2 Uni 160.00 32.10 0.0208 3.33 66 0.00 63 0.00 50 0.00 160.00 35 116.48 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 160.00 100% 116.48 0.00 0.00
TABICA REMATE 48 VCM ANEXO 2 Uni 64.00 246.20 0.1597 10.22 66 0.00 63 0.00 50 0.00 64.00 35 357.73 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 64.00 100% 357.73 0.00 0.00
TABICA REMATE 20 VCM ANEXO 2 Uni 50.00 126.03 0.0818 4.09 66 0.00 63 0.00 50 0.00 30.00 35 85.89 30 0.00 23 0.00 20.00 15 24.54 12 0.00 7 0.00 5 0.00 50.00 100% 110.43 0.00 0.00
PUNTAL HASTA 5M ALSINA C/R/ ANEXO 3 Uni 200.00 254.10 0.1482 29.64 66 0.00 63 0.00 50 0.00 35 0.00 30 0.00 200.00 23 681.72 15 0.00 12 0.00 7 0.00 5 0.00 200.00 100% 681.72 0.00 0.00
MENSULA PUNTAL VCM ANEXO 3 Uni 20.00 105.77 0.0994 1.99 66 0.00 63 0.00 50 0.00 20.00 35 69.58 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 20.00 100% 69.58 0.00 0.00
POSTE 1.2M EN 13374 ANEXO 2 Uni 29.00 80.54 0.0379 1.10 14.00 66 35.02 63 0.00 50 0.00 35 0.00 15.00 30 17.06 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 29.00 100% 52.07 0.00 0.00
PASADOR ELASTICO POSTE 50M ANEXO 2 Uni 14.00 7.54 0.0035 0.05 14.00 66 3.23 63 0.00 50 0.00 20.00 35 2.45 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 34.00 243% 5.68 (20.00) (4.62)
SOPANDA 2M. ST ALM ANEXO 4 Uni 160.00 320.28 0.1868 29.89 66 0.00 63 0.00 50 0.00 35 0.00 30 0.00 160.00 23 687.42 15 0.00 12 0.00 7 0.00 5 0.00 160.00 100% 687.42 0.00 0.00
SOPANDA MIXTA 4M. ST ALM ANEXO 4 Uni 80.00 692.09 0.4037 32.30 66 0.00 63 0.00 50 0.00 35 0.00 30 0.00 80.00 23 742.81 15 0.00 12 0.00 7 0.00 5 0.00 80.00 100% 742.81 0.00 0.00
ALISPLAY MANUAL 270X90 ANEXO 1-2-1 Uni 104.00 3,916.33 1.7502 182.02 42.00 66 4,851.55 54.00 63 5,954.18 8.00 50 700.08 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 104.00 100% 11,505.81 0.00 0.00
ALISPLAY MANUAL 270X30 ANEXO 1 Uni 15.00 2,271.10 1.0150 15.23 12.00 66 803.88 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 12.00 80% 803.88 3.00 200.97
ALISPLAY MANUAL 150X90 ANEXO 2-1 Uni 4.00 2,583.77 1.1547 4.62 2.00 66 152.42 63 0.00 2.00 50 115.47 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 4.00 100% 267.89 0.00 0.00
6170 ALISPLAY MANUAL 150X30 ANEXO 1 Uni 12.00 1,492.47 0.6670 8.00 3.00 66 132.07 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 3.00 25% 132.07 9.00 396.20
PINZA ALISPLY MANUAL UNIV ANEXO 1-2-1 Uni 88.00 238.30 0.1065 9.37 40.00 66 281.16 63 0.00 48.00 50 255.60 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 88.00 100% 536.76 0.00 0.00
PLACA TUERCA PALOMILLA ALISPLY ANEXO 1 Uni 300.00 24.13 0.0108 3.24 300.00 66 213.84 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 300.00 100% 213.84 0.00 0.00
TUERCA PALOMILLA APLISPLY ANEXO 1 Uni 1,664.00 9.48 0.0042 6.99 300.00 66 83.16 63 0.00 50 0.00 1,364.00 35 200.51 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 1,664.00 100% 283.67 0.00 0.00
