PLANILLA DE AVANCE Nº 1 (MANO DE OBRA)

PROYECTO: PROPIETARIO:
UBICACIÓN: FECHA:
PRESUPUESTADO AVANCE FISICO AVANCE FINANCIERO
N° DESCRIPCION UND. CANTIDAD P.UNIT. P.PARCIAL ANTERIOR ACTUAL ACUMULADO ANTERIOR ACTUAL ACUMULADO PORCENT.
ITEM Bs.- Bs.- Bs.- Bs.- Bs.- %
1 REPLANTEO. m² 276.00 5.12 1,413.12 276.00 276.00 1,413.12 1,413.12 100%
2 EXCAVACION m³ 15.00 43.75 656.25 15.00 15.00 656.25 656.25 100%
16.5 HORMIGON POBRE m³ 0.39 16.50 6.44 0.39 0.39 6.44 6.44 100%
4 ZAPATAS DE Hº Aº m³ 2.88 518.75 1,494.00 1.92 1.92 996.00 996.00 67%
5 CIMIENTO DE Hº Aº m³ 9.90 562.50 5,568.75 4.50 4.50 2,531.25 2,531.25 45%
6 COLUMNAS DE H° A° m³ 3.78 575.55 2,175.58
7 VIGAS DE H° A° m³ 4.20 953.90 4,006.38
8 IMPERMEABILIZACION DE CIMIENTOS m 201.60 4.44 895.10
9 RELLENO COMPACTADO DE TIERRA m³ 64.50 39.60 2,554.20
10 MURO DE LADRILLO CERAMICO m² 693.00 25.00 17,325.00
11 CUBIERTA DE VIGUETA, COMPLEM. Y CALAM. m² 276.00 30.00 8,280.00
12 ESTUCADO m² 258.75 25.00 6,468.75
13 PILASTRA pza 3.00 410.00 1,230.00
14 CORDON DE LADRILLO ADOBITO m 14.10 20.85 293.99
15 CONTRAPISO DE LADRILLO m² 258.75 18.00 4,657.50
16 LAVANDERIA pza 3.00 328.00 984.00
17 BAJANTES PLUVIALES m 36.00 21.00 756.00
18 MESON DE COCINA ml 14.10 179.44 2,530.10
19 CARPETA DE NIVELACION m² 258.75 17.16 4,440.15
20 PISO PORCELANATO m² 258.75 37.00 9,573.75
21 ZOCALO ml 197.10 12.00 2,365.20
22 REVOQUE CEMENTO m² 855.00 24.00 20,520.00
23 REVESTIMIENTO DE AZULEJO m² 126.00 33.00 4,158.00
24 LIMPIEZA GENERAL glb 3.00 528.00 1,584.00
25 PUNTO HIDRAULICO pto 21.00 65.00 1,365.00
26 TENDIDO TUBERIA PVC Ø=¾", CON ACCESOR. ml 72.00 14.50 1,044.00
27 TENDIDO TUBERIA PVC Ø=½", CON ACCESOR. ml 36.00 14.50 522.00
28 GRIFO pza 3.00 65.00 195.00
29 LLAVE DE PASO 3/4" pza 3.00 65.00 195.00
30 LLAVE DE PASO 1/2" pza 9.00 65.00 585.00
31 PUNTO SANITARIO pto 21.00 63.00 1,323.00
32 LAVAMANO DE COLOR C/PEDESTAL pza 6.00 75.00 450.00
33 INODORO DE COLOR TANQUE BAJO pza 6.00 75.00 450.00
34 LAVAPLATOS 1 DEPOSITO - 1 FREGADERO pza 3.00 75.00 225.00
TOTAL EN BS.- 110,290.26 0.00 5,603.06 5,603.06
PLANILLA DE AVANCE Nº 21
PROYECTO: PROPIETARIO:
UBICACIÓN: FECHA:
PRESUPUESTADO AV. FISICO AV. FINANCIERO
N° DESCRIPCION UND. CANTIDAD P.UNIT. P.PARCIAL ANTERIOR ACTUAL ACUMULADO ANTERIOR ACTUAL ACUMULADO PORCENT.
ITEM Bs.- Bs.- Bs.- Bs.- Bs.- %
35 REJILLA DE PISO SIFONADA pza 6.00 63.00 378.00 0.00 0.00 0.00 0.00 0%
36 CAMARA DESGRASADORA 8" pza 3.00 65.00 195.00 0.00 0.00 0.00 0.00 0%
37 CAMARA PLUVIAL 40X40 pza 8.00 132.00 1,056.00 4.00 1.00 5.00 528.00 132.00 660.00 63%
