GESTION DEL COSTO

HOJA DE METRADOS

PLANILLA DE METRADOS

PROYECTO PROVINCIA
"CONSTRUCCIÓN DE LA TROCHA CARROZABLE CHACUA-CHARAC, DISTRITO DE SAN RAFAEL
DE AMBO - HUANUCO"
TRAMO : CHACUA-CHARAC
UBICACI : HUANUCO - AMBO - SAN RAFAEL
ÓN

It Descripc Unid Metrad


e ión ad o
m
01 OBRAS PROVISIONALES
01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 4.80 m UND 1.00
01.02 CAMPAMENTO Y ALMACEN PROVISIONAL M2 132.00
02 TRABAJOS PRELIMINARES
02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS GLB 1.00
02.02 TRANSPORTE DE MATERIALES GLB 1.00
02.03 LIMPIEZA Y DESFORESTACION R= 1.0 Ha/día Ha 7.32
02.04 TRAZO Y CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE LA OBRA KM 5.42
03 MOVIMIENTO DE TIERRAS
03.01 CORTE DE MATERIAL SUELTO R=460 m3/día M3 33919.
25
03.02 CONFORMACION DE TERRAPLENES R= 790 m3/día (TP) M3 20519.
70
03.03 ELIMINACION DE MATERIAL EXCEDENTE A BOTADERO M3 13399.
55
04 OBRAS DE ARTE Y DRENAJE
04.01 ALCANTARILLAS
04.01.01 ALCANTARILLAS DE TMC 24" (13 UND)
04.01.01.01 LIMPIEZA DE TERRENO MANUAL M2 302.51
04.01.01.02 TRAZO Y REPLANTEO EN ALCANTARILLAS M2 206.96
04.01.01.03 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS M3 316.69
04.01.01.04 RELLENO COMPACTADO MANUAL MATERIAL PROPIO M3 52.73
CONCRETO F'C=175 KG/CM2 + 30% P.G. CIMENTACION ALCANTARILLAS
04.01.01.05 (TP) M3 14.93
CONCRETO F'C=175 KG/CM2 EN ALCANTARILLAS CABEZALES Y ALETAS
04.01.01.06 (TP) M3 59.45
CONCRETO F'C=140 KG/CM2 + 70% PG EMBOQUILLADO DE
04.01.01.07 M3 21.88
PIEDRA - ENTRADA Y SALIDA DE ALCANTARILLAS (TP)
04.01.01.08 ENCOFRADO Y DESENCOFRADO NORMAL DE ESTRUCTURAS M2 255.91
04.01.01.09 ALCANTARILLA TMC 0=24" C=14 R=12 m/día M 65.00
04.02 CUNETAS
04.02.01 CONFORMACION DE CUNETAS EN TERRENO NATURAL (SIERRA) M 7190.0
0
05 PLAN DE MANEJO AMBIENTAL GLB 1.00

Trabajo Escalonado Página 51


PRESUPUESTO
CRONOGRAMA DE EJECUCION VALORIZADO

PROYECTO "CONSTRUCCIÓN DE LA TROCHA CARROZABLE CHACUA-CHARAC, DISTRITO DE SAN RAFAEL PROVINCIA DE AMBO - HUANUCO"
TRAMO : CHACUA-CHARAC
UBICACIÓN : HUANUCO - AMBO - SAN RAFAEL