ESQ.INT.RETRAC 270X20X20 M ANEXO 5 Uni 6.00 3,999.70 1.7875 10.73 3.00 66 353.93 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 3.00 50% 353.93 3.00 353.93
ESQ.INT.RETRAC 150X25X25 M ANEXO 5 Uni 12.00 2,606.17 1.1647 13.98 6.00 66 461.22 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 6.00 50% 461.22 6.00 461.22
GRAPA ALISPLY MANUAL ANEXO 1-2-1 Uni 910.00 139.15 0.0622 56.60 710.00 66 2,914.69 63 0.00 200.00 50 622.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 910.00 100% 3,536.69 0.00 0.00
GRAPA EXTENSIBLE ALISPLY MAN ANEXO 1-2-1 Uni 109.00 181.89 0.0813 8.86 69.00 66 370.24 63 0.00 40.00 50 162.60 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 109.00 100% 532.84 0.00 0.00
BARRA DYWIDAG 1.20 M. ANEXO 2-1 Uni 151.00 39.00 0.0174 2.63 81.00 66 93.02 63 0.00 70.00 50 60.90 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 151.00 100% 153.92 0.00 0.00
BARRA DYWIDAG 1.00 M. ANEXO 1 Uni 100.00 32.86 0.0147 1.47 100.00 66 97.02 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 100.00 100% 97.02 0.00 0.00
PLACA TUERCA PALOMILLA ALISPLY ANEXO 2-1 Uni 476.00 24.13 0.0108 5.14 256.00 66 182.48 63 0.00 220.00 50 118.80 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 476.00 100% 301.28 0.00 0.00
TUERCA PALOMILLA APLISPLY ANEXO 2 Uni 476.00 9.48 0.0042 2.00 256.00 66 70.96 63 0.00 220.00 50 46.20 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 476.00 100% 117.16 0.00 0.00
ACCESORIO TAPE ALISPLY ANEXO 2 Uni 24.00 65.97 0.0295 0.71 24.00 66 46.73 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 24.00 100% 46.73 0.00 0.00
ALISPLY-M PLUS UNIV. F12 270 ANEXO 2-1 Uni 36.00 3,757.13 1.6791 60.45 34.00 66 3,767.90 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 34.00 94% 3,767.90 2.00 221.64
CONSOLA TRABAJO ALISPLY MAN ANEXO 1-2 Uni 14.00 865.57 0.4068 5.70 14.00 66 375.88 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 14.00 100% 375.88 0.00 0.00
POSTE 1.2M EN 13374 ANEXO 6 Uni 29.00 80.54 0.0379 1.10 66 0.00 63 0.00 50 0.00 35 0.00 5.00 30 5.69 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 5.00 17% 5.69 24.00 60.03
TRNP. 3M S/ANCLAJE APL.ALISPL ANEXO 1-2 Uni 31.00 428.94 0.2016 6.25 66 0.00 31.00 63 393.72 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 31.00 100% 393.72 0.00 0.00
PLACA BASE TORNAPUNT. 3M. C/ ANEXO 1-2 Uni 31.00 181.23 0.0852 2.64 31.00 66 174.32 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 31.00 100% 174.32 0.00 0.00
PASADOR DE SEGURIDAD C/C ALISPL ANEXO 1-2 Uni 32.00 38.51 0.0181 0.58 32.00 66 38.23 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 32.00 100% 38.23 0.00 0.00
ACOPLE TORNAPUNTAS MANUAL ANEXO 2 Uni 32.00 308.90 0.1452 4.65 25.00 66 239.58 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 25.00 78% 239.58 7.00 67.08
