PROYECTO: : "LIMPIEZA, DESCOLMATACION Y ENROCADO DEL SECTOR TRNCOSO DEL DISTRITO DE ASCENSION AFECTADOS POR LAS LLUVIAS INTENSAS PERIODO ENERO - ABRIL DEL AÑO
2023"
EMPRESA : CONSTRUCTORA & CONSULTORA INGARACH
DEPARTAMENTO : HUANCAVELICA
PROVINCIA : HUANCAVELICA
DISTRITO : ASCENSION
SECTOR : TRONCOSO
TIEMPO DE
EJECUCION : 30 DIAS CALENDARIOS
02.01 DESCOLMATACION DEL RIO ICHU L=225m M3 1,215.00 13.86 16,839.90 1,215.00 16,839.90 100.00%
03.00 REFORZAMIENTO DE DEFENSA RIBEREÑA CON ENROCADO 274,638.42
03.01 EXCAVACION PARA ENROCADO M3 1,440.00 13.55 19,512.00 1,440.00 19,512.00 100.00%
03.02 REFORZAMIENTO DE DEFENSA RIBEREÑA CON ENROCADO M3 2,880.00 79.99 230,371.20 2,880.00 230,371.20 100.00%
03.03 ELIMINACION DE MATERIAL EXCEDENTE M3 3,186.00 7.77 24,755.22 3,186.00 24,755.22 100.00%
COSTO DIRECTO S/ 294,421.90 S/ 294,421.90 100.00%
UTILIDAD 6.5% S/ 19,137.42 S/ 19,137.42
SUB TOTAL S/ 313,559.32 S/ 313,559.32
IGV 18.00% S/ 56,440.68 S/ 56,440.68
MONTO TOTAL S/ 370,000.00 S/ 370,000.00 100.00%
CONSORCIO INGARACH GOBIERNO REGIONAL DE JUNIN
DIRECCION REGIONAL DE TRANSPORTE Y COMUNICACIONES
SERVICIO : CONTRATACIÓN DEL SERVICIO DE EJECUCIÓN DEL MANTENIMIENTO PERIÓDICO EN LA VÍA DEPARTAMENTAL RUTA JU-102, TRAMO: SAN
JOSE DE ANDAYCHAGUA - HUAY HUAY – EMP. PE-3S (HUARI) L=30.12 KM.
EMPRESA : CONSTRUCTORA & CONSULTORA INGARACH
DEPARTAMENTO : JUNIN
PROVINCIA : YAULI
DISTRITO : HUAY HUAY, LA OROYA
TIEMPO DE
EJECUCION : 99 DIAS CALENDARIOS
90.0%
80.0%
70.0%
AVANCE MENSUAL ACUMULADO (%)
60.0%
50.0%
40.0%
PROGRAMADO
EJECUTADO
30.0%
20.0%
10.0%
0.00%
0.00%
0.0%
13/11/2023 23/11/2023
METRADO PLAN DE TRABAJO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO
ITEM PARTIDAS
Und. Metrado Precio S/. Parcial S/. Metrado Precio S/. % Metrado Precio S/. % Metrado Precio S/. % Metrado Precio S/. %
01.00 TRABAJOS PRELIMINARES 2,943.58
01.01 MOVILIZACION Y DEMOVILIZACION DE MAQUINARIA GLB 1.00 2,493.47 2,493.47 1.00 2,493.47 100.00% 1.00 2,493.47 100.00% 0.00 0.00
01.02 SEÑALIZACION PREVENTIVA DURANTE LA INTERVENCION GLB 1.00 450.11 450.11 1.00 450.11 100.00% 1.00 450.11 100.00% 0.00 0.00
02.01 DESCOLMATACION DEL RIO ICHU L=225m M3 1,215.00 13.86 16,839.90 1,215.00 16,839.90 100.00% 1,215.00 16,839.90 100.00% 0.00 0.00
03.00 REFORZAMIENTO DE DEFENSA RIBEREÑA CON ENROCADO 274,638.42
03.01 EXCAVACION PARA ENROCADO M3 1,440.00 13.55 19,512.00 1,440.00 19,512.00 100.00% 1,440.00 19,512.00 100.00% 0.00 0.00
03.02 REFORZAMIENTO DE DEFENSA RIBEREÑA CON ENROCADO M3 2,880.00 79.99 230,371.20 2,880.00 230,371.20 100.00% 2,880.00 230,371.20 100.00% 0.00 0.00
03.03 ELIMINACION DE MATERIAL EXCEDENTE M3 3,186.00 7.77 24,755.22 3,186.00 24,755.22 100.00% 3,186.00 24,755.22 100.00% 0.00 0.00
COSTO DIRECTO S/ 294,421.90 S/ - 0.00% S/ 294,421.90 100.00% 294,421.90 100.00% 0.00 0.00%
UTILIDAD 6.5% S/ 19,137.42 S/ - S/ 19,137.42 19,137.42 0.00
SUB TOTAL S/ 313,559.32 S/ - S/ 313,559.32 313,559.32 0.00
IGV 18.00% S/ 56,440.68 S/ - S/ 56,440.68 56,440.68 0.00
MONTO TOTAL S/ 370,000.00 S/ - 0.00% S/ 370,000.00 100.00% 370,000.00 100.00% 0.00 0.00%
RESUMEN DE VALORIZACION Nº 01
PROYECTO:
: "LIMPIEZA, DESCOLMATACION Y ENROCADO DEL SECTOR TRNCOSO DEL DISTRITO DE ASCENSION AFECTADOS POR LAS LLUVIAS INTENSAS PERIODO ENERO - ABRIL DEL AÑO 2023"
EMPRESA : CONSORCIO VIAL SAN JOSE
DEPARTAMENTO : HUANCAVELICA
PROVINCIA : HUANCAVELICA
DISTRITO : ASCENSION
SECTOR : TRONCOSO
TIEMPO DE EJECUCION : 30 DIAS CALENDARIOS
MONTO % SALDO
VALORIZACION
DESCRIPCION CONTRATO AVANCE POR
(s/IGV) ANTERIOR ACTUAL ACUMULADO ACUMULADO VALORIZAR
A: VALORIZACION CONTRACTUAL
CONTRATO PRINCIPAL 313,559.32 - 313,559.32 313,559.32 100.00% 0.00
TOTAL (A) 313,559.32 - 313,559.32 313,559.32 0.00
B: REAJUSTES
CONTRATO PRINCIPAL - - -
TOTAL (B) - - -
C: DEDUCCIONES
DEDUCCION DEL ADELANTO DIRECTO - - -
DEDUCCION DEL ADELANTO POR MATERIALES - - -
TOTAL (C) - - -
D: AMORTIZACIONES
AMORTIZACION DEL ADELANTO DIRECTO 0.00 - - - 0.00
AMORTIZACION DEL ADELANTO DE MATERIALES 0.00 - - - 0.00
TOTAL (D) 0.00 - - - 0.00
E: PENALIDADES
Cláusula Décimo Sexta: Penalidades
Acceso al cuaderno de obra
Seguridad en obra (EPP) y salud ocupacional - señalizacion en obra
Mala calidad de materiales
No presenta el cronograma valorizado al inicio contractual
No realiza pruebas de calidad
Uso de materiales sin ensayos de calidad
Ausencia del personal profesional ofertado en obra
No cumple con equipamiento mínimo ofertado
Actos dolosos
Valorización extemporánea
TOTAL (F) 0.00 0.00 0.00