CONTROL DE VACIADOS DE CONCRETO

PROYECTO: MEJORAMIENTO Y SUSTITUCION DE LA INFRAESTRUCTURA EDUCATIVA DE LA INSTITUCION EDUCATIVA "41041 CRISTO REY"
UBICACION: Distrito CAMANA - Provincia CAMANA - Departamento AREQUIPA
CLIENTE: CONSORCIO INGENIEROS

f´c Slump f'c f'c f'c Resultados / HOY


# Fecha Elemento Ubicación Prob.
(kg/cm2) (pulg) (7 días) (14 días) (28 días) Observaciones 7/2/2023
1 3/30/2017 SZ PAB#4 EJE7 / K-N 100 3 6-Apr 13-Apr 27-Apr 2285
2 3/31/2017 SZ PAB#1 EJE16 / M-N 100 2 7-Apr 14-Apr 28-Apr 2284
3 4/4/2017 SZ PAB#3 EJE9 / L-N 100 3 11-Apr 18-Apr 2-May 2280
4 4/5/2017 SZ PAB#2 EJE13 / L-N 100 3 12-Apr 19-Apr 3-May 2279
5 4/6/2017 SZ PAB#2 EJE12 / L-N 100 3 13-Apr 20-Apr 4-May 2278
6 4/7/2017 Z PAB#5 EJE3 / K-N 210 2" - 4" 3 14-Apr 21-Apr 5-May 2277
7 4/10/2017 Z PAB#5 EJE2 / K-N 210 2" - 4" 3 17-Apr 24-Apr 8-May f 'c1=203.80 2274
8 4/10/2017 Z PAB#1 EJE16 / M-N 210 2" - 4" 3 17-Apr 24-Apr 8-May 2274
9 4/12/2017 Z PAB#1 EJE17 / M-N 210 2" - 4" 3 19-Apr 26-Apr 10-May 2272
10 4/13/2017 Z PAB#4 EJE6 / L-N 210 2" - 4" 3 20-Apr 27-Apr 11-May 2271
11 4/15/2017 Z PAB#4 EJE7 / L-N 210 2" - 4" 3 22-Apr 29-Apr 13-May 2269
12 4/17/2017 VC PAB#5 EJE2-3 / K-D 280 2" - 4" 3 24-Apr 1-May 15-May f 'c1=148.1 2267
13 4/18/2017 CC PAB#1 EJE16Y17 / M-N 140 2" - 4" 3 25-Apr 2-May 16-May f 'c1=64.2 2266
14 4/27/2017 CC PAB#1 EJE16Y17 / M-N 140 2" - 4" 3 4-May 11-May 25-May 2257
17 4/29/2017 VC PAB#1 EJE17-16 / E-N 280 2" - 4" 3 6-May 13-May 27-May 2255
18 5/2/2017 Z PAB#3 EJE8 / L-N 210 2" - 4" 3 9-May 16-May 30-May 2252

SZ : Subzapata C: Columna
Z: Zapata P: Placa
CC : Cimentación LM: Losa Maciza
VC: Viga Cimentacion LA: Losa Aligerada
CONTROL DE VACIADOS DE CONCRETO

PROYECTO: MEJORAMIENTO Y SUSTITUCION DE LA INFRAESTRUCTURA EDUCATIVA DE LA INSTITUCION EDUCATIVA "41041 CRISTO REY"
UBICACION: Distrito CAMANA - Provincia CAMANA - Departamento AREQUIPA
CLIENTE: CONSORCIO INGENIEROS

Slump f'c HOY


