VALORIZACION DE OBRA Nº 01
OBRA : EVALUACIÓN DE SECTORES CRÍTICOS EN LOS PAVIMENTOS DE PLATAFORMA LADO ALFA DEL AEROPUERTO INTERNACIONAL CAPITÁN FAP DAVID ABENZUR RENGIFO
CONTRATISTA : ADP - AEROPUERTOS DEL PERÚ MONTO PRESUP. BASE S/. 191,391.54
FORMULA Nº 01 - PAVIMENTACIÓN
DESCRIPCION PRESUPUESTO BASE AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMUL. SALDO QUE SOBRA
% AVANCE % AVANCE % POR
ITEM UND
MET. P. UNIT. P. TOTAL MET. MONTO S/. % MET. MONTO S/. ACTUAL MET. MONTO S/. ACUMUL. MET. MONTO VAL.
PAVIMENTACIÓN
01 OBRAS PRELIMINARES
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 4200.00 4,200.00 0.00 0.00 1.00 4200.00 100.00% 1.00 4200.00 100.00% 0.00 0.00 0.00%
01.02 TRAZO Y REPLANTEO m2 640.00 0.74 473.60 0.00 0.00 640.00 473.60 100.00% 640.00 473.60 100.00% 0.00 0.00 0.00%
02 PARCHADO CON LOSA DE CONCRETO HIDRAULICO
02.01 REMOCION DE CARPETA ASFALTICA EXISTENTE m3 83.20 24.86 2,068.35 0.00 0.00 15.00 372.90 18.03% 15.00 372.90 18.03% 68.20 1695.45 81.97%
02.02 EXCAVACIÓN DE MATERIAL GRANULAR m3 416.00 112.91 46,970.56 0.00 0.00 110.00 12420.10 26.44% 110.00 12420.10 26.44% 306.00 34550.46 73.56%
02.03 RECONFORMACION Y COMPACTACIÓN DE SUBRASANTE m2 640.00 14.91 9,542.40 0.00 0.00 120.00 1789.20 18.75% 120.00 1789.20 18.75% 520.00 7753.20 81.25%
02.04 MATERIAL GRANULAR m3 192.00 65.21 12,520.32 0.00 0.00 38.00 2477.98 19.79% 38.00 2477.98 19.79% 154.00 10042.34 80.21%
02.05 BASE GRANULAR m3 96.00 65.01 6,240.96 0.00 0.00 15.00 975.15 15.63% 15.00 975.15 15.63% 81.00 5265.81 84.38%
02.06 LOSA DE CONCRETO HIDRÁULICO F'C=350 KG/CM2 m3 211.20 79.52 16,794.62 0.00 0.00 10.00 795.20 4.73% 10.00 795.20 4.73% 201.20 15999.42 95.27%
02.07 JUNTA DE CONTRACCION m 151.00 65.89 9,949.39 0.00 0.00 37.75 2487.35 25.00% 37.75 2487.35 25.00% 113.25 7462.04 75.00%
02.08 JUNTA DE AISLAMIENTO m 124.00 54.60 6,770.40 0.00 0.00 31.00 1692.60 25.00% 31.00 1692.60 25.00% 93.00 5077.80 75.00%
02.09 JUNTA TRANSVERSAL DE CONTRACCIÓN (INSERCIÓN DE DOWELL) m 131.00 56.90 7,453.90 0.00 0.00 32.75 1863.48 25.00% 32.75 1863.48 25.00% 98.25 5590.43 75.00%
03 TRANSPORTE
