RESUMEN DE ADICIONAL DE OBRA N°01

ADICIONAL N°01
ITEM PARQUE
ADICIONAL DEDUCTIVO ADICIO -DEDUC
1 PARQUE: JUAN VELAZCO ALVARADO MZ W (RECTANGULO) 157,451.49 66,068.65 91,382.84
2 PARQUE: JUAN VELAZCO ALVARADO MZ V LOTE 1 (TRIANGULO) 15,450.31 10,233.75 5,216.56
3 PARQUE: VILLA CONTINENTAL MZ M LOTE 1 15,467.74 4,502.12 10,965.62
4 PARQUE: LAS TERRAZAS (TRAPECIO) 75,978.72 88,017.43 -12,038.71
5 PARQUE: LAS TERRAZAS (RECTANGULAR) 85,753.90 93,735.00 -7,981.10
6 PARQUE : A.H.JOSE OLAYA ZONA A MZ S LOTE 1 0.00 0.00 0.00
7 PARQUE: LA EXPLANADA MZ G 33,878.03 23,003.71 10,874.32
8 PARQUE : EL ROSARIO 4,859.92 9,283.80 -4,423.88
9 PARQUE: BOULEVAR 0.00 0.00 0.00
COSTO DIRECTO 388,840.11 294,844.46 93,995.65
GASTOS GENERALES 10.00% 38,884.01 29,484.45 9,399.56
UTILIDAD 7.00% 27,218.81 20,639.11 6,579.70
SUB TOTAL 454,942.93 344,968.02 109,974.91
SUB TOTAL CORREGIDO (VALOR. BRUTA) 1.00 454,942.93 344,968.02 109,974.91
IGV 18% 18.00% 81,889.73 62,094.24 19,795.48
TOTAL ADICIONAL N°01 536,832.66 407,062.26 129,770.39
ADICIONAL DE OBRA N°01
MEJORAMIENTO DE LOS SERVICIOS DE 14 AREAS RECREATIVAS EN EL DISTRITO DE CAYMA PROVINCIA
AREQUIPA DEPARTAMENTO AREQUIPA.
MUNICIPALIDAD DISTRITAL DE CAYMA
PRESUPUESTO REFERENCIAL
ITEM PARTIDA METRAD P.UNITAR
UND. P.PARCIAL
O IO
01 PARQUE:JUANVELAZCOALVARADOMZW(RECTANGULO) 157,451.49
01.01 MUROS DE CONTENCION PERIMETRICO
01.01.01 ESTRUCTURAS
01.01.01.01 OBRAS DE CONCRETO SIMPLE
01.01.01.01.01 SOLADOS
01.01.01.01.01.01 SOLADO DE CONCRETO E=2" 1:12 CEM/HORM M2 94.79 25.60 2,426.64
01.01.01.02 OBRAS DE CONCRETO ARMADO
01.01.01.02.01 ZAPATAS
01.01.01.02.01.01 ZAPATAS, CONCRETO PREMEZCLADO F´C=210KG/CM2 M3 66.19 428.04 28,331.97
01.01.01.02.01.02 ZAPATAS, ACERO fy=4200 kg/cm2 KG 2,999.42 6.01 18,026.51
01.01.01.02.02 MURO DE CONTENCION
MUROS DE CONTENC, CONCRETO PREMEZCLADO 210
01.01.01.02.02.01
kg/cm2
M3 62.72 442.23 27,736.67
01.01.01.02.02.02 MUROS DE CONTENC, ENCOF. Y DESENCOFRADO. M2 448.87 59.77 26,828.96
01.01.01.02.02.03 MUROS DE CONTENC, ACERO Fy=4200 kg/cm2 KG 3,391.82 6.01 20,384.84
01.02 MUROS DE CONTENCION PERIMETRICO
01.02.01 ESTRUCTURAS
01.02.01.01 MOVIMIENTO DE TIERRAS
01.02.01.01.01 EXCAVACION DE TERRENO NATURAL C/MAQUINA M3 142.19 28.20 4,009.76
01.02.01.01.02 RELLENO COMPACTADO C/EQUIPO MAT/PROPIO M3 146.48 37.15 5,441.73
01.02.01.02 OBRAS DE CONCRETO SIMPLE
01.02.01.02.01 CIMIENTOS CORRIDOS
01.02.01.02.01.01 CIMIENTOS CORRIDOS 1:10+30% P.G. M3 14.52 299.42 4,347.58
01.02.01.03 OBRAS DE CONCRETO ARMADO
01.02.01.03.01 SOBRECIMIENTO REFORZADO
01.02.01.03.01.01 CONCRETO F'C=175 KG/CM2 M3 7.99 397.20 3,173.63
01.02.01.03.01.02 SOBRECIMIENTO REORZADO, ENCOF. Y DESENCOFRADO. M2 79.86 68.94 5,505.55
01.02.01.03.01.03 MUROS DE CONTENC, ACERO Fy=4200 kg/cm2 KG 276.79 6.01 1,663.51
01.03 ARQUITECTURA
01.03.01 REVOQUES Y ENLUCIDOS
01.03.01.01 TARRAJEO EN MURO DE CONCRETO: EXTERIORES M2 59.73 29.98 1,790.71
01.03.02 PINTURAS
01.03.02.01 PINTURA LATEX EN MUROS EXTERIORES M2 59.73 28.83 1,722.02
01.04 VEREDAS EXTERNAS
01.04.01 ESTRUCTURAS
01.04.01.01 TRABAJOS PRELIMINARES
01.04.01.01.01 DEMOLICION DE PISO DE VEREDA M3 10.77 23.70 255.25
01.04.01.01.03 ELIMINACION DE MATERIAL DE DEMOLICION M3 14.00 32.64 456.96
01.04.01.02 OBRAS DE CONCRETO SIMPLE
01.04.01.02.01 CONCRETO F'C=175 KG/CM2 M3 10.77 397.20 4,277.84
01.04.01.02.03 ENCOFRADO Y DESENCOFRADO DE VEREDAS M2 18.00 59.52 1,071.36
02 PARQUE: JUAN VELAZCO ALVARADO MZ V LOTE 1 (TRIANGULO) 15,450.31
02.01 MURO DE CONTENCION PERIMETRICO
02.01.01 ESTRUCTURAS
02.01.01.01 MOVIMIENTO DE TIERRAS
02.01.01.01.01 RELLENO COMPACTADO C/EQUIPO MAT/PROPIO M3 165.00 37.15 6,129.75
02.01.01.02 OBRAS DE CONCRETO ARMADO
02.01.01.02.01 ZAPATAS

