CRONOGRAMA DE EJECUCION DE OBRA EJECUTADO VS PROGRAMADO MES DE ABRIL 2022

PROYECTO: "AMPLIACION Y MEJORAMIENTO DEL SANEAMIENTO BASICO INTEGRAL DEL SECTOR DE PIÑALPATA DEL DISTRITO DE MARANURA - PROVINCIA DE LA CONVENCION - DEPARTAMENTO DE CUSCO"
PRESUPUESTO MODIFICADO PARA F 12
PRESUPUESTO DATOS AVALORIACION
ITEM DESCRIPCION PARCIAL + GG ACTUAL
CO+GG % MONTO
UND METRADO PRECIO S/. PARCIAL S/.
1 COMPONENTE 1: ADECUADO SISTEMA DE ABASTECIMENTO DE AGUA 526,005.44 604,071.80
1.1 TRABAJOS PRELIMINARES 47,083.31 54,071.11
1.1.1 CARTEL DE OBRA (3.60X2.40M) und 3.00 659.57 1,978.71 2,272.38 2,272.38 1,978.71 2,272.38 - 0.00
1.1.2 TRANSPORTE DE MATERIALES A OBRA CON MAQUINARIA gbl 1.00 6,134.73 6,134.73 7,045.21 7,045.21 3,094.31 3,553.55 0.20 1,200.01
1.1.3 COMPONENTEMANUAL
TRANSPORTE 1 DE MATERIALES DE PIE DE CARRETERA gbl 1.00 36,569.87 36,569.87 41,997.34 41,997.34 - 0.00 0.04 1,400.00
1.1.4 COMPONENTE 1
ALQUILER DE ALMACEN DE OBRA Y OFICINA mes 8.00 300.00 2,400.00 2,756.19 2,756.19 300.00 344.52 1.00 300.00
1.2 CAPTACIÓN SUPERFICIAL INSIENSUYOC 25,918.32 29,764.95
1.2.1 ESTRUCTURA Y ACABADOS 23,588.94 27,089.86
1.2.1.1 TRAZO, NIVELES Y REPLANTEO m² 37.86 1.62 61.33 70.43 70.43 - 0.00 - 0.00
1.2.1.2 LIMPIEZA MANUAL DE TERRENO m² 37.86 1.34 50.73 58.26 58.26 - 0.00 - 0.00
1.2.1.3 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 29.93 21.37 639.60 734.53 734.53 - 0.00 - 0.00
1.2.1.4 PERFILADO Y COMPACTADO MANUAL m² 30.30 1.49 45.15 51.85 51.85 - 0.00 - 0.00
1.2.1.5 ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 29.93 17.81 533.05 612.16 612.16 - 0.00 - 0.00
1.2.1.6 ENCOFRADO Y DESENCOFRADO m² 64.32 40.29 2,591.45 2,976.06 2,976.06 - 0.00 - 0.00
1.2.1.7 ACERO CORRUGADO f´y=4200 KG/CM2 GRADO 60 kg 595.38 7.64 4,548.70 5,223.79 5,223.79 - 0.00 - 0.00
1.2.1.8 CONCRETO F´C=100 KG/CM2 (MEZCLA MANUAL) m³ 25.12 265.80 6,676.90 7,667.84 7,667.84 - 0.00 - 0.00
1.2.1.9 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 2.23 371.80 829.11 952.16 952.16 - 0.00 - 0.00
1.2.1.10 CONCRETO F´C=210KG/CM2 (MEZCLA MANUAL) m³ 8.33 458.30 3,817.64 4,384.23 4,384.23 - 0.00 - 0.00
1.2.1.11 CURADO DE CONCRETO m² 91.74 0.50 45.87 52.68 52.68 - 0.00 - 0.00
1.2.1.12 TARRAJEO DE MUROS INTERIORES CON IMPERMEABILIZANTE m² 51.01 56.20 2,866.76 3,292.23 3,292.23 - 0.00 - 0.00
1.2.1.13 TARRAJEO EN MUROS E=1.5 CM m² 25.96 18.94 491.68 564.65 564.65 - 0.00 - 0.00
1.2.1.14 PINTADO DE ESTRUCTURAS HIDRAULICAS m² 25.96 6.55 170.04 195.28 195.28 - 0.00 - 0.00
1.2.1.15 EMBOQUILLADO DE PIEDRA Y CONCRETO F´C=140 KG/CM2 (MEZCLA m³ 1.27 173.96 220.93 253.72 253.72 - 0.00 - 0.00
1.2.2 MANUAL)
TUBERÍA Y ACCESORIOS 1,394.54 1,601.51
1.2.2.1 COMPUERTA METÁLICA DE 0.50X0.90M und 1.00 151.07 151.07 173.49 173.49 - 0.00 - 0.00
1.2.2.2 REJILLA METÁLICA DE 0.20X0.10 M und 1.00 28.58 28.58 32.82 32.82 - 0.00 - 0.00
1.2.2.3 ACCESORIOS CAPTACIÓN INSIENSUYOC gbl 1.00 960.45 960.45 1,102.99 1,102.99 - 0.00 - 0.00
1.2.2.4 TAPA METÁLICA DE 0.80X0.80 INCL. ACCESORIOS und 2.00 127.22 254.44 292.20 292.20 - 0.00 - 0.00
1.2.3 CERCO PERIMÉTRICO DE PROTECCIÓN 934.84 1,073.58
1.2.3.1 POSTES DE TUBO F°G° DE 2" CON GANCHOS und 7.00 90.00 630.00 723.50 723.50 - 0.00 - 0.00
1.2.3.2 ALAMBRE DE PUES PARA CERCO PERIMÉTRICO m 150.00 0.84 126.00 144.70 144.70 - 0.00 - 0.00
1.2.3.3 PUERTA METÁLICA DE ACCESO und 1.00 178.84 178.84 205.38 205.38 - 0.00 - 0.00
CRONOGRAMA DE EJECUCION DE OBRA EJECUTADO VS PROGRAMADO MES DE ABRIL 2022
PROYECTO: "AMPLIACION Y MEJORAMIENTO DEL SANEAMIENTO BASICO INTEGRAL DEL SECTOR DE PIÑALPATA DEL DISTRITO DE MARANURA - PROVINCIA DE LA CONVENCION - DEPARTAMENTO DE CUSCO"
PRESUPUESTO MODIFICADO PARA F 12
PRESUPUESTO DATOS AVALORIACION
ITEM DESCRIPCION PARCIAL + GG ACTUAL
CO+GG % MONTO
UND METRADO PRECIO S/. PARCIAL S/.
