L I Q U I D A C I O N DE OBRA

"CONSTRUCCION DE PAVIMENTO Y VEREDA EN EL (LA)PASAJE CRISTOBAL COLON SECTOR RAMON CASTILLA EN LA


OBRA : LOCALIDAD OTUZCO. DISTRITO DE OTUZCO, PROVINCIA OTUZCO, DEPARTAMRNTO LA LIBERTAD"

MODALIDAD : A SUMA ALZADA


PROPIETARIO : MUNICIPALIDAD DISTRITAL DE OTUZCO
CONTRATISTA : CONSORCIO SD
RESIDENTE : ING. DEYSI RUTH PIANTO MENDOZA
SUPERVISOR : ING. JOSE LUIS CORREA FASANANDO

1. PAGOS A CUENTA

1.1. CONTRATO PRINCIPAL AUTORIZADO PAGADO SALDO

1.1.1. CONTRATO PRINCIPAL S/. 275,138.73 S/. 275,138.73 S/. -

* Reintegros: S/. 11,369.52 S/. - S/. 11,369.52

SALDO A FAVOR DEL CONTRATISTA S/. 11,369.52

TRIBUTOS : I.G.V.

1.1. CONTRATO PRINCIPAL

1.1.1. CONTRATO PRINCIPAL S/. 49,524.97 S/. 49,524.97 S/. -

* Reintegros: S/. 2,046.51 S/. - S/. 2,046.51

SALDO A FAVOR DEL CONTRATISTA S/. 2,046.51

SALDO TOTAL A FAVOR DEL CONTRATISTA


S/. 13,416.03

3. FONDO DE GARANTIA

RETENCION DEL 10% POR GARANTIA DE FIEL CUMPLIMIENTO S/. 32,466.03

DEVOLUCIÓN DE LA CARTA FIANZA A FAVOR DEL CONTRATISTA S/. 32,466.03


CALCULO DEL FACTOR DE REAJUSTE "K" - CONTRACTUAL

OBRA
"CONSTRUCCION DE PAVIMENTO Y VEREDA EN EL (LA)PASAJE CRISTOBAL COLON SECTOR RAMON CASTILLA EN LA LOCALIDAD OTUZCO. DISTRITO DE
OTUZCO, PROVINCIA OTUZCO, DEPARTAMRNTO LA LIBERTAD"

CONTRATISTA: CONSORCIO SD

RESIDENTE: ING. DEYSI RUTH PIANTO MENDOZA

SUPERVISOR: ING. JOSE LUIS CORREA FASANANDO

VALOR REFEREN.: S/. 341,764.21

MONTO CONTRAT. S/. 324,663.70

PLAZO DE EJEC. 90 Dias Calendarios

FECHA INICIO : 5/4/2022

FECHA TERMINO REAL : 8/1/2022

K = 0.183*(Mr / Mo) + 0.096*(Mr / Mo) + 0.273*(Ar / Ao) + 0.227*(Cr / Co) + 0.106*(Mr / Mo) + 0.115*(Ir / Io)

INDICE BASE DIC INDICE K JUN INDICE K JUL INDICE K AGOST INDICE K SET
MONOMIO SIMB. INDIC. UNIFIC. FACTOR PORCENT. %
2021 JUN 2022 2022 JUL 2022 2022 AGOST. 2022 2022 SET 2022 2022

1 1 M 47 0.183 100.00%
653.54 702.10 0.1966 702.10 0.1966 702.10 0.1966 702.10 0.1966

2 2 A 49 0.096 100.00%
407.98 402.27 0.0947 422.26 0.0994 422.12 0.0993 426.54 0.1004

3 3 C 5 0.273 100.00%
498.16 508.89 0.2789 504.96 0.2767 509.33 0.2791 513.40 0.2814

4 4 A 21 0.227 100.00%
496.50 522.37 0.2388 530.26 0.2424 531.35 0.2429 539.21 0.2465

5 5 M 43 0.106 100.00%
910.10 924.45 0.1077 922.11 0.1074 921.88 0.1074 921.33 0.1073

6 6 I 39 0.115 100.00%
499.88 522.07 0.1201 526.99 0.1212 530.50 0.1220 533.27 0.1227

SUMA 1.000 SUMA 1.0367 SUMA 1.0438 SUMA 1.0474 SUMA 1.0548
RESOLUCIÓN JEFATURAL Nº 208-2022-INEI
CALCULO DE REINTEGROS A RECONO
OBRA "CONSTRUCCION DE PAVIMENTO Y VEREDA EN EL (LA)PASAJE CRISTOBAL COLON SECTOR RA
PROVINCIA OTUZCO, DEPARTAMRNTO LA
CONTRATISTA CONSORCIO SD
RESIDENTE ING. DEYSI RUTH PIANTO MENDOZA
SUPERVISOR ING. JOSE LUIS CORREA FASANANDO
VALOR REFEREN. S/. 341,764.21
MONTO CONTRAT. S/. 324,663.70
PLAZO DE EJEC. 90 Dias Calendarios
FECHA INICIO : 5/4/2022
FECHA TERMINO REAL. : 8/1/2022

VALORIZACIONES CONTRACTUALES DE OB

Contractuales
Monto Acumulado
Val
Real Programado Real
DEL 04/05/2022 AL 31/05/20 150,941.18 99,630.14 150,941.18
DEL 01/06/2022 AL 30/06/20 121,084.98 157,063.81 272,026.16
DEL 01/07/2022 AL 31/07/20 42,165.62 66,652.61 314,191.78
DEL 01/08/2022 AL 08/08/20 10,471.92 1,317.14 324,663.70

TOTAL VALORIZACIONES 324,663.70 324,663.70 324,663.70


TEGROS A RECONOCER
JE CRISTOBAL COLON SECTOR RAMON CASTILLA EN LA LOCALIDAD OTUZCO. DISTRITO DE OTUZCO,
NCIA OTUZCO, DEPARTAMRNTO LA LIBERTAD"

CONTRACTUALES DE OBRA

Monto Acumulado Mes Reajuste C/IGV


K
Programado Reajuste Real Programado A reconocer
99,630.14 Nov-20 1.0367 5,545.30 3,660.23 5,545.30
256,693.95 Dec-20 1.0438 5,298.05 6,872.30 5,298.05
323,346.56 Jan-21 1.0474 1,998.47 3,159.05 1,998.47
324,663.70 Feb-21 1.0548 574.21 72.22 574.21

324,663.70 13,416.03
97,532.54 40478.62 10052.92
6,038.00 4,843.00 1687 419
13,756.59 18,709.44 10471.92
131,146.59

150,941.18
121,084.98 42165.62

32,466.03