CRONOGRAMA VALORIZADO: "MEJORAMIENTO Y REDISEÑO DE LA VÍA DE LOS JIRONES: CONDE DE SUPERUNDA (CDRAS 2,3,4), RUFINO TORRICO (CDRAS.

1,2,3 Y 4), CAILLOMA (CDRAS. 1,2, Y 3), CAMANÁ (CDRAS. 1,2,3,4), RINCONADA DE SANTO DOMINGO (CDRAS. 1 Y 2) Y CALLAO (CDRAS. 2,3 Y 4) DE LA ZONA DE INTERVENCIÓN 02, DAMERO DEL EJE ESTRUCTURANTE
CALLAO, EN EL CENTRO HISTÓRICO DE LIMA, DISTRITO DE LIMA, PROVINCIA DE LIMA - LIMA, DEPARTAMENTO LIMA”

Item Descripción Und. Metrado Precio S/. Parcial S/. MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12 MES 13 MES 14 MES 15 MES 16
01 OBRAS GENERALES 1,469,682.04 233654.47 94115.6 97252.78 97252.78 94115.6 97252.78 94115.6 37646.25 3137.18 87841.22 97252.78 94115.6 97252.78 94115.6 97252.78 53308.23
01.01 OBRAS PROVISIONALES 165,026.59 76404.4 6745.74 6970.6 6970.6 6745.74 6970.6 6745.74 2698.29 224.85 6296.02 6970.6 6745.74 6970.6 6745.74 6970.6 3850.69
01.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 8.50m x 3.60m und 1.00 2,288.21 2,288.21 2288.21 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
01.01.02 CERCO PERIMETRICO DESMONTABLE Y TEMPORAL m 150.00 139.24 20,886.00 20886 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
01.01.03 CERCO PROVISIONAL DE MALLA HDP H=1.00M m 4,592.34 10.52 48,311.42 48311.42 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
01.01.04 ALQUILER DE ALMACEN, OFICINA Y CASETA DE GUARDIANIA mes 9.00 9,558.00 86,022.00 4523.39 6203.51 6410.29 6410.29 6203.51 6410.29 6203.51 2481.4 206.78 5789.94 6410.29 6203.51 6410.29 6203.51 6410.29 3541.17
01.01.05 BAÑOS QUIMICOS PARA EL PERSONAL mes 9.00 835.44 7,518.96 395.38 542.23 560.31 560.31 542.23 560.31 542.23 216.89 18.07 506.08 560.31 542.23 560.31 542.23 560.31 309.52
01.02 INSTALACIONES PROVISIONALES 48,424.55 22495.2 1978.71 2044.67 2044.67 1978.71 2044.67 1978.71 791.49 65.96 1846.8 2044.67 1978.71 2044.67 1978.71 2044.67 1063.56
01.02.01 OBTENCION DEL SERVICIO DE AGUA PARA LA CONSTRUCCION glb 1.00 2,124.00 2,124.00 111.96 153.54 158.66 158.66 153.54 158.66 153.54 61.42 5.12 143.31 158.66 153.54 158.66 153.54 158.66 82.53
01.02.02 TRATAMIENTO Y DISTRIBUCION DE AGUA PARA LA CONSTRUCCION mes 9.00 1,494.24 13,448.16 708.86 972.16 1004.56 1004.56 972.16 1004.56 972.16 388.86 32.41 907.35 1004.56 972.16 1004.56 972.16 1004.56 522.53
01.02.03 INSTALACION DE DESAGUE PARA LA CONSTRUCCION glb 1.00 944.00 944.00 49.76 68.24 70.52 70.52 68.24 70.52 68.24 27.3 2.27 63.69 70.52 68.24 70.52 68.24 70.52 36.68
01.02.04 CONEXION E INSTALACION DE ENERGIA ELECTRICA PROVISIONAL glb 1.00 2,360.00 2,360.00 124.4 170.6 176.29 176.29 170.6 176.29 170.6 68.24 5.69 159.23 176.29 170.6 176.29 170.6 176.29 91.7
01.02.05 CONSUMO Y MANTENIMIENTO DE ENERGIA ELECTRICA PROVISIONAL mes 9.00 944.00 8,496.00 447.83 614.17 634.64 634.64 614.17 634.64 614.17 245.67 20.47 573.22 634.64 614.17 634.64 614.17 634.64 330.12
01.02.06 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPOS Y HERRAMIENTAS glb 1.00 21,052.39 21,052.39 21052.39 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
01.03 SEGURIDAD Y SALUD EN OBRA 430,620.61 91340.87 25851.94 26713.67 26713.67 25851.94 26713.67 25851.94 10340.78 861.73 24128.47 26713.67 25851.94 26713.67 25851.94 26713.67 14407.01
01.03.01 ELABORACION,IMPLEMENTACION Y ADMINISTRACION DE PLAN DE SEGURIDAD Y SALUD EN ELglb TRABAJO 1.00 21,981.21 21,981.21 1155.86 1585.18 1638.02 1638.02 1585.18 1638.02 1585.18 634.07 52.84 1479.5 1638.02 1585.18 1638.02 1585.18 1638.02 904.88
01.03.02 IMPLEMENTACIÓN DE EQUIPOS DE PROTECCIÓN INDIVIDUAL mes 9.00 16,433.45 147,901.05 7777.25 10665.94 11021.47 11021.47 10665.94 11021.47 10665.94 4266.38 355.53 9954.88 11021.47 10665.94 11021.47 10665.94 11021.47 6088.47
