Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
M.N.
1.1).- SINDICATOS
38,500.00
0.05%
71,830.00
0.09%
892,619.20
1.10%
27,500.00
0.03%
132,000.00
0.16%
1.6).- VELADOR
91,184.02
0.11%
1.7).- SEGURIDAD
91,740.00
0.11%
1.8).- BODEGA
28,820.00
0.04%
Total: 1).-PRELIMINARES $
1,374,193.22
1.69%
2,490,207.31
3.06%
4,270,371.37
5.24%
Total: 2).-TERRACERIAS $
6,760,578.68
8.30%
2).-TERRACERIAS
198,853.88
0.24%
1,233,363.27
1.51%
3,898,560.53
4.79%
3.3).-
6,206,442.74
7.62%
5,997,136.47
7.36%
5,517,094.14
6.77%
300,667.06
0.37%
2,369,020.50
2.91%
3.4).-
LECHOSO. [10%]
3.8).-
3.8).-
87,561.94
0.11%
181,317.98
0.22%
55,469.70
0.07%
Escalera Marina]
3.11).- PINTURA ESMALTE [Puertas de Emergencia, Rampas Niveladoras,
98,846.35
0.12%
26,144,334.55
32.10%
2,656,286.27
3.26%
1,163,747.08
1.43%
407,606.69
0.50%
574,988.11
0.71%
37,862.11
0.05%
5,610.00
0.01%
98,846.35
0.12%
4,944,946.61
6.07%
4.1).-
4.2).-
4.3).-
4.4).-
Pgina 2 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
M.N.
688,789.20
0.85%
217,316.00
0.27%
181,016.00
0.22%
426,316.00
0.52%
930,979.50
1.14%
1,436,143.10
1.76%
60,830.00
0.07%
32,709.60
0.04%
11,550.00
0.01%
49,423.18
0.06%
4,035,072.58
4.95%
72,721.79
0.09%
72,721.79
0.09%
1,925.00
0.00%
7.2).- REGISTRO.
2,630.20
0.00%
16,494.50
0.02%
16,445.00
0.02%
7.5).- GRAVA .
2,920.50
0.00%
40,415.20
0.05%
8.1).- INST. ACOMETIDA MEDIA TENSION [INC. 1 TRANSF. DE 1500 KVA TIPO $
1,726,146.40
2.12%
8).-INSTALACION ELECTRICA.
8.1).-
2,009,165.40
2.47%
1,178,263.90
1.45%
420,420.00
0.52%
114,237.20
0.14%
94,864.00
0.12%
20,535.90
0.03%
20,535.90
0.03%
37,837.80
0.05%
295,020.00
0.36%
20,535.90
0.03%
321,063.60
0.39%
115,615.50
0.14%
Pgina 3 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
63,028.90
0.08%
235,389.00
0.29%
246,243.29
0.30%
6,918,902.69
8.50%
9).-FACHADA DE INGRESO
M.N.
275,000.00
0.34%
275,000.00
0.34%
20,183.53
0.02%
60,871.93
0.07%
24,393.60
0.03%
64,072.80
0.08%
6,600.00
0.01%
176,121.86
0.22%
5,122,150.00
6.29%
5,122,150.00
6.29%
44,370.70
0.05%
367,601.30
0.45%
411,972.00
0.51%
71,988.40
0.09%
13).-INST.
HIDROSANITARIAS,
ELECTRICAS,
DETECTORES PHOTO BEAM. [Varias Areas]
ALARMAS
&
DE PROCESO
13.2).- INST. HIDROSANITARIA AREA EMBALAJE
44,077.00
0.05%
466,527.60
0.57%
139,632.90
0.17%
351,195.90
0.43%
371,444.70
0.46%
1,444,866.50
1.77%
377,638.80
0.46%
15,785.00
0.02%
146,407.80
0.18%
53,884.60
0.07%
102,749.59
0.13%
696,465.79
0.86%
Pgina 4 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
2,731,652.00
3.35%
777,084.00
0.95%
2,216,737.60
2.72%
150,920.00
0.19%
161,331.67
0.20%
6,037,725.27
7.41%
M.N.
