Está en la página 1de 1

J.F.

Construcciones
FICHA DE ANALISIS DE PRECIOS UNITARIOS

OBRA: Remocion de Adoquines en Acera Existentes ANALISIS DE P.U. # 1


UBICACION: PAD Kennedy FECHA: Julio 2017
UNIDAD: M2

MATERIALES
DESCRIPCION CANT UNIDAD P.U. FACTOR IMPORTE

1 Lps. -
2 Lps. -
3 Lps. -
4 Lps. -
5 Lps. -
6 Lps. -
7

TOTAL MATERIALES Lps. -

MANO DE OBRA
DESCRIPCION CANT UNIDAD P.U. FACTOR IMPORTE

1 Captaz 0.30000 Hora 62.50 Lps. 18.75


2 Peon 0.60000 Hora 36.61 Lps. 21.97 2 Peones x 0.25 hr c/u
3 Lps. -
4 Lps. -
5 Lps. -
6 Lps. -
7 Lps. -
Sub-Total Mano de Obra Lps. 40.72

Beneficios Sociales 52% Lps. 21.17


TOTAL MANO DE OBRA Lps. 61.89

HERRAMIENTAS Y EQUIPO
DESCRIPCION CANT UNIDAD P.U. FACTOR IMPORTE

1 Retroexcavadora 0.20000 Hora 650.00 Lps. 130.00 Transportar Adoquin al Plantel


2 Lps. -
3 Lps. -
4 Lps. -
5 Lps. -

6 Herramienta Menor 5.00000 % Lps. 3.09


TOTAL HERRAMIENTAS Y EQUIPO Lps. 133.09

COSTO DIRECTO Lps. 194.98


FSC 20% Lps. 39.00
PRECIO UNITARIO Lps. 233.97