02.01.01.02.01.01 ZAPATAS, CONCRETO PREMEZCLADO F'C=210 KG/CM2 M3 6.22 428.04 2,662.41


02.01.01.02.01.02 ZAPATAS, ACERO fy=4200 kg/cm2 KG 228.87 6.01 1,375.50
02.02 CALZADURAS
02.02.01 ESTRUCTURAS
02.02.01.01 MOVIMIENTO DE TIERRAS
02.02.01.01.01 EXCAVACION DE TERRENO NATURAL C/MAQUINA M3 7.28 41.30 300.66
02.02.01.02 OBRAS DE CONCRETO SIMPLE
02.02.01.02.01 CONCRETO CICLOPEO F´C 100 KG/CM2 + 30 %P.M. 3" M3 7.28 299.42 2,179.78
02.02.01.02.02 CALZADURA, ENCOF. Y DESENCOFRADO. M3 9.10 59.77 543.91
02.02.02 ARQUITECTURA
02.02.02.01 REVOQUES Y ENLUCIDOS
02.02.02.01.01 TARRAJEO EN MURO: -EXTERIORES M2 38.40 29.98 1,151.23
02.02.02.02 PINTURA
02.02.02.02.01 PINTURA LATEX EN MUROS EXTERIORES M2 38.40 28.83 1,107.07
03 PARQUE: VILLA CONTINENTAL MZ M LOTE 1 15,467.74
03.01 CISTERNA POZO AGUA DE RIEGO
03.01.01 ESTRUCTURAS
03.01.01.01 MOVIMIENTO DE TIERRAS
03.01.01.01.01 EXCAVACION DE TERRENO NATURAL C/MAQUINA m3 20.40 28.20 575.28
03.01.01.01.02 RELLENO COMPACTADO C/EQUIPO MAT/PROPIO m3 20.40 37.15 757.86
03.01.02 INSTALACIONES SANITARIAS
03.01.02.01 TUBERIA PVC SAP 2" m 84.00 40.00 3,360.00
03.01.02.02 CODO 90° PVC 2" m 12.00 30.00 360.00
03.01.02.03 VALVULA DE BOLA 2" m 5.00 72.31 361.55
03.01.02.04 TEE PVC SAP 2" m 7.00 30.00 210.00
03.02 GRADERIAS NUEVAS
03.02.01 ESTRUCTURAS
03.02.01.01 TRABAJOS PRELIMINARES
03.02.01.01.02 TRAZO, NIVELES Y REPLANTEO PRELIMINAR M2 4.00 2.31 9.24
03.02.01.02 MOVIMIENTO DE TIERRAS
03.02.01.02.01 EXCAVACION DE TERRENO NATURAL C/MAQUINA M3 3.60 28.20 101.52
03.02.01.02.02 PERFILADO Y NIVELACION M2 4.00 5.53 22.12
03.02.01.02.03 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA M3 4.32 32.81 141.74
03.02.01.03 GRADERIAS
03.02.01.03.01 GRADERIAS CONCRETO f´c = 175 kg/cm2 M3 7.47 392.19 2,929.66
03.02.01.03.02 ENCOFRADO Y DESENCOFRADO NORMAL M2 14.72 68.15 1,003.17
03.02.02 ARQUITECTURA
03.02.02.01 CARPINTERIA METALICA
03.02.02.01.01 BARANDA METALICA - SEGUN DISEÑO ML 8.80 120.95 1,064.36
03.03 CERCO PERIMETRICO - PUERTA INGRESO NUEVA
03.03.01 ESTRUCTURAS
03.03.01.01 COLUMNAS
03.03.01.01.01 COLUMNAS, CONCRETO 210 KG/CM2 M3 0.38 408.25 155.14
03.03.01.01.02 COLUMNAS, ENCOFRADO Y DESENCOFRADO M2 3.00 61.54 184.62
03.03.01.01.03 COLUMNAS, ACERO fy=4200 kg/cm2 KG 45.55 6.01 273.77
03.03.02 ARQUITECTURA
03.03.02.01 REVOQUES Y ENLUCIDOS
03.03.02.01.01 TARRAJEO EN MURO: EXTERIORES M2 3.00 29.98 89.94
03.03.02.02 CARPINTERIA METALICA Y HERRERIA
03.03.02.02.01 PUERTA METALICA (2.00 X 2.60 M) (SEGUN DISEÑO) UND 1.00 1,808.69 1,808.69
03.04 POSTE DE ILUMINACION PUBLICA
03.04.01 ESTRUCTURAS
03.04.01.01 TRABAJOS PRELIMINARES
03.04.01.01.01 TRASLADO DE POSTE PUBLICO UND 1.00 1,957.02 1,957.02
03.04.02 OBRAS DE CONCRETO SIMPLE
03.04.01.01 BASE DE POSTE F'C 210KG/CM2 M3 0.25 408.25 102.06
04 PARQUE: LAS TERRAZAS (TRAPECIO) 75,978.72
04.01 AREA DE CAMINERIAS
04.01.01 ESTRUCTURAS
04.01.01.01 TRABAJOS PRELIMINARES
04.01.01.01.01 TRAZO, NIVELES Y REPLANTEO PRELIMINAR M2 181.50 2.31 419.27
04.01.01.01.02 LIMPIEZA DEL TERRENO MANUAL M2 181.50 2.08 377.52
04.01.01.01.03 DEMOLICION DE MUROS EXISTENTES M3 8.76 22.23 194.73
04.01.01.02 MOVIMIENTO DE TIERRAS
04.01.01.02.01 EXCAVACION DE TERRENO NATURAL C/MAQUINA M3 36.30 28.20 1,023.66
04.01.01.02.02 PERFILADO Y NIVELACION M2 181.50 5.53 1,003.70
04.01.01.02.03 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA M3 43.56 32.81 1,429.20
04.02 ARQUITECTURA
04.02.01 PISOS Y PAVIMENTOS
04.02.01.01 CIRCULACION DE PARQUE