1,523,069.24
1.87%
570,890.34
0.70%
502,860.86
0.62%
1,731,807.04
2.13%
4,328,627.49
5.31%
291,032.87
0.36%
1,925,518.47
2.36%
601,642.43
0.74%
437,998.00
0.54%
510,840.00
0.63%
370,163.04
0.45%
841,747.66
1.03%
4,978,942.46
6.11%
129,347.94
0.16%
287,086.35
0.35%
111,053.16
0.14%
106,432.65
0.13%
114,246.00
0.14%
102,784.00
0.13%
850,950.09
1.04%
437,515.54
0.54%
842,942.43
1.03%
402,379.93
0.49%
126,995.57
0.16%
42,075.02
0.05%
23,137.13
0.03%
1,875,045.62
2.30%
Pgina 5 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
91,912.59
0.11%
103,553.73
0.13%
45,754.70
0.06%
49,148.22
0.06%
290,369.24
0.36%
M.N.
21.1).- CIMENTACION
97,010.96
0.12%
232,190.00
0.29%
208,971.00
0.26%
176,000.00
0.22%
355,300.00
0.44%
19,800.00
0.02%
81,400.00
0.10%
17,380.00
0.02%
1,188,051.95
1.46%
22.1).- CIMENTACION
194,021.92
0.24%
431,873.39
0.53%
275,702.40
0.34%
326,854.00
0.40%
465,384.70
0.57%
24,135.38
0.03%
22.7).- PUERTAS
27,500.00
0.03%
26,070.00
0.03%
1,771,541.79
2.18%
231,320.54
0.28%
27,476.04
0.03%
258,796.58
0.32%
23).-PLANTA DE TRATAMIENTO
163,295.85
0.20%
42,240.00
0.05%
205,535.85
0.25%
Pgina 6 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
M.N.
384,302.27
0.47%
128,100.75
0.16%
128,100.75
0.16%
REALIZADOS
25.4).- SEGURO DE OBRA & POR RESPONSABILIDAD CIVIL.
601,685.37
0.74%
1,242,189.15
1.53%
81,445,516.96
13,031,282.71
94,476,799.67 M.N.
Water
100.00%
Pgina 7 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
Director General
Ing. Juan Enrique Alcocer Naranjo
Grupo Corporativo Jerplan, S.A. De C.V.
1).-PRELIMINARES
1.1).-SINDICATOS
1
SINDICATOS
38,500.00
0.05%
Total: 1.1).-SINDICATOS $
38,500.00
0.05%
71,830.00
0.09%
71,830.00
0.09%
PERMISO DE CONSTRUCCION
892,619.20
1.10%
892,619.20
1.10%
1.4).-TRAILERS OFICINAS
4
TRAILERS OFICINAS
27,500.00
0.03%
27,500.00
0.03%
132,000.00
0.16%
132,000.00
0.16%
1.5).-CERCADO PROVISIONAL
5
CERCADO PROVISIONAL
1.6).-VELADOR
ING. JUAN ENRIQUE ALCOCER NARANJO
Pgina 8 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
VELADOR
91,184.02
0.11%
Total: 1.6).-VELADOR $
91,184.02
0.11%
1.7).-SEGURIDAD
7
SEGURIDAD
91,740.00
0.11%
Total: 1.7).-SEGURIDAD $
91,740.00
0.11%
1.8).-BODEGA
8
BODEGA
28,820.00
0.04%
Total: 1.8).-BODEGA $
28,820.00
0.04%
1,374,193.22
1.69%
109,369.63
0.13%
153,992.44
0.19%
231,943.16
0.28%
279,986.26
0.34%
1,189,941.59
1.46%
524,974.23
0.64%
2,490,207.31
3.06%
272,054.89
0.33%
Total: 1).-PRELIMINARES
2).-TERRACERIAS
2.1).-TERRACERIAS EN NAVE.
9
PRODUCTO DE LA
VOLUMEN SUELTO.
12
EXCAVACION,
ARENA,
GRAVA,
CASCAJO,
2.2).-TERRACERIAS EN VIALIDADES.
15
Pgina 9 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
16
287,289.96
0.35%
576,954.22
0.71%
522,345.38
0.64%
1,305,863.46
1.60%
PRODUCTO DE LA
VOLUMEN SUELTO.
18
EXCAVACION,
ARENA,
GRAVA,
CASCAJO,
1,305,863.46
1.60%
4,270,371.37
5.24%
6,760,578.68
8.30%
LA $
198,853.88
0.24%
198,853.88
0.24%
420,380.82
0.52%
Total: 2).-TERRACERIAS
3).-ALMACEN GENERAL.