1.3 CAPTACIÓN DE LADERA HUERTO DEL EDEN 6,667.46 7,657.00
1.3.1 ESTRUCTURA Y ACABADOS 5,340.12 6,132.67
1.3.1.1 TRAZO, NIVELES Y REPLANTEO m² 13.34 1.62 21.61 24.82 24.82 - 0.00 - 0.00
1.3.1.2 LIMPIEZA MANUAL DE TERRENO m² 13.34 1.34 17.88 20.53 20.53 - 0.00 - 0.00
1.3.1.3 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 12.01 21.37 256.65 294.74 294.74 - 0.00 - 0.00
1.3.1.4 PERFILADO Y COMPACTADO MANUAL m² 13.34 1.49 19.88 22.83 22.83 - 0.00 - 0.00
1.3.1.5 ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 12.01 17.81 213.90 245.65 245.65 - 0.00 - 0.00
1.3.1.6 ENCOFRADO Y DESENCOFRADO m² 25.78 40.29 1,038.68 1,192.83 1,192.83 - 0.00 - 0.00
1.3.1.7 ACERO CORRUGADO f´y=4200 KG/CM2 GRADO 60 kg 87.29 7.64 666.90 765.88 765.88 - 0.00 - 0.00
1.3.1.8 CONCRETO F´C=100 KG/CM2 (MEZCLA MANUAL) m³ 2.33 265.80 619.31 711.22 711.22 - 0.00 - 0.00
1.3.1.9 CONCRETO F´C=140 KG/CM2 (MEZCLA MANUAL)+30% PIEDRA m³ 1.40 238.58 334.01 383.58 383.58 - 0.00 - 0.00
1.3.1.10 MEDIANA
CONCRETO F´C=140 KG/CM2 (MEZCLA MANUAL) m³ 1.26 294.44 370.99 426.05 426.05 - 0.00 - 0.00
1.3.1.11 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 1.31 371.80 487.06 559.35 559.35 - 0.00 - 0.00
1.3.1.12 CURADO DE CONCRETO m² 31.12 0.50 15.56 17.87 17.87 - 0.00 - 0.00
1.3.1.13 TARRAJEO DE MUROS INTERIORES CON IMPERMEABILIZANTE m² 12.35 56.20 694.07 797.08 797.08 - 0.00 - 0.00
1.3.1.14 TARRAJEO EN MUROS E=1.5 CM m² 14.79 18.94 280.12 321.69 321.69 - 0.00 - 0.00
1.3.1.15 PINTADO DE ESTRUCTURAS HIDRAULICAS m² 13.25 6.55 86.79 99.67 99.67 - 0.00 - 0.00
1.3.1.16 EMBOQUILLADO DE PIEDRA Y CONCRETO F´C=140 KG/CM2 (MEZCLA m³ 0.05 173.96 8.70 9.99 9.99 - 0.00 - 0.00
1.3.1.17 MANUAL)
RELLENO DE ZONA DE INFILTRACIÓN CON GRAVA m³ 2.38 87.40 208.01 238.88 238.88 - 0.00 - 0.00
1.3.2 TUBERÍA Y ACCESORIOS 572.50 657.47
1.3.2.1 TAPA METÁLICA DE 0.60X0.60 INCL ACCESORIOS und 2.00 96.21 192.42 220.98 220.98 - 0.00 - 0.00
1.3.2.2 ACCESORIOS CAPTACIÓN HUERTO DEL EDEN gbl 1.00 380.08 380.08 436.49 436.49 - 0.00 - 0.00
1.3.3 CERCO PERIMÉTRICO DE PROTECCIÓN 754.84 866.87
1.3.3.1 POSTES DE TUBO F°G° DE 2" CON GANCHOS und 5.00 90.00 450.00 516.79 516.79 - 0.00 - 0.00
1.3.3.2 ALAMBRE DE PUES PARA CERCO PERIMÉTRICO m 150.00 0.84 126.00 144.70 144.70 - 0.00 - 0.00
1.3.3.3 PUERTA METÁLICA DE ACCESO und 1.00 178.84 178.84 205.38 205.38 - 0.00 - 0.00
1.4 CAPTACIÓN SUPERFICIAL ROCOTOCHAYOC 21,579.81 24,782.55
1.4.1 ESTRUCTURA Y ACABADOS 19,343.83 22,214.72
1.4.1.1 TRAZO, NIVELES Y REPLANTEO m² 26.19 1.62 42.43 48.73 48.73 - 0.00 - 0.00
1.4.1.2 LIMPIEZA MANUAL DE TERRENO m² 26.19 1.34 35.09 40.30 40.30 - 0.00 - 0.00
1.4.1.3 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 21.55 21.37 460.52 528.87 528.87 - 0.00 - 0.00
1.4.1.4 PERFILADO Y COMPACTADO MANUAL m² 26.19 1.49 39.02 44.81 44.81 - 0.00 - 0.00
1.4.1.5 ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 21.55 17.81 383.81 440.77 440.77 - 0.00 - 0.00
1.4.1.6 ENCOFRADO Y DESENCOFRADO m² 61.08 40.29 2,460.91 2,826.14 2,826.14 - 0.00 - 0.00
1.4.1.7 ACERO CORRUGADO f´y=4200 KG/CM2 GRADO 60 kg 513.34 7.64 3,921.92 4,503.99 4,503.99 - 0.00 - 0.00
1.4.1.8 CONCRETO F´C=100 KG/CM2 (MEZCLA MANUAL) m³ 18.49 265.80 4,914.64 5,644.04 5,644.04 - 0.00 - 0.00
1.4.1.9 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 2.23 371.80 829.11 952.16 952.16 - 0.00 - 0.00
1.4.1.10 CONCRETO F´C=210KG/CM2 (MEZCLA MANUAL) m³ 6.61 458.30 3,029.36 3,478.96 3,478.96 - 0.00 - 0.00
1.4.1.11 CURADO DE CONCRETO m² 80.94 0.50 40.47 46.48 46.48 - 0.00 - 0.00
1.4.1.12 TARRAJEO DE MUROS INTERIORES CON IMPERMEABILIZANTE m² 42.14 56.20 2,368.27 2,719.75 2,719.75 - 0.00 - 0.00
1.4.1.13 TARRAJEO EN MUROS E=1.5 CM m² 25.96 18.94 491.68 564.65 564.65 - 0.00 - 0.00
1.4.1.14 PINTADO DE ESTRUCTURAS HIDRAULICAS m² 25.96 6.55 170.04 195.28 195.28 - 0.00 - 0.00
1.4.1.15 EMBOQUILLADO DE PIEDRA Y CONCRETO F´C=140 KG/CM2 (MEZCLA m³ 0.90 173.96 156.56 179.80 179.80 - 0.00 - 0.00
1.4.2 MANUAL)
TUBERÍA Y ACCESORIOS 1,301.14 1,494.25
1.4.2.1 COMPUERTA METÁLICA DE 0.50X0.90M und 1.00 151.07 151.07 173.49 173.49 - 0.00 - 0.00
1.4.2.2 REJILLA METÁLICA DE 0.20X0.10 M und 1.00 28.58 28.58 32.82 32.82 - 0.00 - 0.00
1.4.2.3 ACCESORIOS CAPTACIÓN ROCOTOCHAYOC gbl 1.00 867.05 867.05 995.73 995.73 - 0.00 - 0.00
1.4.2.4 TAPA METÁLICA DE 0.80X0.80 INCL. ACCESORIOS und 2.00 127.22 254.44 292.20 292.20 - 0.00 - 0.00
1.4.3 CERCO PERIMÉTRICO DE PROTECCIÓN 934.84 1,073.58
1.4.3.1 POSTES DE TUBO F°G° DE 2" CON GANCHOS und 7.00 90.00 630.00 723.50 723.50 - 0.00 - 0.00
1.4.3.2 ALAMBRE DE PUES PARA CERCO PERIMÉTRICO m 150.00 0.84 126.00 144.70 144.70 - 0.00 - 0.00
1.4.3.3 PUERTA METÁLICA DE ACCESO und 1.00 178.84 178.84 205.38 205.38 - 0.00 - 0.00
1.5 DESARENADOR 7,050.88 8,097.33
1.5.1 ESTRUCTURA Y ACABADOS 4,111.28 4,721.45
1.5.1.1 TRAZO, NIVELES Y REPLANTEO m² 8.67 1.62 14.05 16.14 16.14 - 0.00 - 0.00
1.5.1.2 LIMPIEZA MANUAL DE TERRENO m² 8.67 1.34 11.62 13.34 13.34 - 0.00 - 0.00
1.5.1.3 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 7.80 21.37 166.69 191.43 191.43 - 0.00 - 0.00
1.5.1.4 PERFILADO Y COMPACTADO MANUAL m² 8.67 1.49 12.92 14.84 14.84 - 0.00 - 0.00
1.5.1.5 ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 7.80 17.81 138.92 159.54 159.54 - 0.00 - 0.00
1.5.1.6 ENCOFRADO Y DESENCOFRADO m² 17.62 40.29 709.91 815.27 815.27 - 0.00 - 0.00
1.5.1.7 ACERO CORRUGADO f´y=4200 KG/CM2 GRADO 60 kg 150.05 7.64 1,146.38 1,316.52 1,316.52 - 0.00 - 0.00
1.5.1.8 CONCRETO F´C=100 KG/CM2 (MEZCLA MANUAL) m³ 0.42 265.80 111.64 128.21 128.21 - 0.00 - 0.00
1.5.1.9 CONCRETO F´C=140 KG/CM2 (MEZCLA MANUAL) m³ 0.04 294.44 11.78 13.53 13.53 - 0.00 - 0.00
CRONOGRAMA DE EJECUCION DE OBRA EJECUTADO VS PROGRAMADO MES DE ABRIL 2022
PROYECTO: "AMPLIACION Y MEJORAMIENTO DEL SANEAMIENTO BASICO INTEGRAL DEL SECTOR DE PIÑALPATA DEL DISTRITO DE MARANURA - PROVINCIA DE LA CONVENCION - DEPARTAMENTO DE CUSCO"
PRESUPUESTO MODIFICADO PARA F 12
PRESUPUESTO DATOS AVALORIACION
ITEM DESCRIPCION PARCIAL + GG ACTUAL
CO+GG % MONTO
UND METRADO PRECIO S/. PARCIAL S/.
