Documentos de Académico
Documentos de Profesional
Documentos de Cultura
MTE03422
105-18028-MTE03422-PLN-430-C-0004
x
xxxxx
CONSTRUC. PLATAFORMA DE CONTRATISTAS Revisión: 0
ETAPA: CONSTRUCCIÓN – 105 Proyecto: 18028
Fecha : 27-06-2023
PLAN DE PRODUCCIÓN N°0004
Página : 2 de 19
105-18028-MTE03422-PLN-430-C-0004
ÍNDICE
INDICE DE IMAGENES
Imagen 1 circuito de producción planta 1................................................................................. 5
Imagen 2 circuito de producción planta 2................................................................................. 5
Imagen 3 circuito de producción planta 3................................................................................. 6
Imagen 4 circuito de producción planta 3-A ............................................................................. 7
Imagen 5 circuito de producción planta 4................................................................................. 8
Imagen 6 Histograma MOD ....................................................................................................... 8
Imagen 7 Histograma de Equipos.............................................................................................. 8
Página 2 de 19
CONSTRUC. PLATAFORMA DE CONTRATISTAS Revisión: 0
ETAPA: CONSTRUCCIÓN – 105 Proyecto: 18028
Fecha : 27-06-2023
PLAN DE PRODUCCIÓN N°0004
Página : 3 de 19
105-18028-MTE03422-PLN-430-C-0004
1. RESUMEN EJECUTIVO
2. ALCANCES Y ANTECEDENTES
Plan de Producción Consolidado Plan de Producción 1 Plan de Producción 2 Plan de Producción 3 Plan de Producción 4
Plan de Producción N° 01+02+03 Volumen Nov Dic Ene Feb Mar Abr Abr May Jun Jul Ago Set Oct Nov Dic
Filtro 2B Calcáreo 350,683 969 27,132 27,617 - 17,442 1,938 17,850 31,535 34,400 44,800 51,200 30,400 22,800 25,600 17,000
Filtro 3A Calcáreo 379,326 26,928 22,848 8,976 - 8,160 3,264 7,650 22,950 37,600 41,600 51,200 57,700 52,650 36,450 1,350
Agregado Global < 3/4# - CP 13,754 - - 3,264 - - - 2,040 5,440 600 450 600 200 500 320 340
Arena para Concreto Plástico 25,112 - - 13,940 - - - 1,530 4,080 760 900 836 750 816 900 600
Arena Hornfels 1,960 - - - - - - - - 720 190 300 300 150 300 -
Arena Mármol 6,444 - - - - - - - - 900 1,710 1,814 480 640 900 -
Grava Dren Calcárea 4,752 - - 680 - - - - 1,700 2,372 - - - - - -
Grava Hornfels 3,000 - - - - - - - - 490 650 600 500 370 390 -
MURO TEM 534,376 - - - 1,806 48,790 4,760 51,480 69,120 89,220 84,600 110,600 52,000 22,000 - -
Relleno Estructural < 4" 19,660 - - 14,535 - - - - 2,805 1,870 150 300 - - - -
Grava Dren sin lavar 5,768 1,170 2,484 816 958 240 100 -
Gravilla Hornfels 6,840 760 1,880 1,200 1,000 1,200 800 -
Global 2B ˂ 1 1/2" 4,680 600 1,000 400 500 900 480 800
TOTAL 1,356,355 27,897 49,980 69,012 1,806 74,392 9,962 80,550 137,630 171,462 180,414 219,866 144,788 102,266 66,240 20,090
146,889 86,160 218,180 905,126
Planeado
Contrato Solicitado por Comprometido
