Bloque B Diseño de Cimentaciones
Bloque B Diseño de Cimentaciones
t1=0.70m
S = 1.50 m
t2=0.70m
T = 1.50 m
DATOS
Pd = 7.66 Tn
Pl = 0.43 Tn
hf = 1.50 m
γs = 1.85 Tn/m3
f'c = 210 Kg/cm2
f'y = 4200 Kg/cm2
qa = 1.17 Kg/cm2
γc = 2.40 Tn/m3
DIMENSIONAMIENTO
Asumimos
h= 0.40 m d= 0.30 m
Hs = 1.10 m
qe = qa - γs x Hs - γc x h qe = 8.71 Tn/m2
T S Total
A = (Pd+Pl)/qe = 0.93 m2 Area = 0.96 m x 0.96 m 0.93 m2
0.96 m Asumimos Area = 1.50 m x 1.50 m 2.25 m2
Lv1 = 0.40
Reacciòn Neta del terreno Lv2 = 0.40 ok
Wu = Pu/A
Pu = 1.4xPd + 1.7xPl = 11.46 Tn Wu = 0.51 Kg/cm2
241.6 Wu = 5.1 Tn/m2
(1) = (2)
527.36 d2 + 372.72 d -8.96 = 0
d = 0.023 m
d= -0.730 m Conforme
Usamos h= 0.40 m
Recubrimiento 7.50 cm
Acero ɸ 5/8 d= 30.91 cm
Verificación por Cortante
As = Mu
ɸ*f'y*(d-a/2)
As = 0.52 cm2
a= 0.08
Espaciamiento (s)
s= 0.23 m
En la dirección Transversal
Espaciamiento (s)
s= 0.23 m
t1=0.70m
5 (unidades)
S = 1.50 m
@ 0.23 m
t2=0.70m
T = 1.50 m
5 (unidades)
@ 0.23 m
Ld = 40.17 m Conforme
Longitud de Desarrollo Lde = 32.14 m
Ldisponible = 32.50 m Conforme
Pn = Pu/ɸ = 16.36 Tn
Pnb = 0.85*f'c*Ao
t1=0.70m
S = 1.50 m
Xo t2=0.70m
T = 1.50 m
Ao = √(A2/A1)*Aco1 ≤ 2Aco1
Xo = 1.50 m
A2 = 2.25 m2
√(A2/A1) = 2.14 m
Ao=2*Ac Pn<Pnb
Pnb = 1749.30 Tn Conforme
DISEÑO DE ZAPATA 2 - BLOQUE B - COLUMNAS T (18-19-20-21-22-23)
t1=0.70m
S = 1.35 m
t2=0.50m
T = 1.55 m
DATOS
Pd = 11.57 Tn
Pl = 1.00 Tn
hf = 1.50 m
γs = 1.85 Tn/m3
f'c = 210 Kg/cm2
f'y = 4200 Kg/cm2
qa = 1.17 Kg/cm2
γc = 2.40 Tn/m3
DIMENSIONAMIENTO
Asumimos
h= 0.40 m d= 0.30 m
Hs = 1.10 m
qe = qa - γs x Hs - γc x h qe = 6.21 Tn/m2
T S Total
A = (Pd+Pl)/qe = 2.03 m2 Area = 1.52 m x 1.32 m 2.02 m2
1.42 m Asumimos Area = 1.55 m x 1.35 m 2.09 m2
Lv1 = 0.43
Reacciòn Neta del terreno Lv2 = 0.43 ok
Wu = Pu/A
Pu = 1.4xPd + 1.7xPl = 17.90 Tn Wu = 0.86 Kg/cm2
241.6 Wu = 8.6 Tn/m2
(1) = (2)
530.82 d2 + 323.63 d -14.90 = 0
d = 0.043 m
d= -0.653 m Conforme
Usamos h= 0.40 m
Recubrimiento 7.50 cm
Acero ɸ 5/8 d= 30.91 cm
Verificación por Cortante
