CRONOGRAMA VALORIZADO DE OBRA

PROYECTO: "MEJORAMIENTO DEL SERVICIO DE MOVILIDAD URBANA EN LA AVENIDA BARREDA Y AGUILAR DE LA URBANIZACIÓN CIUDAD Y CAMPO DISTRITO
DE RIMAC, DE LA PROVINCIA DE LIMA, DEL DEPARTAMENTO DE LIMA" CON CUI 2619279

Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) MES 01 MES 02
01 OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD S/ 83,783.23 S/ 75,453.23 S/ 8,330.00
01.01 OBRAS PROVISIONALES S/ 7,427.78 S/ 4,727.78 S/ 2,700.00
01.01.01 ALQUILER DE ALMACEN Y CASETA DE GUARDIANIA mes 2.00 1,700.00 S/ 3,400.00 S/ 1,700.00 S/ 1,700.00
01.01.02 ALQUILER DE SERVICIOS HIGIENICOS PORTATILES mes 2.00 1,000.00 S/ 2,000.00 S/ 1,000.00 S/ 1,000.00
01.01.03 CARTEL DE OBRA 3.60x4.80m und 1.00 2,027.78 S/ 2,027.78 S/ 2,027.78
01.02 TRABAJOS PRELIMINARES S/ 6,801.19 S/ 6,801.19
01.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 6,801.19 S/ 6,801.19 S/ 6,801.19
01.03 DEMOLICIONES S/ 46,389.26 S/ 46,389.26
01.03.01 DEMOLICION DE VEREDAS, BERMAS Y RAMPAS DE CONCRETO C/EQUIPO LIVIANO m2 2,550.33 11.18 S/ 28,512.69 S/ 28,512.69
01.03.02 ACARREO INTERNO MAT. PROCEDENTE DE DEMOLICION m3 382.55 13.01 S/ 4,976.98 S/ 4,976.98
01.03.03 ELIMINACION DE MATERIAL EXCEDENTE C/EQUIPO = 25KM m3 382.55 33.72 S/ 12,899.59 S/ 12,899.59
01.04 PLAN DE SEGURIDAD Y SALUD S/ 14,754.92 S/ 13,329.96 S/ 1,424.96
01.04.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO glb 1.00 4,000.00 S/ 4,000.00 S/ 4,000.00
01.04.02 EQUIPOS DE PROTECCION INDIVIDUAL glb 1.00 2,772.96 S/ 2,772.96 S/ 2,772.96
01.04.03 EQUIPOS DE PROTECCION COLECTIVA glb 1.00 2,843.72 S/ 2,843.72 S/ 2,843.72
01.04.04 SEÑALIZACION TEMPORAL DE SEGURIDAD mes 2.00 1,424.96 S/ 2,849.92 S/ 1,424.96 S/ 1,424.96
01.04.05 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD EN EL TRABAJO glb 1.00 2,288.32 S/ 2,288.32 S/ 2,288.32
01.05 MITIGACION AMBIENTAL S/ 6,000.00 S/ 3,000.00 S/ 3,000.00
01.05.01 PLAN DE MITIGACION AMBIENTAL DURANTE OBRA mes 2.00 3,000.00 S/ 6,000.00 S/ 3,000.00 S/ 3,000.00
01.06 PLAN DE SEGURIDAD VIAL S/ 2,410.08 S/ 1,205.04 S/ 1,205.04
01.06.01 MANTENIENTO DE TRANSITO Y SEGURIDAD VIAL mes 2.00 1,205.04 S/ 2,410.08 S/ 1,205.04 S/ 1,205.04
02 VEREDAS S/ 98,115.83 S/ 92,578.42 S/ 5,537.41
02.01 TRABAJOS PRELIMINARES S/ 2,642.78 S/ 2,642.78
02.01.01 TRAZO Y REPLANTEO DURANTE EL PROCESO m2 820.74 3.22 S/ 2,642.78 S/ 2,642.78
02.02 MOVIMIENTO DE TIERRAS S/ 14,600.96 S/ 14,600.96