Ítem Descripción LB0*/SDC
Total Antamina Plan TRANSBAT
02 y 03
CONTRACTUAL
1.01 2B Calcareo 594,372 127,521 17,502 350,683
1.02 3A Calcareo 894,900 322,939 20,200 379,326
1.03 Relleno Estructural < 4" 365,643 49,349 0 24,520
1.04 Grava Dren Calcárea 93,852 16,659 0 4,752
1.05 Arena Marmol 10,411 1,280 0 6,444
1.06 Arena Hornfels 15,617 1,920 0 1,960
1.07 Grava Hornfels 15,617 1,920 0 3,000
1.08 Gravilla Hornfels 10,411 1,280 0 6,840
1.09 Arena Concreto Plástico 24,447 5,987 1,581 25,112
1.10 Árido <3/4" CP 14,005 3,323 1,018 13,754
1.11 Global 2B ˂ 1 1/2" 18,382 4,561 0 4,680
1.12 Arena Shotcrete
Lo solicitado por 1,103 263 0 0
1.13 Grava Huso 67
Antamina es 35,360 m3 63,440 25,137 0 0
1.14 Arena Lavada 37,205 14,968 0 0
1.15 Material 3A Almacenado 127,000 127,000 0 0
ADICIONALES
2.01 Relleno Estructural Muro TEM SDC03 35,360 0 47,623 35,360
El volumen No 3.01 Relleno Estructural Muro TEM SDC02 (W1) 340,865 0 48,881 494,156
corresponde a la 3.01 Grava Dren sinGrava
lavarDren sin Lavar 6,844 704,106 0 5,768
grava dren sin lavar Resumen
CONTRATO ORIGINAL 2,286,407 704,106 40,301 821,071
ADICIONALES 376,225 0 96,504 535,284
TOTAL 2,662,632 704,106 136,805 1,356,355
* La LB0 se encuentra en revisión, por lo que los volúmnes del Plan de Producción son referenciales
Completar campos, para la proyección al 28-dic, ya Especificar con notas a pie de cuadro que estas
se debe considerar el 100% solicitado en el RFQ cantidades corresponden a la producción real
4. PLANTAS DE PRODUCCION. registrado a la fecha más la proyección hasta la
Para la producción de filtros Calcáreos y Áridos Transbat cuenta
fecha de corte. con 3 líneas
Asimismo se solicita revisar
de producción operativas (Planta temporal, Panta W1 y Power
dichas Screen) y una
cantidades.
cuarta línea de producción en proceso de precomicionamiento y
comicionamiento a la cual denominaremos planta 4 (Planta definitiva), a
continuación, se detallan los circuitos de producción y el tipo de material que
producen
4.1. Planta 1
➢ Muro Tem
➢ Grava dren sin Lavar
➢ Estructural < 4
No coincide con el cuadro de:
Imagen 1 circuito de producción
planta 1
Página 4 de 19
CONSTRUC. PLATAFORMA DE CONTRATISTAS Revisión: 0
ETAPA: CONSTRUCCIÓN – 105 Proyecto: 18028
Fecha : 27-06-2023
PLAN DE PRODUCCIÓN N°0004
Página : 5 de 19
105-18028-MTE03422-PLN-430-C-0004
Chancadora Kleeman
(Quijada o mandibula)
Muro Tem
Grava
PLANTA 1 - A (Línea 1)
Grava sin Lavar
No coincide con la
descripción líneas
Imagen 1 circuito de producción planta 1
arriba
4.2. Planta 2 (W 1)
➢ Muro tem
Chancadora Finlay
quijada
Planta W1 TEM
Zaranda Astec
Chanccadora de cono
Kleeman
Página 5 de 19
CONSTRUC. PLATAFORMA DE CONTRATISTAS Revisión: 0
ETAPA: CONSTRUCCIÓN – 105 Proyecto: 18028
Fecha : 27-06-2023
PLAN DE PRODUCCIÓN N°0004
Página : 6 de 19
105-18028-MTE03422-PLN-430-C-0004
4.3. Planta 3
Esta planta denominada temporal cuenta con dos circuitos de producción por