01.03.03 IMPLEMENTACIÓN DE EQUIPOS DE PROTECCIÓN COLECTIVA mes 9.00 1,752.73 15,774.57 829.49 1137.59 1175.51 1175.51 1137.59 1175.51 1137.59 455.04 37.92 1061.75 1175.51 1137.59 1175.51 1137.59 1175.51 649.37
01.03.04 CAPACITACION EN SEGURIDAD Y SALUD mes 9.00 1,248.00 11,232.00 590.63 810 837 837 810 837 810 324 27 756 837 810 837 810 837 462.38
01.03.05 SEÑALIZACION TEMPORAL DE SEGURIDAD mes 9.00 8,054.50 72,490.50 72490.5 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
01.03.06 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TRABAJO glb 1.00 15,933.58 15,933.58 837.85 1149.06 1187.36 1187.36 1149.06 1187.36 1149.06 459.62 38.3 1072.45 1187.36 1149.06 1187.36 1149.06 1187.36 655.92
01.03.07 MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL mes 9.00 16,145.30 145,307.70 7659.29 10504.17 10854.31 10854.31 10504.17 10854.31 10504.17 4201.67 350.14 9803.89 10854.31 10504.17 10854.31 10504.17 10854.31 5645.99
01.04 PLAN PARA LA VIGILANCIA, PREVENCIÓN Y CONTROL DE COVID-19 EN EL TRABAJO 621,943.34 32704.35 44851.68 46346.74 46346.74 44851.68 46346.74 44851.68 17940.68 1495.05 41861.57 46346.74 44851.68 46346.74 44851.68 46346.74 25602.84
01.04.01 IMPLEMENTACIÓN DEL PLAN DE VIGILANCIA COVID-19 ANTES DEL INICIO DE LABORES glb 1.00 93,888.00 93,888.00 4937.02 6770.77 6996.46 6996.46 6770.77 6996.46 6770.77 2708.31 225.69 6319.38 6996.46 6770.77 6996.46 6770.77 6996.46 3864.98
01.04.02 PLAN DE VIGILANCIA COVID-19 EN LA ETAPA DE EJECUCIÓN EFECTIVA glb 1.00 528,055.34 528,055.34 27767.33 38080.91 39350.28 39350.28 38080.91 39350.28 38080.91 15232.37 1269.36 35542.19 39350.28 38080.91 39350.28 38080.91 39350.28 21737.86
01.05 MITIGACION AMBIENTAL 203,666.95 10709.65 14687.53 15177.1 15177.1 14687.53 15177.1 14687.53 5875.01 489.59 13708.36 15177.1 14687.53 15177.1 14687.53 15177.1 8384.13
01.05.01 PROGRAMA DE MEDIDAS PREVENTIVAS, MITIGADORAS Y CORRECTIVAS glb 1.00 18,349.00 18,349.00 964.87 1323.25 1367.35 1367.35 1323.25 1367.35 1323.25 529.3 44.11 1235.03 1367.35 1323.25 1367.35 1323.25 1367.35 755.35
01.05.02 PROGRAMA DE MANEJO DE RESIDUOS SOLIDOS glb 1.00 11,888.50 11,888.50 625.15 857.34 885.92 885.92 857.34 885.92 857.34 342.94 28.58 800.19 885.92 857.34 885.92 857.34 885.92 489.4
01.05.03 PROGRAMA DE MONITOREO AMBIENTAL glb 1.00 28,674.00 28,674.00 1507.8 2067.84 2136.76 2136.76 2067.84 2136.76 2067.84 827.13 68.93 1929.98 2136.76 2067.84 2136.76 2067.84 2136.76 1180.39
01.05.04 PROGRAMA DE RELACIONES COMUNITARIAS glb 1.00 8,496.00 8,496.00 446.75 612.69 633.12 633.12 612.69 633.12 612.69 245.08 20.42 571.85 633.12 612.69 633.12 612.69 633.12 349.75
01.05.05 PROGRAMA DE EDUCACION Y CAPACITACIONAMBIENTAL mes 9.00 9,800.00 88,200.00 4637.92 6360.58 6572.6 6572.6 6360.58 6572.6 6360.58 2544.23 212.02 5936.54 6572.6 6360.58 6572.6 6360.58 6572.6 3630.83
01.05.06 PROGRAMA DE CIERRE DE OBRAS glb 1.00 48,059.45 48,059.45 2527.16 3465.83 3581.35 3581.35 3465.83 3581.35 3465.83 1386.33 115.53 3234.77 3581.35 3465.83 3581.35 3465.83 3581.35 1978.41
02 ESTRUCTURAS 2,386,993.33 40578.07 60731.86 98414.24 177651.2 158006.14 127607.11 225074.3 107143.18 8928.62 302129.63 246862.92 228386.46 255656.65 170427.65 149326.41 30069.05
02.01 TRAZO, NIVELES Y REPLANTEO 169,010.60 35279.98 21542.11 10135.79 10135.79 9808.83 10135.79 9808.83 3923.54 326.96 9154.91 10135.79 9808.83 10135.79 9808.83 8868.82 0
02.01.01 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR C/EQUIPO m2 22,777.71 1.75 39,860.99 28127.71 11733.28 0 0 0 0 0 0 0 0 0 0 0 0 0 0
