UGEI-MPT

Calendario de Utilizacion de Recursos


Obra : MEJORAMIENTO DE PISTAS Y VEREDAS EN LAS CALLES Y PASAJES DE LA JUNTA VECINAL QUINTA HIDALGO EN LA CIUDAD DE TACNA, DISTRITO DE TACNA, PROVINCIA
Ubicacion : TACNA - TACNA - TACNA
Costo A : Jul - 2016 Cliente : MUNICIPALIDAD PROVINCIAL DE TACNA
PLAZO DE EJECUCION
TOTAL
Cod Descripcion Unid Cantidad Precio Parcial 30 Dias 30 Dias 30 Dias 30 Dias 15 Dias
135 Dias

MANO DE OBRA
47 00006 CAPATAZ HH 634.46 22.38 14,199.21 4,536.73 4,302.20 1,962.98 2,740.73 656.57 14,199.21
47 00086 TOPOGRAFO HH 71.63 18.65 1,335.90 1,335.90 - - - - 1,335.90
47 00007 OPERARIO HH 2,536.70 18.65 47,309.46 3,214.05 6,114.10 14,608.59 21,000.75 2,371.97 47,309.46
47 00008 OFICIAL HH 1,595.15 15.40 24,565.31 4,277.67 5,185.48 6,803.97 8,096.07 202.12 24,565.31
47 00009 PEON HH 8,015.59 13.80 110,615.14 28,010.77 26,987.58 25,439.69 25,831.71 4,345.39 110,615.14
MATERIALES
02 07367 ABRAZADERA DE FºGº TIPO PARTIDO DE 2" X 1/4" X 140MM. UND 9.00 22.00 198.00 - 198.00 - - - 198.00
02 07366 AISLADOR DE TRACCION 54-2 UND 9.00 15.00 135.00 - 135.00 - - - 135.00
02 07362 ALAMBRE DE ACERO Nº12 kg 0.46 3.50 1.61 - 1.61 - - - 1.61
02 07111 ALAMBRE NEGRO # 8 kg 116.07 3.50 406.25 15.75 37.48 234.26 118.76 - 406.25
02 07110 ALAMBRE NEGRO # 16 kg 21.20 3.50 74.20 23.85 - 21.30 29.05 - 74.20
02 07365 ARANDELA CUADRADA DE 4" X 4" X 1/4" C/AGUJERO 5/8" UND 9.00 5.00 45.00 - 45.00 - - - 45.00
02 07368 BLOQUE DE C° DE 0.40 X 0.40 X 0.10M. UND 9.00 17.00 153.00 - 153.00 - - - 153.00
02 07369 CABLE DE ACERO GALVANIZADO DE 3/8" ML 90.00 5.50 495.00 - 495.00 - - - 495.00
02 02069 CLAVOS PARA MADERA C/C 2" KG 11.22 3.80 42.64 42.64 - - - - 42.64
02 07057 CLAVOS PARA MADERA CON CABEZA DE 1" kg 12.94 10.00 129.40 - 17.85 111.55 - - 129.40
02 06203 CLAVOS PARA MADERA CON CABEZA DE 3" kg 71.26 3.80 270.79 59.36 20.35 127.17 63.91 - 270.79
02 07363 GUARDACABLE DE 1/6" PARA CABLE DE 3/8" UND 18.00 5.00 90.00 - 90.00 - - - 90.00
02 07364 MORDAZA PREFORMADA DE 890MM 48KN UND 36.00 8.50 306.00 - 306.00 - - - 306.00
02 07169 PERNO GALVANIZADO DE 5" X 1/4" C/TUERCA Y VOLANDA pza 30.00 5.00 150.00 - - - 150.00 - 150.00
02 07370 VARILLA DE ANCLAJE DE 5/8" X 2.40 M. ARANDELA Y TUERCA UND 9.00 35.00 315.00 - 315.00 - - - 315.00
03 06206 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 295.98 3.00 887.94 60.00 - 325.61 502.33 - 887.94
03 07171 PERNOS DE FIERRO CORRUGADO DE 1/2" C/ROSCA kg 9.05 8.00 72.40 - - - 72.40 - 72.40
04 00033 ARENA FINA M3 18.88 46.67 881.13 - - 399.13 482.00 - 881.13
04 00029 ARENA GRUESA M3 218.16 40.79 8,898.75 8.16 3,074.47 2,956.65 2,812.51 46.96 8,898.75