03.01 TRANSPORTE DE MATERIAL GRANULAR D<= 1KM m3k 253.44 8.76 2,220.13 0.00 0.00 45.00 394.20 17.76% 45.00 394.20 17.76% 208.44 1825.93 82.24%
03.02 TRANSPORTE DE MATERIAL GRANULAR D> 1KM m3k 3147.84 1.51 4,753.24 0.00 0.00 650.00 981.50 20.65% 650.00 981.50 20.65% 2497.84 3771.74 79.35%
03.03 TRANSPORTE DE EXCEDENTES A DME PARA D<= 1KM m3k 58.24 7.18 418.16 0.00 0.00 12.00 86.16 20.60% 12.00 86.16 20.60% 46.24 332.00 79.40%
03.04 TRANSPORTE DE EXCEDENTES A DME PARA D> 1KM m3k 58.24 1.58 92.02 0.00 0.00 13.00 20.54 22.32% 13.00 20.54 22.32% 45.24 71.48 77.68%
03.05 TRANSPORTE DE EXCEDENTES (CARPETA ASFÁLTICA) A DME PARA D<= 1KM m3k 11.65 7.18 83.65 0.00 0.00 1.00 7.18 8.58% 1.00 7.18 8.58% 10.65 76.47 91.42%
03.06 TRANSPORTE DE EXCEDENTES (CARPETA ASFÁLTICA) A DME PARA D> 1KM m3k 11.65 1.58 18.41 0.00 0.00 4.00 6.32 34.33% 4.00 6.32 34.33% 7.65 12.09 65.67%
04 PROTECIÓN AMBIENTAL
04.01 DISPOSICIÓN Y CONFORMACIÓN DE MATERIAL EXCEDENTE PROVENIENTE DE m3 80.00 29.72 2,377.60 0.00 0.00 20.00 594.40 25.00% 20.00 594.40 25.00% 60.00 1783.20 75.00%
REMOCIÓN ASFÁLTICA
COSTO DIRECTO 132,947.72 0.00 31,637.86 31,637.86 101,309.86
GASTOS GENERALES 12.00% 15,953.73 0.00 3,796.54 3,796.54 12,157.19
UTILIDAD 10.00% 13,294.77 0.00 3,163.79 3,163.79 10,130.98
SUB TOTAL 162,196.22 0.00 38,598.19 38,598.19 123,598.03
FACTOR DE RELACION 1.0000 162,196.22 0.00 38,598.19 38,598.19 123,598.03
IMPUESTO (IGV) 18.00% 29,195.32 0.00 6,947.67 6,947.67 22,247.65
TOTAL PRESUPUESTO CONTRATADO 191,391.54 0.00 45,545.86 45,545.86 145,845.68
PORCENTAJE DE AVANCE (%) 100.00% 0.00% 23.80% 23.80% 76.20%
VALORIZACION DE OBRA Nº 02
OBRA : EVALUACIÓN DE SECTORES CRÍTICOS EN LOS PAVIMENTOS DE PLATAFORMA LADO ALFA DEL AEROPUERTO INTERNACIONAL CAPITÁN FAP DAVID ABENZUR RENGIFO
CONTRATISTA : ADP - AEROPUERTOS DEL PERÚ MONTO PRESUP. BASE S/. 191,391.54
FORMULA Nº 01 - PAVIMENTACIÓN
DESCRIPCION PRESUPUESTO BASE AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMUL. SALDO QUE SOBRA
% AVANCE % AVANCE % POR
ITEM UND
MET. P. UNIT. P. TOTAL MET. MONTO S/. % MET. MONTO S/. ACTUAL MET. MONTO S/. ACUMUL. MET. MONTO VAL.