02.01.02 TRAZO, NIVELACION Y REPLANTEO DURANTE EL PROCESO DE OBRA m2 22,777.71 1.75 39,860.99 2207.49 3027.42 3128.33 3128.33 3027.42 3128.33 3027.42 1210.97 100.91 2825.59 3128.33 3027.42 3128.33 3027.42 2737.29 0
02.01.03 LIMPIEZA DE TERRENO MANUAL m2 22,777.71 3.92 89,288.62 4944.78 6781.41 7007.46 7007.46 6781.41 7007.46 6781.41 2712.57 226.05 6329.32 7007.46 6781.41 7007.46 6781.41 6131.53 0
02.02 REMOCIONES, DESMONTAJES, DEMOLICIONES 626,533.70 4384.18 19887.34 57794.78 81320.4 58312.91 56324.65 47898.79 19159.51 1596.65 48863.29 77368.63 76635.85 65574.87 9406.81 2005.2 0
02.02.01 REMOCIONES 9,422.25 3041.71 611.01 609.32 609.32 589.68 609.32 589.68 235.87 19.66 550.35 609.32 589.68 411.05 0 346.28 0
02.02.01.01 RETIRO DE SEÑALITICA VERTICAL und 50.00 26.70 1,335.00 62.06 125.16 129.33 129.33 125.16 129.33 125.16 50.06 4.17 116.81 129.33 125.16 83.96 0 0 0
02.02.01.02 RETIRO DE BASUREROS EXISTENTES und 57.00 67.63 3,854.91 167.15 361.4 373.44 373.44 361.4 373.44 361.4 144.56 12.05 337.3 373.44 361.4 254.48 0 0 0
02.02.01.03 RETIRO DE BOLARDOS EXISTENTES und 24.00 45.83 1,099.92 47.69 103.12 106.55 106.55 103.12 106.55 103.12 41.25 3.44 96.24 106.55 103.12 72.61 0 0 0
02.02.01.04 RETIRO DE ESTACIONAMIENTO PARA BICICLETAS und 3.00 68.75 206.25 206.25 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
02.02.01.05 RETIRO DE REFLECTORES EN EL PISO und 36.00 56.87 2,047.32 2025.99 21.33 0 0 0 0 0 0 0 0 0 0 0 0 0 0
02.02.01.06 RETIRO DE REJILLAS METALICAS m2 40.50 8.55 346.28 0 0 0 0 0 0 0 0 0 0 0 0 0 0 346.28 0
02.02.01.07 TRASLADO DE MOBILIARIO A PUNTO DE ACOPIO ENTRE 120ML Y 1000ML glb 1.00 532.57 532.57 532.57 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
02.02.02 DESMONTAJE DE PISOS 227,984.92 0 3477.56 20472.66 23602.44 22841.08 23602.44 22841.08 9136.44 761.38 21318.33 23602.44 22841.08 22422.32 9406.81 1658.92 0
02.02.02.01 DESMONTAJE DE PISTA DE ADOQUIN DE CONCRETO ESPINA DE PEZ m2 264.10 18.38 4,854.16 0 240.54 537.42 537.42 520.09 537.42 520.09 208.04 17.34 485.42 537.42 520.09 192.87 0 0 0
02.02.02.02 DESMONTAJE DE PISTA DE ADOQUIN DE CONCRETO ESPINA DE PEZ DOBLE m2 240.11 18.38 4,413.22 0 202.93 488.61 488.61 472.85 488.61 472.85 189.14 15.76 441.32 488.61 472.85 191.11 0 0 0
02.02.02.03 DESMONTAJE DE VEREDA DE LAJA m2 921.58 17.09 15,749.80 0 400.1 1574.98 1574.98 1524.17 1574.98 1524.17 609.67 50.81 1422.56 1574.98 1524.17 1574.98 819.24 0 0
02.02.02.04 DESMONTAJE DE VEREDA DE PIEDRA PARTIDA m2 486.93 22.96 11,179.91 0 293.47 1155.26 1155.26 1117.99 1155.26 1117.99 447.2 37.27 1043.46 1155.26 1117.99 1155.26 228.26 0 0
02.02.02.05 DESMONTAJE DE MARTILLOS DE PIEDRA LAJA FORMATO 0.40 X 0.40 m2 1,087.00 18.38 19,979.06 0 524.45 2064.5 2064.5 1997.91 2064.5 1997.91 799.16 66.6 1864.71 2064.5 1997.91 2064.5 407.91 0 0
02.02.02.06 DESMONTAJE DE VEREDA DE ADOQUÍN DE CONCRETO APAREJO SOGA m2 4,140.48 18.38 76,102.02 0 1816.07 7148.98 7148.98 6918.37 7148.98 6918.37 2767.35 230.61 6457.14 7148.98 6918.37 7148.98 6918.37 1412.5 0
02.02.02.07 DESMONTAJE DE PISO PODODÁCTIL EXISTENTE m2 46.35 18.38 851.91 0 0 0 0 0 0 0 0 0 0 0 0 0 677.98 173.93 0
02.02.02.08 DESMONTAJE DE SARDINEL DE PIEDRA (INCLUIDO DE LOS MARTILLOS) m 4,256.42 22.16 94,322.27 0 0 7502.91 10632.69 10289.7 10632.69 10289.7 4115.88 342.99 9603.72 10632.69 10289.7 9989.59 0 0 0
02.02.02.09 TRASLADO DE MATERIAL RECUPERADO A PUNTO DE ACOPIO ENTRE 120ML Y 1000ML glb 1.00 532.57 532.57 0 0 0 0 0 0 0 0 0 0 0 0 105.03 355.05 72.49 0
02.02.03 DEMOLICIONES 144,593.30 0 2167.02 20304.41 20893.68 18985.4 16296.96 9162.3 3664.92 305.41 13765.09 39048.12 0 0 0 0 0
