Documentos de Académico
Documentos de Profesional
Documentos de Cultura
SALDO V1 V2 V3
12.00
60.00
800.00
8.00
30.00 10.00
300.00 200.00
9.00
100.00 20.00
500.00 200.00
900.00 120.00
30.00
48.00
ANTERIOR
DESCRIPCIÓN UND. CANT. P.UNIT PARCIAL %
CONCRETO ARMADO
COLUMNA
CONCRETO F'C=175 KG/CM2. M3. 12.00 333.94 4,007.28
ENCOF.-DESENCOF. M2. 60.00 42.00 2,520.00
ACERO KG. 800.00 4.94 3,952.00
VIGA
CONCRETO F'C=175 KG/CM2. M3. 8.00 305.15 2,441.20
ENCOF.-DESENCOF. M2. 40.00 46.53 1,861.20
ACERO KG. 500.00 4.94 2,470.00
LOSA ALIGERADA
CONCRETO F'C=175 KG/CM2. M3. 9.00 279.22 2,512.98
ENCOF.-DESENCOF. M2. 120.00 33.07 3,968.40
ACERO KG. 700.00 4.94 3,458.00
LADRILLOS 0.15X0.30X0.30 UND. 1020.00 2.67 2,723.40
MURO
LAD. KK. 18 HCO. SOGA M2. 30.00 48.84 1,465.20
LAD. KK. 18 HCO. CABEZA M2. 48.00 76.09 3,652.32
COSTO DIRECTO 35,031.98
GG (15%) 5,254.80
U ( 10%) 3,503.20
SUBTOTAL 43,789.98
% AVANCE 100.00
23,442.46
3,516.37
2,344.25
29,303.08
66.92%