Página 1 de 8
UGEI-MPT

Calendario de Utilizacion de Recursos


Obra : MEJORAMIENTO DE PISTAS Y VEREDAS EN LAS CALLES Y PASAJES DE LA JUNTA VECINAL QUINTA HIDALGO EN LA CIUDAD DE TACNA, DISTRITO DE TACNA, PROVINCIA
Ubicacion : TACNA - TACNA - TACNA
Costo A : Jul - 2016 Cliente : MUNICIPALIDAD PROVINCIAL DE TACNA
PLAZO DE EJECUCION
TOTAL
Cod Descripcion Unid Cantidad Precio Parcial 30 Dias 30 Dias 30 Dias 30 Dias 15 Dias
135 Dias
04 00074 TIERRA DE CHACRA M3 24.79 33.00 818.07 - - - 818.07 - 818.07
05 00337 AFIRMADO M3 212.28 33.58 7,128.36 - 5,346.27 1,782.09 - - 7,128.36
05 00002 AGUA M3 462.98 10.00 4,629.80 1,697.43 1,566.21 806.13 558.53 1.50 4,629.80
05 02920 CONFITILLO M3 21.35 55.00 1,174.25 - - 572.49 601.76 - 1,174.25
05 00350 MATERIAL CLASIFICADO PARA BASE M3 522.20 34.84 18,193.45 8,820.14 4,410.07 4,963.24 - - 18,193.45
05 00099 PIEDRA CHANCADA DE 1/2" M3 211.34 68.35 14,445.09 13.68 3,201.49 5,886.29 5,343.63 - 14,445.09
10 07115 INODORO DE CONCRETO INCLUYE ACCESORIOS pza 2.03 160.00 324.80 324.80 - - - - 324.80
10 07117 LAVADERO DE CONCRETO INCL LLAVE pza 2.03 28.00 56.84 56.84 - - - - 56.84
11 01334 PRUEBA DE RED ELECTRICA GLB 1.00 1,000.00 1,000.00 - 1,000.00 - - - 1,000.00
13 07149 ASFALTO LIQUIDO MC-30 gln 755.09 14.00 10,571.26 - 7,082.02 3,489.24 - - 10,571.26
13 00666 ASFALTO RC-250 GLN 3,284.52 16.00 52,552.32 - 35,843.71 3,845.29 12,238.14 625.18 52,552.32
21 00442 CEMENTO BLANCO KG 5.21 22.00 114.62 - - - 114.62 - 114.62
21 07107 CEMENTO PORTLAND TIPO IP(42.5 kg) bls 1,917.91 21.00 40,276.11 688.96 1,391.04 21,081.08 16,957.54 157.49 40,276.11
26 07114 BISAGRAS DE FIERRO DE 3 1/2" X 3 1/2" pza 14.37 7.50 107.78 107.78 - - - - 107.78
29 07142 EXTINTOR DE POLVO QUIMICO SECO DE 12 KG und 1.00 120.00 120.00 120.00 - - - - 120.00
29 00862 SOLDADURA CELLOCORD 1/8" KG 3.00 15.00 45.00 - - - 45.00 - 45.00
29 07157 YESO EN BOLSAS DE 18 kg bls 170.58 12.00 2,046.96 2,046.96 - - - - 2,046.96
30 04939 ADITIVO IMPERMEABILIZANTE KG 44.02 5.00 220.10 - - - 220.10 - 220.10
30 02988 CINTA TEFLON UND 23.44 2.50 58.60 - - 18.31 40.29 - 58.60
30 01202 IMPRIMANTE GLN 31.99 7.50 239.93 - - - 12.62 227.31 239.93
30 07172 LACA DESMOLDEADORA MAS DISOLVENTE jgo 26.71 160.00 4,273.60 - 439.72 2,748.24 1,085.64 - 4,273.60
30 02058 LIJA PARA MADERA HJA 44.87 1.80 80.77 5.40 8.21 51.32 15.84 - 80.77
30 04341 PEGAMENTO PARA PVC GLN 3.46 95.00 328.70 - - 102.72 225.98 - 328.70
34 02519 GASOLINA 84 OCTANOS GLN 26.44 13.50 356.94 - 187.91 17.80 151.23 - 356.94
37 07063 BROCHA DE 4" und 27.89 24.00 669.36 - - - 418.30 251.06 669.36
37 06828 ESCOBA UND 57.11 8.00 456.88 - 115.63 113.94 - 227.31 456.88

