RESUMEN GENERAL DE PRESUPUESTO DE OBRA


PROYECTO: “MEJORAMIENTO DEL SERVICIO DE AGUA A TRAVES DEL SISTEMA DE RIEGO TECNIFICADO EN EL CASERIO DE
QUISHU, SECTORES MULLIPAMPA, HUARCON Y QUISHU CENTRO, DISTRITO DE SAN MARCOS - HUARI - ANCASH”.

ÍTEM DESCRIPCIÓN/ OBRA UND COSTO S/.


01 INSTALACION DE OBRAS PROVISIONAL, SEGURIDAD Y SALUD EN EL TRABAJO GLB S/. 49,683.23
01.01 OBRAS PROVISIONALES GLB S/. 34,758.64
01.02 SEGURIDAD Y SALUD GLB S/. 14,924.59
INSTALACION DEL SISTEMA DE RIEGO TECNICIFCADO EN LOS SECTORES MULLIPAMPA,
02 GLB S/. 3,491,578.95
HUARCON Y QUISHU CENTRO
02.01 CAPTACION DE LADERA (01 UND) - CUNCACNANI GLB S/. 28,192.12
02.02 CAPTACION DE QUEBRADA (01 UND), MEJORAMIENTO GLB S/. 3,944.49
02.03 DESARENADOR (01 UND), MEJORAMIENTO GLB S/. 23,960.18
LINEA DE CONDUCCION (Ø=10", L=1,202.99 M, Ø=6", L= 632.51 M, Ø=1.5", L=455.57
02.04 GLB S/. 313,823.02
M); TOTAL = 2,291.06 M
02.05 CAMARA DE REUNION (01 UND); TOTAL=01 UND GLB S/. 3,560.04
02.06 CAMARA ROMPE PRESION (CRP6) (Ø 1.5", 03 UND); TOTAL=03 UND. GLB S/. 6,084.28
02.07 CAMARA DE INSPECCION, TOTAL=03 UND GLB S/. 11,891.24
02.08 VALVULA DE AIRE (Ø 1.5", 01 UND), (Ø 6", 02 UND), (Ø 10", 01 UND), TOTAL 04 UND GLB S/. 4,606.40
02.09 RESERVORIO SECTOR QUISHU V=720m3 (01 UND) GLB S/. 262,061.15
02.10 RESERVORIO SECTOR MULLIPAMPA V=604.80 m3 (01 UND) GLB S/. 224,494.40
02.11 RESERVORIO SECTOR HUARCON V=547.20 m3 (01 UND) GLB S/. 212,601.09
LINEA DE DISTRIBUCION (Ø=3", L=5,734.739 M, Ø=2", L=7,647.061 M, Ø=1.5",
02.12 GLB S/. 1,845,209.36
L=3,103.50 M Y Ø=1", L=6,460.089 M); TOTAL = 22,945.389 M
CAMARA ROMPE PRESION (CRP7) (Ø 1", 06 UND); (Ø 1.5", 09 UND); (Ø 2", 11
02.13 GLB S/. 78,246.94
UND); (Ø 3", 04 UND); TOTAL=30 UND.
02.14 VALVULA DE CONTROL (38 Und DISTRIBUCION, 02 CONDUCCION), Total, 40 UND GLB S/. 34,601.50
02.15 VALVULA DE PURGA (41 Und) GLB S/. 27,864.54
02.16 HIDRANTES (372 Und) GLB S/. 178,076.46
02.17 MODULO DE RIEGO 3/4" (227 UND) GLB S/. 232,361.74
03 FLETE GLB S/. 129,840.79
04 MITIGACION DE IMPACTO AMBIENTAL GLB S/. 16,840.24
4.01 PLAN DE MANEJO AMBIENTAL Y CIERRE DE OBRA GLB S/. 7,126.30
4.02 PLAN DE CAPACITACION Y EDUCACION AMBIENTAL GLB S/. 9,263.94
4.03 PLAN DE CIERRE Y ABANDONO GLB S/. 450.00
05 PLAN DE MONITOREO ARQUEOLOGICO GLB S/. 5,000.00
06 PLAN DE CAPACITACION GLB S/. 17,700.00
6.01 PLAN DE CAPACITACION AISTENCIA TECNICA GLB 17700

COSTO DIRECTO S/. 3,710,643.21


GASTOS GENERALES (8.92%) S/. 330,826.68
UTILIDAD (7.0%) S/. 259,745.02
-------------------------------
SUB TOTAL S/. 4,301,214.91
IGV (18.00%) S/. 774,218.68
================
VALOR REFERENCIAL S/. 5,075,433.59
SUPERVISION S/. 192,039.10
COSTO DEL EXPEDIENTE TECNICO S/. 111,038.00
EVALUACION DE EXPEDIENTE S/. 10,000.00
GESTION DE PROYECTO S/. 120,000.00
PAGOS POR AFECTACIÓN DE TERRENO (CAPTACIÓN Y RESERVORIOS) S/. 156,700.00
================
TOTAL DEL PRESUPUESTO S/. 5,665,210.69

SON: CINCO MILLONES SEISCIENTOS SESENTA Y CINCO MIL DOSCIENTOS DIEZ CON 69/100 SOLES