TORNAP. 6M S/ANCLAJE ALIS.CO ANEXO 2 Uni 16.00 1,818.77 0.8548 13.68 16.00 66 902.67 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 16.00 100% 902.67 0.00 0.00
PLACA BASE TORNAPUNT. 6/9M. ANEXO 2 Uni 16.00 275.83 0.1296 2.07 16.00 66 136.86 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 16.00 100% 136.86 0.00 0.00
PASADOR DE SEGURIDAD C/C ALISPL ANEXO 6 Uni 15.00 38.51 0.0181 0.27 15.00 66 17.92 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 15.00 100% 17.92 0.00 0.00
ACOPLE TORNAPUNTAS ALISPLY ANEXO 1 Uni 15.00 242.94 0.1086 1.63 22.00 66 157.69 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 22.00 147% 157.69 (7.00) (50.17)
PSP 2.00M FEM. 244 MECANOFLEX ANEXO 7 Uni 424.00 0.20 0.2496 105.83 66 0.00 63 0.00 50 0.00 35 0.00 30 0.00 424.00 23 2,434.10 15 0.00 12 0.00 7 0.00 60.00 5 74.88 484.00 114% 2,508.98 (60.00) (988.42)
RIGIDIZADOR UNIVERSAL ANEXO 2 Uni 12.00 651.09 0.2910 3.49 12.00 66 230.47 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 12.00 100% 230.47 0.00 0.00
ENGANCHE DYWIDAG L=220 ALISPLY-MMAN Uni 46.00 84.66 0.0378 1.74 46.00 66 114.76 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 46.00 100% 114.76 0.00 0.00
ENGANCHE DYWIDAG L=140 MMAN ANEXO 1 Uni 68.00 87.27 0.0390 2.65 68.00 66 175.03 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 68.00 100% 175.03 0.00 0.00
ENGANCHE GRUA C/SEG. ALISPLY MMAN ANEXO 1 Uni 2.00 809.03 0.3616 0.72 2.00 66 47.73 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 2.00 100% 47.73 0.00 0.00
6170 ALISPILAR 300X68 ANEXO 1 Uni 12.00 3,118.77 2.3391 28.07 66 0.00 63 0.00 12.00 50 1,403.46 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 12.00 100% 1,403.46 0.00 0.00
6170 ALISPILAR 300X50 ANEXO 1 Uni 12.00 2,521.29 1.8910 22.69 66 0.00 63 0.00 12.00 50 1,134.60 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 12.00 100% 1,134.60 0.00 0.00
6170 ALISPILAR 140X68 ANEXO 1 Uni 12.00 1,733.00 1.2998 15.60 66 0.00 63 0.00 12.00 50 779.88 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 12.00 100% 779.88 0.00 0.00
6170 ACOPLE ALU-ALIS TRNP ANEXO 1 Uni 18.00 212.69 0.1595 2.87 66 0.00 63 0.00 18.00 50 143.55 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 18.00 100% 143.55 0.00 0.00
6170 TORNILLO C/PLACA UNION ALU/ALI ANEXO 1 Uni 60.00 23.03 0.0173 1.04 66 0.00 63 0.00 60.00 50 51.90 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 60.00 100% 51.90 0.00 0.00
6170 TUERCA C/PLACA UNION ALU/ALI ANEXO 1 Uni 60.00 14.95 0.0112 0.67 66 0.00 63 0.00 60.00 50 33.60 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 60.00 100% 33.60 0.00 0.00
TORNILLO DYWIDAG L=210MM MIC Uni 128.00 0.0299 3.83 16.00 66 31.57 63 0.00 112.00 50 167.44 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 128.00 100% 199.01 0.00 0.00