02.02.03.01 DEMOLICION DE VEREDA DE CONCRETO m2 351.93 18.25 6,422.72 0 66.9 1106.14 1106.14 1070.45 1106.14 1070.45 428.18 35.68 432.64 0 0 0 0 0 0
02.02.03.02 DEMOLICION DE SARDINEL DE CONCRETO SUMERGIDO m 4,654.31 12.17 56,642.95 0 0 8058.13 8361.58 8091.85 8361.58 8091.85 3236.74 269.73 7552.39 4619.1 0 0 0 0 0
02.02.03.03 DEMOLICION DE RAMPAS DE ACCESO EN VEREDA m2 108.32 18.25 1,976.84 0 0 260.83 680.91 658.95 376.15 0 0 0 0 0 0 0 0 0 0
02.02.03.04 DEMOLICION DE RAMPAS EN PISTAS m2 147.13 18.25 2,685.12 0 0 1409.69 1275.43 0 0 0 0 0 0 0 0 0 0 0 0
02.02.03.05 DEMOLICION DE BASE DE MARTILLOS Y VEREDAS DE LAJA m2 2,008.58 18.25 36,656.59 0 2100.12 9469.62 9469.62 9164.15 6453.09 0 0 0 0 0 0 0 0 0 0
02.02.03.06 ELIMINACION DE MATERIAL DEMOLICION, D=20Km. m3 817.59 49.18 40,209.08 0 0 0 0 0 0 0 0 0 5780.06 34429.02 0 0 0 0 0
02.02.04 DESMONTAJE DE CAJAS Y BUZONES 8,824.95 0 0 762.88 1729.79 1673.98 1729.79 1673.98 669.58 55.81 506.56 22.61 0 0 0 0 0
02.02.04.01 DESMONTAJE DE MARCO, TAPA Y CAJA DE REGISTRO DE AGUA DOMICILIARIAS und 469.00 7.42 3,479.98 0 0 275.5 719.2 696 719.2 696 278.4 23.2 72.5 0 0 0 0 0 0
02.02.04.02 DESMONTAJE DE MARCO, TAPA Y CAJA DE REGISTRO DE DESAGUE DOMICILIARIAS und 59.00 17.10 1,008.90 0 0 79.87 208.51 201.78 208.51 201.78 80.71 6.73 21.02 0 0 0 0 0 0
02.02.04.03 DESMONTAJE DE TAPA VALVULA DE AGUA und 9.00 6.09 54.81 0 0 3.97 11.33 10.96 11.33 10.96 4.38 0.37 1.51 0 0 0 0 0 0
02.02.04.04 DESMONTAJE DE TAPA DE BUZONES CIRCULARES (SEDAPAL) und 72.00 48.48 3,490.56 0 0 237.25 676.3 654.48 676.3 654.48 261.79 21.82 308.15 0 0 0 0 0 0
02.02.04.05 DESMONTAJE DE TAPAS DE CONCRETO CUADRADAS O RECTANGULARES und 72.00 9.23 664.56 0 0 40.15 114.45 110.76 114.45 110.76 44.3 3.69 103.38 22.61 0 0 0 0 0
02.02.04.06 DESMONTAJE DE TAPAS DE POZO A TIERRA und 17.00 7.42 126.14 0 0 126.14 0 0 0 0 0 0 0 0 0 0 0 0 0
02.02.05 TRASLADOS A ALMACEN CENTRAL 22,549.40 0 0 1559.37 20399.03 591.02 0 0 0 0 0 0 0 0 0 0 0
02.02.05.01 TRANSPORTE DE MOBILIARIO A ALMACEN PRINCIPAL vje 6.00 2,655.00 15,930.00 0 0 1393.88 14536.13 0 0 0 0 0 0 0 0 0 0 0 0
02.02.05.02 CARGUIO DE MATERIAL CON EQUIPO m3 343.33 19.28 6,619.40 0 0 165.49 5862.9 591.02 0 0 0 0 0 0 0 0 0 0 0
02.02.06 DEMOLICION DE PAVIMENTO ASFALTICO EXISTENTE 213,158.88 1342.47 13631.75 14086.14 14086.14 13631.75 14086.14 13631.75 5452.7 454.39 12722.96 14086.14 53205.09 42741.5 0 0 0
02.02.06.01 CORTE CON DISCO EN PAVIMENTO ASFALTICO E= 5" PROMEDIO m 384.00 5.64 2,165.76 56.85 216.58 223.8 223.8 216.58 223.8 216.58 86.63 7.22 202.14 223.8 216.58 51.44 0 0 0
02.02.06.02 FRESADO PAVIMENTO FLEXIBLE EXISTENTE, E promedio= 0.05m m2 13,647.17 9.83 134,151.68 1285.62 13415.17 13862.34 13862.34 13415.17 13862.34 13415.17 5366.07 447.17 12520.82 13862.34 13415.17 5421.96 0 0 0
02.02.06.03 ELIMINACION DE MATERIAL DE FRESADO,D=20 Km. m3 1,419.31 54.14 76,841.44 0 0 0 0 0 0 0 0 0 0 0 39573.34 37268.1 0 0 0
02.03 PAVIMENTO RIGIDO (CALZADA) CON LOSA DE CONCRETO EXISTENTE 47,022.41 0 3585.46 4858.98 4858.98 4702.24 4858.98 4702.24 1880.9 156.74 4388.76 4858.98 4702.24 3467.9 0 0 0
02.03.01 LIMPIEZA PROFUNDA DE LOSA DE CONCRETO EXISTENTE m 7,584.26 6.20 47,022.41 0 3585.46 4858.98 4858.98 4702.24 4858.98 4702.24 1880.9 156.74 4388.76 4858.98 4702.24 3467.9 0 0 0
02.04 PAVIMENTO RIGIDO (CALZADA) CON LOSA DE CONCRETO NUEVA 973,710.50 913.91 14622.59 15110.01 15110.01 14622.59 16466.67 124127.96 66764.63 5563.72 202529.55 103055.6 33650.39 96228.28 111020.44 123855.09 30069.05