Item Descripción Parcial (S/.) Mes 1 Mes 2 Mes 3


01 OBRAS PROVISIONALES
01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 4.80 m S/. 804.15 S/. 804.15
01.02 CAMPAMENTO Y ALMACEN PROVISIONAL S/. 6,221.16 S/. 6,221.16
02 TRABAJOS PRELIMINARES
02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS S/. 2,841.16 S/. 2,841.16
02.02 TRANSPORTE DE MATERIALES S/. 3,403.52 S/. 3,403.52
02.03 LIMPIEZA Y DESFORESTACION R= 1.0 Ha/día S/. 9,376.48 S/. 9,376.48
02.04 TRAZO Y CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE LA OBRA S/. 5,175.02 S/. 1,725.01 S/. 1,725.01 S/. 1,725.01
03 MOVIMIENTO DE TIERRAS
03.01 CORTE DE MATERIAL SUELTO R=460 m3/día S/. 132,285.08 S/. 44,095.03 S/. 44,095.03 S/. 44,095.03
03.02 CONFORMACION DE TERRAPLENES R= 790 m3/día (TP) S/. 72,844.94 S/. 72,844.94
03.03 ELIMINACION DE MATERIAL EXCEDENTE A BOTADERO S/. 32,828.90 S/. 32,828.90
04 OBRAS DE ARTE Y DRENAJE
04.01 ALCANTARILLAS
04.01.01 ALCANTARILLAS DE TMC 24" (13 UND)
04.01.01.01 LIMPIEZA DE TERRENO MANUAL S/. 208.73 S/. 208.73
04.01.01.02 TRAZO Y REPLANTEO EN ALCANTARILLAS S/. 298.02 S/. 298.02
04.01.01.03 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS S/. 3,724.27 S/. 3,724.27
04.01.01.04 RELLENO COMPACTADO MANUAL MATERIAL PROPIO S/. 1,729.54 S/. 1,729.54
04.01.01.05 CONCRETO F'C=175 KG/CM2 + 30% P.G. CIMENTACION ALCANTARILLAS (TP) S/. 3,157.70 S/. 3,157.70
04.01.01.06 CONCRETO F'C=175 KG/CM2 EN ALCANTARILLAS CABEZALES Y ALETAS (TP) S/. 17,283.90 S/. 17,283.90
04.01.01.07 CONCRETO F'C=140 KG/CM2 + 70% PG EMBOQUILLADO DE PIEDRA -ENTRADA Y SALIDA S/.
DE3,595.10
ALCANTARILLAS (TP) S/. 3,595.10
04.01.01.08 ENCOFRADO Y DESENCOFRADO NORMAL DE ESTRUCTURAS S/. 7,505.84 S/. 7,505.84
04.01.01.09 ALCANTARILLA TMC 0=24" C=14 R=12 m/día S/. 17,968.60 S/. 17,968.60
04.02 CUNETAS S/. 0.00
04.02.01 CONFORMACION DE CUNETAS EN TERRENO NATURAL (SIERRA) S/. 23,655.10 S/. 23,655.10
05 PLAN DE MANEJO AMBIENTAL S/. 18,523.11 S/. 6,174.37 S/. 6,174.37 S/. 6,174.37
COSTO DIRECTO S/. 363,430.32 S/. 74,640.87 S/. 203,966.14 S/. 84,823.30
13% GASTOS GENERALES 12.84 % S/. 46,664.45 S/. 9,583.89 S/. 26,189.25 S/. 10,891.31
UTILIDAD (10%) S/. 36,343.03 S/. 7,464.09 S/. 20,396.61 S/. 8,482.33
PRESUPUESTO TOTAL S/. 446,437.80 S/. 91,688.85 S/. 250,552.01 S/. 104,196.94