(PROT) ALISPLY-M PLUS 270X30 ANEXO 1-2 Uni 1.00 3,757.13 1.0150 1.02 1.00 66 66.99 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 1.00 100% 66.99 0.00 0.00

(PROT) ESQ. INT. ALISPLY-M PLUS 270X35X35 Uni 1.00 2.4450 2.45 1.00 66 161.37 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 1.00 100% 161.37 0.00 0.00

(PROT) INSERCION UNION ESQUINA ALISPLY-


Uni 128.00 0.0299 3.83 16.00 66 31.57 63 0.00 112.00 50 167.44 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 128.00 100% 199.01 0.00 0.00
M PLUS
(PROT) CONSOLA TRABAJO ALISPLY-M PLUS Uni 15.00 0.3815 5.72 15.00 66 377.69 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 15.00 100% 377.69 0.00 0.00

PUNTAL HASTA 4M D/60 ALSINA Uni 300.00 0.2317 69.51 66 0.00 300.00 63 4,379.13 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 300.00 100% 4,379.13 0.00 0.00
ESQ.INT.RETRAC 270X35X35 M ANEXO 1-2-1 Uni 15.00 5,471.10 2.4450 36.68 6.00 66 968.22 63 0.00 6.00 50 733.50 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 12.00 80% 1,701.72 3.00 484.11
ESQ.INT.RETRAC 150X35X35 M ANEXO 2-1 Uni 12.00 3,396.93 1.5181 18.22 66 0.00 63 0.00 6.00 50 455.43 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 6.00 50% 455.43 6.00 601.17
ESQ.INT.RETRAC 150X20X20 M Uni 6.00 1.1647 6.99 66 63 50 0.00 6.00 35 244.59 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 6.00 100% 244.59 0.00
ESQ.ARTIC. 270X10 EXT. MANUAL ANEXO 1 Uni 2.00 2,953.47 1.3199 2.64 2.00 66 174.23 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 2.00 100% 174.23 0.00 0.00
ESQ.ARTIC. 270X20 INT. MANUAL ANEXO 1 Uni 2.00 3,625.23 1.6201 3.24 2.00 66 213.85 63 0.00 50 0.00 6.00 35 340.22 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 8.00 400% 554.07 (6.00) (641.56)
6170 ALISPLY MANUAL 270X75 ANEXO 1 Uni 40.00 3,542.13 1.5830 63.32 20.00 66 2,089.56 63 0.00 20.00 50 1,583.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 40.00 100% 3,672.56 0.00 0.00
ALISPLY MANUAL 270X75 UNIV. ANEXO 1 Uni 4.00 4,129.03 1.8453 7.38 4.00 66 487.16 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 4.00 100% 487.16 0.00 0.00
SUPLEMENTO 5CM MMAN H270 ANEXO 1 Uni 2.00 1,033.03 0.4617 0.92 2.00 66 60.94 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 4.00 15 27.70 12 0.00 7 0.00 5 0.00 6.00 300% 88.65 (4.00) (121.89)
ALISPLY MANUAL 270X40 ANEXO 1 Uni 2.00 2,553.07 1.1410 2.28 2.00 66 150.61 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 2.00 100% 150.61 0.00 0.00
ALISPLY MANUAL 270X50 ANEXO 1 Uni 4.00 2,826.13 1.2630 5.05 4.00 66 333.43 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 4.00 100% 333.43 0.00 0.00
ALISPLY MANUAL 270X60 ANEXO 1 Uni 4.00 3,183.67 1.4228 5.69 4.00 66 375.62 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 4.00 100% 375.62 0.00 0.00
ALISPLAY-M PLUS UNIV F12 150X75 Uni 36.00 1.1992 43.17 66 63 12.00 50 719.52 24.00 35 1,007.33 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 36.00 100% 1,726.85 0.00 0.00
