Está en la página 1de 1

VALORIZACION N° 001

PROYECTO:

UBICACION:

PERIODO:

FECHA:

PRESUPUESTO VALORIZACION ANTERIOR VALORIZACION ACTUAL ACUMULADO ACTUAL SALDO POR VALORIZAR
ITEM DESCRIPCION Und.
Metrado Precio TOTAL Metrado Parcial % Metrado Parcial % Metrado Parcial % Metrado Parcial %

1 INSTALACION DE CERCO DE BAMBU


1 OBRAS PRELIMINARES
1.1.1 TRAZO Y REPLANTEO PRELIMINAR m² 472.86 10.00 4,728.60 50.00 500.00 10.57% 400.00 4,000.00 84.59% 450.00 4,500.00 95.17% 22.86 228.60 4.83%
1.1.2 LIMPIEZA MANUAL DEL TERRENO m² 472.86 100.00 47,286.00 472.86 47,286.00 100.00% 472.86 47,286.00 100.00% - 0.00 0.00%
1.1.3 MOVILIZACION DE EQUIPOS, HERRAMIENTAS Y MATERIALES glb 1.00 1000.00 1,000.00 1.00 1,000.00 100.00% 1.00 1,000.00 100.00% - 0.00 0.00%
1.1.4 IMPLEMENTACION Y MANTENIMIENTO DE BAÑO QUIMICO und 1.00 424.00 424.00 1.00 424.00 100.00% 1.00 424.00 100.00% - 0.00 0.00%
1 SEGURIDAD Y SALUD EN EL TRABAJO
1.2.1 IMPLEMENTO DE SEGURIDAD PERSONAL und 7.00 130.51 913.57 7.00 913.57 100.00% 7.00 913.57 100.00% - 0.00 0.00%
1.2.2 IMPLEMENTOS DE PREVENCION DEL COVID-19 glb 1.00 177.97 177.97 1.00 177.97 100.00% 1.00 177.97 100.00% - 0.00 0.00%
1 MOVIMIENTO DE TIERRAS
1.3.1 EXCAVACION MANUAL PARA SOBRECIMIENTOS EN TERRENO NATURAL m³ 51.07 73.41 3,749.05 40.86 2,999.53 80.01% 40.86 2,999.53 80.01% 10.21 749.52 19.99%
1 CONCRETO SIMPLE
1.4.1 CIMIENTO CORRIDO
1.4.1.1 CONCRETO F'C=140 KG/CM2 PARA CIMIENTO CORRIDO INCL/ IMPERMEABILIZANTE m³ 70.93 351.72 24,947.50 0.90 316.55 1.27% 0.90 316.55 1.27% 70.03 24,630.95 98.73%
1.4.1.2 ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS m² 236.43 28.30 6,690.97 17.50 495.25 7.40% 17.50 495.25 7.40% 218.93 6,195.72 92.60%
1.4.2 JUNTAS DE DILATACION
1.4.2.1 JUNTAS DE TECNOPOR DE 1" m² 23.85 11.14 265.69 0.50 5.57 2.10% 0.50 5.57 2.10% 23.35 260.12 97.90%
2 CARPINTERIA DE BAMBÚ
1.5.1 CONFECCION E INSTALACION DE TRONCOS DE BAMBU 4" pza 3310.00 21.00 69,510.00 68.00 1,427.99 2.05% 68.00 1,427.99 2.05% 3,242.00 68,082.01 97.95%
2 BANCAS JARDINERAS
1.6.1 CONCRETO F'C=140 KG/CM2 INCL/ IMPERMEABILIZANTE PARA BANCAS JARDINERAS m³ 26.79 351.72 5,000.00 10.13 3,562.92 71.26% 10.13 3,562.92 71.26% 16.66 5,859.66 117.19%
1.6.2 ACERO DE REFUERZO F'y=4200 kg/cm2 kg 741.89 6.60 4,896.47 290.00 1,914.00 39.09% 290.00 1,914.00 39.09% 451.89 2,982.47 60.91%
1.6.3 ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS m² 102.89 28.30 2,911.79 51.00 1,443.30 49.57% 51.00 1,443.30 49.57% 51.89 1,468.49 50.43%
2 SARDINELES
1.7.1 MOVIMIENTO DE TIERRAS 0.00
1.7.1.1 ESCARIFICADO MANUAL EN TERRENO NATURAL m² 1282.78 1.76 2,257.69 384.83 677.30 30.00% 384.83 677.30 30.00% 897.95 1,580.39 70.00%
1.7.1.2 MANTENIMIENTO DE VIA COMUN m² 1282.78 4.54 5,823.82 384.83 1,747.13 30.00% 384.83 1,747.13 30.00% 897.95 4,076.69 70.00%
1.7.1.3 EXCAVACION MANUAL PARA SARDINEL EN TERRENO NATURAL m³ 17.90 74.41 1,331.94 16.12 1,199.49 90.06% 16.12 1,199.49 90.06% 1.78 132.45 9.94%
1.7.2 CONCRETO SIMPLE
1.7.2.1 CONCRETO F'C=140 KG/CM2 INCL/ IMPERMEABILIZANTE PARA SARDINEL ACABADO FR m³ 17.90 351.72 6,295.79 7.44 2,616.80 41.56% 7.44 2,616.80 41.56% 10.46 3,678.99 58.44%
1.7.2.2 ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS m² 59.68 28.30 1,688.94 24.69 698.73 41.37% 24.69 698.73 41.37% 34.99 990.22 58.63%
2 ACABADOS
1.8.1 SOLAQUEO CON MORTERO ANTI SALITRE MEZCLA C:A 1:6 m² 70.93 18.45 1,308.66 - 0.00 0.00% - 0.00 0.00% 70.93 1,308.66 100.00%
1.8.2 BARNIZADO EN CERCO DE BAMBU m² 2364.30 8.00 1,800.00 - 0.00 0.00% - 0.00 0.00% 2,364.30 18,914.40 1050.80%
1.8.3 TARRAJEO ACABADO RUSTICO ANTI SALITRE m² 102.89 33.96 3,494.14 - 0.00 0.00% - 0.00 0.00% 102.89 3,494.14 100.00%
1.8.4 ASIENTO ENCHAPADO EN PIEDRA LAJA E=1CM m² 24.69 95.16 2,349.50 - 0.00 0.00% - 0.00 0.00% 24.69 2,349.50 100.00%
2 OTROS
1.9.1 TIERRA DE CHACRA m³ 19.75 59.93 1,183.62 - 0.00 0.00% - 0.00 0.00% 19.75 1,183.62 100.00%
1.9.2 ARBOLES Y/O PLANTAS und 55.00 44.94 2,471.70 55.00 2,471.70 100.00% 55.00 2,471.70 100.00% - 0.00 0.00%

COSTO DIRECTO 202,507.41 500.00 75,377.80 75,877.80 148,166.59

GASTOS GENERALES 16,200.59 40.00 6,030.22 6,070.22 11,853.33

UTILIDAD 10,125.37 25.00 3,768.89 3,793.89 7,408.33

SUB TOTAL 228,833.38 565.00 85,176.91 85,741.91 167,428.25

IGV (18%) 41,190.01 101.70 15,331.84 15,433.54 30,137.09

TOTAL PRESUPUESTO CONTRACTUAL 270,023.38 666.70 0.25% 100,508.76 37.22% 101,175.46 37.47% 197,565.34 73.17%

También podría gustarte