04.02.01.01.01 PISO DE CONCRETO PULIDO PARA CIRCULACION PRINCIPAL M2 181.50 49.98 9,071.37
04.02.01.01.02 ENCOFRADO Y DESENCOFRADO DE VEREDAS M2 34.77 59.52 2,069.51
04.03 AREA VERDE
04.03.01 EXCAVACION DE TERRENO NATURAL C/MAQUINA M3 168.29 28.20 4,745.78
04.03.01.01 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA M3 201.95 32.81 6,625.98
04.03.01.02 TIERRA DE CHACRA (E=0.15 M) M2 1,121.95 22.48 25,221.44
04.03.01.03 SEMBRADO DE GRASS NATURAL M2 1,121.95 21.21 23,796.56
05 PARQUE: LAS TERRAZAS (RECTANGULAR) 85,753.90
05.01 AREA CAMINERAS
05.01.01 ESTRUCTURAS
05.01.01.01 TRABAJOS PRELIMINARES
05.01.01.01.01 TRAZO, NIVELES Y REPLANTEO PRELIMINAR M2 273.86 2.31 632.62
05.01.01.01.02 LIMPIEZA DEL TERRENO MANUAL M2 273.86 2.08 569.63
05.01.01.02 MOVIMIENTO DE TIERRAS
05.01.01.02.01 EXCAVACION DE TERRENO NATURAL C/MAQUINA M3 54.77 28.20 1,544.51
05.01.01.02.02 PERFILADO Y NIVELACION M2 273.86 5.53 1,514.45
05.01.01.02.03 ELIMINACION MASIVA DE MATERIAL C/MAQUINA M3 65.73 32.81 2,156.60
05.02 ARQUITECTURA Y ACABADOS
05.02.01 PISOS Y PAVIMENTOS
05.02.01.01 CIRCULACION DE PARQUE

05.02.01.01.01 PISO DE CONCRETO PULIDO PARA CIRCULACION PRINCIPAL M2 273.86 49.98 13,687.52
05.02.01.01.02 ENCOFRADO Y DESENCOFRADO DE VEREDAS M2 43.99 59.52 2,618.28
05.03 AREA VERDE
05.03.01.01 EXCAVACION DE TERRENO NATURAL C/MAQUINA M3 175.66 28.20 4,953.61
05.03.01.02 ELIMINACION MASIVA DE MATERIAL C/MAQUINA M3 210.78 32.81 6,915.69
05.03.01.03 TIERRA DE CHACRA (E=0.15 M) M2 1,171.00 22.48 26,324.08
05.03.01.04 SEMBRADO DE GRASS NATURAL M2 1,171.00 21.21 24,836.91

06 PARQUE: LA EXPLANADA MZ G 33,878.03


06.01 AREA CAMINERAS
06.01.01 ARQUITECTURA Y ACABADOS
06.01.01.01 PISOS Y PAVIMENTOS
06.01.01.01.02 PISOS ADOQUIN DE CONCRETO 8X10X20 CM.
06.01.01.01.02.01 CAMA DE ARENA H=0.07 m M2 74.50 2.80 208.60
PISO ADOQUINADO DE CONCRETO TIPO II GRIS 8X10X20
06.01.01.01.02.02
ALTO TRANSITO
M2 35.00 58.95 2,063.25
PISO ADOQUINADO DE CONCRETO TIPO II ROJO
06.01.01.01.02.03
8X10X20 ALTO TRANSITO
M2 39.50 58.95 2,328.53
06.01.01.01.02.04 SELLADO DE JUNTAS CON ARENA M2 74.50 4.00 298.00
06.02 AREA VERDE
06.02.01 EXCAVACION DE TERRENO NATURAL C/MAQUINA M3 133.55 28.20 3,766.11
06.02.02 ELIMINACION MASIVA DE MATERIAL C/MAQUINA M3 160.26 32.81 5,258.13
06.02.03 SEMBRADO DE GRASS NATURAL M2 456.75 22.48 10,267.74
06.02.04 TIERRA DE CHACRA (E=10CM) M2 456.75 21.21 9,687.67
07 PARQUE : EL ROSARIO 4,859.92
07.01 URNA PARA VIRGEN Y LOCAL DE REUNIONES
07.01.01 ESTRUCTURAS
07.01.01.01 MOVIMIENTO DE TIERRAS
07.01.01.01.01 DEMOLICION DE CONCRETO EXISTENTE M3 8.15 29.65 241.65
07.01.01.01.02 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA M3 10.60 32.64 345.98
07.01.02 ARQUITECTURA Y ACABADOS
07.01.02.01 PISOS Y PAVIMENTOS