38 CAMARA INSPECCION 0.60 X 0.60 pza 9.00 153.00 1,377.00 5.00 5.00 765.00 0.00 765.00 56%
39 CAMARA SEPTICA, 1,1X1,5X1,2 pza 3.00 945.00 2,835.00 0.25 0.25 236.25 0.00 236.25 8%
40 TENDIDO TUBO PVC 2" ml 84.00 13.20 1,108.80 0.00 0.00 0.00 0.00 0%
41 TENDIDO TUBO PVC 4" ml 144.00 15.00 2,160.00 107.00 107.00 1,605.00 0.00 1,605.00 74%
42 POZO ABSORVENTE D=1.20 MTS pza 3.00 1,890.00 5,670.00 1.30 1.30 2,457.00 0.00 2,457.00 43%
43 DUCHA CON ACCESORIOS pza 6.00 47.00 282.00 0.00 0.00 0.00 0.00 0%
44 VIGA PLANA M3 0.85 953.90 810.82 0.85 0.85 810.82 0.00 810.82 100%
45 FILO DE CEMENTO EN PUERTAS Y VENT. ML 96.00 5.50 528.00 84.50 84.50 464.75 0.00 464.75 88%
46 FILO DE CEMENTO,CANALETAS Y BAJANTES ML 140.00 14.00 1,960.00 140.00 140.00 1,960.00 0.00 1,960.00 100%
47 MESON EN VENTANAS ML 12.60 100.00 1,260.00 12.55 12.55 1,255.00 0.00 1,255.00 100%
48 REVOQUE EN MUROS LATERALES M2 103.50 24.00 2,484.00 103.50 103.50 2,484.00 0.00 2,484.00 100%
49 REVOQUE EN FACHADAS M2 115.00 24.00 2,760.00 95.00 95.00 2,280.00 0.00 2,280.00 83%
50 AUMENTO DE ALTURA EN MESONES pza 3.00 200.00 600.00 3.00 3.00 600.00 0.00 600.00 100%
51 REVOQUE EN MUROS DE CUBIERTA M2 37.20 24.00 892.80 37.20 37.20 892.80 0.00 892.80 100%
52 BOTA AGUA ML 31.20 20.00 624.00 30.00 30.00 600.00 0.00 600.00 96%
53 FILOS EN MUROS DE CUBIERTA ML 70.00 10.00 700.00 70.00 70.00 700.00 0.00 700.00 100%
54 DETALLE DE VOLUMEN EN VENTANA POST. pza 3.00 400.00 1,200.00 3.00 3.00 1,200.00 0.00 1,200.00 100%
55 DETALLE DE VOLUMEN DE INGRESO pza 3.00 1,000.00 3,000.00 3.00 3.00 3,000.00 0.00 3,000.00 100%
56 REMATE EN VOLUMEN DE BAÑO pza 3.00 700.00 2,100.00 2.15 2.15 1,505.00 0.00 1,505.00 72%
57 FILOS EN COLUMNAS Y VIGAS ML 260.00 10.00 2,600.00 183.20 183.20 1,832.00 0.00 1,832.00 70%
58 REFACCION TUBERIA EN BAÑO pza 2.00 125.00 250.00 2.00 2.00 250.00 0.00 250.00 100%
59 PINTURA EN FACHADAS m2 55.00 11.50 632.50 55.00 55.00 632.50 0.00 632.50 100%
60 PINTURA ESTUCADO m2 90.00 11.50 1,035.00 90.00 90.00 1,035.00 0.00 1,035.00 100%
61 PINTURA INTERIOR M2 825.00 11.50 9,487.50 275.00 275.00 3,162.50 0.00 3,162.50 33%
62 ILUMUNACION (cableado y placas) PTO 45.00 40.00 1,800.00 14.00 14.00 560.00 0.00 560.00 31%
63 COLOCADO DE LUMINARIAS PTO 48.00 20.00 960.00 13.00 13.00 260.00 0.00 260.00 27%
64 TOMACORR. Tv-cable (cableado y placas) PTO 75.00 40.00 3,000.00 20.00 20.00 800.00 0.00 800.00 27%

TOTAL EN BS.- 53,746.42 31,875.62 132.00 32,007.62


164,036.67 31,875.62 5,735.06 37,610.67 23%
Total avance a la Fecha Bs.- 37,610.67 23%

Son: Tres Mil Setecientos Cincuenta 00/100 Bolivianos