PLAN SEMANAL
S06
(02 Feb – 08 Feb)
PLANEAMIENTO
Programas y cumplimientos
Cumplimiento Mensual al 31-Ene
Cumplimiento Mensual al 31-ene
Plan Diferencia
Realizado % Cump. Mes Oz de Au Acumuadas
Mensual Mes
TMS: 650,650 613,247 94% -37,403 Plan Mensual - Oz_Mes Plan Mensual - Oz Stock in Pad
Realizado - Oz_Mes Realizado - Oz Stock in Pad
Ley Au: 0.379 0.401 106% 0.022
Mineral a Pad 01: Oz Au_Cont: 7,929 7,912 100% -17
% R.M. 71.0% 70.4% 99% -0.6%
Oz Au_Rec: 5,629 5,567 99% -63
TMS: 0 0 100% 0
Ley Au: 0.000 0.000 100% 0.000
Mineral a Pad 02: Oz Au_Cont: 0 0 100% 0
01-ene
02-ene
03-ene
15-ene
16-ene
17-ene
18-ene
30-ene
31-ene
04-ene
05-ene
06-ene
07-ene
08-ene
09-ene
10-ene
11-ene
12-ene
13-ene
14-ene
19-ene
20-ene
21-ene
22-ene
23-ene
24-ene
25-ene
26-ene
27-ene
28-ene
29-ene
% R.M. 0.0% 0.0% 100% 0.0%
Oz Au_Rec: 0 0 100% 0
TMS: 239,552 189,407 79% -50,145 Plan Mensual - Suma de Oro Contenido a PAD 1
Realizado - Suma de Oro Contenido a PAD 1
Ley Au: 0.273 0.335 123% 0.062
Plan Mensual - Suma de Ley Minerala PAD 1
Stock In Pad: Oz Au_Cont: 2,100 2,039 97% -61
Realizado - Suma de Ley Minerala PAD 1
% R.M. 67.7% 71.6% 106% 3.9% 0.8 600
0.7 500
Oz Au_Rec: 1,421 1,459 103% 39 0.6
0.5 400
Desmonte (TMS): 2,273,947 2,105,597 93% -168,349
0.4 300
S.R: 3.18 3.32 104% 0.13 0.3 200
0.2
Mineral Lixiviado (TMS): 633,917 548,162 86% -85,755 0.1 100
0 0
Material Minado (TMS): 2,988,210 2,740,133 92% -248,077
05-ene
07-ene
21-ene
23-ene
25-ene
01-ene
03-ene
09-ene
11-ene
13-ene
15-ene
17-ene
19-ene
27-ene
29-ene
31-ene
Material Transportado (TMS): 3,798,066 3,464,234 91% -333,831
Cumplimiento por fase:
2,200,000
4,000
2,000,000
3,500
1,800,000
1,600,000 3,000
1,400,000
2,500
Ton
Ton
1,200,000
2,000
1,000,000
800,000 1,500
600,000
1,000
400,000
500
200,000
- -
F7 F8 F9 F7 F8
Planeado 413,307 2,285,194 289,709 Planeado 4,112 4,133
Ejecutado 469,093 2,033,801 237,239 Ejecutado 4,047 4,121
160,000 1,600
140,000 1,400
120,000 1,200
100,000 1,000
Oz Au
TMS
80,000 800
60,000 600
40,000 400
20,000 200
- -
S1 S2 S3 S4 S5 S1 S2 S3 S4 S5
Plan Mensual - - - 78,424 161,128 Plan Mensual - - - 547 1,553
Programado Semanal - - - 77,059 127,678 Programado Semanal - - - 615 1,555
Realizado - - - 67,109 122,298 Realizado - - - 565 1,474
Cumplimiento Semanal
500,000 250,000
TMS
400,000 200,000
TMS
300,000 150,000
200,000 100,000
100,000 50,000
- -
S1 S2 S3 S4 S5 S1 S2 S3 S4 S5
Plan Mensual 305,432 539,642 474,313 536,980 417,579 Plan Mensual 43,718 153,014 153,014 153,014 131,155
Programado Semanal 310,932 541,132 429,708 511,745 450,381 Programado Semanal - 123,791 153,014 153,014 131,155
Realizado 241,129 494,894 486,179 465,704 417,690 Realizado 55,356 85,995 150,213 137,347 119,251
MINA
Plan de Perforación
S06
(02 Feb – 08 Feb)
Disponibilidad de perforadoras
Performance de perforadoras
100%
90%
80%
70%
60%
50%
%
40%
30%
20%
10%
0%