08.04.02.04.01 PISO DE CONCRETO PULIDO PARA CIRCULACION PRINCIPAL M2 85.48 49.98 4,272.29

COSTO DIRECTO 388,840.11


GASTOS GENERALES 10.00% 38,884.01
UTILIDAD 7.00% 27,218.81
SUB TOTAL 454,942.93
SUB TOTAL CORREGIDO (VALOR. BRUTA) FR 1.00 454,942.93
IGV 18% 18.00% 81,889.73
TOTAL PRESUPUESTO ADICIONAL 536,832.66
TOTAL PRESUPUESTO DEDUCTIVO 407,062.26
ADICIONAL N°01 129,770.40
HOJA DE METRADOS
PROYECTO MEJORAMIENTO DE LOS SERVICIOS DE 14 AREAS RECREATIVAS EN EL DISTRITO DE CAYMA PROVINCIA AREQUIPA DEPARTAMENTO AREQUIPA.
FECHA Thursday, July 28, 2022
FORMULA MURO CARAVISTA - FACHADA
ESPECIALIDAD ARQUITECTURA

MEDIDAS
ITEM PARTIDA DESCRIPCION UBICACIÓN CANT. PARCIAL TOTAL UND.
LARGO ANCHO ALTO

01 PARQUE:JUANVELAZCOALVARADOMZW(RECTANGULO)

01.01 MURO DE CONTENCION PERIMETRICO


01.01.01 ESTRUCTURAS
01.01.01.01 OBRAS DE CONCRETO SIMPLE
01.01.01.01.01 ZAPATAS
SOLADO DE CONCRETO E=2" 1:12
01.01.01.01.01.01
CEM/HORM
94.79 M2
CM-03 TRAMO 1 1.00 7.71 2.65 20.43
TRAMO 2 1.00 13.30 2.65 35.25
TRAMO 3 1.00 14.76 2.65 39.11
01.01.01.02 OBRAS DE CONCRETO ARMADO
01.01.01.02.01 ZAPATAS
ZAPATAS, CONCRETO PREMEZCLADO
01.01.01.02.01.01
F'C=210 KG/CM2
66.19 M3
CM-03 TRAMO 1 1.00 7.71 2.65 0.55 11.24
TRAMO 2 1.00 13.30 2.65 0.55 19.38
TRAMO 3 1.00 14.76 2.65 0.55 21.51
CM-02 HACIA VEREDA 1.00 25.10 1.40 0.40 14.06

01.01.01.02.01.02 ZAPATAS, ACERO fy=4200 kg/cm2 4,011.91 KG


01.01.01.02.02 MURO DE CONTENCION
MUROS DE CONTENC, CONCRETO
01.01.01.02.02.01
PREMEZCLADO 210 kg/cm2
62.72 M3
CM-03 TRAMO 1 1.00 7.71 0.38 3.55 10.26
TRAMO 2 1.00 13.30 0.38 3.05 15.21
TRAMO 3 1.00 14.76 0.38 2.30 12.73
BARANDA 1.00 35.77 0.20 0.90 6.44
CAM 2 HACIA VEREDA 1.00 25.10 0.20 2.40 12.05
BARANDA 1.00 25.10 0.20 1.20 6.02

MUROS DE CONTENC, ENCOF. Y


01.01.01.02.02.02
DESENCOFRADO.
448.87 M2
CM-03 TRAMO 1 1.00 7.71 2.00 3.55 54.74
TRAMO 2 1.00 13.30 2.00 3.05 81.13
TRAMO 3 1.00 14.76 2.00 2.30 67.90
BARANDA 1.00 35.77 2.00 0.90 64.39
CAM 2 HACIA VEREDA 1.00 25.10 2.00 2.40 120.48
BARANDA 1.00 25.10 2.00 1.20 60.24
MUROS DE CONTENC, ACERO Fy=4200
01.01.01.02.02.03
kg/cm2
5,286.70 KG
x MOVIMIENTO DE TIERRAS
EXCAVACION DE TERRENO NATURAL
02.02
C/MAQUINA
TRAMO 1 142.19 M3
CM-03 TRAMO 1 1.00 7.71 2.65 1.50 30.65
TRAMO 2 1.00 13.30 2.65 1.50 52.87
TRAMO 3 1.00 14.76 2.65 1.50 58.67
RELLENO COMPACTADO C/EQUIPO
02.02.01
MAT/PROPIO
146.48 M3
CM-03 TRAMO 1 1.00 7.71 2.10 1.95 31.57
TRAMO 2 1.00 13.30 2.10 1.95 54.46
TRAMO 3 1.00 14.76 2.10 1.95 60.44
01.02.01.03.01 CIMIENTOS CORRIDO
01.02.01.03.01.01 CIMIENTOS CORRIDOS 1:10+30% P.G. 14.52 M3
CC-1 TRAMO 1 1.00 22.00 0.60 1.10 14.52
01.02.01.03.01 SOBRECIMIENTO
01.02.01.03.01.01 CONCRETO F'C=175 KG/CM2 7.99 M3
CC-1 TRAMO 1 1.00 22.00 0.20 1.82 7.99
ENCOFRADO Y DEDESENCOFRADO
01.02.01.03.01.02
SOBRECIMIENTO
79.86 M2