1.5.1.10 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 1.73 371.80 643.21 738.67 738.67 - 0.00 - 0.00
1.5.1.11 CURADO DE CONCRETO m² 25.55 0.50 12.78 14.68 14.68 - 0.00 - 0.00
1.5.1.12 TARRAJEO DE MUROS INTERIORES CON IMPERMEABILIZANTE m² 14.48 56.20 813.78 934.56 934.56 - 0.00 - 0.00
1.5.1.13 TARRAJEO EN MUROS E=1.5 CM m² 9.73 18.94 184.29 211.64 211.64 - 0.00 - 0.00
1.5.1.14 PINTADO DE ESTRUCTURAS HIDRAULICAS m² 9.73 6.55 63.73 73.19 73.19 - 0.00 - 0.00
1.5.1.15 EMBOQUILLADO DE PIEDRA Y CONCRETO F´C=140 KG/CM2 (MEZCLA m³ 0.40 173.96 69.58 79.91 79.91 - 0.00 - 0.00
1.5.2 MANUAL)
TUBERÍA Y ACCESORIOS 1,429.92 1,642.14
1.5.2.1 TAPA METÁLICA DE 0.40X0.40 INCL ACCESORIOS und 2.00 75.57 151.14 173.57 173.57 - 0.00 - 0.00
1.5.2.2 ACCESORIOS TIPICOS PARA DESARENADORES gbl 1.00 1,094.70 1,094.70 1,257.17 1,257.17 - 0.00 - 0.00
1.5.2.3 BRIDA ROMPE AGUA DE F°G° 1" INCL. ACCESORIOS und 2.00 48.77 97.54 112.02 112.02 - 0.00 - 0.00
1.5.2.4 BRIDA ROMPE AGUA DE F°G° 3/4" INCL. ACCESORIOS und 2.00 43.27 86.54 99.38 99.38 - 0.00 - 0.00
1.5.3 CERCO PERIMÉTRICO DE PROTECCIÓN 1,509.68 1,733.74
1.5.3.1 POSTES DE TUBO F°G° DE 2" CON GANCHOS und 10.00 90.00 900.00 1,033.57 1,033.57 - 0.00 - 0.00
1.5.3.2 ALAMBRE DE PUES PARA CERCO PERIMÉTRICO m 300.00 0.84 252.00 289.40 289.40 - 0.00 - 0.00
1.5.3.3 PUERTA METÁLICA DE ACCESO und 2.00 178.84 357.68 410.76 410.76 - 0.00 - 0.00
1.6 FILTRO LENTO DE ARENA 15,749.53 18,086.97
1.6.1 ESTRUCTURA Y ACABADOS 13,959.38 16,031.14
1.6.1.1 TRAZO, NIVELES Y REPLANTEO m² 15.48 1.62 25.08 28.80 28.80 - 0.00 15.48 25.08
1.6.1.2 LIMPIEZA MANUAL DE TERRENO m² 15.48 1.34 20.74 23.82 23.82 - 0.00 15.48 20.74
1.6.1.3 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 18.58 21.37 397.05 455.98 455.98 - 0.00 18.58 397.05
1.6.1.4 PERFILADO Y COMPACTADO MANUAL m² 15.48 1.49 23.07 26.49 26.49 - 0.00 - 0.00
1.6.1.5 ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 18.58 17.81 330.91 380.02 380.02 - 0.00 - 0.00
1.6.1.6 ENCOFRADO Y DESENCOFRADO m² 80.61 40.29 3,247.78 3,729.79 3,729.79 - 0.00 - 0.00
1.6.1.7 ACERO CORRUGADO f´y=4200 KG/CM2 GRADO 60 kg 395.25 7.64 3,019.71 3,467.88 3,467.88 - 0.00 - 0.00
1.6.1.8 CONCRETO F´C=100 KG/CM2 (MEZCLA MANUAL) m³ 0.48 265.80 127.58 146.51 146.51 - 0.00 - 0.00
1.6.1.9 CONCRETO F´C=140 KG/CM2 (MEZCLA MANUAL) m³ 0.04 294.44 11.78 13.53 13.53 - 0.00 - 0.00
1.6.1.10 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 1.58 371.80 587.44 674.62 674.62 - 0.00 - 0.00
1.6.1.11 CONCRETO F´C=210KG/CM2 (MEZCLA MANUAL) m³ 4.15 458.30 1,901.95 2,184.23 2,184.23 - 0.00 - 0.00
1.6.1.12 CURADO DE CONCRETO m² 85.53 0.50 42.77 49.12 49.12 - 0.00 - 0.00
1.6.1.13 TARRAJEO DE MUROS INTERIORES CON IMPERMEABILIZANTE m² 43.60 56.20 2,450.32 2,813.98 2,813.98 - 0.00 - 0.00
1.6.1.14 TARRAJEO EN MUROS E=1.5 CM m² 35.67 18.94 675.59 775.86 775.86 - 0.00 - 0.00
1.6.1.15 PINTADO DE ESTRUCTURAS HIDRAULICAS m² 35.67 6.55 233.64 268.32 268.32 - 0.00 - 0.00
1.6.1.16 EMBOQUILLADO DE PIEDRA Y CONCRETO F´C=140 KG/CM2 (MEZCLA m³ 0.30 173.96 52.19 59.94 59.94 - 0.00 - 0.00
1.6.1.17 MANUAL)
COLOCADO DE SOPORTE BASE CON LADRILLO TIPO KING KONG m² 6.36 34.22 217.64 249.94 249.94 - 0.00 - 0.00
1.6.1.18 RELLENO DE ZONA DE INFILTRACIÓN CON GRAVA m³ 1.59 87.40 138.97 159.60 159.60 - 0.00 - 0.00
1.6.1.19 RELLENO DE ZONA DE INFILTRACIÓN CON ARENA GRUESA LAVADA m³ 5.08 89.60 455.17 522.72 522.72 - 0.00 - 0.00
1.6.2 TUBERÍA Y ACCESORIOS 1,790.15 2,055.83
1.6.2.1 TAPA METÁLICA DE 0.60X0.60 INCL ACCESORIOS und 1.00 96.21 96.21 110.49 110.49 - 0.00 - 0.00
1.6.2.2 COMPUERTA METÁLICA DE 0.20X0.35 und 2.00 84.40 168.80 193.85 193.85 - 0.00 - 0.00
1.6.2.3 ACCESORIOS PARA FILTRO LENTO gbl 1.00 1,525.14 1,525.14 1,751.49 1,751.49 - 0.00 - 0.00
1.7 LINEA DE CONDUCCIÓN 71,000.04 81,537.41
1.7.1 TRAZO, NIVELES Y REPLANTEO m² 1,201.16 1.62 1,945.88 2,234.68 2,234.68 672.62 772.45 - 0.00
1.7.2 LIMPIEZA MANUAL DE TERRENO m² 1,201.16 1.34 1,609.55 1,848.43 1,848.43 556.37 638.94 - 0.00
1.7.3 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 720.70 21.37 15,401.36 17,687.13 17,687.13 - 0.00 - 0.00
1.7.4 PERFILADO Y COMPACTADO MANUAL m² 1,201.16 1.49 1,789.73 2,055.35 2,055.35 795.66 913.75 414.00 616.86
1.7.5 CAMA DE APOYO CON MATERIAL PROPIO SELECCIONADO E=0.10 m m² 1,201.16 3.38 4,059.92 4,662.47 4,662.47 1,804.92 2,072.79 414.00 1,399.32
1.7.6 TUBO PVC NTP 399.002 DN 30 MM C-15 m 839.92 13.88 11,658.09 13,388.31 13,388.31 1,942.09 2,230.32 700.00 9,716.00
1.7.7 TUBO PVC NTP 399.002 DN 30 MM C-10 m 319.33 12.59 4,020.36 4,617.04 4,617.04 4,020.36 4,617.04 - 0.00
1.7.8 TUBO PVC NTP 399.002 DN 26.5 MM C-15 m 571.96 10.99 6,285.84 7,218.74 7,218.74 1,099.00 1,262.11 - 0.00
1.7.9 TUBO PVC NTP 399.002 DN 26.5 MM C-10 m 1,271.69 10.49 13,340.03 15,319.87 15,319.87 2,360.25 2,710.54 - 0.00
1.7.10 RELLENO Y COMPACTADO MANUAL CON MATERIAL PROPIO EN m³ 660.64 14.54 9,605.71 11,031.33 11,031.33 - 0.00 - 0.00
1.7.11 CAPAS DE E=0.20M
ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 72.07 17.81 1,283.57 1,474.07 1,474.07 - 0.00 - 0.00
1.8 CAMARA DE REUNIÓN 6,767.63 7,772.04
1.8.1 ESTRUCTURA Y ACABADOS 3,800.87 4,364.97