Página 2 de 8
UGEI-MPT

Calendario de Utilizacion de Recursos


Obra : MEJORAMIENTO DE PISTAS Y VEREDAS EN LAS CALLES Y PASAJES DE LA JUNTA VECINAL QUINTA HIDALGO EN LA CIUDAD DE TACNA, DISTRITO DE TACNA, PROVINCIA
Ubicacion : TACNA - TACNA - TACNA
Costo A : Jul - 2016 Cliente : MUNICIPALIDAD PROVINCIAL DE TACNA
PLAZO DE EJECUCION
TOTAL
Cod Descripcion Unid Cantidad Precio Parcial 30 Dias 30 Dias 30 Dias 30 Dias 15 Dias
135 Dias
37 07166 LIJA DE CONCRETO plg 18.87 1.80 33.97 - - - - 33.97 33.97
38 00005 HORMIGON M3 7.67 27.88 213.84 201.99 - - - 11.85 213.84
39 07176 ARBUSTO MEDIANO und 2.00 25.00 50.00 - - - 50.00 - 50.00
39 07130 BLOQUEADOR SOLAR SACHET 5ML FPS50+ und 525.00 3.00 1,575.00 1,575.00 - - - - 1,575.00
39 07126 BOTAS DE JEBE CAÑA ALTA par 7.00 28.00 196.00 196.00 - - - - 196.00
39 07028 BOTELLON DE AGUA DE 20LT und 25.00 18.00 450.00 450.00 - - - - 450.00
39 07143 BOTIQUIN TOPICO DE PRIMEROS AUXILIOS und 1.00 240.00 240.00 240.00 - - - - 240.00
39 07167 BROCHA 2" und 2.41 8.00 19.28 - - - 19.28 - 19.28
39 07144 CAMILLA und 1.00 280.00 280.00 280.00 - - - - 280.00
39 07136 CARTEL INFORMATIVO SOBRE SEGURIDAD INCL/SOPORTES und 2.00 480.00 960.00 960.00 - - - - 960.00
39 07137 CARTEL SEÑALES DE ADVERTENCIA INCL/SOPORTES und 1.00 8.00 8.00 8.00 - - - - 8.00
39 07138 CARTEL SEÑALES DE OBLIGACIÓN INCL/SOPORTES und 1.00 8.00 8.00 8.00 - - - - 8.00
39 07139 CARTEL SEÑALES DE PROHIBICIÓN INCL/SOPORTES und 2.00 8.00 16.00 16.00 - - - - 16.00
39 07016 CASCO DE SEGURIDAD und 35.00 9.00 315.00 315.00 - - - - 315.00
39 07127 CHALECOS DE SEGURIDAD REFLECTIVO und 7.00 45.00 315.00 315.00 - - - - 315.00
39 07058 COLA SINTETICA gal 5.18 19.50 101.01 - 13.93 87.08 - - 101.01
39 07165 CORDEL DE ALGODON m 97.64 0.25 24.41 - - - 24.41 - 24.41
39 07158 ESPONJA 2" pln 72.64 14.00 1,016.96 - - 445.33 571.63 - 1,016.96
39 07177 ESTIERCOL X SACO DE 40 KG sac 0.25 18.00 4.50 - - - 4.50 - 4.50
39 07175 FOSFATO DIAMONICO sac 0.02 64.00 1.28 - - - 1.28 - 1.28
39 07109 GIGANTOGRAFIA 3.60x2.40 und 1.00 750.00 750.00 750.00 - - - - 750.00
39 07012 GUANTES DE CUERO par 70.00 8.50 595.00 595.00 - - - - 595.00
39 07011 GUANTES DE JEBE par 35.00 9.00 315.00 315.00 - - - - 315.00
39 07178 HUMUS kg 4.00 3.00 12.00 - - - 12.00 - 12.00
39 07124 LENTES DE SEGURIDAD und 35.00 8.00 280.00 280.00 - - - - 280.00
39 00729 LIJA PARA CONCRETO HJA 5.64 1.80 10.15 - - - 2.77 7.38 10.15