3.1).-INGENIERIA DE DETALLE.
21
2.1.1).-ELABORACION
DE
INGENIERIA DE DETALLE.
PROYECTO
ARQUITECTONICO
23
ZC1).-ZAPATA
528,570.50
0.65%
24
ZC2).-ZAPATA
284,411.95
0.35%
1,233,363.27
1.51%
Pgina 10 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
25
3,016,149.21
3.70%
18,062.33
0.02%
72,541.42
0.09%
27,930.21
0.03%
429,802.85
0.53%
334,074.51
0.41%
3,898,560.53
4.79%
5,739,364.83
7.05%
439,562.51
0.54%
14,520.00
0.02%
12,995.40
0.02%
6,206,442.74
7.62%
26
2.3.2-A).-ELAB.
27
COMPONENTES SEMIRIGIDO,
HERRAMIENTA MENOR.
30
INCLUYE:
MANO
DE
OBRA
Pgina 11 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
35
67,676.64
0.08%
813,575.90
1.00%
2.6.3).-SUM., HAB.,
1,504,678.01
1.85%
38
2.6.4).-SUM., HAB.,
289,563.04
0.36%
39
2,211,615.30
2.72%
40
359,548.06
0.44%
54,490.97
0.07%
695,988.56
0.85%
5,997,136.47
7.36%
5,190,086.14
6.37%
49,368.00
0.06%
41
44
75,504.00
0.09%
46
188,100.00
0.23%
14,036.00
0.02%
5,517,094.14
6.77%
300,667.06
0.37%
Total: 3.7).-ACRILICOS $
300,667.06
0.37%
3.7).-ACRILICOS
48
Pgina 12 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
49
76,982.40
0.09%
INSULADA MARCA $
RICHARD WILCOX MED.9 X 11 MOD. 150 A RAYAS FUNCIONAMIENTO
VERTICAL LIFT
FABRICADA EN ACERO CAL. 24 DE 2 CAPAS CON
RELLENO DE POLIURETANO CON AISLAMIENTO TRMICO DE R-16-2
QUE NO PERMITE LA TRANSFERENCIA DE CALOR POR MEDIO DE
FACTOR U PARA FACIL MANTENIMIENTO DE LA TEMPERATURA
INTERNA INCLUYE: APARATO DE CADENA
50
204,053.85
0.25%
51
INSULADA MARCA $
RICHARD WILCOX MED.9 X 10 MOD. 150 A RAYAS FUNCIONAMIENTO
VERTICAL LIFT
FABRICADA EN ACERO CAL. 24 DE 2 CAPAS CON
RELLENO DE POLIURETANO CON AISLAMIENTO TRMICO DE R-16-2
QUE NO PERMITE LA TRANSFERENCIA DE CALOR POR MEDIO DE
FACTOR U PARA FACIL MANTENIMIENTO DE LA TEMPERATURA
INTERNA INCLUYE: APARATO DE CADENA
27,695.25
0.03%
52
INSULADA MARCA $
RICHARD WILCOX MED.12 X 14
MOD. 150 A RAYAS
FUNCIONAMIENTO VERTICAL LIFT
FABRICADA EN ACERO CAL. 24
DE 2 CAPAS CON RELLENO DE POLIURETANO CON AISLAMIENTO
TRMICO DE R-16-2 QUE NO PERMITE LA TRANSFERENCIA DE
CALOR POR MEDIO DE FACTOR U PARA FACIL MANTENIMIENTO
DE LA TEMPERATURA INTERNA INCLUYE: AUTOMATIZACION CON
OPERADOR MARCA LIFT MASTER MOD. MH 5011 CON BOTONERA.