# Fecha Vaciado Elemento Ubicación f´c (kg/cm2) PROB Fecha Rotura Edad % OBSERVACION
(pulg) (28 días) 7/2/2023
1 3/30/2017 SZ PAB#4 EJE7 / K-N 100 2" - 4" 1 102.10 5/11/2017 42 102%
SZ PAB#4 EJE7 / K-N 100 2" - 4" 1 105.60 5/11/2017 42 106%
2 4/4/2017 SZ PAB#3 EJE9 / L-N 100 2" - 4" 1 127.50 5/23/2017 49 128%
3 4/5/2017 SZ PAB#2 EJE13 / L-N 100 2" - 4" 1 103.30 5/23/2017 48 103%
4 4/6/2017 SZ PAB#2 EJE12 / L-N 100 2" - 4" 1 89.30 5/23/2017 47 89%
SZ PAB#2 EJE12 / L-N 100 2" - 4" 1 88.10 5/23/2017 47 88%
5 4/7/2017 Z PAB#5 EJE2 / K-N 210 2" - 4" 1 236.50 5/5/2017 28 113%
Z PAB#5 EJE2 / K-N 210 2" - 4" 1 168.70 5/5/2017 28 80%
Z PAB#5 EJE2 / K-N 210 2" - 4" 1 195.70 5/5/2017 28 93%
6 4/10/2017 Z PAB#5 EJE2 / K-N 210 2" - 4" 1 203.20 4/25/2017 15 97%
Z PAB#5 EJE2 / K-N 210 2" - 4" 1 235.70 5/11/2017 31 112%
Z PAB#5 EJE2 / K-N 210 2" - 4" 1 233.20 5/11/2017 31 111%
7 4/10/2017 Z PAB#1 EJE16 / M-N 210 2" - 4" 1 285.00 5/11/2017 31 136%
Z PAB#1 EJE16 / M-N 210 2" - 4" 1 272.40 5/11/2017 31 130%
8 4/12/2017 Z PAB#1 EJE17 / M-N 210 2" - 4" 2272
9 4/13/2017 Z PAB#4 EJE6 / L-N 210 2" - 4" 1 136.70 5/23/2017 40 65% ESCLEROMETRO POSITIVO
Z PAB#4 EJE6 / L-N 210 2" - 4" 1 137.00 5/23/2017 40 65% ESCLEROMETRO POSITIVO
10 4/15/2017 Z PAB#4 EJE7 / L-N 210 2" - 4" 1 197.90 5/23/2017 38 94%
Z PAB#4 EJE7 / L-N 210 2" - 4" 1 222.50 5/23/2017 38 106%
11 4/17/2017 VC PAB#5 EJE2-3 / K-D 280 2" - 4" 1 147.50 4/25/2017 8 53% ESCLEROMETRO POSITIVO
VC PAB#5 EJE2-3 / K-D 280 2" - 4" 1 207.70 5/23/2017 36 74% ESCLEROMETRO POSITIVO
VC PAB#5 EJE2-3 / K-D 280 2" - 4" 1 200.90 5/23/2017 36 72% ESCLEROMETRO POSITIVO
12 4/18/2017 CC PAB#1 EJE16Y17 / M-N 140 2" - 4" 1 64.00 4/25/2017 7 46% ESCLEROMETRO NO HAY
CC PAB#1 EJE16Y17 / M-N 140 2" - 4" 1 112.50 4/25/2017 7 80%
13 4/27/2017 CC PAB#1 EJE16Y17 / M-N 140 2" - 4" 2257
14 4/29/2017 VC PAB#1 EJE16Y17 / E-N 280 2" - 4" 1 94.10 5/5/2017 6 34% ESCLEROMETRO NO HAY
VC PAB#1 EJE16Y17 / E-N 280 2" - 4" 1 110.40 5/5/2017 6 39% ESCLEROMETRO NO HAY