MURO REFORZADO TRAMO 1 1.00 22.00 2.00 1.82 79.86


01.02.01.03.01.03 SOBRECIMIENTO, ACERO Fy=4200 kg/cm2 473.92 KG
01.02.01.03.01.02 ARQUITECTURA
01.02.01.03.01.03 REVOQUES Y ENLUCIDOS
TARRAJEO EN MURO DE CONCRETO:
01.03
EXTERIORES
59.73 M3
BARANDA TRAMO 1 1.00 22.00 1.82 39.93
TRAMO 1 1.00 22.00 0.90 19.80
01.03.01 PINTURAS
01.03.01.01 PINTURA LATEX EN MUROS EXTERIORES 59.73 M3
BARANDA TRAMO 1 1.00 22.00 1.82 39.93
TRAMO 1 1.00 22.00 0.90 19.80
01.04 VEREDAS EXTERNAS
01.04.01 ESTRUCTURAS
01.04.01.01 TRABAJOS PRELIMINARES
01.04.01.01.01 DEMOLICION DE PISO DE VEREDA 10.77 M3
AREA CAD 1.00 107.67 0.10 10.77
ELIMINACION DE MATERIAL DE
01.04.01.01.03
DEMOLICION
14.00 M3
AREA CAD 1.00 107.67 1.30 0.10 14.00
01.04.01.02 OBRAS DE CONCRETO SIMPLE
01.04.01.02.01 VEREDAS
01.04.01.02.03 CONCRETO F'C=175 KG/CM2 10.77 M3
AREA CAD 1.00 107.67 0.10 10.77
ENCOFRADO Y DESENCOFRADO DE
01.04.01.02.03
VEREDAS
18.00 M2
LONG CAD 1.00 90.00 0.20 18.00

PARQUE: JUAN VELAZCO ALVARADO MZ V LOTE 1


02
(TRIANGULO)
02.01 MURO DE CONTENCION PERIMETRICO
02.01.01 ESTRUCTURAS
02.01.01.01 MOVIMIENTO DE TIERRAS
RELLENO COMPACTADO C/EQUIPO
02.01.01.01.01
MAT/PROPIO
165.00 M3
MC.2 1.00 110.00 1.50 165.00
02.01.01.02 OBRAS DE CONCRETO ARMADO
02.01.01.02.01 ZAPATAS
ZAPATAS, CONCRETO
02.01.01.02.01.01
PREMEZCLADO F'C=210 KG/CM2
6.22 M3
MC.2 1.00 31.10 0.50 0.40 6.22
02.03.01.03.01.02 ZAPATAS, ACERO fy=4200 kg/cm2 228.87 KG
02.02 CALZADURA
02.02.01.01 MOVIMIENTO DE TIERRAS
EXCAVACION DE TERRENO NATURAL
02.02.01.01.01
C/MAQUINA
7.28 M3
MC.2 1.00 13.00 0.80 0.70 7.28
02.02.01 ESTRUCTURAS
CONCRETO CICLOPEO F´C 100 KG/CM2 + 30
02.02.01.02.01
%P.M. 3"
7.28 M3
MC.2 1.00 13.00 0.80 0.70 7.28
02.02.01.02.02 CALZADURA, ENCOF. Y DESENCOFRADO. 9.10 M2
MC.2 1.00 13.00 0.70 9.10
02.02.01.01.01 ARQUITECTURA
02.02.01.02 REVOQUES Y ENLUCIDOS
02.02.01.02.01 TARRAJEO EN MURO: -EXTERIORES 38.40 M2
1.00 32.00 1.20 38.40
02.02.01.02.02 PINTURA
PINTURA LATEX EN MUROS
02.02.02
EXTERIORES
38.40 M2
1.00 32.00 1.20 38.40
03 PARQUE: VILLA CONTINENTAL MZ M LOTE 1 168.00
03.01 CISTERNA POZO AGUA DE RIEGO
03.01.01 ESTRUCTURAS
03.01.01.01 MOVIMIENTO DE TIERRAS
EXCAVACION DE TERRENO NATURAL
03.01.01.01.01
C/MAQUINA
20.16 M3
1.00 84.00 0.40 0.60 20.16
RELLENO COMPACTADO C/EQUIPO
03.01.01.01.02
MAT/PROPIO
20.16 M3
1.00 84.00 0.40 0.60 20.16
03.01.02 INSTALACIONES SANITARIAS
03.01.02.01 TUBERIA PVC SAP 2" 84.00 ML
1.00 84.00 84.00
03.01.02.02 CODO 90° PVC 2" 12.00 UND
12.00 12.00
03.01.02.03 VALVULA DE BOLA 2" 5.00 UND
5.00 5.00
03.01.02.04 TEE PVC SAP 2" 7.00 UND
7.00 7.00
03.02 GRADERIAS NUEVAS
03.02.01 ESTRUCTURAS
03.02.01.01 TRABAJOS PRELIMINARES
TRAZO, NIVELES Y REPLANTEO
03.02.01.01.02
PRELIMINAR
4.00 M2
AREA CAD 1.00 4.00 4.00
03.02.01.02 MOVIMIENTO DE TIERRAS
EXCAVACION DE TERRENO NATURAL
03.02.01.02.01
C/MAQUINA
3.60 M3
AREA CAD 1.00 4.00 0.90 3.60
03.02.01.02.02 PERFILADO Y NIVELACION 4.00 M2
AREA CAD 1.00 4.00 4.00
ELIMINACION MATERIAL EXCEDENTE
03.02.01.02.03
C/MAQUINA
4.32 M3
AREA CAD 1.00 4.00 1.20 0.90 4.32
03.02.01.03 GRADERIAS
GRADERIAS CONCRETO f´c = 175
03.02.01.03.01
kg/cm2
7.47 M3
TRAMO 1 1.00 1.45 2.00 2.90
TRAMO 2 1.00 1.46 2.00 2.92
TRAMO 3 1.00 1.10 1.50 1.65
ENCOFRADO Y DESENCOFRADO
03.02.01.03.02
NORMAL
14.72 M2
TRAMO 1 CONTRAPASO 5.00 0.20 2.00 2.00
TAPAS 2.00 1.45 2.90
TRAMO 2 CONTRAPASO 8.00 0.20 2.00 3.20
TAPAS 2.00 1.46 2.92
TRAMO 3 CONTRAPASO 5.00 0.20 1.50 1.50
TAPAS 2.00 1.10 2.20
03.02.02 ARQUITECTURA
03.02.02.01 CARPINTERIA METALICA
03.02.02.01.01 BARANDA METALICA - SEGUN DISEÑO 8.80 ML
TRAMO 1 1.00 1.80 1.80
1.00 1.80 1.80
-
TRAMO 3 1.00 2.60 2.60
1.00 2.60 2.60
04 PARQUE: LAS TERRAZAS (TRAPECIO)
04.01 AREA DE CAMINERIAS
04.01.01 ESTRUCTURAS
04.01.01.01 TRABAJOS PRELIMINARES
#REF! LIMPIEZA DEL TERRENO MANUAL 181.50 M2
AREA CAD 1 181.5 181.50
04.01.01.01.01 TRAZO, NIVELES Y REPLANTEO PRELIMINAR 181.50 M2
AREA CAD 1 181.5 181.50
Perim. 8.76 M3
04.01.01.01.03 DEMOLICION DE MURO DE CONTENCION
CAD
Vereda interior 1 73 0.2 0.6 8.76
04.01.01.02 MOVIMIENTO DE TIERRAS