Página 3 de 8
UGEI-MPT

Calendario de Utilizacion de Recursos


Obra : MEJORAMIENTO DE PISTAS Y VEREDAS EN LAS CALLES Y PASAJES DE LA JUNTA VECINAL QUINTA HIDALGO EN LA CIUDAD DE TACNA, DISTRITO DE TACNA, PROVINCIA
Ubicacion : TACNA - TACNA - TACNA
Costo A : Jul - 2016 Cliente : MUNICIPALIDAD PROVINCIAL DE TACNA
PLAZO DE EJECUCION
TOTAL
Cod Descripcion Unid Cantidad Precio Parcial 30 Dias 30 Dias 30 Dias 30 Dias 15 Dias
135 Dias
39 07131 MALLA DE SEGURIDAD ROLLO 50YD X 1M rll 5.00 55.00 275.00 275.00 - - - - 275.00
39 07361 OTRO MATERIALES Y SERVICIOS glb 9.00 50.00 450.00 - 450.00 - - - 450.00
39 07009 OVEROL PARA PERSONAL DE OBRA und 35.00 65.00 2,275.00 2,275.00 - - - - 2,275.00
39 07133 POSTE APOYO SEÑALIZACIÓN DE MADERA BASE DE CONCR pza 15.00 25.00 375.00 375.00 - - - - 375.00
39 07128 RESPIRADOR 2 VIAS CON CARTUCHO FILTRO POLVO und 70.00 15.00 1,050.00 1,050.00 - - - - 1,050.00
39 07129 TAPONES PROTECTORES DE OIDO und 35.00 3.50 122.50 122.50 - - - - 122.50
39 06192 TIZA kg 31.84 2.50 79.60 - 1.07 6.69 71.84 - 79.60
39 07132 TRANQUERA PORTABLE PARA SEÑALIZACIÓN L=3MTS und 3.00 75.00 225.00 225.00 - - - - 225.00
39 07159 YUTE m2 789.55 8.00 6,316.40 - - - 6,316.40 - 6,316.40
39 07125 ZAPATOS DE SEGURIDAD par 35.00 65.00 2,275.00 2,275.00 - - - - 2,275.00
43 00020 MADERA TORNILLO P2 1,227.91 5.43 6,667.55 3,582.48 174.55 1,090.93 1,819.59 - 6,667.55
43 00274 REGLA DE MADERA P2 99.13 5.43 538.28 - - 262.43 275.85 - 538.28
45 07113 TRIPLAY DE 4' X 8' X 12 mm pln 41.40 75.00 3,105.00 3,105.00 - - - - 3,105.00
45 07173 TRIPLAY DE 4' X 8' X 18 mm pln 24.88 110.00 2,736.80 - 173.11 1,081.95 1,481.74 - 2,736.80
45 07108 TRIPLAY DE 4' X 8' X 4 mm pln 43.52 27.00 1,175.04 1,175.04 - - - - 1,175.04
53 03767 PETROLEO GLN 34.12 13.50 460.62 - 332.44 32.05 96.13 - 460.62
54 03192 DISOLVENTE XILOL GLN 10.88 45.00 489.60 - - - 370.72 118.88 489.60
54 00068 PINTURA ANTICORROSIVA GLN 1.24 38.00 47.12 - - - 47.12 - 47.12
54 04501 PINTURA DE TRAFICO GLN 64.47 63.00 4,061.61 - - - 4,061.61 - 4,061.61
54 00027 PINTURA ESMALTE GLN 40.59 43.00 1,745.37 255.86 - - 126.52 1,362.99 1,745.37
54 07170 THINER STANDARD gln 3.98 18.00 71.64 - - - 40.88 30.76 71.64
56 07112 CALAMINA GALV. DE 1.83x0.83 pln 64.92 27.00 1,752.84 1,752.84 - - - - 1,752.84
56 07087 PLANCHA ACERO 5.0mm X 1.22m X 2.40 m pln 2.63 185.00 486.55 - - - 486.55 - 486.55
62 01138 POSTE DE CONCRETO 8.00M UND 9.00 485.00 4,365.00 - 4,365.00 - - - 4,365.00
65 07168 TUBO REDONDO FºNº 3" X 2.5 MM. und 7.50 85.00 637.50 - - - 637.50 - 637.50
69 07164 CAJA DE CONCRETO CONEXION DESAGUE und 80.00 50.00 4,000.00 - - 1,250.00 2,750.00 - 4,000.00