lo que las denominaremos Planta 3 y Planta 3 A se encuentran ubicadas en
el sector denominado punto G, las cuales producen los siguientes agregados:
Planta 3: Corregir sangría
➢ Planta 3
➢ Material 2B
➢ Arena Mármol
➢ Arena Hornfels
➢ Arena para concreto Plástico
➢ Grava Hornfels
➢ Gravilla Hornfels
➢ Planta 3-A
• Muro Tem
Chancadora Cono HP
200 Metzo
Chancadora Meka
2B
Arena Marmol
Arena Hornfels
PLANTA 3 Arena para concreto
plástico
Grava Hornfels
Zaranda Kleeman Gravilla Hornfels
Lavadora de Finos
Página 6 de 19
CONSTRUC. PLATAFORMA DE CONTRATISTAS Revisión: 0
ETAPA: CONSTRUCCIÓN – 105 Proyecto: 18028
Fecha : 27-06-2023
PLAN DE PRODUCCIÓN N°0004
Página : 7 de 19
105-18028-MTE03422-PLN-430-C-0004
PLANTA 3 - A
Chancadora Primaria
3-A
Astec
4.4. Planta 4
➢ Arena Hornfels
➢ Arena Mármol
➢ Arena para Concreto Plástico
➢ Global 2B ˂ 1 1/2"
➢ Global 2B ˂ 3/4"
➢ Grava Hornfels
➢ Gravilla Hornfels
➢ Material 2B
➢ Material 3ª
➢ Material Grava Dren
➢ Relleno Estructural < 4"
Página 7 de 19
CONSTRUC. PLATAFORMA DE CONTRATISTAS Revisión: 0
ETAPA: CONSTRUCCIÓN – 105 Proyecto: 18028
Fecha : 27-06-2023
PLAN DE PRODUCCIÓN N°0004
Página : 8 de 19
105-18028-MTE03422-PLN-430-C-0004
Arena Hornfels
Arena Mármol
Arena para Concreto Plástico
Global 2B ˂ 1 1/2"
Global 2B ˂ 3/4"
Grava Hornfels
4 DEFINITIVA Gravilla Hornfels
Material 2B
Material 3A
Material Grava Dren
Relleno Estructural < 4"
Áridos para concreto
5.1. MOD
5.2. EQUIPOS
Página 8 de 19
CONSTRUC. PLATAFORMA DE CONTRATISTAS Revisión: 0
ETAPA: CONSTRUCCIÓN – 105 Proyecto: 18028
Fecha : 27-06-2023
PLAN DE PRODUCCIÓN N°0004
Página : 9 de 19
105-18028-MTE03422-PLN-430-C-0004
6. CONCLUSIONES
➢ El presente Plan de Producción tiene en total 869,686 m3 proyectados
producir.
➢ La producción propuesta en el presente plan tiene una desviación de
0.93 respecto a lo solicitado por Antamina.
Indicar el periodo,
asimismo verificar
cantidad, debe
coincidir con la tabla
1: consolidado del
plan de producción
Página 9 de 19
CONSTRUC. PLATAFORMA DE CONTRATISTAS Revisión: 0
ETAPA: CONSTRUCCIÓN – 105 Proyecto: 18028
Fecha : 27-06-2023
PLAN DE PRODUCCIÓN N°0004
Página : 10 de 19
105-18028-MTE03422-PLN-430-C-0004
7. ANEXOS
Página 10 de 19
CONSTRUC. PLATAFORMA DE CONTRATISTAS Revisión: 0
ETAPA: CONSTRUCCIÓN – 105 Proyecto: 18028
Fecha : 27-06-2023
PLAN DE PRODUCCIÓN N°0004
Página : 11 de 19
105-18028-MTE03422-PLN-430-C-0004
Incluir el anexo
correspondiente
(comunicación de la
solicitud)
Página 11 de 19
CONSTRUC. PLATAFORMA DE CONTRATISTAS Revisión: 0
ETAPA: CONSTRUCCIÓN – 105 Proyecto: 18028
Fecha : 27-06-2023
PLAN DE PRODUCCIÓN N°0004
Página : 12 de 19
105-18028-MTE03422-PLN-430-C-0004
Página 12 de 19
Poner leyenda que
días que dias
paran por por qué se para los
mantenimiento. dos turno, si según
comunicaciones
hechas solo paran
un turno por
mantenimiento.
porque se tiene la
mitad de Producción de
producción. Muro TEM?