VC PAB#1 EJE16Y17 / E-N 280 2" - 4" 1 108.90 5/5/2017 6 39% ESCLEROMETRO NO HAY
15 5/2/2017 Z PAB#3 EJE8 / L-N 210 2" - 4" 2252
16 5/3/2017 Z PAB#2 EJE12 / L-N 210 2" - 4" 1 107.30 5/23/2017 20 51% ESCLEROMETRO POSITIVO
Z PAB#2 EJE12 / L-N 210 2" - 4" 1 114.10 5/23/2017 20 54% ESCLEROMETRO POSITIVO
17 5/6/2017 VC PAB#1 EJE17-16 / M-E 280 2" - 4" 1 164.50 5/11/2017 5 59%
VC PAB#1 EJE17-16 / M-E 280 2" - 4" 1 263.30 5/23/2017 17 94%
VC PAB#1 EJE17-16 / M-E 280 2" - 4" 1 244.30 5/23/2017 17 87%
18 5/8/2017 Z PAB#3 EJE8 / L 210 2" - 4" 1 145.70 5/23/2017 15 69%
Z PAB#3 EJE8 / L 210 2" - 4" 1 131.10 5/23/2017 15 62%
19 5/9/2017 Z PAB#2 EJE13 / L-N 210 2" - 4" 1 214.20 5/23/2017 14 102%
Z PAB#2 EJE13 / L-N 210 2" - 4" 1 242.10 6/13/2017 35 115%
Z PAB#2 EJE13 / L-N 210 2" - 4" 1 2245
20 5/10/2017 SC PAB#1 EJE M-N C:H 1:8 + 25% PM 2" - 4" 1 70.59 5/23/2017 13 50%
SC PAB#1 EJE M-N C:H 1:8 + 25% PM 2" - 4" 1 193.50 6/13/2017 34 138%
21 5/10/2017 Z PAB#2 EJE13 / L-N 210 2" - 4" 1 200.50 6/13/2017 34 95%
22 5/12/2017 VC PAB#3 EJE8-9 / E-N 280 2" - 4" 1 210.30 5/23/2017 11 75%
VC PAB#3 EJE8-9 / E-N 280 2" - 4" 1 193.20 6/13/2017 32 69%
VC PAB#3 EJE8-9 / E-N 280 2" - 4" 1 2242
23 5/19/2017 VC PAB#3 EJE8-9 / L-D 280 2" - 4" 1 250.90 6/13/2017 25 90%
VC PAB#3 EJE8-9 / L-D 280 2" - 4" 1 2235
VC PAB#3 EJE8-9 / L-D 280 2" - 4" 1 2235
24 5/20/2017 Z PAB#4 EJE7 / F-N 210 2" - 4" 1 183.60 6/13/2017 24 87%
Z PAB#4 EJE7 / F-N 210 2" - 4" 1 2234
Z PAB#4 EJE7 / F-N 210 2" - 4" 1 2234
25 5/20/2017 CC PAB#4 EJE 7 / L-D Y A Y B 140 2" - 4" 1 62.80 6/13/2017 24 45%
CC PAB#4 EJE 7 / L-D Y A Y B 140 2" - 4" 1 2234
CC PAB#4 EJE 7 / L-D Y A Y B 140 2" - 4" 1 2234
26 5/21/2017 VC PAB#2 EJE13-12/ E-N 280 2" - 4" 1 268.80 6/13/2017 23 96%
VC PAB#2 EJE13-12/ E-N 280 2" - 4" 1 2233
VC PAB#2 EJE13-12/ E-N 280 2" - 4" 1 2233
26 5/22/2017 VC PAB#02 (L-D) Y #05(E-N) 280 2" - 4" 1 279.70 6/13/2017 22 100%
VC PAB#02 (L-D) Y #05(E-N) 280 2" - 4" 1 2232
VC PAB#02 (L-D) Y #05(E-N) 280 2" - 4" 1 2232