02.04.01 DEMOLICION DE LOSA DE CONCRETO EXISTENTE H promedio = 15 cm m2 4,407.05 22.12 97,483.95 913.91 14622.59 15110.01 15110.01 14622.59 15110.01 14622.59 5849.04 487.42 1035.77 0 0 0 0 0 0
02.04.02 EXCAVACIÓN HASTA SUBRASANTE EN MATERIAL SUELTO CON MAQ. PESADA H promedio = 20 m3 cm 661.06 24.88 16,447.17 0 0 0 0 0 1002.25 6167.69 2467.08 205.59 5756.51 848.06 0 0 0 0 0
02.04.03 ELIMINACION DE DEMOLICION CARPETA ASFALTICA,D=20Km.(MATERIAL CONTAMINANTE) m3 1,833.33 49.18 90,163.17 0 0 0 0 0 0 0 0 0 59357.42 30805.75 0 0 0 0 0
02.04.04 CONFORMACION Y COMPACTACION DE SUBRASANTE E=0.15 M m2 4,081.03 7.94 32,403.38 0 0 0 0 0 354.41 12151.27 4860.51 405.04 11341.18 3290.97 0 0 0 0 0
02.04.05 SUB-BASE GRANULAR E=0.15 M m2 4,081.03 16.90 68,969.41 0 0 0 0 0 0 23169.41 10345.41 862.12 24139.29 10453.18 0 0 0 0 0
02.04.06 ENCOFRADO Y DESENCOFRADO PAVIMENTO RIGIDO m2 4,081.03 61.81 252,248.46 0 0 0 0 0 0 68017 43242.59 3603.55 100899.38 36485.94 0 0 0 0 0
02.04.07 SUMINISTRO Y COLOCACION DE ACERO PARA DOWELS H=12.5 CM, L=0.50CM m 827.40 88.62 73,324.19 0 0 0 0 0 0 0 0 0 0 19771.34 31424.65 22128.19 0 0 0
02.04.08 SUMINISTRO Y COLOCACION DE ACERO FY=4200KG/CM2 EN JUNTA und 486.50 9.15 4,451.48 0 0 0 0 0 0 0 0 0 0 1400.36 2225.74 825.38 0 0 0
02.04.09 PAVIMENTO DE CONCRETO F'C=280KG/CM2 CEMENTO HS, h=0.175M m2 4,081.03 70.67 288,406.39 0 0 0 0 0 0 0 0 0 0 0 0 67436.2 101790.49 105183.51 13996.19
02.04.10 FLOTADO Y TEXTURIZADO DE CONCRETO m2 4,081.03 2.55 10,406.63 0 0 0 0 0 0 0 0 0 0 0 0 2405.02 3630.22 3751.23 620.16
02.04.11 CURADO DE CONCRETO m2 4,081.03 2.02 8,243.68 0 0 0 0 0 0 0 0 0 0 0 0 1830.58 2909.53 3006.52 497.05
02.04.12 CORTE CON DISCO EN JUNTAS DE CONTRACCION EN LOSA DE PAVIMENTO m 1,390.92 5.48 7,622.24 0 0 0 0 0 0 0 0 0 0 0 0 1602.91 2690.2 2779.88 549.25
02.04.13 JUNTAS DE DILATACION C/MEZCLA ASFALTICA EN LOSA DE PAVIMENTO m 139.09 4.44 617.56 0 0 0 0 0 0 0 0 0 0 0 0 0 0 324.22 293.34
02.04.14 JUNTAS CON SELLO ELASTOMERICO EN LOSA DE PAVIMENTO m 1,390.92 9.34 12,991.19 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4092.22 8898.97
02.04.15 RAMPAS VEHICULARES DE CONCRETO F´C=280 KG/CM2, ACABADO BRUÑADO m2 68.02 146.01 9,931.60 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4717.51 5214.09
02.05 PAVIMENTO ARTICULADO (CALZADA) SOBRE BASE DE AFIRMADO 31,282.75 0 0 0 0 0 0 0 0 0 1225.74 11622.9 3115.44 4353.93 6562.44 4402.3 0
02.05.01 EXCAVACIÓN HASTA SUBRASANTE EN MATERIAL SUELTO CON MAQ. PESADA H promedio = 20 m3 cm 125.12 24.88 3,112.99 0 0 0 0 0 0 0 0 0 1225.74 1887.25 0 0 0 0 0
02.05.02 ELIMINACIÓN DE EXCEDENTE DE EXCAVACION C/VOLQUETE 15M3 D=25.0Km.(CARGUIO, TRANSPORTEm3 Y162.65
DISPOSICION FINAL)
54.19 8,814.00 0 0 0 0 0 0 0 0 0 0 8814 0 0 0 0 0
02.05.03 CONFORMACION Y COMPACTACION DE SUBRASANTE C/ MOTONIVELADORA 125 HP m2 625.59 9.96 6,230.88 0 0 0 0 0 0 0 0 0 0 921.65 3115.44 2193.79 0 0 0
02.05.04 BASE GRANULAR C/EQUIPO LIVIANO E=0.20 m m2 625.59 20.98 13,124.88 0 0 0 0 0 0 0 0 0 0 0 0 2160.14 6562.44 4402.3 0
02.06 ESTRUCTURAS - PAVIMENTO DE USO PEATONAL (VEREDAS) 539,433.37 0 1094.36 10514.68 66226.02 70559.57 39821.02 38536.48 15414.6 1284.55 35967.38 39821.02 100473.71 75895.88 33629.13 10195 0
02.06.01 VEREDAS SOBRE BASE AFIRMADO 461,485.56 0 1094.36 10242.29 37641.91 36427.66 37641.91 36427.66 14571.07 1214.26 33999.15 37641.91 98364.89 73764.87 32258.67 10195 0
02.06.01.01 EXCAVACIÓN HASTA SUBRASANTE EN MATERIAL SUELTO CON MAQ. PESADA H promedio = 20 m3cm 1,563.93 24.88 38,910.58 0 1094.36 4307.96 4307.96 4168.99 4307.96 4168.99 1667.6 138.97 3891.06 4307.96 4168.99 2379.8 0 0 0
02.06.01.02 ELIMINACION DE EXCEDENTES DE EXCAVACION C/VOLQUETE 15M3 D=25.0KM (CARGUIO, TRANSPORTE
m3 2,033.11