1.8.1.1 TRAZO, NIVELES Y REPLANTEO m² 5.04 1.62 8.16 9.37 9.37 - 0.00 - 0.00
1.8.1.2 LIMPIEZA MANUAL DE TERRENO m² 5.04 1.34 6.75 7.75 7.75 - 0.00 - 0.00
1.8.1.3 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 1.01 21.37 21.58 24.78 24.78 - 0.00 - 0.00
1.8.1.4 PERFILADO Y COMPACTADO MANUAL m² 5.04 1.49 7.51 8.62 8.62 - 0.00 - 0.00
1.8.1.5 ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 1.01 17.81 17.99 20.66 20.66 - 0.00 - 0.00
1.8.1.6 ENCOFRADO Y DESENCOFRADO m² 22.84 40.29 920.22 1,056.79 1,056.79 - 0.00 - 0.00
1.8.1.7 ACERO CORRUGADO f´y=4200 KG/CM2 GRADO 60 kg 121.92 7.64 931.47 1,069.71 1,069.71 - 0.00 - 0.00
1.8.1.8 CONCRETO F´C=100 KG/CM2 (MEZCLA MANUAL) m³ 0.25 265.80 66.45 76.31 76.31 - 0.00 - 0.00
1.8.1.9 CONCRETO F´C=140 KG/CM2 (MEZCLA MANUAL) m³ 0.02 294.44 5.89 6.76 6.76 - 0.00 - 0.00
1.8.1.10 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 1.77 371.80 658.09 755.76 755.76 - 0.00 - 0.00
1.8.1.11 CURADO DE CONCRETO m² 29.12 0.50 14.56 16.72 16.72 - 0.00 - 0.00
1.8.1.12 TARRAJEO DE MUROS INTERIORES CON IMPERMEABILIZANTE m² 12.72 56.20 714.86 820.95 820.95 - 0.00 - 0.00
1.8.1.13 TARRAJEO EN MUROS E=1.5 CM m² 15.40 18.94 291.68 334.97 334.97 - 0.00 - 0.00
1.8.1.14 PINTADO DE ESTRUCTURAS HIDRAULICAS m² 15.40 6.55 100.87 115.84 115.84 - 0.00 - 0.00
1.8.1.15 EMBOQUILLADO DE PIEDRA Y CONCRETO F´C=140 KG/CM2 (MEZCLA m³ 0.20 173.96 34.79 39.95 39.95 - 0.00 - 0.00
1.8.2 MANUAL)
TUBERÍA Y ACCESORIOS 2,966.76 3,407.07
1.8.2.1 TAPA METÁLICA DE 0.60X0.60 INCL ACCESORIOS und 2.00 96.21 192.42 220.98 220.98 - 0.00 - 0.00
1.8.2.2 TAPA METÁLICA DE 0.80X0.80 INCL. ACCESORIOS und 2.00 127.22 254.44 292.20 292.20 - 0.00 - 0.00
1.8.2.3 ACCESORIOS CAMARA DE REUNIÓN INSIENSUYOC gbl 1.00 973.22 973.22 1,117.66 1,117.66 - 0.00 - 0.00
1.8.2.4 ACCESORIOS CAMARA DE REUNIO SISTEMA PIÑALPATA gbl 1.00 1,118.88 1,118.88 1,284.94 1,284.94 - 0.00 - 0.00
1.8.2.5 TUBO DE VENTILACIÓN DE F°G° DE 2" und 2.00 213.90 427.80 491.29 491.29 - 0.00 - 0.00
1.9 CAMARA ROMPE PRESIÓN TIPO 6 6,989.32 8,026.63
1.9.1 ESTRUCTURA Y ACABADOS 5,252.57 6,032.12
1.9.1.1 TRAZO, NIVELES Y REPLANTEO m² 6.60 1.62 10.69 12.28 12.28 - 0.00 - 0.00
1.9.1.2 LIMPIEZA MANUAL DE TERRENO m² 6.60 1.34 8.84 10.15 10.15 - 0.00 - 0.00
1.9.1.3 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 2.94 21.37 62.83 72.15 72.15 - 0.00 - 0.00
CRONOGRAMA DE EJECUCION DE OBRA EJECUTADO VS PROGRAMADO MES DE ABRIL 2022
PROYECTO: "AMPLIACION Y MEJORAMIENTO DEL SANEAMIENTO BASICO INTEGRAL DEL SECTOR DE PIÑALPATA DEL DISTRITO DE MARANURA - PROVINCIA DE LA CONVENCION - DEPARTAMENTO DE CUSCO"
PRESUPUESTO MODIFICADO PARA F 12
PRESUPUESTO DATOS AVALORIACION
ITEM DESCRIPCION PARCIAL + GG ACTUAL
CO+GG % MONTO
UND METRADO PRECIO S/. PARCIAL S/.
1.9.1.4 PERFILADO Y COMPACTADO MANUAL m² 6.03 1.49 8.98 10.31 10.31 - 0.00 - 0.00
1.9.1.5 ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 2.94 17.81 52.36 60.13 60.13 - 0.00 - 0.00
1.9.1.6 ENCOFRADO Y DESENCOFRADO m² 37.80 40.29 1,522.96 1,748.99 1,748.99 - 0.00 - 0.00
1.9.1.7 ACERO CORRUGADO f´y=4200 KG/CM2 GRADO 60 kg 107.18 7.64 818.86 940.39 940.39 - 0.00 - 0.00
1.9.1.8 CONCRETO F´C=100 KG/CM2 (MEZCLA MANUAL) m³ 0.30 265.80 79.74 91.57 91.57 - 0.00 - 0.00
1.9.1.9 CONCRETO F´C=140 KG/CM2 (MEZCLA MANUAL) m³ 0.04 294.44 11.78 13.53 13.53 - 0.00 - 0.00
1.9.1.10 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 3.36 371.80 1,249.25 1,434.66 1,434.66 - 0.00 - 0.00
1.9.1.11 CURADO DE CONCRETO m² 44.31 0.50 22.16 25.45 25.45 - 0.00 - 0.00
1.9.1.12 TARRAJEO DE MUROS INTERIORES CON IMPERMEABILIZANTE m² 13.32 56.20 748.58 859.68 859.68 - 0.00 - 0.00
1.9.1.13 TARRAJEO EN MUROS E=1.5 CM m² 23.67 18.94 448.31 514.85 514.85 - 0.00 - 0.00
1.9.1.14 PINTADO DE ESTRUCTURAS HIDRAULICAS m² 23.67 6.55 155.04 178.05 178.05 - 0.00 - 0.00
1.9.1.15 EMBOQUILLADO DE PIEDRA Y CONCRETO F´C=140 KG/CM2 (MEZCLA m³ 0.30 173.96 52.19 59.94 59.94 - 0.00 - 0.00
1.9.2 MANUAL)
TUBERÍA Y ACCESORIOS 1,736.75 1,994.51
1.9.2.1 VÁLVULA COMPUERTA DE 3/4" INCL. ACCESORIOS und 2.00 97.43 194.86 223.78 223.78 - 0.00 - 0.00
1.9.2.2 CANASTILLA PVC DE 3/4" INCL. ACCESORIOS und 2.00 23.33 46.66 53.58 53.58 - 0.00 - 0.00
1.9.2.3 VÁLVULA COMPUERTA DE 1" INCL. ACCESORIOS und 1.00 125.97 125.97 144.67 144.67 - 0.00 - 0.00
1.9.2.4 CANASTILLA PVC DE 1" INCL. ACCESORIOS und 1.00 39.81 39.81 45.72 45.72 - 0.00 - 0.00
1.9.2.5 TUBERÍA DE LIMPIA Y REBOSE DE 2" und 3.00 146.25 438.75 503.87 503.87 - 0.00 - 0.00
1.9.2.6 TUBO DE VENTILACIÓN DE F°G° DE 2" und 3.00 213.90 641.70 736.94 736.94 - 0.00 - 0.00
1.9.2.7 TAPA METÁLICA DE 0.60X0.60 INCL ACCESORIOS und 1.00 96.21 96.21 110.49 110.49 - 0.00 - 0.00
1.9.2.8 TAPA METÁLICA DE 0.50X0.40 INCL ACCESORIOS und 1.00 152.79 152.79 175.47 175.47 - 0.00 - 0.00
1.10 RESERVORIO 5 M3 17,328.35 19,900.11
1.10.1 ESTRUCTURA Y ACABADOS 13,607.09 15,626.57
1.10.1.1 TRAZO, NIVELES Y REPLANTEO m² 19.60 1.62 31.75 36.46 36.46 - 0.00 - 0.00
1.10.1.2 LIMPIEZA MANUAL DE TERRENO m² 19.60 1.34 26.26 30.16 30.16 - 0.00 - 0.00
1.10.1.3 CORTE MANUAL EN TERRENO NORMAL m³ 5.53 21.37 118.18 135.72 135.72 - 0.00 - 0.00
1.10.1.4 PERFILADO Y COMPACTADO MANUAL m² 21.17 1.49 31.54 36.22 36.22 - 0.00 - 0.00