As = Mu
ɸ*f'y*(d-a/2)
As = 0.89 cm2
a= 0.16
Espaciamiento (s)
s= 0.29 m
En la dirección Transversal
Espaciamiento (s)
s= 0.25 m
t1=0.70m
5 (unidades)
S = 1.35 m
@ 0.25 m
t2=0.50m
T = 1.55 m
4 (unidades)
@ 0.29 m
Ld = 40.17 m Conforme
Longitud de Desarrollo Lde = 32.14 m
Ldisponible = 35.00 m Conforme
Pn = Pu/ɸ = 25.57 Tn
Pnb = 0.85*f'c*Ao
t1=0.70m
S = 1.35 m
Xo t2=0.50m
T = 1.55 m
Ao = √(A2/A1)*Aco1 ≤ 2Aco1
Xo = 1.11 m
A2 = 1.72 m2
√(A2/A1) = 2.21 m
Ao=2*Ac Pn<Pnb
Pnb = 1249.50 Tn Conforme
DISEÑO DE ZAPATA 3 RECTANGULAR - BLOQUE B (17-24-25-26-27-28-29-31)
t1=0.25m
S = 1.40 m
t2=0.60m
T = 1.05 m
DATOS
Pd = 8.22 Tn
Pl = 0.93 Tn
hf = 1.50 m
γs = 1.85 Tn/m3
f'c = 210 Kg/cm2
f'y = 4200 Kg/cm2
qa = 1.17 Kg/cm2
γc = 2.40 Tn/m3
DIMENSIONAMIENTO
Asumimos
h= 0.40 m d= 0.30 m
Hs = 1.10 m
qe = qa - γs x Hs - γc x h qe = 6.21 Tn/m2
T S Total
A = (Pd+Pl)/qe = 1.47 m2 Area = 1.04 m x 1.39 m 1.44 m2
1.21 m Asumimos Area = 1.05 m x 1.40 m 1.47 m2
Lv1 = 0.40
Reacciòn Neta del terreno Lv2 = 0.40 ok
Wu = Pu/A
Pu = 1.4xPd + 1.7xPl = 13.09 Tn Wu = 0.89 Kg/cm2
241.6 Wu = 8.9 Tn/m2
(1) = (2)
531.17 d2 + 229.53 d -11.75 = 0
d = 0.046 m
d= -0.478 m Conforme
Usamos h= 0.40 m
Recubrimiento 7.50 cm
Acero ɸ 5/8 d= 30.91 cm
Verificación por Cortante
As = Mu
ɸ*f'y*(d-a/2)
As = 0.85 cm2
a= 0.14
Espaciamiento (s)
s= 0.31 m
En la dirección Transversal
Espaciamiento (s)
s= 0.34 m
t1=0.25m
3 (unidades)
S = 1.40 m
@ 0.34 m
t2=0.60m
T = 1.05 m
4 (unidades)
@ 0.31 m
Ld = 40.17 m Conforme
Longitud de Desarrollo Lde = 32.14 m
Ldisponible = 32.50 m Conforme
Pn = Pu/ɸ = 18.70 Tn
Pnb = 0.85*f'c*Ao
t1=0.25m
S = 1.40 m
Xo t2=0.60m
T = 1.05 m
Ao = √(A2/A1)*Aco1 ≤ 2Aco1
Xo = 2.52 m
A2 = 2.65 m2
√(A2/A1) = 4.20 m
Ao=2*Ac Pn<Pnb
Pnb = 535.50 Tn Conforme
DISEÑO DE ZAPATA 4 RECTANGULAR - BLOQUE B (1-3-5-7-9-11-13)
t1=0.30m
S = 1.10 m
t2=0.30m
T = 1.10 m
DATOS
Pd = 5.66 Tn
Pl = 0.40 Tn
hf = 1.50 m
γs = 1.85 Tn/m3
f'c = 210 Kg/cm2
f'y = 4200 Kg/cm2
qa = 1.17 Kg/cm2