PAVIMENTACIÓN
01 OBRAS PRELIMINARES
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 4200.00 4,200.00 1.00 4200.00 100.00% 0.00 0.00 0.00% 1.00 4200.00 100.00% 0.00 0.00 0.00%
01.02 TRAZO Y REPLANTEO m2 640.00 0.74 473.60 640.00 473.60 100.00% 0.00 0.00 0.00% 640.00 473.60 100.00% 0.00 0.00 0.00%
02 PARCHADO CON LOSA DE CONCRETO HIDRAULICO
02.01 REMOCION DE CARPETA ASFALTICA EXISTENTE m3 83.20 24.86 2,068.35 15.00 372.90 18.03% 15.00 372.90 18.03% 30.00 745.80 36.06% 53.20 1322.55 63.94%
02.02 EXCAVACIÓN DE MATERIAL GRANULAR m3 416.00 112.91 46,970.56 110.00 12420.10 26.44% 110.00 12420.10 26.44% 220.00 24840.20 52.88% 196.00 22130.36 47.12%
02.03 RECONFORMACION Y COMPACTACIÓN DE SUBRASANTE m2 640.00 14.91 9,542.40 120.00 1789.20 18.75% 120.00 1789.20 18.75% 240.00 3578.40 37.50% 400.00 5964.00 62.50%
02.04 MATERIAL GRANULAR m3 192.00 65.21 12,520.32 38.00 2477.98 19.79% 38.00 2477.98 19.79% 76.00 4955.96 39.58% 116.00 7564.36 60.42%
02.05 BASE GRANULAR m3 96.00 65.01 6,240.96 15.00 975.15 15.63% 15.00 975.15 15.63% 30.00 1950.30 31.25% 66.00 4290.66 68.75%
02.06 LOSA DE CONCRETO HIDRÁULICO F'C=350 KG/CM2 m3 211.20 79.52 16,794.62 10.00 795.20 4.73% 10.00 795.20 4.73% 20.00 1590.40 9.47% 191.20 15204.22 90.53%
02.07 JUNTA DE CONTRACCION m 151.00 65.89 9,949.39 37.75 2487.35 25.00% 37.75 2487.35 25.00% 75.50 4974.70 50.00% 75.50 4974.70 50.00%
02.08 JUNTA DE AISLAMIENTO m 124.00 54.60 6,770.40 31.00 1692.60 25.00% 31.00 1692.60 25.00% 62.00 3385.20 50.00% 62.00 3385.20 50.00%
02.09 JUNTA TRANSVERSAL DE CONTRACCIÓN (INSERCIÓN DE m 131.00 56.90 7,453.90 32.75 1863.48 25.00% 32.75 1863.48 25.00% 65.50 3726.96 50.00% 65.50 3726.95 50.00%
03 DOWELL)
TRANSPORTE
03.01 TRANSPORTE DE MATERIAL GRANULAR D<= 1KM m3k 253.44 8.76 2,220.13 45.00 394.20 17.76% 45.00 394.20 17.76% 90.00 788.40 35.51% 163.44 1431.73 64.49%
03.02 TRANSPORTE DE MATERIAL GRANULAR D> 1KM m3k 3147.84 1.51 4,753.24 650.00 981.50 20.65% 650.00 981.50 20.65% 1300.00 1963.00 41.30% 1847.84 2790.24 58.70%
03.03 TRANSPORTE DE EXCEDENTES A DME PARA D<= 1KM m3k 58.24 7.18 418.16 12.00 86.16 20.60% 12.00 86.16 20.60% 24.00 172.32 41.21% 34.24 245.84 58.79%
03.04 TRANSPORTE DE EXCEDENTES A DME PARA D> 1KM m3k 58.24 1.58 92.02 13.00 20.54 22.32% 13.00 20.54 22.32% 26.00 41.08 44.64% 32.24 50.94 55.36%
03.05 TRANSPORTE DE EXCEDENTES (CARPETA ASFÁLTICA) A DME m3k 11.65 7.18 83.65 1.00 7.18 8.58% 1.00 7.18 8.58% 2.00 14.36 17.17% 9.65 69.29 82.83%