Producción de
SEM 40
Muro TEM para SEM 41 SEM 42 SEM 43 SEM 44
Ratios Ratio
18-Jun
19-Jun
20-Jun
21-Jun
22-Jun
23-Jun
24-Jun
25-Jun
26-Jun
27-Jun
28-Jun
29-Jun
30-Jun
DESCRIPCIÓN Contractuales / Propuestos TIPO
10-Jul
11-Jul
12-Jul
13-Jul
14-Jul
15-Jul
16-Jul
17-Jul
18-Jul
19-Jul
20-Jul
2B?
1-Jul
2-Jul
3-Jul
4-Jul
5-Jul
6-Jul
7-Jul
8-Jul
9-Jul
SDC (m3/día) TRA (m3/día)
D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J
Planta 2: Planta W1
2,559 2,021 D 1,000 1,000 500 1,000 1,000 500 1,000 1,000 1,000 500 1,000 1,000 500 1,000 1,000 1,000 1,000 1,000 1,000 500 1,000 1,000 1,000 1,000 1,000 1,000 500 1,000 1,000 1,000 1,000 1,000
Relleno Estructural Muro TEM
N 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 500 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000
Contratactual
producciones
1,000 600 D
Arena Hornfels
N
1,600 600 D
Arena Mármol
N
1,300 600 D
Arena para Concreto Plástico
N
2,500 551 D
Global 2B ˂ 1 1/2"
N 300 300 300 300
1,600 430 D
Global 2B ˂ 3/4"
N 300 300 300
1,100 448 D 300
Grava Hornfels
N
1,000 523 D 380
Gravilla Hornfels
N
1,900 2,091 D 800 800 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200
Material 2B
N 800 800 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200
3,200 2,587 D
Material 3A
N
1,600 1,186 D 600
Material Grava Dren
N 600 600 572
3,800 300 D
Relleno Estructural < 4"
N
Adicional
1,200 1,700 D 500 1,200 1,200
Relleno Estructural Muro TEM
N 500 500 1,200
290 D
Grava Dren sin lavar
N
Por que no es Para la última
Mismos continua la semana de julio se
comentarios de la requiere este
producción? y Por material. Adelantar la
página anterios qué baja el programación
ratio???
10-Ago
11-Ago
12-Ago
13-Ago
14-Ago
15-Ago
16-Ago
17-Ago
18-Ago
19-Ago
20-Ago
21-Ago
22-Ago
23-Ago
24-Ago
25-Ago
26-Ago
27-Ago
28-Ago
29-Ago
30-Ago
31-Ago
DESCRIPCIÓN Contractuales / Propuestos TIPO
21-Jul
22-Jul
23-Jul
24-Jul
25-Jul
26-Jul
27-Jul
28-Jul
29-Jul
30-Jul
31-Jul
1-Ago
2-Ago
3-Ago
4-Ago
5-Ago
6-Ago
7-Ago
8-Ago
9-Ago
SDC (m3/día) TRA (m3/día)
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J
Planta 2: Planta W1
2,559 2,021 D 1,000 500 1,000 1,000 1,000 1,000 1,000 1,000 500 1,000 1,000 1,000 1,000 1,000 1,000 500 1,000 1,000 1,000 1,000 1,000 1,000 500 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200
Relleno Estructural Muro TEM
N 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200
Contratactual