γc = 2.40 Tn/m3
DIMENSIONAMIENTO
Asumimos
h= 0.40 m d= 0.30 m
Hs = 1.10 m
qe = qa - γs x Hs - γc x h qe = 6.21 Tn/m2
T S Total
A = (Pd+Pl)/qe = 0.98 m2 Area = 0.99 m x 0.99 m 0.98 m2
0.99 m Asumimos Area = 1.10 m x 1.10 m 1.21 m2
Lv1 = 0.40
Reacciòn Neta del terreno Lv2 = 0.40 ok
Wu = Pu/A
Pu = 1.4xPd + 1.7xPl = 8.60 Tn Wu = 0.71 Kg/cm2
241.6 Wu = 7.1 Tn/m2
(1) = (2)
529.38 d2 + 160.95 d -7.96 = 0
d = 0.043 m
d= -0.347 m Conforme
Usamos h= 0.40 m
Recubrimiento 7.50 cm
Acero ɸ 5/8 d= 30.91 cm
Verificación por Cortante
As = Mu
ɸ*f'y*(d-a/2)
As = 0.53 cm2
a= 0.11
Espaciamiento (s)
s= 0.21 m
En la dirección Transversal
Espaciamiento (s)
s= 0.21 m
t1=0.30m
4 (unidades)
S = 1.10 m
@ 0.21 m
t2=0.30m
T = 1.10 m
4 (unidades)
@ 0.21 m
Ld = 40.17 m Conforme
Longitud de Desarrollo Lde = 32.14 m
Ldisponible = 32.50 m Conforme
Pn = Pu/ɸ = 12.29 Tn
Pnb = 0.85*f'c*Ao
t1=0.30m
S = 1.10 m
Xo t2=0.30m
T = 1.10 m
Ao = √(A2/A1)*Aco1 ≤ 2Aco1
Xo = 1.10 m
A2 = 1.21 m2
√(A2/A1) = 3.67 m
Ao=2*Ac Pn<Pnb
Pnb = 321.30 Tn Conforme
DISEÑO DE VIGAS DE CONEXIÓN - BLOQUE B - EJE A-G
15 17
P1 P2
hf
hz
Re 4.00 m.
L1
σ= 1.17 Kg/cm2
hf= 1.50 m
jm= 1.85 Tn/m3
f'c= 210 Kg/cm2
f'y= 4200 Kg/cm2
s/c = 0.20 Tn/m2
Pd= 7.61 Tn Pd= 7.52 Tn
Pl= 0.42 Tn Pl= 0.64 Tn
P1= 8.03 Tn P2= 8.16 Tn
0.57 m
0.06 m = 0.29 m
Entonces usamos:
b h
V-C 0.25 x 0.60 m2
Estimamos
σn = 8.725 Tn/m2
Az = 1.10 m2 T = 2*S
S= 0.74 m
Preliminar
T= 1.49 m
T T=2S
S
Dimensiones Finales de zapata S = 0.75 m T = 1.50 m
Pu = 1.4Pd + 1.7Pl
Pu= 11.368 Tn
Wv = 0.36 Tn/m
ΣM2=0
Ru= 12.29 Tn Wnu = Ru/S
Wnu= 16.38 Tn/m
Vx=(Wnu-Wv)Xo-Pu=0
Xo= 0.71 < S OK¡
Mumax = (Wnu-Wv)Xo2/2-Pu(Xo-T1/2)
0.00453
OK
0.00333
As = 4.33 cm2
Vc = 0.53*√f'c*10*b*d = 10.08 Tn OK
Debe ser mayor
Estribos de Montaje
S = 36*Ø = 57.16 cm
Usamos Ø 3/8 @ 50.00 cm
Diseño Final
S = 0.75 m
Viga de Conexión
h = 50.00 cm 3 Ø 5/8
4 Ø 5/8
T = 1.50 m
0.60 cm
3 Ø 5/8
b = 0.25 cm
10 Ø 5/8
DISEÑO DE VIGAS DE CONEXIÓN - BLOQUE B - EJE E-F
25 26
P1 P2
hf
hz
Re 4.00 m.