1.10.1.5 ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 5.53 17.81 98.49 113.11 113.11 - 0.00 - 0.00
1.10.1.6 ENCOFRADO Y DESENCOFRADO m² 55.39 40.29 2,231.66 2,562.87 2,562.87 - 0.00 - 0.00
1.10.1.7 ACERO CORRUGADO f´y=4200 KG/CM2 GRADO 60 kg 492.58 7.64 3,763.31 4,321.84 4,321.84 - 0.00 - 0.00
1.10.1.8 CONCRETO F´C=100 KG/CM2 (MEZCLA MANUAL) m³ 0.49 265.80 130.24 149.57 149.57 - 0.00 - 0.00
1.10.1.9 EMPEDRADO E=12.5CM m² 12.00 13.95 167.40 192.24 192.24 - 0.00 - 0.00
1.10.1.10 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 2.08 371.80 773.34 888.11 888.11 - 0.00 - 0.00
1.10.1.11 CONCRETO F´C=280 KG/CM2 (MEZCLA MANUAL) m³ 5.20 813.92 4,232.38 4,860.52 4,860.52 - 0.00 - 0.00
1.10.1.12 C/IMPERMEABILIZANTE
CURADO DE CONCRETO m² 55.66 0.50 27.83 31.96 31.96 - 0.00 - 0.00
1.10.1.13 TARRAJEO DE MUROS INTERIORES CON IMPERMEABILIZANTE m² 18.27 56.20 1,026.77 1,179.16 1,179.16 - 0.00 - 0.00
1.10.1.14 TARRAJEO EN MUROS E=1.5 CM m² 37.79 18.94 715.74 821.97 821.97 - 0.00 - 0.00
1.10.1.15 PINTADO DE ESTRUCTURAS HIDRAULICAS m² 35.45 6.55 232.20 266.66 266.66 - 0.00 - 0.00
1.10.2 TUBERÍA Y ACCESORIOS 2,556.02 2,935.37
1.10.2.1 ACCESORIOS DE CAJA DE VÁLVULAS PARA RESERVORIO DE 5 M3 gbl 1.00 1,932.29 1,932.29 2,219.07 2,219.07 - 0.00 - 0.00
1.10.2.2 TUBO DE VENTILACIÓN DE F°G° DE 2" und 1.00 213.90 213.90 245.65 245.65 - 0.00 - 0.00
1.10.2.3 SISTEMA DE CLORACIÓN DE 60 LITROS und 1.00 217.41 217.41 249.68 249.68 - 0.00 - 0.00
1.10.2.4 TAPA METÁLICA DE 0.60X0.60 INCL ACCESORIOS und 2.00 96.21 192.42 220.98 220.98 - 0.00 - 0.00
1.10.3 CERCO PERIMÉTRICO DE PROTECCIÓN 1,165.24 1,338.18
1.10.3.1 POSTES DE TUBO F°G° DE 2" CON GANCHOS und 9.00 90.00 810.00 930.22 930.22 - 0.00 - 0.00
1.10.3.2 ALAMBRE DE PUES PARA CERCO PERIMÉTRICO m 210.00 0.84 176.40 202.58 202.58 - 0.00 - 0.00
1.10.3.3 PUERTA METÁLICA DE ACCESO und 1.00 178.84 178.84 205.38 205.38 - 0.00 - 0.00
1.11 RESERVORIO 2.5 M3 12,871.67 14,782.00
1.11.1 ESTRUCTURA Y ACABADOS 9,384.30 10,777.06
1.11.1.1 TRAZO, NIVELES Y REPLANTEO m² 11.36 1.62 18.40 21.13 21.13 - 0.00 11.36 18.40
1.11.1.2 LIMPIEZA MANUAL DE TERRENO m² 11.36 1.34 15.22 17.48 17.48 - 0.00 11.36 15.22
1.11.1.3 CORTE MANUAL EN TERRENO NORMAL m³ 3.58 21.37 76.50 87.85 87.85 - 0.00 3.58 76.50
1.11.1.4 PERFILADO Y COMPACTADO MANUAL m² 13.44 1.49 20.03 23.00 23.00 - 0.00 - 0.00
1.11.1.5 ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 3.58 17.81 63.76 73.22 73.22 - 0.00 - 0.00
1.11.1.6 ENCOFRADO Y DESENCOFRADO m² 40.80 40.29 1,643.83 1,887.80 1,887.80 - 0.00 - 0.00
1.11.1.7 ACERO CORRUGADO f´y=4200 KG/CM2 GRADO 60 kg 328.04 7.64 2,506.23 2,878.19 2,878.19 - 0.00 - 0.00
1.11.1.8 CONCRETO F´C=100 KG/CM2 (MEZCLA MANUAL) m³ 0.29 265.80 77.08 88.52 88.52 - 0.00 - 0.00
1.11.1.9 EMPEDRADO E=12.5CM m² 7.59 13.95 105.88 121.59 121.59 - 0.00 - 0.00
1.11.1.10 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 1.54 371.80 572.57 657.55 657.55 - 0.00 - 0.00
1.11.1.11 CONCRETO F´C=280 KG/CM2 (MEZCLA MANUAL) m³ 3.50 813.92 2,848.72 3,271.51 3,271.51 - 0.00 - 0.00
1.11.1.12 C/IMPERMEABILIZANTE
CURADO DE CONCRETO m² 40.80 0.50 20.40 23.43 23.43 - 0.00 - 0.00
1.11.1.13 TARRAJEO DE MUROS INTERIORES CON IMPERMEABILIZANTE m² 11.67 56.20 655.85 753.19 753.19 - 0.00 - 0.00
1.11.1.14 TARRAJEO EN MUROS E=1.5 CM m² 30.41 18.94 575.97 661.45 661.45 - 0.00 - 0.00
1.11.1.15 PINTADO DE ESTRUCTURAS HIDRAULICAS m² 28.07 6.55 183.86 211.15 211.15 - 0.00 - 0.00
1.11.2 TUBERÍA Y ACCESORIOS 2,462.53 2,828.00
1.11.2.1 ACCESORIOS DE CAJA DE VÁLVULAS PARA RESERVORIO DE 2.5 M3 gbl 1.00 1,844.80 1,844.80 2,118.59 2,118.59 - 0.00 - 0.00
1.11.2.2 TUBO DE VENTILACIÓN DE F°G° DE 2" und 1.00 213.90 213.90 245.65 245.65 - 0.00 - 0.00
1.11.2.3 SISTEMA DE CLORACIÓN DE 30 LITROS und 1.00 211.41 211.41 242.79 242.79 - 0.00 - 0.00
1.11.2.4 TAPA METÁLICA DE 0.60X0.60 INCL ACCESORIOS und 2.00 96.21 192.42 220.98 220.98 - 0.00 - 0.00
1.11.3 CERCO PERIMÉTRICO DE PROTECCIÓN 1,024.84 1,176.94
1.11.3.1 POSTES DE TUBO F°G° DE 2" CON GANCHOS und 8.00 90.00 720.00 826.86 826.86 - 0.00 - 0.00
1.11.3.2 ALAMBRE DE PUES PARA CERCO PERIMÉTRICO m 150.00 0.84 126.00 144.70 144.70 - 0.00 - 0.00
1.11.3.3 PUERTA METÁLICA DE ACCESO und 1.00 178.84 178.84 205.38 205.38 - 0.00 - 0.00
1.12 TANQUE DE POLIETILENO 11,039.53 12,677.95
1.12.1 ESTRUCTURA Y ACABADOS 10,351.89 11,888.25
1.12.1.1 TRAZO, NIVELES Y REPLANTEO m² 11.25 1.62 18.23 20.94 20.94 - 0.00 - 0.00
1.12.1.2 LIMPIEZA MANUAL DE TERRENO m² 11.25 1.34 15.08 17.32 17.32 - 0.00 - 0.00
1.12.1.3 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 1.13 21.37 24.15 27.73 27.73 - 0.00 - 0.00
1.12.1.4 PERFILADO Y COMPACTADO MANUAL m² 11.25 1.49 16.76 19.25 19.25 - 0.00 - 0.00
1.12.1.5 ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 1.13 17.81 20.13 23.12 23.12 - 0.00 - 0.00
CRONOGRAMA DE EJECUCION DE OBRA EJECUTADO VS PROGRAMADO MES DE ABRIL 2022
PROYECTO: "AMPLIACION Y MEJORAMIENTO DEL SANEAMIENTO BASICO INTEGRAL DEL SECTOR DE PIÑALPATA DEL DISTRITO DE MARANURA - PROVINCIA DE LA CONVENCION - DEPARTAMENTO DE CUSCO"
PRESUPUESTO MODIFICADO PARA F 12
PRESUPUESTO DATOS AVALORIACION
ITEM DESCRIPCION PARCIAL + GG ACTUAL
CO+GG % MONTO
UND METRADO PRECIO S/. PARCIAL S/.