26* 5/22/2017 VC PAB#02 (L-D) Y #05(E-N) 280 2" - 4" 3 2232
27 5/23/2017 SC PAB#3 Y 2 EJES L-D C:H 1:8 + 25% PM 2" - 4" 1 189.30 6/13/2017 21 135%
SC PAB#3 Y 2 EJES L-D C:H 1:8 + 25% PM 2" - 4" 1 2231
SC PAB#3 Y 2 EJES L-D C:H 1:8 + 25% PM 2" - 4" 1 2231
28 5/24/2017 VC PAB#04 EJE7Y6 / K-N 280 2" - 4" 1 237.90 6/13/2017 20 85%
VC PAB#04 EJE7Y6 / K-N 280 2" - 4" 1 2230
VC PAB#04 EJE7Y6 / K-N 280 2" - 4" 1 2230
29 5/25/2017 VC PAB#4 EJE 7 / F-N, A Y B 280 2" - 4" 1 184.30 6/13/2017 19 66%
VC PAB#4 EJE 7 / F-N, A Y B 280 2" - 4" 1 2229
VC PAB#4 EJE 7 / F-N, A Y B 280 2" - 4" 1 2229
30 5/25/2017 SC PAB#5 EJE 3Y2 / K-N C:H 1:8 + 25% PM 2" - 4" 1 84.50 6/13/2017 19 60%
SC PAB#5 EJE 3Y2 / K-N C:H 1:8 + 25% PM 2" - 4" 1 2229
SC PAB#5 EJE 3Y2 / K-N C:H 1:8 + 25% PM 2" - 4" 1 2229
31 5/26/2017 SC PAB#04 EJE7Y6 / L-N 210 2" - 4" 1 238.90 6/13/2017 18 114%
SC PAB#04 EJE7Y6 / L-N 210 2" - 4" 1 2228
32 5/27/2017 C PAB#1 (A,C,F,H,J/17Y16) Y #2(A/13) 210 2" - 4" 1 337.80 6/13/2017 17 161%
C PAB#1 (A,C,F,H,J/17Y16) Y #2(A/13) 210 2" - 4" 1 2227
C PAB#1 (A,C,F,H,J/17Y16) Y #2(A/13) 210 2" - 4" 1 2227
33 5/29/2017 C PAB#2 (A,C,F,H,J/13) Y #3(A,C,F,H,J/9) 210 2" - 4" 1 340.00 6/13/2017 15 162%
C PAB#2 (A,C,F,H,J/13) Y #3(A,C,F,H,J/9) 210 2" - 4" 1 2225
34 5/29/2017 SZ POLIDEPORTIVO 100 2" - 4" 1 64.90 6/13/2017 15 65%
SZ POLIDEPORTIVO 100 2" - 4" 1 2225
35 5/30/2017 C PAB#2 (A,C,F,H,J/12) Y #3(A,C,F,H,J/8) 210 2" - 4" 1 240.50 6/13/2017 14 115%
C PAB#2 (A,C,F,H,J/12) Y #3(A,C,F,H,J/8) 210 2" - 4" 1 2224
C PAB#2 (A,C,F,H,J/12) Y #3(A,C,F,H,J/8) 210 2" - 4" 1 2224
36 5/31/2017 C PAB#5 (A,C/3Y2) 210 2" - 4" 1 348.30 6/13/2017 13 166%
C PAB#5 (A,C/3Y2) 210 2" - 4" 1 2223
C PAB#5 (A,C/3Y2) 210 2" - 4" 1
37 6/1/2017 C PAB#4 (H,J/6Y7), #5(F,H,J/2Y3) 210 2" - 4" 1 326.30 6/13/2017 12 155%
C PAB#4 (H,J/6Y7), #5(F,H,J/2Y3) 210 2" - 4" 1 2222
C PAB#4 (H,J/6Y7), #5(F,H,J/2Y3) 210 2" - 4" 1 2222
38 6/2/2017 C PAB#4 (C,F/6Y7) 210 2" - 4" 1 259.70 6/13/2017 11 124%