110,781.00
0.14%
53
INSULADA MARCA $
RICHARD WILCOX MED.10 X 12
MOD. 150 A RAYAS
FUNCIONAMIENTO VERTICAL LIFT
FABRICADA EN ACERO CAL. 24
DE 2 CAPAS CON RELLENO DE POLIURETANO CON AISLAMIENTO
TRMICO DE R-16-2 QUE NO PERMITE LA TRANSFERENCIA DE
CALOR POR MEDIO DE FACTOR U PARA FACIL MANTENIMIENTO
DE LA TEMPERATURA INTERNA INCLUYE: APARATO DE CADENA
109,815.75
0.13%
Pgina 13 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
54
1,279,832.40
1.57%
41,877.00
0.05%
376,299.00
0.46%
114,656.85
0.14%
27,027.00
0.03%
2,369,020.50
2.91%
87,561.94
0.11%
87,561.94
0.11%
42,774.77
0.05%
55
56
2.10.5).-BASE
Bollards, Angulo
p/rampas
Pgina 14 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
61
Concepto
Importe
98,128.80
0.12%
24,134.42
0.03%
63
16,280.00
0.02%
p/rampas $
181,317.98
0.22%
10,230.00
0.01%
Metalica,
Bollards,
Angulo
Emergencia,
Rampas
8,085.00
0.01%
66
34,650.00
0.04%
2,504.70
0.00%
55,469.70
0.07%
98,846.35
0.12%
98,846.35
0.12%
26,144,334.55
32.10%
69
231,897.34
0.28%
70
2,424,388.93
2.98%
2,656,286.27
3.26%
COMO MINIMO.
67
Pgina 15 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
71
1,163,747.08
1.43%
1,163,747.08
1.43%
DE
CONCRETO,
CON
MEDIDAS
DE $
0.15x0.40mts., DE PERALTE, INCLUYE: TRAZO, EXCAVACION, AFINE,
PLANTILLA, REFORZADO CON ARMEX, CIMBRA Y DESCIMBRA
ACABADO APARENTE, CONCRETO PREMEZCLADO F'c=200kgs/cm2.,
F.N.D. (colado directo), GRAVA 3/4" (19mm.), VIBRADO, CURADO,
CARGA, ACARREO Y RETIRO DEL MATERIAL FUERA DE LA OBRA,
MANO DE OBRA Y HERRAMIENTA MENOR.
378,672.79
0.46%
28,933.91
0.04%
407,606.69
0.50%
147,259.60
0.18%
51,973.98
0.06%
153,086.99
0.19%
138,597.27
0.17%
84,070.27
0.10%
574,988.11
0.71%
6.3.1).-GUARNICIONES
73
PRODUCTO DE LA
VOLUMEN SUELTO.
77
EXCAVACION,
ARENA,
GRAVA,
CASCAJO,
79
28,516.51
0.04%
80
9,345.60
0.01%
37,862.11
0.05%
Pgina 16 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
2,310.00
0.00%
3,300.00
0.00%
5,610.00
0.01%
98,846.35
0.12%
98,846.35
0.12%
4,944,946.61
6.07%
COMO MINIMO.
Total: 4.6).-PINTURA ESMALTE [Escalera metalica & bollards]
32,857.00
0.04%
85
219,978.00
0.27%
86
68,605.90
0.08%
87
130,059.60
0.16%
88
237,288.70
0.29%
688,789.20
0.85%
217,316.00
0.27%
217,316.00
0.27%
181,016.00
0.22%
181,016.00
0.22%
426,316.00
0.52%
426,316.00
0.52%
930,979.50
1.14%
930,979.50
1.14%
Pgina 17 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
93
18,150.00
0.02%
94
8.7.2).-EXCAVACION A MAQUINA
134,763.75
0.17%
95
31,036.50
0.04%
96
232,160.50
0.29%
145,544.85
0.18%
766,307.85
0.94%
36,732.74
0.05%
71,446.91
0.09%
1,436,143.10
1.76%
60,830.00
0.07%
60,830.00
0.07%
32,709.60
0.04%
32,709.60
0.04%
PRODUCTO DE LA
VOLUMEN SUELTO.
98
EXCAVACION,
ARENA,
GRAVA,
CASCAJO,
99
100
5.8).-HERRERIA [Bollards]
102
Pgina 18 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
103
11,550.00
0.01%
11,550.00
0.01%
49,423.18
0.06%
49,423.18
0.06%
4,035,072.58
4.95%
72,721.79
0.09%
72,721.79
0.09%
72,721.79
0.09%
1,925.00
0.00%
1,925.00
0.00%
DE
CONCRETO
PREFABRICADO
DE $
1.35x1.35x1.35mts. DE PROFUNDIDAD, INCLUYE: EXCAVACION, AFINE,
PLANTILLA, CARGA, ACARREO Y RETIRO DE MATERIAL SOBRANTE
FUERA DE LA OBRA, EQUIPO, MANO DE OBRA Y HERRAMIENTA
MENOR.