03.06 PARA D<= 1KMDE EXCEDENTES (CARPETA ASFÁLTICA) A DME
TRANSPORTE m3k 11.65 1.58 18.41 4.00 6.32 34.33% 4.00 6.32 34.33% 8.00 12.64 68.67% 3.65 5.77 31.33%
04 PARA D> 1KMAMBIENTAL
PROTECIÓN
04.01 DISPOSICIÓN Y CONFORMACIÓN DE MATERIAL EXCEDENTE m3 80.00 29.72 2,377.60 20.00 594.40 25.00% 20.00 594.40 25.00% 40.00 1188.80 50.00% 40.00 1188.80 50.00%
PROVENIENTE DE
REMOCIÓN
COSTO ASFÁLTICA
DIRECTO 132,947.72 31,637.86 26,964.26 58,602.12 74,345.60
GASTOS GENERALES 12.00% 15,953.73 3,796.54 3,235.71 7,032.25 8,921.48
UTILIDAD 10.00% 13,294.77 3,163.79 2,696.43 5,860.21 7,434.56
SUB TOTAL 162,196.22 38,598.19 32,896.40 71,494.58 90,701.64
FACTOR DE RELACION 1.0000 162,196.22 38,598.19 32,896.40 71,494.58 90,701.64
IMPUESTO (IGV) 18.00% 29,195.32 6,947.67 5,921.35 12,869.02 16,326.30
TOTAL PRESUPUESTO CONTRATADO 191,391.54 45,545.86 38,817.75 84,363.60 107,027.94
PORCENTAJE DE AVANCE (%) 100.00% 23.80% 20.28% 44.08% 55.92%
VALORIZACION DE OBRA Nº 03
OBRA : MEJORAMIENTO DEL SERVICIO DE EDUCACION PRIMARIA EN LA INSTUCION EDUCATIVA N16297 JUAN VELAZCO ALVARADO, DISTRITO DE NIEVA PROVINCIA CONDORCANQUI EGION AMAZONAS
FORMULA Nº 01 - EDIFICACIONES
DESCRIPCION PRESUPUESTO BASE AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMUL. SALDO QUE SOBRA
% AVANCE % AVANCE % POR
ITEM UND
MET. P. UNIT. P. TOTAL MET. MONTO S/. % MET. MONTO S/. ACTUAL MET. MONTO S/. ACUMUL. MET. MONTO VAL.
PAVIMENTACIÓN
01 OBRAS PRELIMINARES
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 4200.00 4,200.00 1.00 4200.00 100.00% 0.00 0.00 0.00% 1.00 4200.00 100.00% 0.00 0.00 0.00%
01.02 TRAZO Y REPLANTEO m2 640.00 0.74 473.60 640.00 473.60 100.00% 0.00 0.00 0.00% 640.00 473.60 100.00% 0.00 0.00 0.00%
02 PARCHADO CON LOSA DE CONCRETO
02.01 REMOCION DE CARPETA ASFALTICA EXISTENTE m3 83.20 24.86 2,068.35 30.00 745.80 36.06% 15.00 372.90 18.03% 45.00 1118.70 54.09% 38.20 949.65 45.91%
02.02 EXCAVACIÓN DE MATERIAL GRANULAR m3 416.00 112.91 46,970.56 220.00 24840.20 52.88% 110.00 12420.10 26.44% 330.00 37260.30 79.33% 86.00 9710.26 20.67%
02.03 RECONFORMACION Y COMPACTACIÓN DE SUBRASANTE m2 640.00 14.91 9,542.40 240.00 3578.40 37.50% 120.00 1789.20 18.75% 360.00 5367.60 56.25% 280.00 4174.80 43.75%
02.04 MATERIAL GRANULAR m3 192.00 65.21 12,520.32 76.00 4955.96 39.58% 38.00 2477.98 19.79% 114.00 7433.94 59.38% 78.00 5086.38 40.63%