02.02.01 CONFORMACION Y COMPACTACION A NIVEL DE SUBRASANTE PARA VEREDAS m2 820.74 17.79 S/ 14,600.96 S/ 14,600.96
02.03 BASE S/ 17,022.15 S/ 17,022.15
02.03.01 CONFORMACION, NIVELADO Y COMPACTADO DE BASE E=0.10 M m2 820.74 20.74 S/ 17,022.15 S/ 17,022.15
02.04 NIVELACION DE CAJAS DOMICILIARIAS S/ 13,762.93 S/ 13,762.93
02.04.01 NIVELACION DE CAJAS DE AGUA und 65.00 142.61 S/ 9,269.65 S/ 9,269.65
02.04.02 NIVELACION DE CAJAS DE DESAGUE und 24.00 187.22 S/ 4,493.28 S/ 4,493.28
02.05 VEREDAS DE CONCRETO S/ 37,140.68 S/ 37,140.68
02.05.01 ENCOFRADO Y DESENCOFRADO NORMAL EN VEREDAS m2 69.41 92.69 S/ 6,433.61 S/ 6,433.61
02.05.02 CONCRETO PREMEZCLADO f'c=175 kg/cm2, ACABADO SEMIPULIDO, INC. BRUÑADO m3 82.07 312.38 S/ 25,637.03 S/ 25,637.03
02.05.03 CURADO DE CONCRETO CON ADITIVO CURADOR m2 820.74 4.30 S/ 3,529.18 S/ 3,529.18
02.05.04 JUNTAS DE DILATACION C/N MORTERO ASFALTICO 1" @4.00M m 221.07 6.97 S/ 1,540.86 S/ 1,540.86
02.06 RAMPAS DE CONCRETO S/ 5,621.82 S/ 5,621.82
02.06.01 ENCOFRADO Y DESENCOFRADO NORMAL EN RAMPAS PEATONALES m2 7.65 53.13 S/ 406.44 S/ 406.44
02.06.02 CONCRETO PREMEZCLADO f'c=175 kg/cm2, ACABADO SEMIPULIDO, INC. BRUÑADO m3 4.83 312.38 S/ 1,508.80 S/ 1,508.80
02.06.03 CURADO DE CONCRETO CON ADITIVO CURADOR m2 64.34 4.30 S/ 276.66 S/ 276.66
02.06.04 SUMINISTRO E INSTALACION DE PODOTACTILES m2 34.00 100.88 S/ 3,429.92 S/ 3,429.92
02.07 SEÑALIZACION S/ 7,324.51 S/ 1,787.10 S/ 5,537.41
02.07.01 LINEAS DE BORDE EN ACERAS m 403.11 18.17 S/ 7,324.51 S/ 1,787.10 S/ 5,537.41
03 PISO ADOQUINADO S/ 78,544.06 S/ 16,699.04 S/ 61,845.02
03.01 TRABAJOS PRELIMINARES S/ 3,173.70 S/ 3,173.70
03.01.01 TRAZO Y REPLANTEO DURANTE EL PROCESO m2 985.62 3.22 S/ 3,173.70 S/ 3,173.70
03.02 MOVIMIENTO DE TIERRAS S/ 3,903.06 S/ 3,903.06
03.02.01 CONFORMACION Y COMPACTACION A NIVEL DE SUBRASANTE PARA PISO ADOQUINADO m2 985.62 3.96 S/ 3,903.06 S/ 3,903.06
03.03 BASE S/ 10,132.17 S/ 9,622.28 S/ 509.89
03.03.01 BASE GRANULAR PARA PISO ADOQUINADO E=0.15 m m2 985.62 10.28 S/ 10,132.17 S/ 9,622.28 S/ 509.89
03.04 ADOQUINADO S/ 61,335.13 S/ 61,335.13
03.04.01 CAMA DE ARENA h=0.04m m2 985.62 9.00 S/ 8,870.58 S/ 8,870.58
03.04.02 COLOCACION DE ADOQUIN DE CONCRETO COLOR ROJO 20x10x6CM m2 985.62 53.23 S/ 52,464.55 S/ 52,464.55
04 MARTILLO DE CONCRETO S/ 78,737.45 S/ 40,131.50 S/ 38,605.95
04.01 TRABAJOS PRELIMINARES S/ 3,286.88 S/ 3,286.88
04.01.01 TRAZO Y REPLANTEO DURANTE EL PROCESO m2 1,020.77 3.22 S/ 3,286.88 S/ 3,286.88