2,630.20
0.00%
Total: 7.2).-REGISTRO.
2,630.20
0.00%
16,494.50
0.02%
16,494.50
0.02%
COMO MINIMO.
Total: 5.9).-PINTURA ESMALTE [Bollards]
(BALIZAMIENTO ).
7.2).-REGISTRO.
107
REG-01).-REGISTRO
Pgina 19 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
109
Concepto
Importe
MTA-01).-MURETE DE TABICON
16,445.00
0.02%
16,445.00
0.02%
2,920.50
0.00%
2,920.50
0.00%
40,415.20
0.05%
8).-INSTALACION ELECTRICA.
8.1).-INST. ACOMETIDA MEDIA TENSION [INC. 1 TRANSF. DE 1500 KVA
TIPO ESTACION, SUBESTACION COMPACTA DE 15 KV, NEMA 3R &
EQUIPO DE MEDICION]
111
648,736.00
0.80%
112
274,912.00
0.34%
113
119,038.70
0.15%
114
683,459.70
0.84%
1,726,146.40
2.12%
32,971.40
0.04%
TABLERO NQOD424L21
116
TABLERO NF424L22-S
35,090.00
0.04%
117
TABLERO QDPAC
336,369.00
0.41%
118
11,803.00
0.01%
119
3,326.40
0.00%
120
48,832.30
0.06%
121
29,949.70
0.04%
122
131,527.00
0.16%
123
411,657.40
0.51%
124
457,063.20
0.56%
125
205,370.00
0.25%
126
12,441.00
0.02%
127
205,370.00
0.25%
128
87,395.00
0.11%
2,009,165.40
2.47%
Pgina 20 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
533,933.40
0.66%
130
578,578.00
0.71%
131
65,752.50
0.08%
1,178,263.90
1.45%
420,420.00
0.52%
420,420.00
0.52%
8.5).-ALUMBRADO PERIMETRAL
133
76,230.00
0.09%
134
38,007.20
0.05%
114,237.20
0.14%
8.6).-ALUMBRADO DE EMERGENCIA
135
58,674.00
0.07%
136
36,190.00
0.04%
94,864.00
0.12%
20,535.90
0.03%
20,535.90
0.03%
20,535.90
0.03%
20,535.90
0.03%
29,937.60
0.04%
8.8).-CONTACTOS DOCKS
138
140
$
$
7,900.20
0.01%
37,837.80
0.05%
8.10).-ALUMBRADO ESTACIONAMIENTO
141
130,350.00
0.16%
142
164,670.00
0.20%
295,020.00
0.36%
20,535.90
0.03%
Pgina 21 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
20,535.90
0.03%
123,215.40
0.15%
145
99,343.20
0.12%
145
98,505.00
0.12%
321,063.60
0.39%
102,679.50
0.13%
147
12,936.00
0.02%
115,615.50
0.14%
SISTEMA DE TIERRAS
63,028.90
0.08%
63,028.90
0.08%
235,389.00
0.29%
235,389.00
0.29%
6,600.00
0.01%
151
8.7.2).-EXCAVACION A MAQUINA
39,600.00
0.05%
152
6,688.00
0.01%
153
46,790.30
0.06%
REG-01).-REGISTRO
DE
CONCRETO
PREFABRICADO
DE $
1.35x1.35x1.35mts. DE PROFUNDIDAD, INCLUYE: EXCAVACION, AFINE,
PLANTILLA, CARGA, ACARREO Y RETIRO DE MATERIAL SOBRANTE
FUERA DE LA OBRA, EQUIPO, MANO DE OBRA Y HERRAMIENTA
MENOR.
37,301.99
0.05%
155
42,768.00
0.05%
66,495.00
0.08%
246,243.29
0.30%
6,918,902.69
8.50%
PRODUCTO DE LA
VOLUMEN SUELTO.
