DATOS:

Pb= S/.43,789.98
Fpb= 7/1/2019

INICIO: OCTUBRE
DURACIÓN: 3 MESES
PRESUPUESTO CONTRACTUAL

OBRA: AMPLIACIÓN DE MUNICIPALIDAD PROVINCIAL


CONTRATISTA:
PROPIETARIO: MUNICIPALIDAD PROVINCIAL XXXXXXX

PRESUPUESTO CONTRACTUAL
ITEM DESCRIPCIÓN
UND. CANT. P.UNIT PARCIAL
1.00 CONCRETO ARMADO
1.01 COLUMNA
1.01.01 CONCRETO F'C=175 KG/CM2. M3. 12.00 333.94 4,007.28
1.01.02 ENCOF.-DESENCOF. M2. 60.00 42.00 2,520.00
1.01.03 ACERO KG. 800.00 4.94 3,952.00
1.02 VIGA
1.02.01 CONCRETO F'C=175 KG/CM2. M3. 8.00 305.15 2,441.20
1.02.02 ENCOF.-DESENCOF. M2. 40.00 46.53 1,861.20
1.02.03 ACERO KG. 500.00 4.94 2,470.00
1.03 LOSA ALIGERADA
1.03.01 CONCRETO F'C=175 KG/CM2. M3. 9.00 279.22 2,512.98
1.03.02 ENCOF.-DESENCOF. M2. 120.00 33.07 3,968.40
1.03.03 ACERO KG. 700.00 4.94 3,458.00
1.03.04 LADRILLOS 0.15X0.30X0.30 UND. 1020.00 2.67 2,723.40
2.00 MURO
2.01 LAD. KK. 18 HCO. SOGA M2. 30.00 48.84 1,465.20
2.02 LAD. KK. 18 HCO. CABEZA M2. 48.00 76.09 3,652.32
COSTO DIRECTO 35,031.98
GG (15%) 5,254.80
U ( 10%) 3,503.20
SUBTOTAL 43,789.98
IGV (18%) 7,882.20
PRESUPUESTO TOTAL 51,672.18
% AVANCE 100.00
CONCILIACION DE METRADOS
ITEM DESCRIPCIÓN
UND. CANT.
1.00 CONCRETO ARMADO
1.01 COLUMNA
1.01.01 CONCRETO F'C=175 KG/CM2. M3. 0.00
1.01.02 ENCOF.-DESENCOF. M2. 24.00
1.01.03 ACERO KG. 560.00
1.02 VIGA
1.02.01 CONCRETO F'C=175 KG/CM2. M3.
1.02.02 ENCOF.-DESENCOF. M2.
1.02.03 ACERO KG.
1.03 LOSA ALIGERADA
1.03.01 CONCRETO F'C=175 KG/CM2. M3.
1.03.02 ENCOF.-DESENCOF. M2.
1.03.03 ACERO KG.
1.03.04 LADRILLOS 0.15X0.30X0.30 UND.
2.00 MURO
2.01 LAD. KK. 18 HCO. SOGA M2. 4.50
2.02 LAD. KK. 18 HCO. CABEZA M2. 28.80
VALORIZACIÓN DE OBRA PRINCIPAL
01 AL 31 OCTUBRE 2019

OBRA: AMPLIACIÓN DE MUNICIPALIDAD PROVINCIAL


CONTRATISTA:
PROPIETARIO: MUNICIPALIDAD PROVINCIAL XXXXX

PRESUPUESTO CONTRACTUAL VAL ANTERIOR VAL ACTUAL VAL ACUMULADO SALDO


ITEM DESCRIPCIÓN
UND. CANT. P.UNIT PARCIAL MET PARCIAL MET PARCIAL MET PARCIAL MET PARCIAL
1.00 CONCRETO ARMADO
1.01 COLUMNA
1.01.01 CONCRETO F'C=175 KG/CM2. M3. 12.00 333.94 4,007.28 - - - - - - 12.00 4,007.28
1.01.02 ENCOF.-DESENCOF. M2. 60.00 42.00 2,520.00 - - 24.00 1,008.00 24.00 1,008.00 36.00 1,512.00
1.01.03 ACERO KG. 800.00 4.94 3,952.00 - - 560.00 2,766.40 560.00 2,766.40 240.00 1,185.60
1.02 VIGA - - - - - - - -
1.02.01 CONCRETO F'C=175 KG/CM2. M3. 8.00 305.15 2,441.20 - - - - - - 8.00 2,441.20
1.02.02 ENCOF.-DESENCOF. M2. 40.00 46.53 1,861.20 - - - - - - 40.00 1,861.20
1.02.03 ACERO KG. 500.00 4.94 2,470.00 - - - - - - 500.00 2,470.00
1.03 LOSA ALIGERADA - - - - - - - -
1.03.01 CONCRETO F'C=175 KG/CM2. M3. 9.00 279.22 2,512.98 - - - - - - 9.00 2,512.98
1.03.02 ENCOF.-DESENCOF. M2. 120.00 33.07 3,968.40 - - - - - - 120.00 3,968.40
1.03.03 ACERO KG. 700.00 4.94 3,458.00 - - - - - - 700.00 3,458.00
1.03.04 LADRILLOS 0.15X0.30X0.30 UND. 1020.00 2.67 2,723.40 - - - - - - 1,020.00 2,723.40
2.00 MURO - - - - - - - -
2.01 LAD. KK. 18 HCO. SOGA M2. 30.00 48.84 1,465.20 - - 4.50 219.78 4.50 219.78 25.50 1,245.42
2.02 LAD. KK. 18 HCO. CABEZA M2. 48.00 76.09 3,652.32 - - 28.80 2,191.39 28.80 2,191.39 19.20 1,460.93
COSTO DIRECTO 35,031.98 6,185.57 6,185.57 28,846.41
GG (15%) 5,254.80 927.84 927.84 4,326.96
U ( 10%) 3,503.20 618.56 618.56 2,884.64
SUBTOTAL 43,789.98 7,731.97 7,731.97 36,058.01
IGV (18%) 7,882.20 1,391.75 1,391.75 6,490.44
PRESUPUESTO TOTAL 51,672.18 9,123.72 9,123.72 42,548.45
% AVANCE 100.00 18% 18% 82%
ACUMULADO= ANTERIOR + ACTUAL
SALDO= PRESUPUESTO - ACUMULADO
FÓRMULA POLINÓMICA

