PROYECTO: MEJORAMIENTO DE CAMINO VECINAL SECTOR CCALA CCALA - JARPAÑA - MILLO CCOCHAPATA - LLANCA - QUILLISANI DEL
FECHA Mayo 2015
DISTRITO DE PARATIA, PROVINCIA LAMPA - PUNO
MESES
DESCRIPCION UNIDAD CANTIDAD PRECIO PARCIAL MES1 MES2 MES3 MES4 MES5 MES6 MES7
CAPATAZ hh 1,608.9951 21.89 35,220.90 7,009.36 5,582.71 1,664.26 1,617.12 4,215.44 4,361.87 10,770.14
OPERARIO hh 3,944.1204 16.84 66,418.99 8,681.57 1,122.79 12,374.42 15,409.12 6,356.21 12,374.42 10,100.46
OFICIAL hh 6,122.4616 13.97 85,530.79 21,957.91 4,219.77 14,864.63 11,980.82 6,551.84 14,864.63 11,091.19
PEON hh 14,451.1891 12.48 180,350.84 53,826.12 26,517.25 8,454.92 14,794.02 34,547.55 32,362.12 9,848.86
OPERADOR DE EQUIPO PESADO hh 5,880.2054 18.52 108,901.40 10,198.97 26,442.93 6,331.48 10,441.64 12,424.39 26,012.02 17,049.97
OPERADOR DE EQUIPO LIVIANO hh 418.7533 18.52 7,755.31 1,699.91 6,055.40
TOPOGRAFO hh 383.2000 21.89 8,388.25 8,388.25
CONTROLADOR OFICIAL hh 22.6800 16.84 381.93 381.93
GASOLINA gal 150.5064 10.88 1,637.51 772.14 865.37
PETROLEO D2 gal 24,894.0201 11.02 274,332.10 37,889.94 50,366.00 35,743.00 50,113.16 100,220.00
NEOPRENE SHORE DE (350X350X88) und 2.0000 386.07 772.14 309.60 462.54
ALAMBRE NEGRO N° 16 kg 890.8220 4.50 4,008.70 4,008.70
ALAMBRE NEGRO RECOCIDO N° 8 kg 640.2980 4.50 2,881.34 2,881.34
ACERO CORRUG. fy = 4200 kg/cm2 GRADO 60 kg 18,764.2220 3.00 56,292.67 23,006.00 1,122.00 15,678.00 16,486.67
CLAVOS PARA CALAMINA kg 15.0000 3.60 54.00 54.00
CLAVOS CON CABEZA PROMEDIO kg 767.7980 4.50 3,455.09 1,256.00 1,229.00 970.09
PLANCHA ACERO LAC DE 450X350X16 pza 4.0000 119.88 479.52 479.52
PLANCHA ACERO LAC DE 160X130X10 pza 9.2400 9.47 87.50 87.50
PLANCHA ACERO 9.5mmx1.22x2.40mm pln 0.1540 663.11 102.12 102.12
PLANCHA ACERO 16mmx1.22x2.40mm pln 0.1410 1,269.16 178.95 178.95
TEE DE ACERO LIVIANO DE 1 1/2"X1 1/2"X3/16" x 6 m pza 2.2590 52.02 117.51 117.51
ALCANTARILLA TMC Ø=36" m 39.2000 387.39 15,185.69 15,185.69
ALCANTARILLA TMC Ø=24" m 338.1000 295.00 99,739.50 99,739.50
ALCANTARILLA TMC Ø=48" m 9.8000 543.52 5,326.50 5,326.50
HORMIGON m3 7.5000 131.21 984.08 984.08
FIBRA DE VIDRIO DE 4 mm ACABADO m2 8.5261 88.01 750.38 750.38
TECNOPORT E=2" m2 20.5000 3.37 69.09 69.09
CEMENTO PORTLAND TIPO I (42.5 kg) bol 6,286.1003 18.64 117,172.91 27,690.00 55,920.00 33,562.91
YESO BOLSA 28 kg bol 2.6000 4.00 10.40 10.40