AVANCE MENSUAL (%) 20.54% 56.12% 23.34%


AVANCE ACUMULADO (%) 20.54% 76.66% 100.00%
Item Descripción Parcial (S/.) % Mes 1 Mes 2 Mes 3 PV EV AC CV SV CPI SPI
01 OBRAS PROVISIONALES
01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 4.80 m S/. 804.15 0.22 S/. 804.15 804.15 S/804.15 S/789.50 14.65 0.00 1.02 1.00
01.02 CAMPAMENTO Y ALMACEN PROVISIONAL S/. 6,221.16 1.71 S/. 6,221.16 6,221.16 S/6,221.16 S/5,545.50 675.66 0.00 1.12 1.00
02 TRABAJOS PRELIMINARES
02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS S/. 2,841.16 0.78 S/. 2,841.16 2,841.16 S/2,841.16 S/2,400.00 441.16 0.00 1.18 1.00
02.02 TRANSPORTE DE MATERIALES S/. 3,403.52 0.94 S/. 3,403.52 3,403.52 S/3,403.52 S/3,210.53 192.99 0.00 1.06 1.00
02.03 LIMPIEZA Y DESFORESTACION R= 1.0 Ha/día S/. 9,376.48 2.58 S/. 9,376.48 9,376.48 S/9,376.48 S/8,123.00 1253.48 0.00 1.15 1.00
02.04 TRAZO Y CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE LA OBRA S/. 5,175.02 1.42 S/. 1,725.01 S/. 1,725.01 S/. 1,725.01 3,450.01 S/3,450.01 S/4,576.00 -1125.99 0.00 0.75 1.00
03 MOVIMIENTO DE TIERRAS
03.01 CORTE DE MATERIAL SUELTO R=460 m3/día S/. 132,285.08 36.40 S/. 44,095.03 S/. 44,095.03 S/. 44,095.03 88,190.05 S/88,190.05 S/99,456.00 -11265.95 0.00 0.89 1.00
03.02 CONFORMACION DE TERRAPLENES R= 790 m3/día (TP) S/. 72,844.94 20.04 S/. 72,844.94 72,844.94 S/72,844.94 S/66,487.53 6357.41 0.00 1.10 1.00
03.03 ELIMINACION DE MATERIAL EXCEDENTE A BOTADERO S/. 32,828.90 9.03 S/. 32,828.90 0.00 S/0.00 S/27,564.58 -27564.58 0.00 0.00 0.00
04 OBRAS DE ARTE Y DRENAJE
04.01 ALCANTARILLAS
04.01.01 ALCANTARILLAS DE TMC 24" (13 UND)
04.01.01.01 LIMPIEZA DE TERRENO MANUAL S/. 208.73 0.06 S/. 208.73 208.73 S/208.73 S/158.65 50.08 0.00 1.32 1.00
04.01.01.02 TRAZO Y REPLANTEO EN ALCANTARILLAS S/. 298.02 0.08 S/. 298.02 298.02 S/298.02 S/198.65 99.37 0.00 1.50 1.00
04.01.01.03 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS S/. 3,724.27 1.02 S/. 3,724.27 3,724.27 S/3,724.27 S/3,412.56 311.71 0.00 1.09 1.00
04.01.01.04 RELLENO COMPACTADO MANUAL MATERIAL PROPIO S/. 1,729.54 0.48 S/. 1,729.54 1,729.54 S/1,729.54 S/1,589.65 139.89 0.00 1.09 1.00
04.01.01.05 CONCRETO F'C=175 KG/CM2 + 30% P.G. CIMENTACION ALCANTARILLAS (TP) S/. 3,157.70 0.87 S/. 3,157.70 3,157.70 S/3,157.70 S/2,987.56 170.14 0.00 1.06 1.00
04.01.01.06 CONCRETO F'C=175 KG/CM2 EN ALCANTARILLAS CABEZALES Y ALETAS (TP) S/. 17,283.90 4.76 S/. 17,283.90 17,283.90 S/17,283.90 S/15,789.55 1494.35 0.00 1.09 1.00
CONCRETO F'C=140 KG/CM2 + 70% PG EMBOQUILLADO DE PIEDRA -ENTRADA Y SALIDA DE
04.01.01.07 S/. 3,595.10 0.99 S/. 3,595.10 3,595.10 S/3,595.10 S/3,259.46 335.64 0.00 1.10 1.00
ALCANTARILLAS (TP)
04.01.01.08 ENCOFRADO Y DESENCOFRADO NORMAL DE ESTRUCTURAS S/. 7,505.84 2.07 S/. 7,505.84 7,505.84 S/7,505.84 S/6,788.46 717.38 0.00 1.11 1.00
04.01.01.09 ALCANTARILLA TMC 0=24" C=14 R=12 m/día S/. 17,968.60 4.94 S/. 17,968.60 17,968.60 S/17,968.60 S/16,587.56 1381.04 0.00 1.08 1.00
04.02 CUNETAS
04.02.01 CONFORMACION DE CUNETAS EN TERRENO NATURAL (SIERRA) S/. 23,655.10 6.51 S/. 23,655.10 23,655.10 S/23,655.10 S/19,654.56 4000.54 0.00 1.20 1.00
05 PLAN DE MANEJO AMBIENTAL S/. 18,523.11 5.10 S/. 6,174.37 S/. 6,174.37 S/. 6,174.37 12,348.7 S/12,348.74 S/17,564.00 -5215.26 0.00 0.70 1.00
COSTO DIRECTO S/. 363,430.32 100 S/. 74,640.87 S/. 203,966.14 S/. 84,823.30 S/. 266,258.28 278,607.0 S/306,143.30 -27536.28 0.00 0.91 1.05
acumulado S/. 74,640.87 S/. 278,607.02 S/. 438,071.19
indice indice
varianza Indicado varianza de Indicado
desempeño desempeñ
de r cronogram r Obseravcion, Acciones Correctivas y
cost o
costo a Preventivas
cronogram
os
>1 ok a SPI >1 ok
CV CPI SV

SPI=EV/PV
CV=EV- CPI=EV/A SV=EV-
C
AC PV

$ 1.02 $ - Ganancia y Partida Terminada

14.65
$ 1.12 $ - Ganancia y Partida Terminada

675.66
$ - Ganancia y Partida Terminada
$ 1.18 $ - Ganancia y Partida Terminada

441.16
$ 1.06 $ - Ganancia y Partida Terminada

192.99
$ 1.15 $ - Ganancia y Partida Terminada

1,253.48
- 1,129.4 0.75 $ - Sin Ganancias y Partida No Terminada
$ 4
$ -
- 11,265.9 0.89 $ - Sin Ganancias y Partida No Terminada
$ 5
$ 1.10 $ - Ganancia y Partida Terminada

6,357.41
- 27,564.5 $ - Ganancia y Partida Terminada
$ 8
$ -
$ 1.32 $ - Ganancia y Partida Terminada

50.08
$ 1.50 $ - Ganancia y Partida Terminada

99.37
$ 1.09 $ - Ganancia y Partida Terminada

311.71
$ 1.09 $ - Ganancia y Partida Terminada

139.89
$ 1.06 $ - Ganancia y Partida Terminada

170.14
$ 1.09 $ - Ganancia y Partida Terminada

1,494.36
$ 1.10 $ - Ganancia y Partida Terminada

335.64
$ 1.11 $ - Ganancia y Partida Terminada

717.38
$ 1.08 $ - Ganancia y Partida Terminada

1,381.04
$ -
$ 1.20 $ - Ganancia y Partida Terminada

4,000.54
- 5,215.2 0.70 Sin Ganancias y Partida No Terminada
$ 6