Página 4 de 8
UGEI-MPT

Calendario de Utilizacion de Recursos


Obra : MEJORAMIENTO DE PISTAS Y VEREDAS EN LAS CALLES Y PASAJES DE LA JUNTA VECINAL QUINTA HIDALGO EN LA CIUDAD DE TACNA, DISTRITO DE TACNA, PROVINCIA
Ubicacion : TACNA - TACNA - TACNA
Costo A : Jul - 2016 Cliente : MUNICIPALIDAD PROVINCIAL DE TACNA
PLAZO DE EJECUCION
TOTAL
Cod Descripcion Unid Cantidad Precio Parcial 30 Dias 30 Dias 30 Dias 30 Dias 15 Dias
135 Dias
69 07160 CAJA DE CONCRETO PARA MEDIDOR AGUA und 93.00 15.00 1,395.00 - - 435.94 959.06 - 1,395.00
72 07134 CINTA DE SEÑALIZACIÓN AMARILLA X400M rll 1.00 55.00 55.00 55.00 - - - - 55.00
72 07135 CONO DE SEÑALIZACIÓN 28" und 2.00 55.00 110.00 110.00 - - - - 110.00
72 07116 DUCHA CON BRAZO Y CABEZA INCL ACCESORIOS pza 2.03 35.00 71.05 71.05 - - - - 71.05
72 07084 LAMINA REFLECTORIZANTE m2 8.25 170.00 1,402.50 - - - 1,402.50 - 1,402.50
72 07078 MARCO Y TAPA DE TERMOPLASTICO PARA DESAGÜE und 80.00 38.00 3,040.00 - - 950.00 2,090.00 - 3,040.00
72 07163 MARCO Y TAPA TERMOPLASTICA PARA MEDIDOR AGUA und 93.00 20.00 1,860.00 - - 581.25 1,278.75 - 1,860.00
72 07161 TUBERIA PVC PARA AGUA C/A und 37.20 17.50 651.00 - - 203.44 447.56 - 651.00
72 07118 TUBERIA PVC SAL 4" und 58.69 24.00 1,408.56 122.12 - 402.01 884.43 - 1,408.56
72 07174 TUBERIA PVC SAP 3/4" m 75.78 6.00 454.68 - - - 454.68 - 454.68
72 07119 TUBERIA PVC SAP DE 1/2" X 6m und 5.09 12.50 63.63 63.63 - - - - 63.63
72 07162 UNION SIMPLE PVC SAP 3/4" und 186.00 2.50 465.00 - - 145.31 319.69 - 465.00
EQUIPO
37 01542 EQUIPO DE PINTURA HM 18.00 20.00 360.00 - - - 360.00 - 360.00
37 00004 HERRAMIENTAS MANUALES %MO 8,815.35 1,654.41 1,965.13 2,308.72 2,549.64 337.45 8,815.35
48 07268 CAMION GRUA HM 34.68 120.00 4,161.60 720.00 3,441.60 - - - 4,161.60
48 00691 CIZALLA HM 2.40 2.00 4.80 - - 2.03 2.77 - 4.80
48 02029 EQUIPO DE SOLDAR HM 15.00 10.00 150.00 - - - 150.00 - 150.00
48 06864 ESTACION TOTAL hm 71.25 25.00 1,781.25 1,781.25 - - - - 1,781.25
48 07037 MIRA TOPOGRAFICA hm 85.67 1.88 161.06 161.06 - - - - 161.06
49 00110 BARRENOS HM 192.51 10.00 1,925.10 1,914.78 5.07 4.05 1.20 - 1,925.10
49 07154 CALENTADOR DE ASFALTO C-300 8000 GLN hm 17.84 95.00 1,694.80 - 612.51 270.57 811.72 - 1,694.80
49 07145 CAMION CISTERNA 4 X 2 (AGUA) 122 HP 2,000 gl hm 18.44 105.63 1,947.82 1,611.66 336.16 - - - 1,947.82
49 07049 CAMION IMPRIMADOR 2300 GL 175HP hm 10.56 124.00 1,309.44 - 953.53 355.91 - - 1,309.44
49 00362 CAMION VOLQUETE 12 m3 HM 207.10 130.64 27,055.54 5,192.06 10,446.68 5,807.63 5,609.17 - 27,055.54
49 07148 CARGADOR FRONTAL 3.50 M3. hm 46.76 163.12 7,627.49 2,160.19 2,612.64 1,453.57 1,401.09 - 7,627.49

