PROYECTO VIVIENDA - FC Classic Schedule Layout 23-Abr-23 09:31

ID de actividad Calendario Nombre de actividad Duración Costo total en Costo de gastos en Costo de mano de Costo de Costo de materiales Inicio Finalización Abr 09 Abr 16 Abr 23 Abr 30 May 07 May 14 May 21
original finalización finalización obra en finalización equipamiento en en finalización Dom Lun Mar Mié Jue Vie Sáb Dom Lun Mar Mié Jue Vie Sáb Dom Lun Mar Mié Jue Vie Sáb Dom Lun Mar Mié Jue Vie Sáb Dom Lun Mar Mié Jue Vie Sáb Dom Lun Mar Mié Jue Vie Sáb Dom Lun Mar Mié Jue Vie Sáb
finalización
Corporate-- Standard
PROYECTO VIVIENDA FC Full Time 32d S/.35,448.50 S/.2,000.00 S/.16,728.00 S/.690.00 S/.16,030.50 10-Abr-23 24-May-23 32d

ETAPA 1 Corporate - Standard Full Time 19d S/.27,256.00 S/.1,330.00 S/.10,456.00 S/.690.00 S/.14,780.00 10-Abr-23 05-May-23 19d

T-1 Corporate - Standard Full Time Limpieza de Terreno 3d S/.1,617.00 S/.150.00 S/.717.00 S/.240.00 S/.510.00 10-Abr-23 12-Abr-23 3d
T-2 Corporate - Standard Full Time Cimientos 10d S/.16,380.00 S/.800.00 S/.6,235.00 S/.450.00 S/.8,895.00 13-Abr-23 26-Abr-23 10d
T-3 Corporate - Standard Full Time Levantar Estructura 4d S/.8,599.00 S/.280.00 S/.2,944.00 S/.0.00 S/.5,375.00 27-Abr-23 03-May-23 4d
T-4 Corporate - Standard Full Time Secado 2d S/.660.00 S/.100.00 S/.560.00 S/.0.00 S/.0.00 04-May-23 05-May-23 2d
ETAPA 2 Corporate - Standard Full Time 9d S/.6,505.50 S/.500.00 S/.5,608.00 S/.0.00 S/.397.50 08-May-23 18-May-23 9d

T-5 Corporate - Standard Full Time Acabado de Exteriores 5d S/.4,336.50 S/.300.00 S/.3,800.00 S/.0.00 S/.236.50 08-May-23 12-May-23 5d
T-6 Corporate - Standard Full Time Instalaciones 2d S/.948.00 S/.100.00 S/.848.00 S/.0.00 S/.0.00 15-May-23 16-May-23 2d
T-7 Corporate - Standard Full Time Acabado de Interiores 2d S/.1,221.00 S/.100.00 S/.960.00 S/.0.00 S/.161.00 17-May-23 18-May-23 2d
ETAPA 3 Corporate - Standard Full Time 4d S/.1,687.00 S/.170.00 S/.664.00 S/.0.00 S/.853.00 19-May-23 24-May-23 4d

T-8 Corporate - Standard Full Time Pintado 3d S/.1,546.50 S/.120.00 S/.576.00 S/.0.00 S/.850.50 19-May-23 23-May-23 3d
T-9 Corporate - Standard Full Time Jardineria 1d S/.140.50 S/.50.00 S/.88.00 S/.0.00 S/.2.50 24-May-23 24-May-23 1d

Actual Level of Effort Remaining Work Milestone Page 1 of 1 TASK filter: Todas las actividades
Actual Work Critical Remaining Work summary © Oracle Corporation