1.12.1.6 ENCOFRADO Y DESENCOFRADO m² 6.00 40.29 241.74 277.62 277.62 - 0.00 - 0.00
1.12.1.7 EMPEDRADO E=12.5CM m² 11.25 13.95 156.94 180.23 180.23 - 0.00 - 0.00
1.12.1.8 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 1.13 371.80 420.13 482.48 482.48 - 0.00 - 0.00
1.12.1.9 CURADO DE CONCRETO m² 11.25 0.50 5.63 6.47 6.47 - 0.00 - 0.00
1.12.1.10 TANQUE DE POLIETILENO DE 600 LT INCL. ACCESORIOS und 3.00 568.54 1,705.62 1,958.76 1,958.76 - 0.00 - 0.00
1.12.1.11 TANQUE DE POLIETILENO DE 1100 LT INCL. ACCESORIOS und 1.00 918.54 918.54 1,054.86 1,054.86 - 0.00 - 0.00
1.12.1.12 TANQUE DE POLIETILENO DE 1500 LT INCL. ACCESORIOS und 1.00 1,283.54 1,283.54 1,474.03 1,474.03 - 0.00 - 0.00
1.12.1.13 COBERTURA DE TANQUES DE POLIETILENO und 5.00 1,105.08 5,525.40 6,345.44 6,345.44 - 0.00 - 0.00
1.12.2 CERCO PERIMÉTRICO DE PROTECCIÓN 687.64 789.70
1.12.2.1 POSTES DE TUBO F°G° DE 2" CON GANCHOS und 5.00 90.00 450.00 516.79 516.79 - 0.00 - 0.00
1.12.2.2 ALAMBRE DE PUES PARA CERCO PERIMÉTRICO m 70.00 0.84 58.80 67.53 67.53 - 0.00 - 0.00
1.12.2.3 PUERTA METÁLICA DE ACCESO und 1.00 178.84 178.84 205.38 205.38 - 0.00 - 0.00
1.13 LINEA DE ADUCCIÓN 107,577.36 123,543.30
1.13.1 TRAZO, NIVELES Y REPLANTEO m² 2,127.19 1.62 3,446.05 3,957.49 3,957.49 - 0.00 819.60 1,327.75
1.13.2 LIMPIEZA MANUAL DE TERRENO m² 2,127.19 1.34 2,850.43 3,273.47 3,273.47 - 0.00 855.60 1,146.50
1.13.3 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 1,276.32 21.37 27,274.96 31,322.93 31,322.93 4,303.92 4,942.68 571.00 12,202.27
1.13.4 PERFILADO Y COMPACTADO MANUAL m² 2,127.19 1.49 3,169.51 3,639.91 3,639.91 1,352.92 1,553.71 - 0.00
1.13.5 CAMA DE APOYO CON MATERIAL PROPIO SELECCIONADO E=0.10 m m² 2,127.19 3.38 7,189.90 8,256.98 8,256.98 3,069.04 3,524.53 - 0.00
1.13.6 TUBO PVC NTP 399.002 DN 30 MM C-10 m 201.32 12.59 2,534.62 2,910.79 2,910.79 2,534.62 2,910.79 - 0.00
1.13.7 TUBO PVC NTP 399.002 DN 26.5 MM C-10 m 1,841.64 10.49 19,318.80 22,185.97 22,185.97 8,182.20 9,396.55 - 0.00
1.13.8 TUBO PVC NTP 399.002 DN 21 MM C-15 und 674.11 8.08 5,446.81 6,255.19 6,255.19 1,010.00 1,159.90 435.00 3,514.80
1.13.9 TUBO PVC NTP 399.002 DN 21 MM C-10 m 2,600.91 6.56 17,061.97 19,594.20 19,594.20 8,200.00 9,416.99 - 0.00
1.13.10 RELLENO Y COMPACTADO MANUAL CON MATERIAL PROPIO EN m³ 1,169.96 14.54 17,011.22 19,535.92 19,535.92 - 0.00 - 0.00
1.13.11 CAPAS DE E=0.20M
ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 127.63 17.81 2,273.09 2,610.45 2,610.45 - 0.00 - 0.00
1.14 CAMARA DE DISTRIBUCIÓN DE CAUDALES 19,249.52 22,106.41
1.14.1 ESTRUCTURA Y ACABADOS 11,232.00 12,898.98
1.14.1.1 TRAZO, NIVELES Y REPLANTEO m² 17.28 1.62 27.99 32.14 32.14 - 0.00 - 0.00
1.14.1.2 LIMPIEZA MANUAL DE TERRENO m² 17.28 1.34 23.16 26.60 26.60 - 0.00 - 0.00
1.14.1.3 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 4.51 21.37 96.38 110.68 110.68 - 0.00 - 0.00
CRONOGRAMA DE EJECUCION DE OBRA EJECUTADO VS PROGRAMADO MES DE ABRIL 2022
PROYECTO: "AMPLIACION Y MEJORAMIENTO DEL SANEAMIENTO BASICO INTEGRAL DEL SECTOR DE PIÑALPATA DEL DISTRITO DE MARANURA - PROVINCIA DE LA CONVENCION - DEPARTAMENTO DE CUSCO"
PRESUPUESTO MODIFICADO PARA F 12
PRESUPUESTO DATOS AVALORIACION
ITEM DESCRIPCION PARCIAL + GG ACTUAL
CO+GG % MONTO
UND METRADO PRECIO S/. PARCIAL S/.
1.14.1.4 PERFILADO Y COMPACTADO MANUAL m² 17.28 1.49 25.75 29.57 29.57 - 0.00 - 0.00
1.14.1.5 ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 4.51 17.81 80.32 92.24 92.24 - 0.00 - 0.00
1.14.1.6 ENCOFRADO Y DESENCOFRADO m² 71.22 40.29 2,869.45 3,295.32 3,295.32 - 0.00 - 0.00
1.14.1.7 ACERO CORRUGADO f´y=4200 KG/CM2 GRADO 60 kg 360.35 7.64 2,753.07 3,161.66 3,161.66 - 0.00 - 0.00
1.14.1.8 CONCRETO F´C=100 KG/CM2 (MEZCLA MANUAL) m³ 0.76 265.80 202.01 231.99 231.99 - 0.00 - 0.00
1.14.1.9 CONCRETO F´C=140 KG/CM2 (MEZCLA MANUAL) m³ 0.07 294.44 20.61 23.67 23.67 - 0.00 - 0.00
1.14.1.10 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 5.33 371.80 1,981.69 2,275.80 2,275.80 - 0.00 - 0.00
1.14.1.11 CURADO DE CONCRETO m² 89.70 0.50 44.85 51.51 51.51 - 0.00 - 0.00
1.14.1.12 TARRAJEO DE MUROS INTERIORES CON IMPERMEABILIZANTE m² 26.10 56.20 1,466.82 1,684.52 1,684.52 - 0.00 - 0.00
1.14.1.13 TARRAJEO EN MUROS E=1.5 CM m² 60.24 18.94 1,140.95 1,310.28 1,310.28 - 0.00 - 0.00
1.14.1.14 PINTADO DE ESTRUCTURAS HIDRAULICAS m² 60.24 6.55 394.57 453.13 453.13 - 0.00 - 0.00
1.14.1.15 EMBOQUILLADO DE PIEDRA Y CONCRETO F´C=140 KG/CM2 (MEZCLA m³ 0.60 173.96 104.38 119.87 119.87 - 0.00 - 0.00
1.14.2 MANUAL)
TUBERÍA Y ACCESORIOS 8,017.52 9,207.43
1.14.2.1 TAPA METÁLICA DE 0.60X0.60 INCL ACCESORIOS und 12.00 96.21 1,154.52 1,325.87 1,325.87 - 0.00 - 0.00
1.14.2.2 ACCESORIOS CAMARA DE DISTRIBUCIÓN DE CAUDALES TIPO gbl 2.00 1,480.56 2,961.12 3,400.59 3,400.59 - 0.00 - 0.00
1.14.2.3 ACCESORIOS CAMARA DE DISTRIBUCIÓN DE CAUDALES LUYCHO gbl 1.00 2,618.48 2,618.48 3,007.10 3,007.10 - 0.00 - 0.00
1.14.2.4 ALTO
TUBO DE VENTILACIÓN DE F°G° DE 2" und 6.00 213.90 1,283.40 1,473.87 1,473.87 - 0.00 - 0.00
1.15 CAMARA ROMPE PRESIÓN TIPO 7 62,224.90 71,459.92
1.15.1 ESTRUCTURA Y ACABADOS 36,719.68 42,169.38
1.15.1.1 TRAZO, NIVELES Y REPLANTEO m² 50.40 1.62 81.65 93.77 93.77 - 0.00 - 0.00
1.15.1.2 LIMPIEZA MANUAL DE TERRENO m² 50.40 1.34 67.54 77.56 77.56 - 0.00 - 0.00
1.15.1.3 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 35.28 21.37 753.93 865.82 865.82 - 0.00 - 0.00
1.15.1.4 PERFILADO Y COMPACTADO MANUAL m² 50.40 1.49 75.10 86.25 86.25 - 0.00 - 0.00
1.15.1.5 ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 35.28 17.81 628.34 721.59 721.59 - 0.00 - 0.00
1.15.1.6 ENCOFRADO Y DESENCOFRADO m² 253.60 40.29 10,217.54 11,733.96 11,733.96 - 0.00 - 0.00
1.15.1.7 ACERO CORRUGADO f´y=4200 KG/CM2 GRADO 60 kg 1,121.72 7.64 8,569.94 9,841.84 9,841.84 - 0.00 - 0.00
1.15.1.8 CONCRETO F´C=100 KG/CM2 (MEZCLA MANUAL) m³ 2.64 265.80 701.71 805.85 805.85 - 0.00 - 0.00
1.15.1.9 CONCRETO F´C=140 KG/CM2 (MEZCLA MANUAL) m³ 0.26 294.44 76.55 87.91 87.91 - 0.00 - 0.00
1.15.1.10 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 16.80 371.80 6,246.24 7,173.27 7,173.27 - 0.00 - 0.00
1.15.1.11 CURADO DE CONCRETO m² 306.40 0.50 153.20 175.94 175.94 - 0.00 - 0.00
1.15.1.12 TARRAJEO DE MUROS INTERIORES CON IMPERMEABILIZANTE m² 84.00 56.20 4,720.80 5,421.43 5,421.43 - 0.00 - 0.00
1.15.1.13 TARRAJEO EN MUROS E=1.5 CM m² 173.60 18.94 3,287.98 3,775.96 3,775.96 - 0.00 - 0.00
1.15.1.14 PINTADO DE ESTRUCTURAS HIDRAULICAS m² 120.80 6.55 791.24 908.67 908.67 - 0.00 - 0.00
CRONOGRAMA DE EJECUCION DE OBRA EJECUTADO VS PROGRAMADO MES DE ABRIL 2022
PROYECTO: "AMPLIACION Y MEJORAMIENTO DEL SANEAMIENTO BASICO INTEGRAL DEL SECTOR DE PIÑALPATA DEL DISTRITO DE MARANURA - PROVINCIA DE LA CONVENCION - DEPARTAMENTO DE CUSCO"
PRESUPUESTO MODIFICADO PARA F 12
PRESUPUESTO DATOS AVALORIACION
ITEM DESCRIPCION PARCIAL + GG ACTUAL
CO+GG % MONTO
UND METRADO PRECIO S/. PARCIAL S/.