ALISPLAY-M PLUS UNIV F12 270X75 Uni 40.00 1.6791 67.16 66 63 6.00 50 503.73 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 6.00 15% 503.73 34.00 3,767.90
ALISPILAR 140X50 Uni 12.00 1.1310 13.57 66 63 12.00 50 678.60 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 12.00 100% 678.60 0.00 0.00
VIGA PLATAF. INF. TREPANTE ANEXO 1 Uni 30.00 1,027.10 0.4590 13.77 66 0.00 30.00 63 867.51 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 30.00 100% 867.51 0.00 0.00
ANG.EXTER. 270X110 MANUAL ANEXO 2 Uni 12.00 1,091.90 0.4880 5.86 12.00 66 386.50 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 12.00 100% 386.50 0.00 0.00
6170 ANG.EXTER. 150X110 MANUAL ANEXO 1 Uni 12.00 668.97 0.5017 6.02 66 0.00 63 0.00 12.00 50 301.02 35 0.00 30 0.00 23 0.00 15 0.00 12 0.00 7 0.00 5 0.00 12.00 100% 301.02 0.00 0.00
FONDO 157X20 VCM Uni 63.00 0.2747 17.31 66 0.00 63 0.00 50 0.00 35 0.00 20.00 30 164.82 23 0.00 43.00 15 177.18 12 0.00 7 0.00 5 0.00 63.00 100% 342.00 0.00 0.00
FONDO 109X20 VCM Uni 41.00 0.2153 8.83 66 0.00 63 0.00 50 0.00 35 0.00 20.00 30 129.18 23 0.00 21.00 15 67.82 12 0.00 7 0.00 5 0.00 41.00 100% 197.00 0.00 0.00
SUPLEMENTO 5CM FONDO 109 VCM Uni 20.00 0.0675 1.35 66 0.00 63 0.00 50 0.00 35 0.00 20.00 30 40.50 23 0.00 8.00 15 8.10 21.00 12 17.01 7 0.00 5 0.00 49.00 245% 65.61 (29.00) (129.20)
SUPLEMENTO 5CM FONDO 157 VCM Uni 63.00 0.0877 5.53 66 0.00 63 0.00 50 0.00 35 0.00 20.00 30 52.62 23 0.00 43.00 15 56.57 12 0.00 7 0.00 5 0.00 63.00 100% 109.19 0.00 0.00
FONDO DE RECUPERACION 20 VCM Uni 144.00 0.1115 16.06 66 0.00 63 0.00 50 0.00 35 0.00 80.00 30 267.60 23 0.00 64.00 15 107.04 12 0.00 7 0.00 5 0.00 144.00 100% 374.64 0.00 0.00
SOPORTE 1.2-1.5 PER Uni 72.00 0.2295 66 63 50 35 30 0.00 23 0.00 36.00 15 123.93 44.00 12 121.18 7 0.00 5 0.00 80.00 111% 245.11 (8.00) (121.18)
PUNTAL HASTA 4M ALSINA Uni 300.00 0.1549 46.47 66 0.00 63 0.00 50 0.00 35 0.00 30 0.00 23 0.00 100.00 15 232.35 12 0.00 1,000.00 7 1,084.30 1,000.00 5 774.50 2,100.00 700% 2,091.15 (1,800.00) (18,402.12)
PUNTAL HASTA 6M. 4MM. Uni 200.00 0.1482 29.64 66 63 50 35 30 0.00 23 0.00 100.00 15 222.30 200.00 12 355.68 500.00 7 518.70 35.00 5 25.94 835.00 418% 1,122.62 (635.00) (6,211.06)
VIGA MADERA HT-20 1.95M. Uni 30.00 0.2085 66 63 50 35 30 0.00 23 0.00 30.00 15 93.83 12 0.00 7 0.00 5 0.00 30.00 100% 93.83 0.00 0.00
HORIZONTAL 1.09M (1.04) Uni 206.00 0.1142 66 63 50 35 30 0.00 23 0.00 206.00 15 352.88 81.00 12 111.00 7 0.00 5 0.00 287.00 139% 463.88 (81.00) (610.51)
HORIZONTAL 1.57M (1.52) Uni 236.00 0.1474 66 63 50 35 30 0.00 23 0.00 236.00 15 521.80 86.00 12 152.12 7 0.00 5 0.00 322.00 136% 673.91 (86.00) (836.64)
DIAGONAL 2.00X1.09M (2.25) Uni 71.00 0.1958 66 63 50 35 30 0.00 23 0.00 71.00 15 208.53 12 0.00 7 0.00 5 0.00 71.00 100% 208.53 0.00 0.00