DM 45_2 DM 45_3
Disp 89% 89%
Util 75% 75%
1 3
3
1
2
1
5
Proyección de toneladas rotas
Proyectado Toneladas Rotas
1,500,000
1,070,686
1,300,000
880,236
1,100,000
900,000
700,000
500,000 Voladura
Voladura
300,000
100,000
Stock actual 02-feb 03-feb 04-feb 05-feb 06-feb 07-feb 08-feb
Stock Acum In Situ
Proyección de mineral roto (Oz Au)
Proyectado Oz Rotas
5,000
4,500
4,000
3,500
2,574
3,000
2,200
2,500
2,000
1,500
500
-
Stock actual 02-feb 03-feb 04-feb 05-feb 06-feb 07-feb 08-feb
Plan de Producción
S06
(02 Feb – 08 Feb)
Plan de Producción Semanal – Material Movido
Etiquetas de fila 02-feb 03-feb 04-feb 05-feb 06-feb 07-feb 08-feb Total general
Mineral -> PAD 1
Toneladas 24,350 24,972 25,211 17,162 16,683 20,461 25,702 154,541
Ley Au 0.338 0.515 0.348 0.454 0.559 0.411 0.408 0.426
Oz Au 264 413 282 250 300 271 337 2,117
S2_Prom 0.277 0.209 0.341 0.220 0.432 0.013 0.092 0.221
%R.M. 61.3% 69.9% 55.7% 69.6% 69.6% 73.7% 72.6% 67.8%
Oz_Au_Rec 162 289 157 174 209 199 245 1,435
Desmonte
Toneladas 72,080 71,360 71,134 79,154 79,790 75,868 70,640 520,025
Lixiviado
Toneladas 21,859 21,859 21,859 21,859 21,859 21,859 21,859 153,014
Total Toneladas 118,289 118,191 118,204 118,175 118,332 118,188 118,201 827,581
Plan de Producción Semanal – Mineral a Proceso por Fase
Fase Banco Valores Dia 01 Dia 02 Dia 03 Dia 04 Dia 05 Dia 06 Dia 07 Total general
F07 3140Toneladas 4,770 16,392 10,278 10,053 16,683 11,161 16,846 86,182
Oz Au 45 309 77 192 300 153 251 1,326
Toneladas F07 4,770 16,392 10,278 10,053 16,683 11,161 16,846 86,182
Oz Au F07 45 309 77 192 300 153 251 1,326
F08 3300Toneladas 4,364 2,690 5,453 2,633 9,300 8,857 33,297
Oz Au 49 12 31 20 118 86 316
3292Toneladas 15,216 5,890 9,480 4,475 35,062
Oz Au 171 92 174 38 475
Toneladas F08 19,581 8,580 14,933 7,108 9,300 8,857 68,359
Oz Au F08 219 104 205 59 118 86 791
Total Toneladas 24,350 24,972 25,211 17,162 16,683 20,461 25,702 154,541
Total Oz Au 264 413 282 250 300 271 337 2,117
Plan de Producción Semanal – Material Minado por Fase
Total
Fase Banco Dia 01 Dia 02 Dia 03 Dia 04 Dia 05 Dia 06 Dia 07 general
F07
3140 16,891 16,824 16,808 16,767 16,871 16,862 16,846 117,868
Total F07 16,891 16,824 16,808 16,767 16,871 16,862 16,846 117,868
F08
3308 26,821 26,837 26,852 26,847 26,878 26,834 161,070
3300 33,118 26,328 26,370 26,318 52,724 52,633 53,131 270,622
3292 19,600 26,343 26,314 26,383 26,366 125,006
Total F08 79,539 79,508 79,536 79,549 79,603 79,467 79,496 556,698
Total general 96,430 96,332 96,345 96,316 96,473 96,329 96,342 674,566
Plan de Producción Semanal – Mineral por litología
120,000 1,200
100,000 1,000
OZ Au
800
80,000
Oz Au
600
60,000
400
40,000 200
20,000 -
Total
QSO 1,569
- QSM 245
Total
HBM 0
QSO 118,899
QSD_2 19,959 CBO 16
CBO 1,040 CBM 17
ADO 4,719 ADO 116
ADM 9,040 ADM 154
Plan de Producción Semanal – Desmonte
90,000
80,000
70,000
60,000
50,000
TMS
40,000