1.15.1.15 EMBOQUILLADO DE PIEDRA Y CONCRETO F´C=140 KG/CM2 (MEZCLA m³ 2.00 173.96 347.92 399.56 399.56 - 0.00 - 0.00
1.15.2 MANUAL)
TUBERÍA Y ACCESORIOS 25,505.22 29,290.54
1.15.2.1 TAPA METÁLICA DE 0.60X0.60 INCL ACCESORIOS und 20.00 96.21 1,924.20 2,209.78 2,209.78 - 0.00 - 0.00
1.15.2.2 TAPA METÁLICA DE 0.80X0.80 INCL. ACCESORIOS und 20.00 127.22 2,544.40 2,922.02 2,922.02 - 0.00 - 0.00
1.15.2.3 ACCESORIOS DE DIAMETRO DE 3/4" PARA CAMARA ROMPE PRESION und 4.00 923.05 3,692.20 4,240.17 4,240.17 - 0.00 - 0.00
1.15.2.4 TIPO 7
ACCESORIOS DE DIAMETRO DE 1/2" PARA CAMARA ROMPE PRESION und 16.00 815.02 13,040.32 14,975.68 14,975.68 - 0.00 - 0.00
1.15.2.5 TIPO 7
REDUCCIÓN PVC DE 3/4" A 1/2" und 6.00 4.35 26.10 29.97 29.97 - 0.00 - 0.00
1.15.2.6 TUBO DE VENTILACIÓN DE F°G° DE 2" und 20.00 213.90 4,278.00 4,912.91 4,912.91 - 0.00 - 0.00
1.16 LINEA DE DISTRIBUCIÓN 46,809.58 53,756.76
1.16.1 TRAZO, NIVELES Y REPLANTEO m² 1,302.58 1.62 2,110.18 2,423.36 2,423.36 - 0.00 60.40 97.85
1.16.2 LIMPIEZA MANUAL DE TERRENO m² 1,302.58 1.34 1,745.46 2,004.51 2,004.51 - 0.00 60.40 80.94
1.16.3 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 781.55 21.37 16,701.72 19,180.48 19,180.48 - 0.00 151.00 3,226.87
1.16.4 PERFILADO Y COMPACTADO MANUAL m² 1,302.58 1.49 1,940.84 2,228.89 2,228.89 - 0.00 - 0.00
1.16.5 CAMA DE APOYO CON MATERIAL PROPIO SELECCIONADO E=0.10 m m² 1,302.58 3.38 4,402.72 5,056.14 5,056.14 - 0.00 - 0.00
1.16.6 TUBO PVC NTP 399.002 DN 21 MM C-10 m 1,302.58 6.56 8,544.92 9,813.10 9,813.10 - 0.00 - 0.00
1.16.7 RELLENO Y COMPACTADO MANUAL CON MATERIAL PROPIO EN m³ 781.55 14.54 11,363.74 13,050.27 13,050.27 - 0.00 - 0.00
1.17 CAPAS
VÁVULASDEDE
E=0.20M
CONTROL, PURGA Y PURGA DE AIRE 13,280.65 15,251.68
1.17.1 ESTRUCTURA Y ACABADOS 4,712.98 5,412.45
1.17.1.1 TRAZO, NIVELES Y REPLANTEO m² 18.36 1.62 29.74 34.15 34.15 - 0.00 - 0.00
1.17.1.2 LIMPIEZA MANUAL DE TERRENO m² 18.36 1.34 24.60 28.25 28.25 - 0.00 - 0.00
1.17.1.3 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 7.34 21.37 156.86 180.14 180.14 - 0.00 - 0.00
1.17.1.4 PERFILADO Y COMPACTADO MANUAL m² 18.36 1.49 27.36 31.42 31.42 - 0.00 - 0.00
1.17.1.5 ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 7.34 17.81 130.73 150.13 150.13 - 0.00 - 0.00
1.17.1.6 ENCOFRADO Y DESENCOFRADO m² 81.60 40.29 3,287.66 3,775.59 3,775.59 - 0.00 - 0.00
1.17.1.7 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 2.71 371.80 1,007.58 1,157.12 1,157.12 - 0.00 - 0.00
1.17.1.8 CURADO DE CONCRETO m² 96.90 0.50 48.45 55.64 55.64 - 0.00 - 0.00
1.17.2 TUBERÍA Y ACCESORIOS 8,567.67 9,839.23
1.17.2.1 VÁLVULA GLOBO DE 1/2" INCL. ACCESORIOS und 61.00 25.95 1,582.95 1,817.88 1,817.88 - 0.00 - 0.00
1.17.2.2 VÁLVULA GLOBO DE 3/4" INCL. ACCESORIOS und 27.00 37.25 1,005.75 1,155.02 1,155.02 - 0.00 - 0.00
1.17.2.3 VÁLVULA GLOBO DE 1" INCL. ACCESORIOS und 8.00 47.57 380.56 437.04 437.04 - 0.00 - 0.00
1.17.2.4 TAPA METÁLICA DE 0.40X0.40 INCL ACCESORIOS und 68.00 75.57 5,138.76 5,901.42 5,901.42 - 0.00 - 0.00
1.17.2.5 VÁLVULA DE PURGA DE AIRE DE 1" INCL. ACCESORIOS und 1.00 99.11 99.11 113.82 113.82 - 0.00 - 0.00
1.17.2.6 VÁLVULA DE PURGA DE AIRE DE 3/4" INCL. ACCESORIOS und 3.00 79.50 238.50 273.90 273.90 - 0.00 - 0.00
1.17.2.7 VÁLVULA DE PURGA DE AIRE DE 1/2" INCL. ACCESORIOS und 2.00 61.02 122.04 140.15 140.15 - 0.00 - 0.00
1.18 PASE AEREO DE 5 M 4,594.52 5,276.41
1.18.1 OBRAS DE CONCRETO ARMADO 3,521.70 4,044.37
1.18.1.1 TRAZO, NIVELES Y REPLANTEO m² 48.00 1.62 77.76 89.30 89.30 - 0.00 - 0.00
1.18.1.2 LIMPIEZA MANUAL DE TERRENO m² 48.00 1.34 64.32 73.87 73.87 - 0.00 - 0.00
1.18.1.3 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 5.28 21.37 112.83 129.58 129.58 - 0.00 - 0.00
1.18.1.4 PERFILADO Y COMPACTADO MANUAL m² 5.96 1.49 8.88 10.20 10.20 - 0.00 - 0.00
1.18.1.5 ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 2.88 17.81 51.29 58.90 58.90 - 0.00 - 0.00
1.18.1.6 ENCOFRADO Y DESENCOFRADO m² 10.56 40.29 425.46 488.60 488.60 - 0.00 - 0.00
1.18.1.7 ACERO CORRUGADO f´y=4200 KG/CM2 GRADO 60 kg 160.06 7.64 1,222.86 1,404.35 1,404.35 - 0.00 - 0.00
1.18.1.8 CONCRETO F´C=100 KG/CM2 (MEZCLA MANUAL) m³ 0.20 265.80 53.16 61.05 61.05 - 0.00 - 0.00
1.18.1.9 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 1.08 371.80 401.54 461.13 461.13 - 0.00 - 0.00
1.18.1.10 CONCRETO F´C=210KG/CM2 (MEZCLA MANUAL) m³ 2.39 458.30 1,095.34 1,257.90 1,257.90 - 0.00 - 0.00
1.18.1.11 CURADO DE CONCRETO m² 16.52 0.50 8.26 9.49 9.49 - 0.00 - 0.00
1.18.2 TUBERÍA Y ACCESORIOS 1,072.82 1,232.04
1.18.2.1 TUBO HDPE NTP-ISO 4427:2008 DN 32 MM INCL ACCESORIOS m 11.05 2.55 28.18 32.36 32.36 - 0.00 - 0.00
1.18.2.2 ENLACE ROSCADO TIPO MACHO HDPE DN 32 MM INCL ACCESORIOS und 2.00 17.09 34.18 39.25 39.25 - 0.00 - 0.00
1.18.2.3 TUBO HDPE NTP-ISO 4427:2008 DN 25 MM INCL ACCESORIOS m 11.05 1.97 21.77 25.00 25.00 - 0.00 - 0.00
1.18.2.4 ENLACE ROSCADO TIPO MACHO HDPE DN 25 MM INCL ACCESORIOS und 2.00 11.67 23.34 26.80 26.80 - 0.00 - 0.00
1.18.2.5 ABRAZADERA DE PLATINA DE 1/8" INCL ACCESORIOS und 10.00 9.71 97.10 111.51 111.51 - 0.00 - 0.00
1.18.2.6 ABRAZADERA DE PLATINA DE 1/2" INCL. ACCESORIOS und 10.00 15.61 156.10 179.27 179.27 - 0.00 - 0.00
1.18.2.7 CABLE TIPO BOA DE 1/2" m 25.70 7.18 184.53 211.92 211.92 - 0.00 - 0.00
1.18.2.8 PÉNDOLAS DE ACERO DE 1/4" SERIE 6x19 TIPO BOA m 7.00 5.35 37.45 43.01 43.01 - 0.00 - 0.00
