PRESUPUESTO DE CONSTRUCCION

PROYECTO MODULO DE NICHOS PARA CEMENTERIO "EL ANGEL"


PROPIETARIO :

PARTIDAD DESCRIPCION UND METRADO COSTO UNIT. PARCIAL(S/.) TOTAL(S/.)

01.00.00 TRABAJOS PRELIMINARES


01.01.00 LIMPIEZA DE TERRENO
01.01.01 ELIMINACION DE MALEZA Y ARBUSTO M2 280.75 15.56 4,368.47
01.01.02 TRAZO, NIVEL Y REPLANTEO M2 199.23 1.47 292.87 4,661.34

02.00.00 MOVIMIENTO DE TIERRAS


02.01.00 NIVELACION DE TERRENO M2 280.75 0.43 120.72
02.02.00 NIVELACION Y APISONADO M2 226.63 3.51 795.47
02.03.00 EXCAVACIONDE ZANJAS PARA CIMIENTOS M3 118.92 29.79 3,542.63
02.04.00 RELLENO CON MATERIAL PROPIO DE TERRENO M3 39.64 13.85 549.01
02.05.00 ELIMINACION DE MATERIAL EXCEDENTE M3 79.28 14.90 1,181.27
02.06.00 RELLENO CON MATERIAL DE PRESTAMO (ARENILLA) M3 19.31 13.85 267.44 6,456.55

03.00.00 OBRAS DE CONCRETO SIMPLE


03.01.00 ZAPATAS DE CONCRETO CICLOPEO F'C = 175 Kg/cm2. M3 79.28 127.28 10,090.76
03.02.00 ENCOF. Y DESENCOF. CIMIENTOS CONCRETO F`C=175kg/cm2 M3 26.87 20.27 544.65 10,635.41

04.00.00 OBRAS DE CONCRETO ARMADO


04.01.00 VIGA TRANVERSAL DE CIMENTACION
04.01.01 CONCRETO PARA VIGAS F'C = 175 Kg/cm2. M3 10.32 228.60 2,359.15
04.01.02 ENCOFRADO Y DESENCOFRADO DE VIGAS M2 46.73 33.71 1,575.27
04.01.03 ACERO F'y = 4200 Kg/cm2, Ø = 1/2" KG 194.39 2.16 419.88
04.01.04 ACERO F'y = 4200 Kg/cm2, Ø = 1/4" KG 114.41 0.62 70.93 4,425.24
04.02.00 VIGA LONGITUDINAL DE CIMENTACION
04.02.01 CONCRETO PARA VIGAS F'C = 175 Kg/cm2. M3 20.31 228.60 4,642.87
04.02.02 ENCOFRADO Y DESENCOFRADO DE VIGAS M2 82.43 33.71 2,778.72
04.02.03 ACERO F'y = 4200 Kg/cm2, Ø = 1/2" KG 422.73 2.16 913.10
04.02.04 ACERO F'y = 4200 Kg/cm2, Ø = 1/4" KG 167.20 0.62 103.66 8,438.34

PRESUPUESTO DE CONSTRUCCION
PROYECTO MODULO DE NICHOS PARA CEMENTERIO "EL ANGEL"
PROPIETARIO :
04.03.00 COLUMNAS
04.03.01 CONCRETO PARA COLUMNAS F'C = 175 Kg/cm2. M3 3.46 333.37 1,153.46
04.03.02 ENCOFRADO Y DESENCOFRADO DE VIGAS M2 79.49 49.34 3,922.04
04.03.03 ACERO F'y = 4200 Kg/cm2, Ø = 1/2" KG 404.39 2.16 873.48
04.03.04 ACERO F'y = 4200 Kg/cm2, Ø = 1/4" KG 75.60 0.62 46.87 5,995.85
04.04.00 LOSAS DE CONCRETO
04.04.01 CONCRETO PARA VIGAS F'C = 175 Kg/cm2. M3 78.16 249.06 19,466.53
04.04.02 ENCOFRADO Y DESENCOFRADO DE VIGAS M2 1,254.14 0.62 777.57
04.04.03 ACERO F'y = 4200 Kg/cm2, Ø = 1/2" KG 813.45 33.90 27,575.96 47,820.05

05.00.00 MUROS DE ALBAÑILERIA


05.01.00 MUROS DE LADRILLO KK DE 23X13X7cm MEZCLA 1:5
05.01.01 MURO DE LADRILLO DE CABEZA, CON JUNTA 1.5 cm, MORTERO C:H M2 213.84 50.79 10,860.93
05.01.02 MURO DE LADRILLO DE CABEZA, CON JUNTA 1.5 cm, MORTERO C:H M2 338.40 30.99 10,487.02
05.01.03 MURO DE LADRILLO PANDERETA, CON JUNTA 1.5 cm, MORTERO C:H M2 153.12 49.64 7,600.88 28,948.83

06.00.00 REVOQUES Y ENLUCIDOS


06.01.00 TARRAJEO FINO EN EXTERIORES M2 58.81 20.57 1,209.72
06.01.00 TARRAJEO EXTERIOR DE COLUMNAS M2 75.94 22.45 1,704.85 2,914.57

SUBTOTAL 120,296.18
C.U + UTILIDAD (10%) 12029.62
TOTAL (S/.) 132,325.80
I.G.V. 19% 25141.90
TOTAL GENERAL (S/.) 157,467.71