1,000 600 D
Arena Hornfels
N
1,600 600 D
Arena Mármol
N
1,300 600 D
Arena para Concreto Plástico
N
2,500 551 D 200
Global 2B ˂ 1 1/2"
N 200 200
1,600 430 D
Global 2B ˂ 3/4"
N 150 200 200
1,100 448 D 200 200 200
Grava Hornfels
N 250
1,000 523 D 300 165 300 300 300
Gravilla Hornfels
N 300 300
1,900 2,091 D 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 800 800 800 800 800 800 800 800 800 800
Material 2B
N 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 800 800 800 800 800 800 800 800 800 800 800
3,200 2,587 D 800 800 800 800 800 800
Material 3A
N 800 800 800 800 800 800
1,600 1,186 D
Material Grava Dren
N
3,800 300 D
Relleno Estructural < 4"
N 150
Adicional
1,200 1,700 D
Relleno Estructural Muro TEM
N
290 D
Grava Dren sin lavar
N
SEM 51 SEM 52 SEM 53 SEM 54 SEM 55 SEM 56 SEM 57 SEM 58 SEM 59
Ratios Ratio
10-Oct
11-Oct
12-Oct
13-Oct
14-Oct
15-Oct
16-Oct
17-Oct
18-Oct
19-Oct
20-Oct
21-Oct
22-Oct
23-Oct
24-Oct
25-Oct
26-Oct
27-Oct
28-Oct
29-Oct
30-Oct
31-Oct
10-Set
11-Set
12-Set
13-Set
14-Set
15-Set
16-Set
17-Set
18-Set
19-Set
20-Set
21-Set
22-Set
23-Set
24-Set
25-Set
26-Set
27-Set
28-Set
29-Set
30-Set
1-Nov
2-Nov
DESCRIPCIÓN Contractuales / Propuestos TIPO
1-Oct
2-Oct
3-Oct
4-Oct
5-Oct
6-Oct
7-Oct
8-Oct
9-Oct
1-Set
2-Set
3-Set
4-Set
5-Set
6-Set
7-Set
8-Set
9-Set
SDC (m3/día) TRA (m3/día)
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J
Planta 2: Planta W1
2,559 2,021 D 1,200 1,200 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000
Relleno Estructural Muro TEM
N 1,200 1,200 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000
Contratactual
1,000 600 D
Arena Hornfels
N
1,600 600 D
Arena Mármol
N
1,300 600 D
Arena para Concreto Plástico
N
2,500 551 D
Global 2B ˂ 1 1/2"
N 200 300 200 450 450
1,600 430 D
Global 2B ˂ 3/4"
N 200 200 250 250
1,100 448 D 200 250
Grava Hornfels
N 250
1,000 523 D 300 250 250
Gravilla Hornfels
N 250 250
1,900 2,091 D 800 800 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200
Material 2B
N 800 800 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200
3,200 2,587 D 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350
Material 3A
N 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350
1,600 1,186 D
Material Grava Dren
N
3,800 300 D
Relleno Estructural < 4"
N
Adicional
1,200 1,700 D
Relleno Estructural Muro TEM
N
290 D
Grava Dren sin lavar
N 190
mismos
comentarios de
Hoja anterior.