C PAB#4 (C,F/6Y7) 210 2" - 4" 1 2221
C PAB#4 (C,F/6Y7) 210 2" - 4" 1 2221
39 6/12/2017 C PAB#1 (M,B,E,G,I,N/17Y16) 210 2" - 4" 1 2211
C PAB#1 (M,B,E,G,I,N/17Y16) 210 2" - 4" 1 2211
C PAB#1 (M,B,E,G,I,N/17Y16) 210 2" - 4" 1 2211
40 6/14/2017 Z POLIDEPORTIVO, EJE 1/C 210 2" - 4" 1 2209
Z POLIDEPORTIVO, EJE 1/C 210 2" - 4" 1 2209
Z POLIDEPORTIVO, EJE 1/C 210 2" - 4" 1 2209
41 6/15/2017 Z POLIDEPORTIVO, EJE B´´,B´,B1´/1´ 210 2" - 4" 1 2208
Z POLIDEPORTIVO, EJE B´´,B´,B1´/1´ 210 2" - 4" 1 2208
Z POLIDEPORTIVO, EJE B´´,B´,B1´/1´ 210 2" - 4" 1 2208
42 6/16/2017 C PAB#2 (E,G/13Y12) 210 2" - 4" 1 2207
C PAB#2 (E,G/13Y12) 210 2" - 4" 1 2207
C PAB#2 (E,G/13Y12) 210 2" - 4" 1 2207
43 6/17/2017 C PAB#1 (D/17Y 16), PAB#2(D,G/13Y12) 210 2" - 4" 1 2206
C PAB#1 (D/17Y 16), PAB#2(D,G/13Y12) 210 2" - 4" 1 2206
C PAB#1 (D/17Y 16), PAB#2(D,G/13Y12) 210 2" - 4" 1 2206
44 6/21/2017 C PAB#3 (L,B,D,G/9Y8) 210 2" - 4" 1 2202
C PAB#3 (L,B,D,G/9Y8) 210 2" - 4" 1 2202
C PAB#3 (L,B,D,G/9Y8) 210 2" - 4" 1 2202
45 6/22/2017 C PAB#3 (I,N/9Y8) 210 2" - 4" 1 2201
C PAB#3 (I,N/9Y8) 210 2" - 4" 1 2201
C PAB#3 (I,N/9Y8) 210 2" - 4" 1 2201
46 6/24/2017 Z POLIDEPORTIVO, EJE 1',2',3',4',5'6'/A' 210 2" - 4" 1 2199
Z POLIDEPORTIVO, EJE 1',2',3',4',5'6'/A' 210 2" - 4" 1 2199
Z POLIDEPORTIVO, EJE 1',2',3',4',5'6'/A' 210 2" - 4" 1 2199
47 6/26/2017 Z PAB#6 (G,G',H/1A' Y G',H/1B') 210 2" - 4" 1 2197
Z PAB#6 (G,G',H/1A' Y G',H/1B') 210 2" - 4" 1 2197
Z PAB#6 (G,G',H/1A' Y G',H/1B') 210 2" - 4" 1 2197
48 6/26/2017 C PAB#4 (B,D/7) 210 2" - 4" 1 2197
C PAB#4 (B,D/7) 210 2" - 4" 1 2197
49 6/27/2017 Z PAB#6 (H',I,IJ/1B' Y I,IJ/1A') 210 2" - 4" 1 2196
Z PAB#6 (H',I,IJ/1B' Y I,IJ/1A') 210 2" - 4" 1 2196
Z PAB#6 (H',I,IJ/1B' Y I,IJ/1A') 210 2" - 4" 1 2196
50 6/28/2017 Z POLIDEPORTIVO, EJE B1',B',B''/6' 210 2" - 4" 1 2195
Z POLIDEPORTIVO, EJE B1',B',B''/6' 210 2" - 4" 1 2195
SZ : Subzapata C: Columna
Z: Zapata LM: Losa Maciza
CC : Cimentación LA: Losa Aligerada
VC: Viga Cimentacion
SC : Sobrecimiento