CONTRATO MODIFICATORIO #1 C.M.

# 1

NOMBRE DEL PROYECTO : Del : Al:

EMPRESA CONTRATISTA : ALVARADO BURGOS S.R.L. FECHA DE INICIO : PLAZO CONT : 150 Días calendario MONTO DEL CONTRATO : Bs.

PROVINCIA : FECHA DE CONCLUSIÓN : AMP. PLAZO : 0 Días calendario CODIGO DEL PROYECTO :

MUNICIPIO : FECHA CONCLUSIÓN CON A.P. : L DIAS CON A. P. : Días S C : FACTOR MULTAS 1*X : x= 0

PRECIO CONTRATO ORIGINAL BALANCE DE CANTIDADES PARA CONTRATO MODIFICATORIO #1


ITEM DESCRIPCION UNIDAD UNITARIO CANT. PRECIO BALANCE DE CANTIDADES BALANCE DE MONTOS BALANCE DE PORCENTAJES
Bs. PROGR. TOTAL Bs. ANTERIOR ACTUAL DIFERENCIA ANTERIOR ACTUAL DIFERENCIA ANTERIOR ACTUAL DIFERENCIA
A G H I=G+H J=A*G K=A*H L=A*I M=J/F*% N=K/F*% O=L/F*%
Módulo: 44 - ACTIVIDADES COMPLEMENTARIAS
2040 LIMPIEZA Y RETIRO DE ESCOMBROS EN VOLQUETA M3 61.21 355.68 21,771.17 355.68 2,208.26 1,852.58 21,771.17 135,167.80 113,396.63 100.00% 620.86% 520.86%
2050 PROVISION Y COLOCACION PLACA ENTREGA DE OBRAS PZA 2,474.54 1.00 2,474.54 1.00 1.00 - 2,474.54 2,474.54 - 100.00% 100.00% 0.00%
Módulo: 46 - ACTIVIDADES PRELIMINARES
2312 INSTALACION DE FAENAS GENERAL GLB 45,267.61 1.00 45,267.61 1.00 1.00 - 45,267.61 45,267.61 - 100.00% 100.00% 0.00%
Módulo: 247 - MEDIDAS DE MITIGACION AMBIENTAL
1763 CINTA PLASTICA DE SEGURIDAD M 4.42 400.00 1,768.00 400.00 400.00 - 1,768.00 1,768.00 - 100.00% 100.00% 0.00%
1773 CONTENEDOR DE RESIDUOS SOLIDOS PZA 1,462.54 3.00 4,387.62 3.00 3.00 - 4,387.62 4,387.62 - 100.00% 100.00% 0.00%
2660 GESTION Y DISPOSICION DE RESIDUOS SOLIDOS GLB 6,756.42 2.00 13,512.84 2.00 2.00 - 13,512.84 13,512.84 - 100.00% 100.00% 0.00%
3890 SEÑALIZACION FIJA PZA 1,431.32 10.00 14,313.20 10.00 10.00 - 14,313.20 14,313.20 - 100.00% 100.00% 0.00%
3891 SEÑALIZACION MOVIL (TIPO CABALLETE) PZA 1,664.12 5.00 8,320.60 5.00 5.00 - 8,320.60 8,320.60 - 100.00% 100.00% 0.00%
Módulo: 723 - ACTIVIDADES COMPLEMENTARIAS
70 LETRERO DE OBRA PZA 11,401.54 1.00 11,401.54 1.00 1.00 - 11,401.54 11,401.54 - 100.00% 100.00% 0.00%
5267 REPLANTEO Y TRAZADO M 25.10 1,635.81 41,058.83 1,635.81 1,322.35 - 313.46 41,058.83 33,190.96 -7,867.87 100.00% 80.84% -19.16%
4559 LIMPIEZA Y DESHIERBE M2 3.94 2,067.95 8,147.72 2,067.95 - - 2,067.95 8,147.72 - -8,147.72 100.00% 0.00% -100.00%
2748 EXCAVACION 0-1 M S/AGOTAMIENTO TERRENO SEMIDURO M3 46.05 2,471.53 113,813.96 2,471.53 2,208.26 - 263.27 113,813.96 101,690.53 -12,123.43 100.00% 89.35% -10.65%
173 NIVELADO Y PERFILADO DE PLATAFORMA M2 32.88 9,056.31 297,771.47 9,056.31 8,896.36 - 159.95 297,771.47 292,512.40 -5,259.07 100.00% 98.23% -1.77%
649 ENLOSETADO CON LOSETA ONDULADA DE 10 CM M2 183.44 8,238.40 1,511,252.10 8,238.40 8,092.90 - 145.50 1,511,252.10 1,484,561.21 -26,690.89 100.00% 98.23% -1.77%
5270 CORDON DE SUJECION DE HORMIGON SIMPLE 15x30cm M 202.61 206.90 41,920.01 206.90 222.40 15.50 41,920.01 45,060.46 3,140.45 100.00% 107.49% 7.49%
1106 CUNETA DE HORMIGON SIMPLE H21 (ANCHO=30cm) M 85.19 2,727.00 232,313.13 2,727.00 2,585.86 - 141.14 232,313.13 220,289.67 -12,023.46 100.00% 94.82% -5.18%

ACTIVIDADES NUEVAS
PROV. Y COLOC. PLACA REFLECTIVA DENOMINACION DE CALLES PZA 834.19 - - 10.00 10.00 - 8,341.90 8,341.90 0.00% 100.00% 100.00%

MONTOS TOTALES DE CONTRATO (1)= 2,369,494.34 2,369,494.34 2,422,260.88 52,766.55 100.00% 102.23% -2.23%
(R)
MENOS MULTAS y /o SANCIONES SEGÚN CONTRATO
MULTAS POR INCUMPLIMIENTO CONTRACTUAL dc. - 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00%
MULTAS POR INCUMPLIMIENTO DE PLAZOS dc. - 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00%
TOTAL DESCUENTOS : (4)= 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00%
( MS )

TOTAL CONTRATO ORIGINAL: 2,369,494.34 Bs.


TOTAL CON CONTRATO MODIFICATORIO 2,422,260.88 Bs.
DIFERENCIA CONTRATO ORIGINAL / O.C.#1 52,766.55 Bs.

Presentado por : Revisado por: Revisado por: Revisado por:

RESIDENTE DE OBRA SUPERVISOR DE OBRA FISCAL FPS FISCAL MUNICIPAL