10-Nov
11-Nov
12-Nov
13-Nov
14-Nov
15-Nov
16-Nov
17-Nov
18-Nov
19-Nov
20-Nov
21-Nov
22-Nov
23-Nov
24-Nov
25-Nov
26-Nov
27-Nov
28-Nov
29-Nov
30-Nov
10-Dic
11-Dic
12-Dic
13-Dic
14-Dic
15-Dic
16-Dic
17-Dic
18-Dic
19-Dic
20-Dic
21-Dic
22-Dic
23-Dic
24-Dic
DESCRIPCIÓN Contractuales / Propuestos TIPO
3-Nov
4-Nov
5-Nov
6-Nov
7-Nov
8-Nov
9-Nov
1-Dic
2-Dic
3-Dic
4-Dic
5-Dic
6-Dic
7-Dic
8-Dic
9-Dic
SDC (m 3/día) TRA (m 3/día)
V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D
Planta 2: Planta W1
2,559 2,021 D
Relleno Estructural Muro TEM
N
Contratactual
1,000 600 D
Arena Hornfels
N 300
1,600 600 D 300
Arena Mármol
N 300 300
1,300 600 D 300 300
Arena para Concreto Plástico
N 300 300 300
2,500 551 D 160
Global 2B ˂ 1 1/2"
N 160 160 400 400
1,600 430 D 160 170
Global 2B ˂ 3/4"
N 160 170
1,100 448 D 195
Grava Hornfels
N 195
1,000 523 D 200 200
Gravilla Hornfels
N 200 200
1,900 2,091 D 1,000 800 800 800 800 800 1,000 800 1,000 1,000 1,000 1,000 1,000 800 800 800 800 900 900 900 900 900
Material 2B
N 800 800 800 800 1,000 800 800 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 800 800 800 800 900 900 900 900 900 800 800
3,200 2,587 D 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350
Material 3A
N 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350 1,350
1,600 1,186 D
Material Grava Dren
N
3,800 300 D
Relleno Estructural < 4"
N
Adicional
1,200 1,700 D
Relleno Estructural Muro TEM
N
290 D
Grava Dren sin lavar
N 100
CONSTRUC. PLATAFORMA DE CONTRATISTAS Revisión: 0
ETAPA: CONSTRUCCIÓN – 105 Proyecto: 18028
Fecha : 27-06-2023
PLAN DE PRODUCCIÓN N°0004
Página : 17 de 19
105-18028-MTE03422-PLN-430-C-0004
Página 17 de 19
Total Requerido (Jun-Dic 2023)
Arena para Concreto Plástico 623.00 1,499.00 2,176.00 2,872.00 3,742.00 4,438.00 5,134.00
Material Grava Dren 2,121.00 2,121.00 2,121.00 2,121.00 2,121.00 2,121.00 2,121.00
Relleno Estructural < 4" 0.00 139.00 417.00 417.00 417.00 417.00 417.00
Adicional
Relleno Estructural Muro TEM 73,375.00 175,539.00 252,610.00 329,206.00 360,667.00 366,481.00 366,481.00
Grava Dren sin lavar 1,002.00 3,146.00 4,736.00 6,024.00 6,508.00 6,594.00 6,594.00
Total Producción
Arena para Concreto Plástico 760.00 1,660.00 2,496.00 3,246.00 4,062.00 4,962.00 5,562.00
Material Grava Dren 0.00 2,372.00 2,372.00 2,372.00 2,372.00 2,372.00 2,372.00
Relleno Estructural < 4" 0.00 450.00 450.00 450.00 450.00 450.00 450.00
Adicional
Relleno Estructural Muro TEM 91,584.00 200,434.00 298,534.00 350,534.00 381,534.00 381,534.00 381,534.00
Grava Dren sin lavar 2,065.00 5,146.00 5,770.00 6,488.00 6,968.00 7,068.00 7,068.00
Arena para Concreto Plástico 137.00 161.00 320.00 374.00 320.00 524.00 428.00
Material Grava Dren -2,121.00 251.00 251.00 251.00 251.00 251.00 251.00
Relleno Estructural < 4" 0.00 311.00 33.00 33.00 33.00 33.00 33.00
Adicional
Relleno Estructural Muro TEM 18,209.00 24,895.00 45,924.00 21,328.00 20,867.00 15,053.00 15,053.00
Grava Dren sin lavar 1,063.00 2,000.00 1,034.00 464.00 460.00 474.00 474.00
Adjuntar el excel
CONSTRUC. PLATAFORMA DE CONTRATISTAS Revisión: 0
ETAPA: CONSTRUCCIÓN – 105 Proyecto: 18028
Fecha : 27-06-2023
PLAN DE PRODUCCIÓN N°0004
Página : 19 de 19
105-18028-MTE03422-PLN-430-C-0004
Página 19 de 19
JUN JUL AGO SET OCT NOV DIC
SEM 40 SEM 41 SEM 42 SEM 43 SEM 44 SEM 45 SEM 46 SEM 47 SEM 48 SEM 49 SEM 50 SEM 51 SEM 52 SEM 53 SEM 54 SEM 55 SEM 56 SEM 57 SEM 58 SEM 59 SEM 60 SEM 61 SEM 62 SEM 63 SEM 64 SEM 65 SEM 66 SEM 67 SEM 68
CANT. CANT.
