Cronograma de trabajo-Gantt

ARQ-URBANA REDOMA PETARE


Arquitectos Silva-Arenas / Colmenares Fecha de hoy 4/28/2022 Thursday
(Linea roja vertical)
Coordinador: Antonio Iemma Altieri
Fecha de inicio: 12/21/2018 viernes 119
[42] First Day of Week (Mon=2): ###
###
###
2###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

Dias Completos
Dias calendario

Dias laborables

Días Restantes

17 - Dec - 18

24 - Dec - 18

31 - Dec - 18

07 - Jan - 19
EDT ACTIVIDAD INICIO FINALIZACION
0 Tiempo total del proyecto 3/05/12 7/01/12 119 85 #REF! #REF!
1 Fase de Iniciacion 3/05/12 3/29/12 25 19 #REF! #REF!
2 Anteproyectos 3/30/12 5/03/12 35 25 0 35
2.1 Arquitectura Urbana 3/30/12 4/18/12 20 14 0 20
2.2 Alumbrado Público 3/30/12 4/24/12 26 18 0 26
2.3 Drenajes aguas de lluvias 3/30/12 4/24/12 26 18 0 26
2.4 Arquitectura Paisajista 3/30/12 4/24/12 26 18 0 26
2.5 Revision coordi y present 4/19/12 5/03/12 15 11 0 15
3 Proyectos 5/04/12 6/22/12 50 36 0 50
3.1 Arquitectura Urbana 5/04/12 6/07/12 35 25 0 35
3.2 Drenajes aguas de lluvias 5/04/12 6/07/12 35 25 0 35
3.3 TdR licitación obras 6/13/12 6/27/12 15 11 0 15
3.4 Revision coordi y present 6/23/12 7/01/12 9 5 0 9
[42]

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

06 - May - 19
04 - Mar - 19

11 - Mar - 19

18 - Mar - 19

25 - Mar - 19
04 - Feb - 19

11 - Feb - 19

18 - Feb - 19

25 - Feb - 19
07 - Jan - 19

14 - Jan - 19

21 - Jan - 19

28 - Jan - 19

01 - Apr - 19

08 - Apr - 19

15 - Apr - 19

22 - Apr - 19

29 - Apr - 19

###
Cronograma de trabajo-Gantt
[Nombre del proyecto]
[Nombre de empresa] Fecha de hoy: 12/18/2018 martes
(vertical red line)
Lider del proyecto:
Fecha de inicio: 12/21/2018 viernes

[42] Primer día semana (lun=2): ###


###
###
2###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
0 Tiempo total del proyecto Respon. 12/18/18 2/05/19 50 22% 36 10 40
1 Fase de Iniciacion Rol 1 12/18/18 12/22/18 5 0% 4 0 5
1.1 Recibir EIR Proyecto 12/18/18 12/18/18 1 0% 1 0 1
1.1.1 Revisión EIR 12/18/18 12/18/18 1 0% 1 0 1
1.1.2 Revisión Programa 12/18/18 12/18/18 1 0% 1 0 1
1.1.3 Revisión Planos 12/18/18 12/18/18 1 0% 1 0 1
1.1.4 Revisión Doc. Legal 12/18/18 12/18/18 1 0% 1 0 1
1.2 Elaborar Pre-BEP de Proyecto 12/19/18 12/21/18 3 0% 3 0 3
1.3 Coordinación Pre-BEP TOTAL 12/21/18 12/25/18 5 0% 3 0 5
2 Formular BEP Rol 1 12/21/18 12/27/18 7 24% 5 1 6
2.1 Arquitectura Rol 2 12/21/18 12/27/18 7 25% 5 1 6
2.2 Estructura Rol 3 12/21/18 12/27/18 7 25% 5 1 6
2.3 Instalaciones Electricas Rol 4 12/21/18 12/27/18 7 25% 5 1 6
2.4 Instalaciones Especiales Rol 5 12/21/18 12/27/18 7 25% 5 1 6
2.4.1 Gas 1/05/09 1/05/09 1 0% 1 0 1
2.4.2 Incendio 1/05/09 1/05/09 1 0% 1 0 1
2.5 Instalaciones Mecánicas Rol 6 12/21/18 12/27/18 7 25% 5 1 6
2.6 Instalaciones Sanitarias Rol 7 12/21/18 12/27/18 7 25% 5 1 6
2.7 Coordinación BEP 12/21/18 12/27/18 7 25% 5 1 6
3 Modelado BIM/MDIP Rol 1 12/21/18 12/27/18 7 24% 5 1 6
3.1 Arquitectura Rol 2 12/21/18 12/27/18 7 25% 5 1 6
3.2 Estructura Rol 3 12/21/18 12/27/18 7 25% 5 1 6
3.3 Instalaciones Electricas Rol 4 12/21/18 12/27/18 7 25% 5 1 6
3.4 Instalaciones Especiales Rol 5 12/21/18 12/27/18 7 25% 5 1 6
3.4.1 Gas 12/21/18 12/21/18 1 0% 1 0 1
3.4.2 Incendio 12/21/18 12/21/18 1 0% 1 0 1
3.5 Instalaciones Mecánicas Rol 6 12/21/18 12/27/18 7 25% 5 1 6
3.6 Instalaciones Sanitarias Rol 7 12/21/18 12/27/18 7 25% 5 1 6
3.7 Coordinación BIM/MDIP 12/21/18 12/27/18 7 25% 5 1 6
4 Control Fallos Rol 1 12/21/18 12/27/18 7 24% 5 1 6
4.1 Arquitectura Rol 2 12/21/18 12/27/18 7 25% 5 1 6
4.2 Estructura Rol 3 12/21/18 12/27/18 7 25% 5 1 6
4.3 Instalaciones Electricas Rol 4 12/21/18 12/27/18 7 25% 5 1 6
4.4 Instalaciones Especiales Rol 5 12/21/18 12/27/18 7 25% 5 1 6
4.4.1 Gas 12/21/18 12/21/18 1 0% 1 0 1
4.4.2 Incendio 12/21/18 12/21/18 1 0% 1 0 1
4.5 Instalaciones Mecánicas Rol 6 12/21/18 12/27/18 7 25% 5 1 6
4.6 Instalaciones Sanitarias Rol 7 12/21/18 12/27/18 7 25% 5 1 6
4.7 Coordinación Fallos 12/21/18 12/27/18 7 25% 5 1 6