30,000
20,000
10,000
-
Dia 01 Dia 02 Dia 03 Dia 04 Dia 05 Dia 06 Dia 07
Desmonte competente 62,355 53,112 50,056 69,622 79,112 68,524 43,996
Desmonte incompetente 9,725 18,248 21,078 9,533 678 7,344 26,643
Plan de Producción Semanal – Proyectado de Oz Puestas
Oz de Oro Acumuladas
10,000
9,000 7,860
8,000
7,000
4,344
6,000
2,000
1,000
-
01-feb
16-feb
02-feb
03-feb
04-feb
05-feb
06-feb
07-feb
08-feb
09-feb
10-feb
11-feb
12-feb
13-feb
14-feb
15-feb
17-feb
18-feb
19-feb
20-feb
21-feb
22-feb
23-feb
24-feb
25-feb
26-feb
27-feb
28-feb
Plan Mensual - Prod. Mes Plan Mensual - Stock In Pad Proyectado Semanal - Prod. Mes Proyectado Semanal - Stock In Pad
Plan de Producción Semanal – Sectores de minado
B_3308
B_3140
B_3292
B_3300 Leyenda
Dia 00
Dia 01
Dia 02
Dia 03
Dia 04
Dia 05
Dia 06
Dia 07
MINA
Plan de Equipos
S06
(02 Feb – 08 Feb)
Excavadoras
Equipos de Carguío
100%
90% 92% 90% 92% 90% 92% 90% 92% 90% 92%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%
CAT_390DL_01 CAT_390DL_03 Volvo_950DL_01 Volvo_750DL_01 CAT_349DL_01
Disponibilidad 90% 90% 90% 90% 90%
Utilizacion 92% 92% 92% 92% 92%
Remanejo PAD´s
Dimensionamiento de flota
Dimensionamiento de Flota
80 80
70 70
60 60
50 50
# Volquetes
40 40
30 30
20 20
10 10
0 0
Dia 01 Dia 02 Dia 03 Dia 04 Dia 05 Dia 06 Dia 07
Proyectos 3 3 3 3 3 3 3
Remanejo 9 9 9 9 9 9 9
Mina 58 58 58 56 56 58 58
Total 70 70 70 68 68 70 70
Equipos Auxiliares
Tipo Equipo Actividad Modelo Cant Tipo Equipo Actividad Modelo Cant Tipo Equipo Actividad Modelo Cant
Cargador Frontal Auxiliares L150H 1 Cargador Empuje Mineral L120F 1 Cargador Frontal Auxiliares L120F 2
Empuje Desm L120F 3 Empuje Remanejo L120F 1 Cisterna Auxiliares Cisterna 1
Mantto Vias L150H 1 Cisterna Auxiliares Cisterna 1 Excavadora Auxiliares 380DL 1
Cisterna Auxiliares CIST_01 1 Manejo de Aguas Cisterna 2 Motoniveladora Auxiliares Moto 1
Cisterna de Agua Mantto Vias CIST_01 5 Excavadora Manejo de Aguas 380DL 1 Retroexcavadora Auxiliares 420E 1
Excavadora Auxiliares 380DL 1 Reparación Pad 02 380DL 1 Rodillo Auxiliares Rodillo 1
Mantto Vias 380DL 1 Motoniveladora Manejo de Aguas 12M 1 Tractor Auxiliares D6T 1
Motoniveladora Mantto Vias 12M 1 Retroexcavadora Auxiliares 420E 1 Volquetes Acarreo Vol 20m3 2
Retroexcavadora Auxiliares 420F 1 Botadero ilegales 420E 1 Vol 24m3 0
Mantto Vias 420F 1 Manejo de Aguas 420E 1
Rodillo Mantto Vias CS56B 1 Tractor Auxiliares D7T 1
Rompebancos Auxiliares 380DL 1 Area Otras Areas
Tractor Auxiliares D8T 1
Mantto Vias D8T 1 Tipo Equipo Actividad Modelo Cant
Volquetes Mantto Vias Vol 20m3 1 Motoniveladora Mantto Vias 12M 1
Retroexcavadora Auxiliares 420F 1
Tractor Auxiliares D8T 1
Cargador Frontal Auxiliares L150H 1
Costos
Plan de Botaderos
S06
(02 Feb – 08 Feb)
Botadero Norte F07
BNF07 (BLD)
Capacidad: 480,000 ton
Nv 3460
BNF07 (QSD)
Capacidad: 450,000 ton
MINA
23,500 ton
Nv 3460
2
1
300,000 ton