ITEM DESCRIPCION CONTRACTUAL PLANEADA
16-Jun 23-Jun 30-Jun 7-Jul 14-Jul 21-Jul 28-Jul 4-Ago 11-Ago 18-Ago 25-Ago 1-Set 8-Set 15-Set 22-Set 29-Set 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dic 8-Dic 15-Dic 22-Dic 29-Dic
22-Jun 29-Jun 6-Jul 13-Jul 20-Jul 27-Jul 3-Ago 10-Ago 17-Ago 24-Ago 31-Ago 7-Set 14-Set 21-Set 28-Set 5-Oct 12-Oct 19-Oct 26-Oct 2-Nov 9-Nov 16-Nov 23-Nov 30-Nov 7-Dic 14-Dic 21-Dic 28-Dic 31-Dic
1 PLANTA 1
1.1 OP. Volquete 9 9 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18
1.2 OP. Cargador 3 3 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
1.3 OP. Tractor 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
1.4 OP. Cisterna 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
1.5 Operador de planta 4 2 4 4 4 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
1.6 Oficial 1 1 2 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1.7 Ayudante 4 3 6 6 6 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
1.8 Capataz 4 4 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
1.9 Vigia 14 8 16 16 16 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14
2 PLANTA 2 (SDC - W1)
2.1 OP. Volquete 3 3 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
2.2 OP. Cargador 3 3 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
2.3 OP. Tractor 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2.4 OP. Cisterna 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2.5 Operador de planta 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2.6 Oficial
2.7 Ayudante (Peon) 3 3 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
2.8 Capataz 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2.9 Vigia / Cuadrador 7 7 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14
3 PLANTA 3
3.1 OP. Volquete
3.2 OP. Cargador
3.3 OP. Tractor
3.4 OP. Cisterna
3.5 Operador de planta 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
3.6 Oficial
3.7 Peón 3 3 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
3.8 Capataz 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
3.9 Vigia / Cuadrador 7 7 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14
4 PLANTA 4
4.1 OP. Volquete
4.2 OP. Cargador 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
4.3 OP. Tractor
4.4 OP. Cisterna
4.5 Operador de planta 2 4 4 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
4.6 Oficial
4.7 Ayudante 2 4 4 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
4.8 Capataz 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
4.9 Vigia 6 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12
TOTAL 74 77 154 154 154 149 149 149 149 149 149 149 149 149 149 149 149 149 149 149 149 149 149 149 149 149 149 149 149 149 149
160
Que recursos se
van a compartir 140
MOD
120
100
SEM 40 SEM 41 SEM 42 SEM 43 SEM 44 SEM 45 SEM 46 SEM 47 SEM 48 SEM 49 SEM 50 SEM 51 SEM 52 SEM 53 SEM 54 SEM 55 SEM 56 SEM 57 SEM 58 SEM 59 SEM 60 SEM 61 SEM 62 SEM 63 SEM 64 SEM 65 SEM 66 SEM 67 SEM 68
SEMANAS
Incluir la MOI
0
Incluir los equipos de
producción
50
Que recursos se
van a compartir
EQP
30
10
SEM 40 SEM 41 SEM 42 SEM 43 SEM 44 SEM 45 SEM 46 SEM 47 SEM 48 SEM 49 SEM 50 SEM 51 SEM 52 SEM 53 SEM 54 SEM 55 SEM 56 SEM 57 SEM 58 SEM 59 SEM 60 SEM 61 SEM 62 SEM 63 SEM 64 SEM 65 SEM 66 SEM 67 SEM 68
SEMANAS