36.30 M3
EXCAVACION DE TERRENO NATURAL
04.01.01.02.01
C/MAQUINA
Vereda interior 1 Area 181.5 0.2 36.30
04.01.01.02.02 PERFILADO Y NIVELACION CAD 181.50 M2
Vereda interior 1 Area 181.5 181.50
CAD
43.56 M3
ELIMINACION MATERIAL EXCEDENTE
04.01.01.02.03
C/MAQUINA
VOLE RET. 1 36.30 1.2 43.56
04.02 ARQUITECTURA
04.02.01 PISOS Y PAVIMENTOS
04.02.01.01 CIRCULACION DE PARQUE

181.50 M2
PISO DE CONCRETO PULIDO PARA
04.02.01.01.01
CIRCULACION PRINCIPAL
Vereda interior 1 Area 181.5 181.50
CAD
34.77 M2
ENCOFRADO Y DESENCOFRADO DE
04.02.01.01.02
VEREDAS
CORTE 1-1 95.55 0.25 23.89
CORTE 2-2 43.54 0.25 10.89
04.03 AREA VERDE

168.29 M3
EXCAVACION DE TERRENO NATURAL
04.03.01
C/MAQUINA
Vereda interior 1 Area 1121.95 0.15 168.29
CAD
04.03.01.01
ELIMINACION MATERIAL EXCEDENTE 201.95 M3
C/MAQUINA
VOLE RET. 1 168.29 1.2 201.95
04.03.01.02 TIERRA DE CHACRA (E=0.10 M) 1,121.95 M2
Vereda interior 1 Area 1121.95 1,121.95
04.03.01.03 SEMBRADO DE GRASS NATURAL CAD 1,121.95 M2
Vereda interior 1 Area 1121.95 1,121.95
CAD
05 PARQUE: LAS TERRAZAS (RECTANGULAR)
05.01 AREA DE CAMINERIAS
05.01.01 ESTRUCTURAS
05.01.01.01 TRABAJOS PRELIMINARES
05.01.01.01.01 LIMPIEZA DEL TERRENO MANUAL 273.86 M2
AREA CAD 1 273.86 273.86
05.01.01.01.02 TRAZO, NIVELES Y REPLANTEO PRELIMINAR 273.86 M2
AREA CAD 1 273.86 273.86
05.01.01.02 MOVIMIENTO DE TIERRAS

54.77 M3
EXCAVACION DE TERRENO NATURAL
05.01.01.02.01
C/MAQUINA
1 273.86 0.2 54.77
05.01.01.02.02 PERFILADO Y NIVELACION 273.86 M2
1 273.86 273.86
05.01.01.02.03
ELIMINACION MATERIAL EXCEDENTE 65.73 M3
C/MAQUINA
VOL. RET. 1 54.77 1.2 65.73
05.02 ARQUITECTURA
05.02.01 PISOS Y PAVIMENTOS
05.02.01.01 CIRCULACION DE PARQUE

05.02.01.01.01
PISO DE CONCRETO PULIDO PARA 273.86 M2
CIRCULACION PRINCIPAL
Corte 3-3 1 44.53 1.3 57.89
Corte 2-2 1 32.39 1.3 42.11
1 20.23 1.3 26.30
1 23.29 1.3 30.28
Corte 1-1 1 36.651 3.2 117.28
05.02.01.01.02 ENCOFRADO Y DESENCOFRADO DE VEREDAS 43.99 M2

Corte 3-3 1 44.53 0.4 17.81


Corte 2-2 1 32.39 0.2 6.48
1 20.23 0.2 4.05
1 23.29 0.2 4.66
05.03 AREA VERDE Corte 1-1 1 36.651 0.3 11.00
05.03.01.01
EXCAVACION DE TERRENO NATURAL 175.65 M3
C/MAQUINA
Vereda interior 1 Area 1171 0.15 175.65
CAD
ELIMINACION MATERIAL EXCEDENTE 210.78 M3
05.03.01.02
C/MAQUINA
VOL. RET. 1 175.65 1.2 210.78
05.03.01.03 TIERRA DE CHACRA (E=0.10 M) 1,171.00 M2
Vereda interior 1 Area 1171 1,171.00
CAD
05.03.01.04 SEMBRADO DE GRASS NATURAL 1,171.00 M2
Vereda interior 1 Area 1171 1,171.00
CAD