DIAGONAL 2.00X1.57M (2.50) Uni 32.00 0.2070 66 63 50 35 30 0.00 23 0.00 32.00 15 99.36 12 0.00 7 0.00 5 0.00 32.00 100% 99.36 0.00 0.00
DIAGONAL 1.50X1.57M (2.11) Uni 22.00 0.2001 66 63 50 35 30 0.00 23 0.00 22.00 15 66.03 12 0.00 7 0.00 5 0.00 22.00 100% 66.03 0.00 0.00
DIAGONAL 1.00X1.09M (1.42) Uni 30.00 0.1575 66 63 50 35 30 0.00 23 0.00 30.00 15 70.88 81.00 12 153.09 7 0.00 5 0.00 111.00 370% 223.97 (81.00) (842.00)
DIAGONAL 1.00X1.57M (1.78) Uni 30.00 0.1843 66 63 50 35 30 0.00 23 0.00 30.00 15 82.94 86.00 12 190.20 7 0.00 5 0.00 116.00 387% 273.13 (86.00) (1,046.09)
VIGA MADERA HT-20 1.80M. Uni 24.00 0.2310 66 63 50 35 30 0.00 23 0.00 24.00 15 83.16 12 0.00 7 0.00 5 0.00 24.00 100% 83.16 0.00 0.00
VIGA MADERA HT-20 2.95M. Uni 6.00 0.3786 66 63 50 35 30 0.00 23 0.00 6.00 15 34.07 12 0.00 7 0.00 5 0.00 6.00 100% 34.07 0.00 0.00
VIGA MADERA HT-20 3.60M. Uni 28.00 0.3850 66 63 50 35 30 0.00 23 0.00 28.00 15 161.70 12 0.00 7 0.00 5 0.00 28.00 100% 161.70 0.00 0.00
VIGA 2UPN 1.97M MF Uni 12.00 0.8475 66 63 50 35 30 0.00 23 0.00 12.00 15 152.55 12 0.00 7 0.00 5 0.00 12.00 100% 152.55 0.00 0.00
ANGULO REMATE FONDO 20 VCM Uni 32.00 0.0093 66 63 50 35 30 0.00 23 0.00 32.00 15 4.46 12 0.00 7 0.00 5 0.00 32.00 100% 4.46 0.00 0.00
FONDO REMATE 20 VCM Uni 12.00 0.1067 66 63 50 35 30 0.00 23 0.00 12.00 15 19.21 12 0.00 7 0.00 5 0.00 12.00 100% 19.21 0.00 0.00
HORIZONTAL 2.07M (2.02) Uni 24.00 0.1805 66 63 50 35 30 0.00 23 0.00 24.00 15 64.98 8.00 12 17.33 7 0.00 5 0.00 32.00 133% 82.31 (8.00) (95.30)
DIAGONAL 1.50X1.09M (1.81) Uni 8.00 0.1762 66 63 50 35 30 0.00 23 0.00 8.00 15 21.14 12 0.00 7 0.00 5 0.00 8.00 100% 21.14 0.00 0.00
DIAGONAL 1.50X2.07M (2.48) Uni 4.00 0.2174 66 63 50 35 30 0.00 23 0.00 4.00 15 13.04 12 0.00 7 0.00 5 0.00 4.00 100% 13.04 0.00 0.00
DIAGONAL 1.00X2.07M (2.21) Uni 4.00 0.2051 66 63 50 35 30 0.00 23 0.00 4.00 15 12.31 8.00 12 19.69 7 0.00 5 0.00 12.00 300% 32.00 (8.00) (108.29)
VIGA MADERA HT-20 2.45M. Uni 40.00 0.2620 66 63 50 35 30 0.00 23 0.00 40.00 15 157.20 12 0.00 7 0.00 5 0.00 40.00 100% 157.20 0.00 0.00
VIGA MADERA HT-20 4.90M. Uni 12.00 0.5240 66 63 50 35 30 0.00 23 0.00 12.00 15 94.32 12 0.00 7 0.00 5 0.00 12.00 100% 94.32 0.00 0.00
BRIDA RIOST. FIJA 48X60 (FIJA Y MOVIL) Uni 320.00 0.1868 66 63 50 35 30 0.00 23 0.00 320.00 15 896.64 320.00 12 717.31 7 0.00 5 0.00 640.00 200% 1,613.95 (320.00) (3,945.22)
TUERCA CON PLACA FIJA D10 Uni 362.00 0.0042 66 63 50 35 30 0.00 23 0.00 362.00 15 22.81 12 0.00 7 0.00 5 0.00 362.00 100% 22.81 0.00 0.00
HUSILLO 0.62M D/48X5MM AR Uni 140.00 0.1612 66 63 50 35 30 0.00 23 0.00 140.00 15 338.52 12 0.00 7 0.00 5 0.00 140.00 100% 338.52 0.00 0.00
CABEZAL ARTIC. 0.62M D/48X8 AR Uni 140.00 0.2342 66 63 50 35 30 0.00 23 0.00 140.00 15 491.82 12 0.00 7 0.00 5 0.00 140.00 100% 491.82 0.00 0.00