L1
σ= 1.17 Kg/cm2
hf= 1.50 m
jm= 1.85 Tn/m3
f'c= 210 Kg/cm2
f'y= 4200 Kg/cm2
s/c = 0.20 Tn/m2
Pd= 8.22 Tn Pd= 7.46 Tn
Pl= 0.93 Tn Pl= 0.57 Tn
P1= 9.15 Tn P2= 8.03 Tn
0.57 m
0.07 m = 0.29 m
Entonces usamos:
b h
V-C 0.25 x 0.60 m2
Estimamos
σn = 8.725 Tn/m2
Az = 1.26 m2 T = 2*S
S= 0.79 m
Preliminar
T= 1.59 m
T T=2S
S
Dimensiones Finales de zapata S = 1.40 m T = 1.10 m
Pu = 1.4Pd + 1.7Pl
Pu= 13.089 Tn
Wv = 0.36 Tn/m
ΣM2=0
Ru= 14.86 Tn Wnu = Ru/S
Wnu= 10.62 Tn/m
Vx=(Wnu-Wv)Xo-Pu=0
Xo= 1.28 < S OK¡
Mumax = (Wnu-Wv)Xo2/2-Pu(Xo-T1/2)
0.00453
OK
0.00333
As = 4.33 cm2
Vc = 0.53*√f'c*10*b*d = 10.08 Tn OK
Debe ser mayor
Estribos de Montaje
S = 36*Ø = 57.16 cm
Usamos Ø 3/8 @ 50.00 cm
Diseño Final
S = 1.40 m
Viga de Conexión
h = 50.00 cm 3 Ø 5/8
4 Ø 5/8
T = 1.10 m
0.60 cm
3 Ø 5/8
b = 0.25 cm
10 Ø 5/8
DISEÑO DE VIGAS DE CONEXIÓN - BLOQUE B - EJE 4
21 23
P1 P2
hf
hz
Re 3.95 m.
L1
σ= 1.17 Kg/cm2
hf= 1.50 m
jm= 1.85 Tn/m3
f'c= 210 Kg/cm2
f'y= 4200 Kg/cm2
s/c = 0.20 Tn/m2
Pd= 11.57 Tn Pd= 11.02 Tn
Pl= 1 Tn Pl= 0.93 Tn
P1= 12.57 Tn P2= 11.95 Tn
0.56 m
0.10 m = 0.28 m
Entonces usamos:
b h
V-C 0.25 x 0.60 m2
Estimamos
σn = 8.725 Tn/m2
Az = 1.73 m2 T = 2*S
S= 0.93 m
Preliminar
T= 1.86 m
T T=2S
S
Dimensiones Finales de zapata S = 1.55 m T = 1.35 m
Pu = 1.4Pd + 1.7Pl
Pu= 17.898 Tn
Wv = 0.36 Tn/m
ΣM2=0
Ru= 19.30 Tn Wnu = Ru/S
Wnu= 12.45 Tn/m
Vx=(Wnu-Wv)Xo-Pu=0
Xo= 1.48 < S OK¡
Mumax = (Wnu-Wv)Xo2/2-Pu(Xo-T1/2)
0.00453
OK
0.00333
As = 4.33 cm2
Vc = 0.53*√f'c*10*b*d = 10.08 Tn OK
Debe ser mayor
Estribos de Montaje
S = 36*Ø = 57.16 cm
Usamos Ø 3/8 @ 50.00 cm
Diseño Final
S = 1.55 m
Viga de Conexión
h = 50.00 cm 3 Ø 5/8
4 Ø 5/8
T = 1.35 m
0.60 cm
3 Ø 5/8
b = 0.25 cm
10 Ø 5/8
DISEÑO DE VIGAS DE CONEXIÓN - BLOQUE B - EJE 2
20 18
P1 P2
hf
hz
Re 3.95 m.