04.02 MOVIMIENTO DE TIERRAS S/ 11,208.05 S/ 11,208.05
04.02.01 CONFORMACION Y COMPACTACION A NIVEL DE SUBRASANTE PARA MARTILLOS m2 1,020.77 10.98 S/ 11,208.05 S/ 11,208.05
04.03 BASE S/ 21,170.77 S/ 21,170.77
04.03.01 CONFORMACION, NIVELADO Y COMPACTADO DE BASE E=0.10 M m2 1,020.77 20.74 S/ 21,170.77 S/ 21,170.77
04.04 MARTILLO DE CONCRETO S/ 43,071.75 S/ 4,465.80 S/ 38,605.95
04.04.01 ENCOFRADO Y DESENCOFRADO NORMAL EN MARTILLO m2 101.58 66.89 S/ 6,794.69 S/ 4,465.80 S/ 2,328.89
04.04.02 CONCRETO PREMEZCLADO f'c=175 kg/cm2, ACABADO SEMIPULIDO, INC. BRUÑADO m3 102.08 312.38 S/ 31,887.75 S/ 31,887.75
04.04.03 CURADO DE CONCRETO CON ADITIVO CURADOR m2 1,020.77 4.30 S/ 4,389.31 S/ 4,389.31
05 SARDINELES Y JARDINERAS S/ 49,080.13 S/ 45,118.68 S/ 3,961.45
05.01 SARDINEL SUMERGIDO S/ 2,315.14 S/ 2,055.66 S/ 259.48
05.01.01 EXCAVACION SARDINEL SUMERGIDO m3 5.56 60.14 S/ 334.38 S/ 334.38
05.01.02 CONCRETO PREMEZCLADO f'c=175 kg/cm2 m3 5.56 298.14 S/ 1,657.66 S/ 1,657.66
05.01.03 CURADO DE CONCRETO CON ADITIVO CURADOR m2 18.52 4.30 S/ 79.64 S/ 63.62 S/ 16.02
05.01.04 ELIMINACION DE MATERIAL EXCEDENTE C/EQUIPO = 25KM m3 7.22 33.72 S/ 243.46 S/ 243.46
05.02 SARDINEL PERALTADO S/ 46,764.99 S/ 43,063.02 S/ 3,701.97
05.02.01 EXCAVACION SARDINEL PERALTADO m3 26.62 60.14 S/ 1,600.93 S/ 1,600.93
05.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA EN SARDINELES m2 212.93 80.65 S/ 17,172.80 S/ 17,172.80
05.02.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 1,778.71 7.17 S/ 12,753.35 S/ 12,753.35
05.02.04 CONCRETO PREMEZCLADO f'c=175 kg/cm2 m3 42.59 298.14 S/ 12,697.78 S/ 11,535.94 S/ 1,161.85
05.02.05 CURADO DE CONCRETO CON ADITIVO CURADOR m2 319.40 4.30 S/ 1,373.42 S/ 1,373.42
05.02.06 ELIMINACION DE MATERIAL EXCEDENTE C/EQUIPO = 25KM m3 34.60 33.72 S/ 1,166.71 S/ 1,166.71
06 JARDINERIA S/ 26,806.18 S/ 26,806.18
06.01 MOVIMIENTO DE TIERRAS S/ 16,392.13 S/ 16,392.13
06.01.01 PERFILADO Y COMPACTADO A NIVEL DE SUB-RASANTE PARA AREAS VERDES m2 656.21 11.81 S/ 7,749.84 S/ 7,749.84
06.01.02 INCORPORACION DE TIERRA DE JARDIN e=0.15m m2 656.21 13.17 S/ 8,642.29 S/ 8,642.29
06.02 AREAS VERDES S/ 10,414.05 S/ 10,414.05
06.02.01 SEMBRIO DE GRASS TIPO AMERICANO m2 656.21 15.87 S/ 10,414.05 S/ 10,414.05
07 PAVIMENTOS S/ 589,836.85 S/ 51,920.20 S/ 537,916.65
07.01 DEMOLICIONES S/ 41,647.35 S/ 41,647.35 S/ 0.00