156
EXCAVACION,
ARENA,
GRAVA,
CASCAJO,
Pgina 22 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
9).-FACHADA DE INGRESO
9.1).-FACHADA DE INGRESO
157
FACHADA DE INGRESO
275,000.00
0.34%
275,000.00
0.34%
275,000.00
0.34%
348.48
0.00%
1,829.52
0.00%
4,234.03
0.01%
3,833.28
0.00%
9,938.21
0.01%
Total: 10.1).-TERRACERIAS. $
20,183.53
0.02%
60,871.93
0.07%
60,871.93
0.07%
24,393.60
0.03%
24,393.60
0.03%
CORDENADAS.
159
PRODUCTO DE LA
VOLUMEN SUELTO.
161
EXCAVACION,
ARENA,
GRAVA,
CASCAJO,
10.2).-MURO DE CONCRETO.
163
10.3).-RAMPA DE CONCRETO.
164
11.3.1a).-SUM. Y ELAB.
Pgina 23 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
165
59,400.00
0.07%
166
4,672.80
0.01%
64,072.80
0.08%
PINTURA EN BARANDAL
4,950.00
0.01%
168
1,650.00
0.00%
6,600.00
0.01%
176,121.86
0.22%
5,122,150.00
6.29%
5,122,150.00
6.29%
5,122,150.00
6.29%
COMO MINIMO.
Total: 10.5).-PINTURA ESMALTE [Barandal & Bollards]
1,028.50
0.00%
171
866.80
0.00%
172
3,985.30
0.00%
173
13,142.80
0.02%
174
2,737.90
0.00%
175
1,837.00
0.00%
176
20,772.40
0.03%
44,370.70
0.05%
8,665.80
0.01%
178
4,169.00
0.01%
179
75,774.60
0.09%
180
34,511.40
0.04%
181
17,545.00
0.02%
182
474.10
0.00%
183
28,373.40
0.03%
184
198,088.00
0.24%
367,601.30
0.45%
Pgina 24 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
ALARMAS
411,972.00
0.51%
&
3,085.50
0.00%
186
2,600.40
0.00%
187
3,985.30
0.00%
188
62,317.20
0.08%
71,988.40
0.09%
5,874.00
0.01%
190
1,650.00
0.00%
191
5,016.00
0.01%
192
1,375.00
0.00%
193
21,450.00
0.03%
194
2,838.00
0.00%
195
5,874.00
0.01%
44,077.00
0.05%
237,837.60
0.29%
197
109,771.20
0.13%
198
39,639.60
0.05%
199
39,639.60
0.05%
200
39,639.60
0.05%
466,527.60
0.57%
3,894.00
0.00%
202
709.50
0.00%
203
1,419.00
0.00%
204
3,916.00
0.00%
205
1,958.00
0.00%
206
1,419.00
0.00%
207
2,860.00
0.00%
208
5,478.00
0.01%
Pgina 25 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
$
209
TABLERO QO320L125G
4,378.00
0.01%
210
211
319.00
0.00%
2,217.60
0.00%
212
213
21,846.00
0.03%
89,218.80
0.11%
139,632.90
0.17%
56,271.60
0.07%
215
56,271.60
0.07%
216
96,534.90
0.12%
217
2,714.80
0.00%
218
34,621.40
0.04%
219
104,781.60
0.13%
351,195.90
0.43%
40,194.00
0.05%
221
40,194.00
0.05%
222
128,620.80
0.16%
223
24,667.50
0.03%
224
ESTACION MANUAL
22,770.00
0.03%
225
114,998.40
0.14%
371,444.70
0.46%
1,444,866.50
1.77%
377,638.80
0.46%
377,638.80
0.46%
Pgina 26 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
14.2).-SISTEMA CONDUCTOR.
227
228
7,037.80
0.01%
8,747.20
0.01%
15,785.00
0.02%
146,407.80
0.18%
146,407.80
0.18%
CASO
DE
230
BOCINA DE ALERTA
5,066.60
0.01%
231
6,406.40
0.01%
232
7,653.80
0.01%
233
7,653.80
0.01%
234
CONTROL
FRECUENCIA)
(RADIO $
27,104.00
0.03%
53,884.60
0.07%
235
7,130.20
0.01%
236
36,384.39
0.04%
237
59,235.00
0.07%
102,749.59
0.13%
696,465.79
0.86%
REMOTO
COLGANTE
INDEPENDIENTE
14.5).-OBRA CIVIL
Pgina 27 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
238
Concepto
Importe
2,731,652.00
3.35%
2,731,652.00
3.35%
777,084.00
0.95%
777,084.00
0.95%
15.3).-CUARTO DE BOMBAS.