L1
σ= 1.17 Kg/cm2
hf= 1.50 m
jm= 1.85 Tn/m3
f'c= 210 Kg/cm2
f'y= 4200 Kg/cm2
s/c = 0.20 Tn/m2
Pd= 11.48 Tn Pd= 10.79 Tn
Pl= 1.15 Tn Pl= 1.09 Tn
P1= 12.63 Tn P2= 11.88 Tn
0.56 m
0.10 m = 0.28 m
Entonces usamos:
b h
V-C 0.25 x 0.60 m2
Estimamos
σn = 8.725 Tn/m2
Az = 1.74 m2 T = 2*S
S= 0.93 m
Preliminar
T= 1.86 m
T T=2S
S
Dimensiones Finales de zapata S = 1.55 m T = 1.35 m
Pu = 1.4Pd + 1.7Pl
Pu= 18.027 Tn
Wv = 0.36 Tn/m
ΣM2=0
Ru= 19.44 Tn Wnu = Ru/S
Wnu= 12.54 Tn/m
Vx=(Wnu-Wv)Xo-Pu=0
Xo= 1.48 < S OK¡
Mumax = (Wnu-Wv)Xo2/2-Pu(Xo-T1/2)
0.00453
OK
0.00333
Refuerzo en la Carga Inferior
As = 4.33 cm2
Vc = 0.53*√f'c*10*b*d = 10.08 Tn OK
Debe ser mayor
Estribos de Montaje
S = 36*Ø = 57.16 cm
Usamos Ø 3/8 @ 50.00 cm
Diseño Final
S = 1.55 m
Viga de Conexión
h = 50.00 cm 3 Ø 5/8
4 Ø 5/8
T = 1.35 m
0.60 cm
3 Ø 5/8
b = 0.25 cm
10 Ø 5/8
DISEÑO DE VIGAS DE CONEXIÓN - BLOQUE A - EJE 1
11 9
P1 P2
hf
hz
Re 3.95 m.
L1
σ= 1.17 Kg/cm2
hf= 1.50 m
jm= 1.85 Tn/m3
f'c= 210 Kg/cm2
f'y= 4200 Kg/cm2
s/c = 0.20 Tn/m2
Pd= 5.66 Tn Pd= 5.51 Tn
Pl= 0.4 Tn Pl= 0.37 Tn
P1= 6.06 Tn P2= 5.88 Tn
0.56 m
0.05 m = 0.28 m
Entonces usamos:
b h
V-C 0.25 x 0.50 m2
Estimamos
σn = 8.725 Tn/m2
Az = 0.83 m2 T = 2*S
S= 0.65 m
Preliminar
T= 1.29 m
T T=2S
S
Dimensiones Finales de zapata S = 1.10 m T = 1.10 m
Pu = 1.4Pd + 1.7Pl
Pu= 8.604 Tn
Wv = 0.30 Tn/m
ΣM2=0
Ru= 9.67 Tn Wnu = Ru/S
Wnu= 8.79 Tn/m
Vx=(Wnu-Wv)Xo-Pu=0
Xo= 1.01 < S OK¡
Mumax = (Wnu-Wv)Xo2/2-Pu(Xo-T1/2)
0.00559
OK
0.00333
As = 3.51 cm2
Vc = 0.53*√f'c*10*b*d = 8.16 Tn OK
Debe ser mayor
Estribos de Montaje
S = 36*Ø = 57.16 cm
Usamos Ø 3/8 @ 50.00 cm
Diseño Final
S = 1.10 m
Viga de Conexión
h = 50.00 cm 3 Ø 5/8
4 Ø 5/8
T = 1.10 m
0.50 cm
3 Ø 5/8
b = 0.25 cm
10 Ø 5/8