CRONOGRAMA VALORIZADO EJECUTADO, MANTENIMIENTO PERIODICO

CONTRATANTE: MUNICIPALIDAD PROVINCIAL DE EL DORADO


CONTRATISTA: CONSROCIO EJECUTOR LA UNIÓN
ING; RESIDENTE: ING ANDY LOPEZ INGA : C.I.P: 42030575
ING INSPECTOR: ING GEYCEN BLADISLAV DELGADO VASQUEZ
SERVICIO: MANTENIMIENTO PERIODICO Y RUTINARIO DEL CAMINO VECINAL TRAMO EMP.SM -100(SHATOJA)-LA UNION-LA FLORIDA AMIÑIO -HUANCABAMBA;EMP SM -100 -PONCIANO - NUEVO TRUJILLO

SAN PEDRO; EMP.SM -101 (DV. ALTO ROQUE) - LA LIBERTAD.


PROGRAMACIÓN

PRECIO MES 01 MES 02 (01/11/2020 MES 03 (01/12/2020 -


ITEM DESCRIPCION UND. METRADO PARCIAL (S/.) SUB TOTAL S/.
(S/.) (01/10/2020 - 31/10/2020) - 30/11/2020) 31/12/2020)

METRADO PARCIAL (S/.) METRADO PARCIAL (S/.) METRADO PARCIAL (S/.)


01 OBRAS PRELIMINARES
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 26,970.23 26,970.23 0.50 13,485.12 0.25 6,742.56 0.25 6,742.56 26,970.23
01.02 TRAZO Y REPLANTEO KM 22.42 828.81 18,581.92 11.21 9,290.96 5.61 4,645.48 5.61 4,645.48 18,581.92
02 PAVIMENTOS
CAPA NIVELANTE DE SUB RASANTE E=VARIABLE
02.01 m3 1,702.98 28.47 48,483.84 800.00 22,776.00 700.00 19,929.00 202.98 5,778.84 48,483.84
MATERIAL GRANULAR DE CANTERA PARA AFIRMADO E=0.15 M
02.02 m3 13,454.40 31.25 420,450.00 3,030.00 94,687.50 2,200.00 68,750.00 8,224.40 257,012.50 420,450.00
03 TRANSPORTE
03.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1KM M3K 13,602.33 5.95 80,933.86 560.00 3,332.00 1,200.00 7,140.00 11,842.30 70,461.69 80,933.69
03.02 TRANSPORTE DE MATERIAL GRANULAR MAYOR A 1KM M3K 59,589.62 6.41 381,969.46 3,960.00 25,383.60 2,800.00 17,948.00 52,829.65 338,638.06 381,969.66
03.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1KM M3K 2,281.03 5.72 13,047.49 1,100.00 6,292.00 1,181.03 6,755.49 13,047.49
03.04 TRANSPORTE DE MATERIAL EXCEDENTE MAYOR A 1KM M3K 3,600.37 2.03 7,308.75 540.00 1,096.20 3,060.37 6,212.55 7,308.75
04 OBRAS DE ARTE Y DRENAJE
04.01 RECONFORMACION DE CUNETAS ml 25,303.00 1.91 48,328.73 9,800.00 18,718.00 2,000.00 3,820.00 13,503.00 25,790.73 48,328.73
05 SEÑALIZACION
05.01 INSTALACIÒN DE POSTES KILOMETRICOS und 26.00 200.00 5,200.00 26.00 5,200.00 5,200.00
05.02 SEÑALES PREVENTIVAS und 18.00 416.51 7,497.18 18.00 7,497.18 7,497.18
05.03 SEÑALES REGLAMENTARIAS und 4.00 545.75 2,183.00 4.00 2,183.00 2,183.00
05.04 SEÑALES INFORMATIVAS und 6.00 2,883.29 17,299.74 6.00 17,299.74 17,299.74
06 IMPACTO AMBIENTAL
06.01 RECUPERACION AMBIENTAL DE AREAS OCUPADAS HA 4.38 9,416.85 41,245.80 4.38 41,245.80 41,245.80
07 EMERGENCIA SANITARIA
07.01 EMERGENCIA SANITARIA COVID-19 GLB 1.00 17,668.80 17,668.80 0.33 5,889.60 0.33 5,889.60 0.33 5,889.60 17,668.80
COSTO DIRECTO S/. 193,562.77 142,252.84 801,353.21 1,137,168.82
GASTOS GENERALES 19,795.96 14,548.42 81,955.62 116,300.00
UTILIDAD 15,485.02 11,380.23 64,108.26 90,973.50
PRESUPUESTO DE OBRA 228,843.76 168,178.57 947,417.10 1,344,439.39
% DE AVANCE PARCIAL 17.02% 12.51% 70.47%
% DE AVANCE ACUMULADO 17.02% 29.53% 100.00%