BASE COLLARIN 60MM AR Uni 140.00 0.0515 66 63 50 35 30 0.00 23 0.00 140.00 15 108.15 12 0.00 7 0.00 5 0.00 140.00 100% 108.15 0.00 0.00
VERTICAL 1.50M S/E 60MM AR Uni 40.00 0.1875 66 63 50 35 30 0.00 23 0.00 40.00 15 112.50 70.00 12 157.50 7 0.00 5 0.00 110.00 275% 270.00 (70.00) (866.25)
VERTICAL 2.0M S/E 60MM AR Uni 28.00 0.2289 66 63 50 35 30 0.00 23 0.00 19.00 15 65.24 35.00 12 96.14 7 0.00 5 0.00 54.00 193% 161.37 (26.00) (392.79)
VERTICAL 1.0M S/E 60MM AR Uni 58.00 0.1431 66 63 50 35 30 0.00 23 0.00 58.00 15 124.50 300.00 12 515.16 7 0.00 5 0.00 358.00 617% 639.66 (300.00) (2,833.38)
VERTICAL 1.50M 60MM AR Uni 114.00 0.1767 66 63 50 35 30 0.00 23 0.00 114.00 15 302.16 12 0.00 7 0.00 5 0.00 114.00 100% 302.16 0.00 0.00
VERTICAL 2.0M 60MM AR Uni 19.00 0.2181 66 63 50 35 30 0.00 23 0.00 28.00 15 91.60 30.00 12 78.52 7 0.00 5 0.00 58.00 305% 170.12 (39.00) (561.39)
BARRA RIOSTRA. D/48-3.00M Uni 160.00 0.1868 66 63 50 35 30 0.00 23 0.00 160.00 15 448.32 160.00 12 358.66 7 0.00 5 0.00 320.00 200% 806.98 (160.00) (1,972.61)
ESPIGA CIMBRA AR-80 Uni 128.00 66 63 50 35 30 0.00 23 0.00 15 0.00 128.00 12 0.00 7 0.00 5 0.00 128.00 100% 0.00 0.00 0.00
CLIP PASADOR AR-80 MF Uni 66 63 50 35 30 0.00 23 0.00 15 0.00 128.00 12 0.00 7 0.00 5 0.00 128.00 #DIV/0! 0.00 (128.00) 0.00

sub-total (1) 2,519.46 23,434.98 15,031.83 10,938.32 12,058.21 10,713.30 7,594.56 8,336.67 4,182.82 1,603.00 1,394.42 95,288.10 (24,154.86)

VENTA CONSUMIBLES
REF.: 818000005748
44061 CONO TERMINAL (TUBO PVC 22/26) Uni 0.00 0.00 500.00 0.00 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 500.00 #DIV/0! 0.00 (500.00) 0.00
44076 CONO IMPERMEA 22/26 TPVC 22/26 Uni 0.00 0.00 500.00 0.00 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 500.00 #DIV/0! 0.00 (500.00) 0.00
BASQUIT ALSINA Uni 2,600.00 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0.24 0 624.00 0 0.00 0 0.00 0 0.00 0 0.00 0.00 #DIV/0! 0.00 0.00 0.00
TAPON CONO IMPERMEABLE D/22 Uni 0.00 0.00 500.00 0.00 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 500.00 #DIV/0! 0.00 (500.00) 0.00
Uni 0.00 0.00 0.00 0 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0.00 #DIV/0! 0.00 0.00 0.00
sub-total (2) 0.00 0.00 0.00 0.00 0.00 0.00 624.00 0.00 0.00 0.00 0.00 0.00 0.00

SUB TOTAL BRUTO ACUMULADO 23,434.98 15,031.83 10,938.32 12,058.21 10,713.30 8,218.56 8,336.67 4,182.82 1,603.00 1,394.42
Cargo 5% (condicion contractual, por adquisicion directa de SICE) 1,171.75 751.59 546.92 602.91 535.66 410.93 416.83 209.14 80.15 69.72
SUB TOTAL NETO ACUMULADO 24,606.73 15,783.42 11,485.24 12,661.12 11,248.96 8,629.49 8,753.51 4,391.96 1,683.15 1,464.14 100,707.71
SUB TOTAL ANTERIOR ACUMULADO 14,934.67 7,399.52 10,210.16 1,805.90 0.00 0.00 0.00 0.00 0.00 0.00 34,350.24
A DEDUCIR EN ESTE PERIODO 9,672.06 8,383.90 1,275.08 10,855.23 11,248.96 8,629.49 8,753.51 4,391.96 1,683.15 1,464.14 66,357.47