Y DISPOSICION FINAL)
49.18 99,988.35 0 0 0 0 0 0 0 0 0 0 0 61937.23 38051.12 0 0 0
02.06.01.03 CONFORMACION Y COMPACTACION DE SUBRASANTE (EQUIPO LIVIANO) m2 10,426.20 9.96 103,844.95 0 0 2379.78 10730.64 10384.5 10730.64 10384.5 4153.8 346.15 9692.2 10730.64 10384.5 10730.64 10384.5 2812.47 0
02.06.01.04 BASE GRANULAR PARA VEREDA C/EQUIPO LIVIANO E=0.10m m2 10,426.20 20.98 218,741.68 0 0 3554.55 22603.31 21874.17 22603.31 21874.17 8749.67 729.14 20415.89 22603.31 21874.17 22603.31 21874.17 7382.53 0
02.06.02 VARIOS 77,947.81 0 0 272.39 28584.11 34131.91 2179.11 2108.82 843.53 70.29 1968.23 2179.11 2108.82 2131.01 1370.46 0 0
02.06.02.01 TECHO DE BUZON DE ALCANTARILLADO, INCLUYE ARMADURA und 63.00 927.43 58,428.09 0 0 0 26405 32023.09 0 0 0 0 0 0 0 0 0 0 0
02.06.02.02 NIVELACION DE BUZONES Y CAJAS EN GENERAL 19,519.72 0 0 272.39 2179.11 2108.82 2179.11 2108.82 843.53 70.29 1968.23 2179.11 2108.82 2131.01 1370.46 0 0
02.06.02.02.01 SUMINISTRO E INSTALACION DE TAPA DE BUZON EN VEREDA und 9.00 336.30 3,026.70 0 0 41.89 335.1 324.29 335.1 324.29 129.72 10.81 302.67 335.1 324.29 335.1 228.35 0 0
02.06.02.02.02 NIVELACION DE TAPAS CUADRADAS Y RECTANGULARES DE CONCRETO (EN VEREDA) und 67.00 225.94 15,137.98 0 0 209.5 1675.99 1621.93 1675.99 1621.93 648.77 54.06 1513.8 1675.99 1621.93 1675.99 1142.11 0 0
02.06.02.02.03 NIVELACION DE TAPAS DE VALVULAS DE AGUA und 9.00 150.56 1,355.04 0 0 21 168.02 162.6 168.02 162.6 65.04 5.42 151.76 168.02 162.6 119.92 0 0 0
03 ARQUITECTURA 11,341,575.04 0 0 0 651876.85 946095.86 978819.59 946766.02 376526.24 31377.2 878561.22 972692.79 941315.6 972692.79 1118272.77 1786054.02 740524.12
03.01 REVESTIMIENTOS 9,944,544.80 0 0 0 651876.85 941315.6 972692.79 941315.6 376526.24 31377.2 878561.22 972692.79 941315.6 972692.79 944645.69 1001448.22 318084.24
03.01.01 PAVIMENTO DE USO VEHICULAR 5,556,124.19 0 0 0 255630.31 533136.6 550907.82 533136.6 213254.63 17771.23 497594.15 550907.82 533136.6 550907.82 533136.6 550907.82 235696.25
03.01.01.01 PISO ADOQUIN DE PIEDRA GRANITICA GRIS OSCURO DE 0.15 x 0.30 , e=8cm, APAREJO SOGAm2 10,352.10 422.76 4,376,453.80 0 0 0 221261.8 418132.53 432070.28 418132.53 167253.01 13937.75 390257.03 432070.28 418132.53 432070.28 418132.53 432070.28 182932.98
03.01.01.02 PISO ADOQUIN DE PIEDRA GRANITICA GRIS OSCURO DE 0.15 x 0.30 , e=8cm, APAREJO ESPINA
m2DE PEZ 845.29 421.06 355,917.81 0 0 0 17994.25 34004.89 35138.38 34004.89 13601.95 1133.5 31737.89 35138.38 34004.89 35138.38 34004.89 35138.38 14877.14
03.01.01.03 PISO BALDOSA DE BASALTO de 0.30 x 0.60, e=4cm APAREJO SOGA m2 589.03 326.08 192,070.90 0 0 0 6343.48 19271.33 19913.71 19271.33 7708.53 642.38 17986.57 19913.71 19271.33 19913.71 19271.33 19913.71 2649.81
03.01.01.04 SARDINEL SUMERGIDO ADOQUIN DE PIEDRA GRANITICA GRIS CLARO DE 0.15 x 0.30 ,e=8cm m 3,363.05 187.83 631,681.68 0 0 0 10030.78 61727.85 63785.45 61727.85 24691.14 2057.6 57612.66 63785.45 61727.85 63785.45 61727.85 63785.45 35236.32
03.01.02 PAVIMENTO DE USO PEATONAL 4,388,420.61 0 0 0 396246.54 408179 421784.97 408179 163271.61 13605.97 380967.07 421784.97 408179 421784.97 411509.09 450540.4 82387.99
03.01.02.01 PISO CON PIEDRA TALAMOYE PARTIDA IRREGULAR ,e=5cm a 10cm, APAREJO IRREGULAR m2 1,456.22 153.72 223,850.14 0 0 0 18799.91 20985.95 21685.48 20985.95 8394.38 699.53 19586.89 21685.48 20985.95 21685.48 20985.95 21685.48 5683.69
03.01.02.02 PISO BALDOSA DE BASALTO de 0.30 x 0.60, e=4cm APAREJO SOGA m2 7,503.97 326.08 2,446,894.54 0 0 0 236087.09 229396.36 237042.91 229396.36 91758.55 7646.55 214103.27 237042.91 229396.36 237042.91 229396.36 237042.91 31542