06 PARQUE: LA EXPLANADA MZ G
06.01 AREA DE CAMINERIAS
06.01.01 ARQUITECTURA
06.01.01.01 PISOS Y PAVIMENTOS
PISO DE ADOQUIN DE CONCRETO 8 x
06.01.01.01.02
10 x 20 cm.
06.01.01.01.02.01 CAMA DE ARENA H=0.07m ADOQUIN GRIS 1 35.00 35.00 74.50 M2
ADOQUIN ROJO 1.00 39.50 39.50

PISO ADOQUINADO DE CONCRETO TIPO II GRIS 35.00 M2


06.01.01.01.02.02
8X10X20 ALTO TRANSITO

ADOQUIN GRIS 1.00 1.65 1.65


1.00 2.15 2.15
1.00 11.97 11.97
1.00 3.63 3.63
1.00 11.97 11.97
1.00 3.63 3.63
PISO ADOQUINADO DE 39.50 M2
06.01.01.01.02.03 CONCRETO TIPO II ROJO 8X10X20
ALTO TRANSITO
ADOQUIN ROJO 1.00 4.50 4.50
1.00 1.64 1.64
1.00 2.45 2.45
2.00 2.01 4.02
2.00 2.28 4.56
2.00 4.75 9.50
4.00 1.85 7.40
1.00 3.41 3.41
1.00 2.02 2.02

06.01.01.01.02.04 SELLADO DE JUNTAS CON ARENA 74.50 M2

ADOQUIN ROJO 1.00 AREA CAD 39.50 39.50


ADOQUIN NEGRO 1.00 AREA CAD 35.00 35.00
06.02 AREA VERDE

133.55 M3
EXCAVACION DE TERRENO NATURAL
-
C/MAQUINA
Vereda interior 1 Area 445.16 0.3 133.55
CAD
-
ELIMINACION MATERIAL EXCEDENTE 160.26 M3
C/MAQUINA
VOLE RET. 1 133.55 1.2 160.26
06.02.03 TIERRA DE CHACRA (E=0.10 M) area 285.33 M2
AREA CAD 1.00 100.17 100.17
1.00 93.37 93.37
2.00 21.56 43.12
2.00 7.74 15.48
1.00 10.89 10.89
2.00 11.15 22.30

06.02.04 SEMBRADO DE GRASS NATURAL 285.33 M2


AREA CAD 1.00 285.33 285.33
07 PARQUE : EL ROSARIO
07.01 LOCAL DE REUNIONES
07.01.01 ESTRUCTURAS
07.01.01.01 MOVIMIENTO DE TIERRAS

07.01.01.01.01
DEMOLICION DE CONCRETO 8.15 M3
EXISTENTE
PISO 1 11.56 6.95 0.1 8.03
ENTRADAS 1 1.97 0.6 0.1 0.12
ELIMINACION MATERIAL EXCEDENTE F. 10.60 M3
07.01.01.01.02
C/MAQUINA ESPONJ.
VOL EXCAV 1 8.15 1.3 10.60
07.01.02 ARQUITECTURA Y ACABADOS
07.01.02.01 PISOS Y PAVIMENTOS

07.01.02.01.01
PISO DE CONCRETO PULIDO PARA 85.48 M2
CIRCULACION PRINCIPAL
PISO 1 11.68 7.01 81.88
ENTRADAS 1 2 1.8 3.60
PLANILLA DE METRADOS DE ACERO: ZAPATAS - JVA RECTANGULO
ITEM NOMBRE DE PARTIDA UNIDAD TOTAL PESO (KG)
01.02.05 ACERO DE REFUERZO fy = 4200 kg/cm2 - COLUMNETAS KG

N° de DIAMETRO DE CADA FIERRO( METROS)


Longitud * Total (varillas de
Descripcion Ø Diseño de acero Traslp. elementos Cant.
c/fierro 9.00m c/u)
iguales 6mm. 8MM. Ø 3/8" 12mm. Ø 1/2" Ø 5/8" Ø 3/4" Ø 1"
6mm. 0.00
MC1
ZAPATA
TRAMO 1 LONG 1 Ø 1/2" 0.30 56.79 0.30 6.08 26.90 7.00 1.00 188.30
TRANSVERSA Ø 1/2" 0.3 1.00 0.30 1.50 286.00 1.00 429.00
MC2 - VEREDA
ZAPATA
TRAMO 1 LONG 1 Ø 1/2" 0.30 25.10 0.30 2.69 26.90 7.00 1.00 188.30
TRANSVERSA Ø 1/2" 0.3 2.00 0.30 1.50 128.00 1.00 192.00
MC2 - ESCALERAS
ZAPATA
TRAMO 1 LONG 1 Ø 1/2" 0.30 27.88 0.30 2.98 26.90 7.00 1.00 188.30
TRANSVERSA Ø 1/2" 0.3 2.00 0.30 1.50 142.00 1.00 213.00
MC3
ZAPATA
TRAMO 1 LONG 1 Ø 5/8" 0.3 35.77 0.3 3.83 38.80 7.00 1.00 271.60
LONG 2 Ø 5/8" 0.30 35.77 0.30 3.83 38.80 14.00 1.00 543.20
TRANS 1 Ø 5/8" 0.3 2.65 0.30 3.25 179.00 1.00 581.75
TRANS 2 Ø 5/8" 0.30 2.65 0.30 3.25 90.00 1.00 292.50

Longitud Total por Ø en metros lineales 0.00 0.00 0.00 0.00 1398.90 1689.05 0.00 0.00 (*)El dato
Peso en Kilogramos por metro lineal 0.22 0.40 0.56 0.888 0.994 1.55 2.24 3.97 presentado es
Peso Total por Ø en Kilogramos 0.00 0.00 0.00 0.00 1390.51 2621.41 0.00 0.00 referencial
4011.91
0 0 166.92 201.16 0 0
PLANILLA DE METRADOS DE ACERO: MURO DE CONTENCION - JVA RECTANGULO
ITEM NOMBRE DE PARTIDA UNIDAD TOTAL PESO (KG)
01.02.05 ACERO DE REFUERZO fy = 4200 kg/cm2 - COLUMNETAS KG