TUBO DE ACERO D= 3/8" mll 18.6000 9.46 175.96 175.96
MORTERO EPOXICO gal 9.9788 1.78 17.76 17.76
RESINA EPOXICA gal 0.1060 53.59 5.68 5.68
PEGAMENTO EPOXICO UNIVERSAL gal 0.4100 240.74 98.70 98.70
DESMOLDANTE PARA MADERA gal 320.1490 107.74 34,492.85 8,071.04 6,791.10 19,630.71
ADITIVO INCORPORADOR DE AIRE kg 161.1266 8.75 1,409.86 1,409.86
ADITIVO CURADOR gal 133.3354 13.46 1,794.69 1,794.69
MADERA TORNILLO p2 17,462.9857 4.50 78,583.44 78,583.44
MADERA CORRIENTE p2 625.0000 2.52 1,575.00 1,575.00
TRIPLAY DE 1.20X2.40 m X 6 mm und 12.5000 33.50 418.75 418.75
TRIPLAY DE 19mm Para encofrado pln 15.5176 100.00 1,551.76 1,551.76
TRIPLAY DE10 mm Para encofrado pln 211.7367 93.70 19,839.73 19,839.73
LIJA PARA CONCRETO hja 36.0000 1.10 39.60 39.60
PINTURA ESMALTE gal 25.6392 34.62 887.63 887.63
PINTURA IMPRIMANTE gal 29.8166 17.07 508.97 508.97
PINTURA PARA TRAFICO gal 0.8750 54.11 47.35 47.35
TINTA SERIGRAFICA NEGRA gal 1.1880 1,108.88 1,317.35 1,317.35
PINTURA ANTICORROSIVA gal 1.9000 33.55 63.75 63.75
SOLVENTE XILOL gal 5.2873 35.89 189.76 189.76
SELLANTE ELASTOMERICO kg 1.6400 7.08 11.61 11.61
SOLDADURA E 8111 NI2 H4 kg 39.2000 18.54 726.77 726.77
SOLDADURA CELLOCORD (AWS E6011) kg 8.8492 16.05 142.03 142.03
TUBO DE FIERRO NEGRO D=5" m 4.2000 83.35 350.07 350.07
TUBO DE FIERRO NEGRO D=4" m 28.0000 68.80 1,926.40 1,926.40
TUBO DE FIERRO NEGRO SDT D=3" m 78.0000 45.89 3,579.42 3,579.42
LAMINA REFLECTIVA ALTA INTENSIDAD p2 291.4059 12.60 3,671.71 3,671.71
PROYECTO 003-003
CRONOGRAMA DE ADQUISICION DE MATERIALES REVISION FGT
APROBADO EEQA
PROYECTO: MEJORAMIENTO DE CAMINO VECINAL SECTOR CCALA CCALA - JARPAÑA - MILLO CCOCHAPATA - LLANCA - QUILLISANI DEL
FECHA Mayo 2015
DISTRITO DE PARATIA, PROVINCIA LAMPA - PUNO
MESES
DESCRIPCION UNIDAD CANTIDAD PRECIO PARCIAL MES1 MES2 MES3 MES4 MES5 MES6 MES7
PROYECTO: MEJORAMIENTO DE CAMINO VECINAL SECTOR CCALA CCALA - JARPAÑA - MILLO CCOCHAPATA - LLANCA - QUILLISANI DEL DISTRITO DE PARATIA, PROVINCIA LAMPA - PUNO FECHA Mayo 2015
MESES
ITEM PARTIDA UND METRADO PRECIO PARCIAL MES1 MES2 MES3 MES4 MES5 MES6 MES7
PROYECTO: MEJORAMIENTO DE CAMINO VECINAL SECTOR CCALA CCALA - JARPAÑA - MILLO CCOCHAPATA - LLANCA - QUILLISANI DEL DISTRITO DE PARATIA, PROVINCIA LAMPA - PUNO FECHA Mayo 2015
MESES
ITEM PARTIDA UND METRADO PRECIO PARCIAL MES1 MES2 MES3 MES4 MES5 MES6 MES7