Página 5 de 8
UGEI-MPT

Calendario de Utilizacion de Recursos


Obra : MEJORAMIENTO DE PISTAS Y VEREDAS EN LAS CALLES Y PASAJES DE LA JUNTA VECINAL QUINTA HIDALGO EN LA CIUDAD DE TACNA, DISTRITO DE TACNA, PROVINCIA
Ubicacion : TACNA - TACNA - TACNA
Costo A : Jul - 2016 Cliente : MUNICIPALIDAD PROVINCIAL DE TACNA
PLAZO DE EJECUCION
TOTAL
Cod Descripcion Unid Cantidad Precio Parcial 30 Dias 30 Dias 30 Dias 30 Dias 15 Dias
135 Dias
49 07155 COMPACTADOR VIBRATORIO TIPO PLANCHA 7 HP hm 386.49 25.00 9,662.25 - 5,502.04 3,732.96 427.25 - 9,662.25
49 07150 COMPRESORA NEUMATICA 90HP, 250P3 hm 96.30 87.96 8,470.55 8,425.13 22.30 17.84 5.28 - 8,470.55
49 07156 MARTILLO NEUMATICO DE 25 kg hm 192.51 15.00 2,887.65 2,872.17 7.60 6.08 1.80 - 2,887.65
49 07147 MEZCLADORA DE CONCRETO DE 11p3 18 HP hm 250.50 25.00 6,262.50 100.00 20.25 3,280.31 2,861.94 - 6,262.50
49 07041 MOTONIVELADORA DE 162 HP hm 30.27 149.26 4,518.10 4,047.43 470.67 - - - 4,518.10
49 07146 NIVEL TOPOGRÁFICO hm 71.52 5.63 402.66 402.66 - - - - 402.66
49 07152 PAVIMENTADORA DE 12 M3 hm 6.42 163.02 1,046.59 - 1,046.59 - - - 1,046.59
49 07054 PLANTA DE ASFALTO DE 100 TON/HORA hm 17.83 240.00 4,279.20 - 1,545.47 683.43 2,050.30 - 4,279.20
49 07371 RODILLO DOBLE ROLA DE 1TN hm 1.64 80.00 131.20 - 131.20 - - - 131.20
49 07153 RODILLO NEUMATICO AUTOP 126 HP 10 ton hm 4.79 123.02 589.27 - 589.27 - - - 589.27
49 07043 RODILLO TANDEM VIBRATORIO AUTOPROPULSADO 130HP - 10 hm 23.27 130.18 3,029.29 1,993.18 1,036.11 - - - 3,029.29
49 00668 VIBRADOR DE CONCRETO 4 HP 1.50" HM 149.57 10.00 1,495.70 40.00 8.10 785.69 661.91 - 1,495.70
SERVICIOS
S 07140 CAPACITADOR TECNICO SOBRE SEGURIDAD EN OBRA Charl 2.00 1,500.00 3,000.00 3,000.00 - - - - 3,000.00
S 07123 ELABORACIÓN, IMPLEMENTACIÓN Y ADMINISTRACIÓN DEL P glb 1.00 2,000.00 2,000.00 2,000.00 - - - - 2,000.00
S 07141 MATERIAL PARA CAPACITACIÓN EN SEGURIDAD Y SALUD glb 1.00 500.00 500.00 500.00 - - - - 500.00
S 07094 MITIGACION DE IMPACTO AMBIENTAL glb 1.00 4,500.00 4,500.00 4,500.00 - - - - 4,500.00
S 07120 PAGO A ELECTROSUR POR CONSUMO DE ENERGIA glb 5.00 450.00 2,250.00 2,250.00 - - - - 2,250.00
S 07030 PAGO DE SEGUROS und 1.00 5,000.00 5,000.00 5,000.00 - - - - 5,000.00
S 07121 PAGO POR SUMINISTRO E INSTALACION DE AGUA PROVISION mes 5.00 350.00 1,750.00 1,750.00 - - - - 1,750.00
S 07029 SERVICIO DE EXAMEN MEDICO OCUPACIONAL mes 1.00 3,000.00 3,000.00 3,000.00 - - - - 3,000.00
S 07122 SERVICIO DE MOVILIZACION DE EQUIPOS Y HERRAMIENTAS glb 1.00 3,500.00 3,500.00 3,500.00 - - - - 3,500.00