02.05 BASE GRANULAR m3 96.00 65.01 6,240.96 30.00 1950.30 31.25% 15.00 975.15 15.63% 45.00 2925.45 46.88% 51.00 3315.51 53.13%
02.06 LOSA DE CONCRETO HIDRÁULICO F'C=350 KG/CM2 m3 211.20 79.52 16,794.62 20.00 1590.40 9.47% 10.00 795.20 4.73% 30.00 2385.60 14.20% 181.20 14409.02 85.80%
02.07 JUNTA DE CONTRACCION m 151.00 65.89 9,949.39 75.50 4974.70 50.00% 37.75 2487.35 25.00% 113.25 7462.05 75.00% 37.75 2487.35 25.00%
02.08 JUNTA DE AISLAMIENTO m 124.00 54.60 6,770.40 62.00 3385.20 50.00% 31.00 1692.60 25.00% 93.00 5077.80 75.00% 31.00 1692.60 25.00%
02.09 JUNTA TRANSVERSAL DE CONTRACCIÓN (INSERCIÓN DE DOWELL) m 131.00 56.90 7,453.90 65.50 3726.95 50.00% 32.75 1863.48 25.00% 98.25 5590.43 75.00% 32.75 1863.48 25.00%
03 TRANSPORTE
03.01 TRANSPORTE DE MATERIAL GRANULAR D<= 1KM m3k 253.44 8.76 2,220.13 90.00 788.40 35.51% 45.00 394.20 17.76% 135.00 1182.60 53.27% 118.44 1037.53 46.73%
03.02 TRANSPORTE DE MATERIAL GRANULAR D> 1KM m3k 3147.84 1.51 4,753.24 1300.00 1963.00 41.30% 650.00 981.50 20.65% 1950.00 2944.50 61.95% 1197.84 1808.74 38.05%
03.03 TRANSPORTE DE EXCEDENTES A DME PARA D<= 1KM m3k 58.24 7.18 418.16 24.00 172.32 41.21% 12.00 86.16 20.60% 36.00 258.48 61.81% 22.24 159.68 38.19%
03.04 TRANSPORTE DE EXCEDENTES A DME PARA D> 1KM m3k 58.24 1.58 92.02 26.00 41.08 44.64% 13.00 20.54 22.32% 39.00 61.62 66.96% 19.24 30.40 33.04%
03.05 TRANSPORTE DE EXCEDENTES (CARPETA ASFÁLTICA) A DME PARA D<= 1KM m3k 11.65 7.18 83.65 2.00 14.36 17.17% 1.00 7.18 8.58% 3.00 21.54 25.75% 8.65 62.11 74.25%
03.06 TRANSPORTE DE EXCEDENTES (CARPETA ASFÁLTICA) A DME PARA D> 1KM m3k 11.65 1.58 18.41 8.00 12.64 68.67% 3.65 5.77 31.33% 11.65 18.41 100.00% 0.00 0.00 0.00%
04 PROTECIÓN AMBIENTAL
04.01 DISPOSICIÓN Y CONFORMACIÓN DE MATERIAL EXCEDENTE PROVENIENTE DE m3 80.00 29.72 2,377.60 40.00 1188.80 50.00% 20.00 594.40 25.00% 60.00 1783.20 75.00% 20.00 594.40 25.00%
REMOCIÓN ASFÁLTICA
COSTO DIRECTO 132,947.72 58,602.11 26,963.71 85,565.82 47,381.90
GASTOS GENERALES 12.00% 15,953.73 7,032.25 3,235.65 10,267.90 5,685.83
UTILIDAD 10.00% 13,294.77 5,860.21 2,696.37 8,556.58 4,738.19
SUB TOTAL 162,196.22 71,494.57 32,895.73 104,390.30 57,805.92
FACTOR DE RELACION 1.0000 162,196.22 71,494.57 32,895.73 104,390.30 57,805.92
IMPUESTO (IGV) 18.00% 29,195.32 12,869.02 5,921.23 18,790.25 10,405.07
TOTAL PRESUPUESTO CONTRATADO 191,391.54 84,363.59 38,816.96 123,180.55 68,210.99
PORCENTAJE DE AVANCE (%) 100.00% 44.08% 20.28% 64.36% 35.64%