N° de DIAMETRO DE CADA FIERRO( METROS)


Longitud * Total (varillas de
Descripcion Ø Diseño de acero Traslp. elementos Cant.
c/fierro 9.00m c/u)
iguales 6mm. 8MM. Ø 3/8" 12mm. Ø 1/2" Ø 5/8" Ø 3/4" Ø 1"
6mm. 0.00
MC1 0 0.00
PANTALLA - VEREDA 0 3619.64
TRAMO 1 LONG 1 Ø 1/2" 0.30 56.79 0.30 8.10 65.50 14.00 1.00 916.94 0 0.00
TRANSVERSA Ø 3/8" 0.3 3.00 3.30 381.00 1.00 1257.30 0 3279.37
MC2 8MM. 0.00
PANTALLA - VEREDA Ø 3/8" 403.00
TRAMO 1 LONG 1 Ø 1/2" 0.30 25.10 0.30 3.58 29.28 18.00 1.00 527.06 12mm. 0.00
TRANSVERSA Ø 3/8" 0.3 3.90 4.20 170.00 1.00 714.00 Ø 1/2" 365.00
MC2 Ø 5/8" 0.00
PANTALLA - ESCALERA Ø 3/4" 0.00
TRAMO 1 LONG 1 Ø 1/2" 0.10 27.88 27.98 4.00 1.00 111.92 Ø 1" 0.00
TRANSVERSA Ø 3/8" 0.1 0.30 0.30 0.70 188.00 1.00 131.60
MC-3
PANTALLA
TRAMO 1 TRANS 1 Ø 3/8" 0.20 3.95 0.30 4.45 29.00 1.00 129.05
TRANS 2 Ø 1/2" 0.20 3.95 0.30 4.45 43.00 1.00 191.35
BALAN 1 Ø 1/2" 0.30 1.88 2.18 71.00 1.00 154.78
LONG 1 Ø 3/8" 0.30 8.48 0.30 9.08 24.00 1.00 217.94
LONG 2 Ø 1/2" 0.30 8.48 0.30 9.08 11.00 1.00 99.89
TRAMO 2 TRANS 1 Ø 3/8" 0.20 3.45 0.30 3.95 49.00 1.00 193.55
TRANS 2 Ø 1/2" 0.20 3.45 0.30 3.95 74.00 1.00 292.30
BALAN 1 Ø 1/2" 0.30 1.88 2.18 122.00 1.00 265.96
LONG 1 Ø 3/8" 0.30 14.63 0.30 1.00 16.23 21.00 1.00 340.83
LONG 2 Ø 1/2" 0.30 14.63 0.30 0.80 16.03 10.00 1.00 160.30
TRAMO 3 TRANS 1 Ø 3/8" 0.20 2.70 0.30 3.20 55.00 1.00 176.00
TRANS 2 Ø 1/2" 0.20 2.70 0.30 3.20 82.00 1.00 262.40
BALAN 1 Ø 1/2" 0.30 1.88 2.18 136.00 1.00 296.48
LONG 1 Ø 3/8" 0.30 16.24 0.30 1.00 17.84 16.00 1.00 285.38
LONG 2 Ø 1/2" 0.30 16.24 0.30 0.80 17.64 0.00 1.00 0.00
BARANDA TRANS 1 Ø 3/8" 1.40 1.40 1.00 1.00 1.40
LONG 1 Ø 3/8" 0.30 39.35 0.30 3.20 43.15 4.00 1.00 172.59

Longitud Total por Ø en metros lineales 0.00 0.00 3619.64 0.00 3279.37 0.00 0.00 0.00 (*)El dato
Peso en Kilogramos por metro lineal 0.22 0.40 0.56 0.888 0.994 1.55 2.24 3.97 presentado es
Peso Total por Ø en Kilogramos 0.00 0.00 2027.00 0.00 3259.70 0.00 0.00 0.00 referencial
5286.70
0 0 403 0 365 0 0 0
PLANILLA DE METRADOS DE ACERO: SOBRECIMIENTO ARMADO - JVA RECTANGULO
ITEM NOMBRE DE PARTIDA UNIDAD TOTAL PESO (KG)
01.02.05 ACERO DE REFUERZO fy = 4200 kg/cm2 - COLUMNETAS KG

N° de DIAMETRO DE CADA FIERRO( METROS)


Longitud * Total (varillas de
Descripcion Ø Diseño de acero Traslp. elementos Cant.
c/fierro 9.00m c/u)
iguales 6mm. 8MM. Ø 3/8" 12mm. Ø 1/2" Ø 5/8" Ø 3/4" Ø 1"
6mm. 0.00
CC-1 8MM. 0.00
BARANDA Ø 3/8" 95.00
TRAMO 1 LONG 1 Ø 3/8" 0.30 38.00 0.30 5.42 44.02 10.00 1.00 440.21 12mm. 0.00
TRANSVERSA Ø 3/8" 0.3 1.82 2.12 192.00 1.00 406.08 Ø 1/2" 0.00

Longitud Total por Ø en metros lineales 0.00 0.00 846.29 0.00 0.00 0.00 0.00 0.00 (*)El dato
Peso en Kilogramos por metro lineal 0.22 0.40 0.56 0.888 0.994 1.55 2.24 3.97 presentado es
Peso Total por Ø en Kilogramos 0.00 0.00 473.92 0.00 0.00 0.00 0.00 0.00 referencial
473.92
0 0 95 0 0 0 0 0

ALAMBRE 16 33.17

También podría gustarte