COSTO DIRECTO 561,686.77 137,438.36 144,333.42 124,152.28 144,746.57 11,016.14 561,686.77


GASTOS GENERALES (12.5%CD) 12.5 % 70,210.85 17,179.80 18,041.68 15,519.04 18,093.32 1,377.01 70,210.85
PRESUPUESTO TOTAL DE OBRA 631,897.62 154,618.16 162,375.10 139,671.32 162,839.89 12,393.15 631,897.62
INSPECCION (6%CD) 6% 33,701.21 8,246.30 8,660.01 7,449.14 8,684.80 660.96 33,701.21

Página 6 de 8
UGEI-MPT

Calendario de Utilizacion de Recursos


Obra : MEJORAMIENTO DE PISTAS Y VEREDAS EN LAS CALLES Y PASAJES DE LA JUNTA VECINAL QUINTA HIDALGO EN LA CIUDAD DE TACNA, DISTRITO DE TACNA, PROVINCIA
Ubicacion : TACNA - TACNA - TACNA
Costo A : Jul - 2016 Cliente : MUNICIPALIDAD PROVINCIAL DE TACNA
PLAZO DE EJECUCION
TOTAL
Cod Descripcion Unid Cantidad Precio Parcial 30 Dias 30 Dias 30 Dias 30 Dias 15 Dias
135 Dias
LIQUIDACION(1.6%CD) 1.6 % 8,986.99 2,199.01 2,309.34 1,986.44 2,315.95 176.25 8,986.99
ESTUDIO (REPORTADO) 14,788.37 3,618.55 3,800.08 3,268.74 3,810.96 290.04 14,788.37
PRESUPUESTO TOTAL DE INVERSION 689,374.19 168,682.02 177,144.52 152,375.63 177,651.59 13,520.43 689,374.19
TOTAL ACUMULADO 168,682.02 345,826.54 498,202.17 675,853.76 689,374.19
PORCENTAJE DE AVANCE 24.47% 25.70% 22.10% 25.77% 1.96%
PORCENTAJE ACUMULADO 24.47% 50.17% 72.27% 98.04% 100.00%