240
241
242
243
2,216,737.60
2.72%
2,216,737.60
2.72%
150,920.00
0.19%
150,920.00
0.19%
245
63,835.20
0.08%
246
AFINE DE TERRENO
8,293.12
0.01%
247
1,224.30
0.00%
15.5).-OBRA CIVIL
Pgina 28 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
248
6,270.00
0.01%
249
81,709.06
0.10%
161,331.67
0.20%
6,037,725.27
7.41%
250
941,885.56
1.16%
251
433,667.08
0.53%
252
65,034.20
0.08%
253
82,482.40
0.10%
1,523,069.24
1.87%
190,206.02
0.23%
16.2).-AREA PACKAGING
254
Pgina 29 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
255
217,144.95
0.27%
256
128,624.50
0.16%
257
13,133.12
0.02%
258
21,781.76
0.03%
570,890.34
0.70%
259
92,279.58
0.11%
260
92,279.58
0.11%
261
44,629.82
0.05%
262
78,453.17
0.10%
16.3).-AREAS ESPECIALES.
Pgina 30 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
263
110,660.40
0.14%
264
60,072.32
0.07%
265
13,385.68
0.02%
266
11,100.32
0.01%
502,860.86
0.62%
267
944,412.10
1.16%
268
42,772.90
0.05%
269
15,016.85
0.02%
270
258,930.67
0.32%
271
256,794.41
0.32%
16.4).-CAMARA FRIGORIFICA.
Pgina 31 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
272
66,664.75
0.08%
273
MATERIAL
MECANICO
DE
INTERCONEXION
EVAPORADOR- $
CONDENSADOR COMO ES TUBERIA DE COBRE RIGIDA DE 13/8" EN
SUCCION, 5/8" EN DESCARGA, AISLANTE TERMICO EN 1/2" DE
ESPESOR, CONEXIONES DE COBRE, SOPORTES, TORNILLERIA,
CARGA DE REFRIGERANTE, NITROGENO PARA PRESURIZACION,
AJUSTES Y PRUEBAS.
94,436.50
0.12%
274
52,778.88
0.06%
1,731,807.04
2.13%
4,328,627.49
5.31%
291,032.87
0.36%
Total: 17.1).-CIMENTACION $
291,032.87
0.36%
1,925,518.47
2.36%
1,925,518.47
2.36%
601,642.43
0.74%
601,642.43
0.74%
262,515.00
0.32%
29,172.00
0.04%
278
CAL.
24
COLOR $
279
44,616.00
0.05%
281
64,075.00
0.08%
Pgina 32 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
282
37,620.00
0.05%
437,998.00
0.54%
510,840.00
0.63%
510,840.00
0.63%
COLOR $
188,443.04
0.23%
285
116,820.00
0.14%
286
64,900.00
0.08%
370,163.04
0.45%
649,273.42
0.80%
6,252.35
0.01%
15,615.68
0.02%
6,012.42
0.01%
92,521.80
0.11%
72,072.00
0.09%
841,747.66
1.03%
4,978,942.46
6.11%
CAL.
24
288
2.3.2-A).-ELAB.
289
COMPONENTES SEMIRIGIDO,
HERRAMIENTA MENOR.
292
INCLUYE:
MANO
DE
OBRA
Pgina 33 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
129,347.94
0.16%
Total: 19.1).-CIMENTACION $
129,347.94
0.16%
287,086.35
0.35%
287,086.35
0.35%
111,053.16
0.14%
111,053.16
0.14%
COLOR $
57,123.00
0.07%
5,023.76
0.01%
296
297
CAL.
24
7,683.39
0.01%
299
24,062.50
0.03%
12,540.00
0.02%
106,432.65
0.13%
114,246.00
0.14%
114,246.00
0.14%
COLOR $
35,409.00
0.04%
CAL.