03.01.02.03 PISO PODOTACTIL BALDOSA DE CONCRETO 0.30x 0.30m,e=0.02 a 0.05m m2 108.69 239.23 26,001.91 0 0 0 0 0 0 0 0 0 0 0 0 0 0 15646.5 10355.41
03.01.02.04 SARDINEL SUMERGIDO ADOQUIN DE PIEDRA GRANITICA GRIS CLARO DE 0.15 x 0.30 ,e=8cm m 8,905.10 187.83 1,672,644.93 0 0 0 141359.54 157796.69 163056.58 157796.69 63118.68 5259.89 147276.91 163056.58 157796.69 163056.58 157796.69 163056.58 32216.82
03.01.02.05 SARDINEL ADOQUIN DE PIEDRA GRANITICA GRIS CLARO DE 0.15 x 0.30 ,e=8cm EN CURVAS m 93.07 204.46 19,029.09 0 0 0 0 0 0 0 0 0 0 0 0 0 3330.09 13108.93 2590.07
03.02 MOBILIARIO 1,152,788.80 0 0 0 0 0 0 0 0 0 0 0 0 0 173627.08 748015.62 231146.1
03.02.01 SUMINISTRO E INSTALACION DE BOLARDOS B-1 und 752.00 670.16 503,960.32 0 0 0 0 0 0 0 0 0 0 0 0 0 110591.29 347172.66 46196.36
03.02.02 SUMINISTRO E INSTALACION DE BOLARDOS B-2 und 478.00 587.56 280,853.68 0 0 0 0 0 0 0 0 0 0 0 0 0 34229.04 217661.6 28963.04
03.02.03 SUMINISTRO E INSTALACION DE BOLARDOS B-4 und 477.00 495.52 236,363.04 0 0 0 0 0 0 0 0 0 0 0 0 0 28806.75 183181.36 24374.94
03.02.04 SUMINISTRO Y COLOCACION DE TACHO DE BASURA und 58.00 1,165.72 67,611.76 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 67611.76
03.02.05 SUMINISTRO Y COLOCACION DE ESTACION DE BICICLETAS und 8.00 8,000.00 64,000.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 64000
03.03 SEÑALIZACION 16,357.49 0 0 0 0 4780.26 6126.8 5450.42 0 0 0 0 0 0 0 0 0
03.03.01 SUMINISTRO E INSTALACION DE NOMENCLATURA DE VIA ADOSADO A PARED und 38.00 354.00 13,452.00 0 0 0 0 4780.26 5957.31 2714.42 0 0 0 0 0 0 0 0 0
03.03.02 CARGUÍO Y TRASLADO DE MATERIAL EXCEDENTE A ALMACÉN CENTRAL glb 1.00 2,905.49 2,905.49 0 0 0 0 0 169.49 2736 0 0 0 0 0 0 0 0 0
03.04 PAISAJISMO 218,325.95 0 0 0 0 0 0 0 0 0 0 0 0 0 0 27032.18 191293.78
03.04.01 RETIRO DE GRASS m2 617.49 18.48 11,411.22 0 0 0 0 0 0 0 0 0 0 0 0 0 0 11411.22 0
03.04.02 PREPARACION DE TERRENO m2 617.49 67.46 41,655.88 0 0 0 0 0 0 0 0 0 0 0 0 0 0 15620.96 26034.93
03.04.03 TIERRA DE CHACRA PREPARADA PARA JARDIN m3 617.49 147.74 91,227.97 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 91227.97
03.04.04 PLANTACION 74,030.88 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 74030.88
03.04.04.01 SEMBRADO DE GRASS EN CHAMPA m2 617.49 119.89 74,030.88 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 74030.88
03.05 VARIOS 9,558.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 9558 0
03.05.01 CAMBIO DE REJILLAS METALICAS m2 40.50 236.00 9,558.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 9558 0
04 INSTALACIONES SANITARIAS 281,385.03 6084.54 0 0 13509.08 21600.85 23159.18 22412.1 8964.84 747.07 20917.96 23159.18 22412.1 23159.18 4759.33 90499.66 0
04.01 HIDRANTES 96,584.20 6084.54 0 0 0 0 0 0 0 0 0 0 0 0 0 90499.66 0
04.01.01 RETIRO DE HIDRANTES und 7.00 869.22 6,084.54 6084.54 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
04.01.02 INSTALACION Y COLOCACÓN DE HIDRANTES und 7.00 12,001.38 84,009.66 0 0 0 0 0 0 0 0 0 0 0 0 0 0 84009.66 0
04.01.03 GESTION DE HIDRANTES glb 1.00 6,490.00 6,490.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 6490 0
04.02 CONEXIONES DOMICILIARIAS 184,800.83 0 0 0 13509.08 21600.85 23159.18 22412.1 8964.84 747.07 20917.96 23159.18 22412.1 23159.18 4759.33 0 0
04.02.01 SUMINISTRO Y COLOCACIÓN DE MARCO, TAPA Y CAJA DE REGISTRO DE AGUA und 469.00 254.34 119,285.46 0 0 0 12346.05 14314.26 14791.4 14314.26 5725.7 477.14 13359.97 14791.4 14314.26 14791.4 59.64 0 0
04.02.02 SUMINISTRO Y COLOCACIÓN DE MARCO, TAPA Y CAJA DE REGISTRO DE DESAGUE und 59.00 310.43 18,315.37 0 0 0 1163.03 2197.84 2271.11 2197.84 879.14 73.26 2051.32 2271.11 2197.84 2271.11 741.77 0 0