OBRA: AMPLIACIÓN DE MUNICIPALIDAD PROVINCIAL P.B= 43,789.98


CONTRATISTA: FECHA= Jul-19
ESPECIALIDAD: AREA GEOGRAFICA: 02

FÓRMULA POLINÓMICA K = 0.133*(CPMr/CPMo) + 0.109*(LAr/LAo) + 0.103*(DHr/DHo) + 0.170*(Fr/Fo) + 0.285*(Jr/Jo) + 0.200*(GGUr/GGUo)

JUL SET.
MONOMIO DESCRIPCION SIMBOLO I.U C.I % Io Ir K
CEMENTO P.T 1 21 72.93 423.68 423.68
1 PIEDRA CHANCADA CPM 5 0.133 17.29 215.53 215.03 0.133
MAQUINARIA NACIONAL 48 9.78 369.59 373.24
LADRILLO ARCILLA 17 11.93 677.49 679.94 0.109
2 LA 0.109
ARENA GRUESA 4 88.07 954.04 957.87
MADERA NACIONAL P/ENCOFRADO 43 0.103 89.32 702.38 704.1 0.103
3 DH
HERRA. 37 10.68 314.62 312.4
4 ACERO CORRUGADO F 3 0.170 100.00 527.67 538.41 0.173
5 MANO DE OBRA INC. BS J 47 0.285 100.00 600.4 619.76 0.294
6 G.G.U G.G.U 39 0.200 100.00 458.29 458.59 0.2
1.012

Nota: Los Subindices "o" representan los Indices de Precios a la fecha del Presupuesto Base y los
Subinddices "r" son los indices a la fecha del reajuste
REINTEGROS

V = 7,731.97
k= 1.012
R = V x (K-1)

N° FECHA V K-1 R
1 OCT. 7,731.97 0.012 92.78
A PAGAR

N° FECHA Vb R Vn IGV TOTAL


1 OCT. 7,731.97 92.78 7,824.75 1,408.46 9,233.21

Vb = V + R
IGV = 0.18 x Vb
TOTAL = Vn + IGV
CUADRO RESUMEN DE VALORIZACIÓN N° 01
(DEL 1 AL 31 OCTUBRE 2019)
OBRA:
SUPERVISOR:
CONTRATISTA:
PRESUPUESTO BASE: S/.
PRESUPUESTO CONTRATADO: S/.
MONTO VALORIZACIÓN % DE SALDO POR
DESCRIPCIÓN CONTRATADO ANTERIOR ACTUAL ACUMULADO AVANCE VALORIZAR
SIN IGV (S/.) (S/.) (S/.) (S/.) ACUMULADO (S/.)

VALORIZACIÓN (V) 43,789.98 0.00 7,731.97 7,731.97 18% 36,058.01

TOTAL CONTRACTUAL
Avances en porcentaje
REAJUSTES (R) 0.00 92.78 92.78
DEDUCCIONES (D)

POR ADELANTO EN EFECTIVO


POR ADELANTO PARA MATERIALES

TOTAL DEDUCCIONES

VALORIZACIÓN BRUTA (VB = V + R - D) 7,824.75

AMORTIZACIONES (A)

AMORT. ADELANTO EN EFECTIVO


AMORT. ADELANTO PARA MATERIALES

TOTAL AMORTIZACIONES (A)

7,824.75
VALORIZACIÓN NETA (VN = VB - A)

RETENCIONES ( C )
FONDOS DE GARANTIA (5% X VB)
GASTOS DE LICITACION
MULTA POR ATRASO DE OBRA
TOTAL

MONTO A PAGAR AL CONTRATISTA


EN EFECTIVO (VN-C) 7,824.75
MONTO POR I.G.V. (VN x 0,18) 1,408.46

MONTO TOTAL CON I.G.V. 9,233.21

TOTAL COMPROMISO DE PAGO S/. 9,233.21