24
Pgina 34 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
303
43,312.50
0.05%
304
24,062.50
0.03%
102,784.00
0.13%
850,950.09
1.04%
437,515.54
0.54%
437,515.54
0.54%
842,942.43
1.03%
842,942.43
1.03%
402,379.93
0.49%
402,379.93
0.49%
126,995.57
0.16%
126,995.57
0.16%
42,075.02
0.05%
42,075.02
0.05%
Pgina 35 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
23,137.13
0.03%
23,137.13
0.03%
1,875,045.62
2.30%
71,461.94
0.09%
1,718.73
0.00%
661.75
0.00%
10,183.36
0.01%
7,886.80
0.01%
91,912.59
0.11%
103,553.73
0.13%
103,553.73
0.13%
45,754.70
0.06%
45,754.70
0.06%
312
COMPONENTES SEMIRIGIDO,
HERRAMIENTA MENOR.
315
INCLUYE:
MANO
DE
OBRA
20.2).-TRINCHERA DE CONCRETO
316
Pgina 36 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
318
37,427.72
0.05%
319
11,720.50
0.01%
49,148.22
0.06%
290,369.24
0.36%
97,010.96
0.12%
Total: 21.1).-CIMENTACION $
97,010.96
0.12%
232,190.00
0.29%
232,190.00
0.29%
208,971.00
0.26%
208,971.00
0.26%
159,500.00
0.20%
16,500.00
0.02%
176,000.00
0.22%
325
334,950.00
0.41%
326
20,350.00
0.02%
355,300.00
0.44%
21.4).-CUBIERTA DE MULTYPANEL
323
324
21.5).-MUROS DE MULTYPANEL
Pgina 37 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
19,800.00
0.02%
19,800.00
0.02%
81,400.00
0.10%
81,400.00
0.10%
17,380.00
0.02%
17,380.00
0.02%
1,188,051.95
1.46%
194,021.92
0.24%
Total: 22.1).-CIMENTACION $
194,021.92
0.24%
431,873.39
0.53%
431,873.39
0.53%
275,702.40
0.34%
275,702.40
0.34%
296,670.00
0.36%
21.7).-PUERTAS DE MULTYPANEL
328
22.4).-CUBIERTA DE MULTYPANEL
333
Pgina 38 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
334
30,184.00
0.04%
326,854.00
0.40%
335
441,910.70
0.54%
336
23,474.00
0.03%
465,384.70
0.57%
24,135.38
0.03%
24,135.38
0.03%
22.5).-MUROS DE MULTYPANEL
22.7).-PUERTAS
338
27,500.00
0.03%
Total: 22.7).-PUERTAS $
27,500.00
0.03%
26,070.00
0.03%
26,070.00
0.03%
1,771,541.79
2.18%
231,320.54
0.28%
231,320.54
0.28%
23).-PLANTA DE TRATAMIENTO
23.1).-PLANTA DE TRATAMIENTO DE 1000 GAL. DE CAP.
340
23.2).-OBRA CIVIL
341
8.7.2).-EXCAVACION A MAQUINA
4,663.73
0.01%
342
621.78
0.00%
343
PLANTILLA DE CONCRETO
4,908.75
0.01%
344
5,652.79
0.01%
1,422.30
0.00%
PRODUCTO DE LA
VOLUMEN SUELTO.
EXCAVACION,
ARENA,
GRAVA,
CASCAJO,
Pgina 39 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
346
Concepto
Importe
10,206.70
0.01%
27,476.04
0.03%
258,796.58
0.32%
PRUEBAS DE LABORATORIO
163,295.85
0.20%
163,295.85
0.20%
42,240.00
0.05%
42,240.00
0.05%
205,535.85
0.25%
384,302.27
0.47%
384,302.27
0.47%
128,100.75
0.16%
128,100.75
0.16%
128,100.75
0.16%
128,100.75
0.16%
601,685.37
0.74%
601,685.37
0.74%
16.2).-BAOS TEMPORALES
348
BAOS TEMPORALES
OBRA.
Total: 17.2).-FIANZA DEL 10% POR EL CUMPLIMIENTO DE TERMINACION DE
OBRA.
TRABAJOS REALIZADOS
Total: 17.3).-FIANZA DEL 10% POR CONCEPTO DE GARANTIA DE LOS
TRABAJOS REALIZADOS
Pgina 40 de 40
Propietario :
Ppto No. BUNGE [02] - 18/10-11
18-Oct-11
ARQ.HRCH.
PRESUPUESTO
Cdigo
Concepto
Importe
1,242,189.15
81,445,516.96
13,031,282.71
94,476,799.67 M.N.
1.53%
100.00%