04.02.03 REPOSICIÓN DE CONEXIONES SANITARIAS EXISTENTES glb 1.00 47,200.00 47,200.00 0 0 0 0 5088.75 6096.67 5900 2360 196.67 5506.67 6096.67 5900 6096.67 3957.92 0 0
05 INSTALACIONES ELECTRICAS 430,876.90 0 361.18 37829.2 62959.32 61197.23 63237.14 61197.23 24478.89 2039.92 28720.6 16056 4505.54 4314.99 12426 39158.86 12394.87
05.01 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR C/EQUIPO m2 21,536.00 1.75 37,688.00 0 361.18 3894.43 3894.43 3768.8 3894.43 3768.8 1507.52 125.63 3517.55 3894.43 3768.8 3894.43 1397.6 0 0
05.02 EXCAVACION A MANO EN TERRENO NORMAL m3 918.80 78.77 72,373.88 0 0 9951.41 10683.76 10339.13 10683.76 10339.13 4135.65 344.64 9649.85 6246.56 0 0 0 0 0
05.03 CANALIZACION EN PISTA, DUCTO DE CONCRETO DE 4 VÍAS m 236.55 187.91 44,450.11 0 0 0 7377.48 7408.35 7655.3 7408.35 2963.34 246.95 6914.46 4475.88 0 0 0 0 0
05.04 CANALIZACIÓN EN VEREDA DE 4 VIAS m 1,832.31 106.92 195,910.59 0 0 23111.33 37957.68 36733.24 37957.68 36733.24 14693.29 1224.44 7499.7 0 0 0 0 0 0
05.05 CANALIZACIÓN EN VEREDA DE 1 VIA m 103.50 106.81 11,054.84 0 0 654.08 2284.67 2210.97 2284.67 2210.97 884.39 73.7 451.41 0 0 0 0 0 0
05.06 ELIMINACION DE MATERIAL EXCEDENTE A UNA DISTANCIA d=25KM C/VOLQUETE m3 19.11 35.47 677.83 0 0 0 0 0 0 0 0 0 0 677.83 0 0 0 0 0
05.07 RELLENO COMPACTADO CON MATERIAL PROPIO m3 902.87 6.80 6,139.52 0 0 217.95 761.3 736.74 761.3 736.74 294.7 24.56 687.63 761.3 736.74 420.56 0 0 0
05.08 CAJA DE PASO TIPO CE-02 und 117.00 284.03 33,231.51 0 0 0 0 0 0 0 0 0 0 0 0 0 9886.37 20603.54 2741.6
05.09 CAJA DE PASO TIPO CE-03 und 13.00 295.29 3,838.77 0 0 0 0 0 0 0 0 0 0 0 0 0 1142.03 2380.04 316.7
05.10 TAPA DE CONCRETO PARA CAJA DE PASO TIPO CE-02 und 117.00 190.69 22,310.73 0 0 0 0 0 0 0 0 0 0 0 0 0 0 16175.28 6135.45
05.11 TAPA DE CONCRETO PARA CAJA DE PASO TIPO CE-03 und 13.00 246.24 3,201.12 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3201.12
COSTO DIRECTO S/ 15,910,512.34 S/ 280,317.08 S/ 155,208.64 S/ 233,496.22 S/ 1,003,249.23 S/ 1,281,015.68 S/ 1,290,075.80 S/ 1,349,565.25 S/ 554,759.40 S/ 46,229.99 S/ 1,318,170.63 S/ 1,356,023.67 S/ 1,290,735.30 S/ 1,353,076.39 S/ 1,400,001.35 S/ 2,162,291.73 S/ 836,296.27

GASTOS GENERALES (10.00%) S/ 1,591,051.23 S/ 28,031.71 S/ 15,520.86 S/ 23,349.62 S/ 100,324.92 S/ 128,101.57 S/ 129,007.58 S/ 134,956.53 S/ 55,475.94 S/ 4,623.00 S/ 131,817.06 S/ 135,602.37 S/ 129,073.53 S/ 135,307.64 S/ 140,000.14 S/ 216,229.17 S/ 83,629.63

SERVICIO DE AFECTACION DE REDES ELECTRICAS S/ 2,908,495.60 S/ 157,874.30 S/ 216,513.32 S/ 223,730.43 S/ 223,730.43 S/ 216,513.32 S/ 223,730.43 S/ 216,513.32 S/ 86,605.33 S/ 7,217.11 S/ 202,079.10 S/ 223,730.43 S/ 216,513.32 S/ 223,730.43 S/ 216,513.32 S/ 223,730.43 S/ 29,770.58

SERVICIO DE REDES DE AGUA POTABLE Y CONEXIONES DOMICILIARIAS S/ 1,986,435.71 S/ 114,350.74 S/ 156,823.87 S/ 162,051.33 S/ 162,051.33 S/ 156,823.87 S/ 162,051.33 S/ 156,823.87 S/ 62,729.55 S/ 5,227.46 S/ 146,368.95 S/ 162,051.33 S/ 156,823.87 S/ 162,051.33 S/ 156,823.87 S/ 63,382.98 S/ -

TOTAL S/ 22,396,494.88 S/ 580,573.83 S/ 544,066.69 S/ 642,627.60 S/ 1,489,355.91 S/ 1,782,454.44 S/ 1,804,865.14 S/ 1,857,858.97 S/ 759,570.22 S/ 63,297.56 S/ 1,798,435.74 S/ 1,877,407.80 S/ 1,793,146.02 S/ 1,874,165.79 S/ 1,913,338.68 S/ 2,665,634.31 S/ 949,696.48

PORCENTAJES EJECUTADOS 2.59% 2.43% 2.87% 6.65% 7.96% 8.06% 8.30% 3.39% 0.28% 8.03% 8.38% 8.01% 8.37% 8.54% 11.90% 4.24%

PORCENTAJES ACUMULADOS 2.59% 5.02% 7.89% 14.54% 22.50% 30.56% 38.85% 42.24% 42.53% 50.56% 58.94% 66.95% 75.31% 83.86% 95.76% 100.00%