TEMPLATE ROWS: Copy and insert the entire section, or just the specific sub tasks, depending on which level you want to use (formulas are different for d
1 Task Category 1 1/05/09 1/05/09 1 0% 1 0 1
1.1 Sub Task level 2 1/05/09 1/05/09 1 0% 1 0 1
1.2 Sub Task level 2 1/05/09 1/05/09 1 0% 1 0 1
1.2.1 Level 3 Task 1/05/09 1/05/09 1 0% 1 0 1
1.2.2 Level 3 Task 1/05/09 1/05/09 1 0% 1 0 1
1.2.2.1 Level 4 task 1/05/09 1/05/09 1 0% 1 0 1
1.3 Sub Task level 2 1/05/09 1/05/09 1 0% 1 0 1
1.4 Sub Task level 2 1/05/09 1/05/09 1 0% 1 0 1

HELP

- Modify the GREEN cells and the Tasks, and Task Lead columns.
- The number of weeks shown in the gantt chart is limited by the maximum number of columns available in Excel.
- The Start Date that you choose determines the first week in the gantt chart.
- Change the first day of the week via cell K8
- Use the slider to adjust the range of dates shown in the gantt chart.
- Only 34 weeks (7 1/2 months) can be shown/printed at one time, because each week uses up 7 columns.

Q: The Working Days column shows "###". How do I fix that?


You need to install the Analysis ToolPak add-in that comes with Excel. Go to Tools > Add-ins, and select Analysis ToolPak.

Q: How do I make Task 2 start the day after the end of Task 1?
Use the following formula for the start date of Task 2:
=EndDate+1
where EndDate is the reference to the cell containing the end date of task 1

Q: How do I add/insert tasks and subtasks?


Copy the entire ROW (or a group of rows) for the type of task(s) you want to add and then right-click on the row where you
Copied Cells. You can copy rows from within the gantt chart, or copy rows from the Template Rows.
Important Note: When inserting a new subtask after the last subtask or before the first subtask, you will need to update th
Duration (see below) to include the new subtask, because the ranges won't automatically expand to include the additional r

Q: How do I calculate the %Complete for a Level 1 task based upon the %Complete of all of the associated subtasks?
Example: If Task 1 is on row 10 and the subtasks are on rows 11-14, use the following formula:
=SUMPRODUCT(F11:F14,G11:G14)/SUM(F11:F14)

Q: How do I calculate the Duration for a Level 1 task based upon the largest end date of a sub task?
Example: If the Level 1 task is on row 10 and the sub tasks are on rows 11-14, use the following formula
=MAX(D11:D14)-C10+1

Q: How can I include holidays in the calculation of the Working Days?


You can add a list of holidays to exclude in the NETWORKDAYS function. See Excel's help (F1) for more information.

Q: How do I change the print settings?


Select the entire range of cells that you want to print and then go to File > Print Area > Set Print Area. Then go to File > Pa
Scaling and Page Orientation as desired.

Q: How do I use grouping?


You can expand or collapse a group of rows using Excel's "Group and Outline" feature. To define a group of rows, select th
select Group ...

Q: How do I change the background color of the bars in the Gantt Chart?
The colors used for the bars in the Gantt Chart are set using Conditional Formatting. The simplest approach for Excel 2002
palette. Go to Tools > Options > Color tab. Or, you can select all of the cells in the Gantt Chart and go to Format > Conditio
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

use (formulas are different for different WBS levels)


ilable in Excel.

columns.

select Analysis ToolPak.

ck on the row where you want to insert the new tasks, then select Insert
.
ou will need to update the formulas for calculating the Level 1 %Complete and
o include the additional row.

ssociated subtasks?

sk?
rmula

r more information.

ea. Then go to File > Page Setup or File > Print Preview and adjust the

group of rows, select the rows and go to Data > Group and Outline and

approach for Excel 2002/2003 would be to change the colors via the color
go to Format > Conditional Formatting to change the colors.
[42]