07.01.01 DEMOLICION DE ASFALTO (e=0.05m) m2 3,474.23 9.88 S/ 34,325.39 S/ 34,325.39
07.01.02 ELIMINACION DE MATERIAL EXCEDENTE C/EQUIPO = 25KM m3 217.14 33.72 S/ 7,321.96 S/ 7,321.96
07.02 TRABAJOS PRELIMINARES S/ 13,473.96 S/ 10,272.85 S/ 3,201.11
07.02.01 TRAZO Y REPLANTEO DURANTE EL PROCESO m2 4,184.46 3.22 S/ 13,473.96 S/ 10,272.85 S/ 3,201.11
07.03 MOVIMIENTO DE TIERRAS S/ 66,041.36 S/ 66,041.36
07.03.01 CORTE CON EQUIPO A NIVEL DE SUBRASANTE PARA PAVIMENTO m2 4,184.46 9.46 S/ 39,584.99 S/ 39,584.99
07.03.02 ELIMINACION DE MATERIAL EXCEDENTE C/EQUIPO = 25KM m3 784.59 33.72 S/ 26,456.37 S/ 26,456.37
07.04 PAVIMENTO FLEXIBLE S/ 453,511.77 S/ 453,511.77
07.04.01 CONFORMACION Y COMPACTACION DE SUBRASANTE C/ EQUIPO PARA PAVIMENTOS m2 4,184.46 5.18 S/ 21,675.50 S/ 21,675.50
07.04.02 BASE GRANULAR E=0.20 m , CON EQUIPO m2 4,184.46 43.13 S/ 180,475.76 S/ 180,475.76
07.04.03 IMPRIMACION ASFALTICA m2 4,184.46 12.20 S/ 51,050.41 S/ 51,050.41
07.04.04 CARPETA ASFALTICA EN CALIENTE DE 2" m2 4,184.46 47.87 S/ 200,310.10 S/ 200,310.10
07.05 SEÑALIZACION HORIZONTAL S/ 10,564.69 S/ 10,564.69
07.05.01 LINEA CENTRAL m 123.00 18.59 S/ 2,286.57 S/ 2,286.57
07.05.02 LINEA DE PARE m2 21.49 41.94 S/ 901.29 S/ 901.29
07.05.03 LINEA DE CRUCE PEATONAL m2 113.68 41.94 S/ 4,767.74 S/ 4,767.74
07.05.04 PALABRAS, SIMBOLOS Y LEYENDA m2 62.21 41.94 S/ 2,609.09 S/ 2,609.09
07.06 SEÑALIZACION VERTICAL S/ 1,894.72 S/ 1,894.72
07.06.01 SEÑALES DE INFORMACION und 4.00 473.68 S/ 1,894.72 S/ 1,894.72
07.07 OTROS S/ 2,703.00 S/ 2,703.00
07.07.01 NIVELACION DE BUZONES DE ALCANTARILLADO und 10.00 270.30 S/ 2,703.00 S/ 2,703.00
08 EQUIPAMIENTO S/ 2,700.00 S/ 2,700.00
08.01 COLOCACION DE BANCAS ORNAMENTALES und 6.00 450.00 S/ 2,700.00 S/ 2,700.00
09 TRABAJOS FINALES S/ 16,919.84 S/ 16,919.84
09.01 LIMPIEZA FINAL DE OBRA m2 7,833.26 2.16 S/ 16,919.84 S/ 16,919.84
COSTO DIRECTO S/ 1,024,523.57 S/ 321,901.07 S/ 702,622.50
GASTOS GENERALES (11.52%) S/ 118,045.24 S/ 37,089.33 S/ 80,955.91
UTILIDADES (5.00%) S/ 51,226.18 S/ 16,095.05 S/ 35,131.13

SUB TOTAL S/ 1,193,794.99 S/ 375,085.45 S/ 818,709.54


I.G.V. (18.00%) S/ 214,883.10 S/ 67,515.38 S/ 147,367.72

TOTAL PRESUPUESTO S/ 1,408,678.09 S/ 442,600.83 S/ 966,077.26


GASTOS SUPERVISION (4.10%) S/ 57,754.16 S/ 18,146.12 S/ 39,608.04

PRESUPUESTO TOTAL S/ 1,466,432.25 S/ 460,746.95 S/ 1,005,685.30


PORCENTAJE DE AVANCE MENSUAL 31.42% 68.58%
PORCENTAJE ACUMULADO 31.42% 100.00%