1.18.2.9 GRAPA GROSBY DE 1/2" und 24.00 7.83 187.92 215.81 215.81 - 0.00 - 0.00
1.18.2.10 TEMPLADOR DE DOS ESPIGAS DE 1/2" CON GUADACABO und 4.00 15.08 60.32 69.27 69.27 - 0.00 - 0.00
1.18.2.11 CARRITO DE DILATACIÓN DE 0.30X0.30 INCL. ACCESORIOS und 4.00 52.28 209.12 240.16 240.16 - 0.00 - 0.00
1.18.2.12 RIEL DE ACERO PARA FIJADO 2"x3"x1/2 m 0.80 41.01 32.81 37.68 37.68 - 0.00 - 0.00
1.19 PASE AREO DE 10 M 6,229.08 7,153.56
1.19.1 OBRAS DE CONCRETO ARMADO 4,756.37 5,462.28
1.19.1.1 TRAZO, NIVELES Y REPLANTEO m² 100.00 1.62 162.00 186.04 186.04 - 0.00 - 0.00
1.19.1.2 LIMPIEZA MANUAL DE TERRENO m² 100.00 1.34 134.00 153.89 153.89 - 0.00 - 0.00
1.19.1.3 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 9.61 21.37 205.37 235.85 235.85 - 0.00 - 0.00
1.19.1.4 PERFILADO Y COMPACTADO MANUAL m² 7.69 1.49 11.46 13.16 13.16 - 0.00 - 0.00
1.19.1.5 ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 5.05 17.81 89.94 103.29 103.29 - 0.00 - 0.00
1.19.1.6 ENCOFRADO Y DESENCOFRADO m² 13.44 40.29 541.50 621.87 621.87 - 0.00 - 0.00
1.19.1.7 ACERO CORRUGADO f´y=4200 KG/CM2 GRADO 60 kg 181.69 7.64 1,388.11 1,594.12 1,594.12 - 0.00 - 0.00
1.19.1.8 CONCRETO F´C=100 KG/CM2 (MEZCLA MANUAL) m³ 0.24 265.80 63.79 73.26 73.26 - 0.00 - 0.00
1.19.1.9 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 2.17 371.80 806.81 926.55 926.55 - 0.00 - 0.00
1.19.1.10 CONCRETO F´C=210KG/CM2 (MEZCLA MANUAL) m³ 2.93 458.30 1,342.82 1,542.11 1,542.11 - 0.00 - 0.00
1.19.1.11 CURADO DE CONCRETO m² 21.13 0.50 10.57 12.14 12.14 - 0.00 - 0.00
1.19.2 TUBERÍA Y ACCESORIOS 1,472.71 1,691.28
1.19.2.1 TUBO HDPE NTP-ISO 4427:2008 DN 32 MM INCL INSTALACIÓN m 17.50 3.14 54.95 63.11 63.11 - 0.00 - 0.00
1.19.2.2 ENLACE ROSCADO TIPO MACHO HDPE DN 32 MM INCL ACCESORIOS und 2.00 17.25 34.50 39.62 39.62 - 0.00 - 0.00
1.19.2.3 TUBO HDPE NTP-ISO 4427:2008 DN 25 MM INCL INSTALACIÓN m 17.50 2.56 44.80 51.45 51.45 - 0.00 - 0.00
1.19.2.4 ENLACE ROSCADO TIPO MACHO HDPE DN 25 MM INCL ACCESORIOS und 2.00 12.00 24.00 27.56 27.56 - 0.00 - 0.00
1.19.2.5 ABRAZADERA DE PLATINA DE 1/8" INCL ACCESORIOS und 18.00 9.71 174.78 200.72 200.72 - 0.00 - 0.00
1.19.2.6 ABRAZADERA DE PLATINA DE 1/2" INCL. ACCESORIOS und 18.00 15.61 280.98 322.68 322.68 - 0.00 - 0.00
CRONOGRAMA DE EJECUCION DE OBRA EJECUTADO VS PROGRAMADO MES DE ABRIL 2022
PROYECTO: "AMPLIACION Y MEJORAMIENTO DEL SANEAMIENTO BASICO INTEGRAL DEL SECTOR DE PIÑALPATA DEL DISTRITO DE MARANURA - PROVINCIA DE LA CONVENCION - DEPARTAMENTO DE CUSCO"
PRESUPUESTO MODIFICADO PARA F 12
PRESUPUESTO DATOS AVALORIACION
ITEM DESCRIPCION PARCIAL + GG ACTUAL
CO+GG % MONTO
UND METRADO PRECIO S/. PARCIAL S/.
1.19.2.7 CABLE TIPO BOA DE 1/2" m 40.30 7.18 289.35 332.29 332.29 - 0.00 - 0.00
1.19.2.8 PÉNDOLAS DE ACERO DE 1/4" SERIE 6x19 TIPO BOA m 14.80 5.35 79.18 90.93 90.93 - 0.00 - 0.00
1.19.2.9 GRAPA GROSBY DE 1/2" und 24.00 7.83 187.92 215.81 215.81 - 0.00 - 0.00
1.19.2.10 TEMPLADOR DE DOS ESPIGAS DE 1/2" CON GUADACABO und 4.00 15.08 60.32 69.27 69.27 - 0.00 - 0.00
1.19.2.11 CARRITO DE DILATACIÓN DE 0.30X0.30 INCL. ACCESORIOS und 4.00 52.28 209.12 240.16 240.16 - 0.00 - 0.00
1.19.2.12 RIEL DE ACERO PARA FIJADO 2"x3"x1/2 m 0.80 41.01 32.81 37.68 37.68 - 0.00 - 0.00
1.20 PASE AEREO LINEA DE CONDUCCIÓN LUYCHO ALTO 1,558.79 1,790.14
1.20.1 TUBO HDPE NTP-ISO 4427:2008 DN 63 MM INCL INSTALACIÓN m 166.60 5.71 951.29 1,092.47 1,092.47 - 0.00 - 0.00
1.20.2 ENLACE ROSCADO TIPO MACHO HDPE DN 63 MM INCL ACCESORIOS und 10.00 60.75 607.50 697.66 697.66 - 0.00 - 0.00
1.21 CONTROL DE CALIDAD 14,435.19 16,577.57
1.21.1 PRUEBA HIDRÁULICA m 9,623.46 1.50 14,435.19 16,577.57 16,577.57 - 0.00 - 0.00
2 COMPONENTE 2: ADECUADO SISTEMA DE ELIMINACION DE 856,906.14 984,082.66
2.1 EXCRETAS
TRABAJOS PRELIMINARES 86,623.85 99,480.01
2.1.1 TRANSPORTE DE MATERIALES A OBRA CON MAQUINARIA gbl 1.00 12,443.96 12,443.96 14,290.81 14,290.81 9,706.29 11,146.84 - 0.00
2.1.2 COMPONENTEMANUAL
TRANSPORTE 2 DE MATERIALES DE PIE DE CARRETERA gbl 1.00 74,179.89 74,179.89 85,189.19 85,189.19 22,995.77 26,408.65 - 0.00
2.2 COMPONENTE
LETRINAS 2 459,057.68 527,188.08
2.2.1 OBRAS PRELIMINARES 2,908.26 3,339.89
2.2.1.1 LIMPIEZA MANUAL DE TERRENO m² 615.68 1.34 825.01 947.45 947.45 445.95 512.14 - 0.00
2.2.1.2 TRAZO, NIVELES Y REPLANTEO EN LETRINAS m² 532.80 3.91 2,083.25 2,392.43 2,392.43 1,126.08 1,293.21 - 0.00
2.2.2 MOVIMIENTO DE TIERRAS 8,652.06 9,936.14
2.2.2.1 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 199.27 21.37 4,258.40 4,890.40 4,890.40 1,601.04 1,838.66 - 0.00
2.2.2.2 PERFILADO Y COMPACTADO MANUAL m² 635.85 1.49 947.42 1,088.03 1,088.03 185.95 213.55 - 0.00
2.2.2.3 ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 193.50 17.81 3,446.24 3,957.71 3,957.71 1,111.34 1,276.28 - 0.00
2.2.3 CIMIENTOS Y SOBRECIMIENTOS 41,189.43 47,302.50
2.2.3.1 CIMIENTO CORRIDO C:H 1:10+60%P.G. (MEZCLA MANUAL) m³ 115.44 190.24 21,961.31 25,220.67 25,220.67 10,980.65 12,610.33 - 0.00
2.2.3.2 ENCOFRADO Y DESENCOFRADO m² 307.47 40.29 12,387.97 14,226.51 14,226.51 6,263.08 7,192.61 - 0.00
2.2.3.3 SOBRECIMIENTO C:H 1:6+25%P..M. (MEZCLA MANUAL) m³ 22.31 293.66 6,551.55 7,523.89 7,523.89 3,259.63 3,743.40 - 0.00
2.2.3.4 CURADO DE CONCRETO m² 577.20 0.50 288.60 331.43 331.43 148.59 170.64 - 0.00
2.2.4 MUROS Y TABIQUES DE ALBAÑILERÍA 53,110.79 60,993.15
2.2.4.1 MURO DE BLOQUETA DE 15X20X40CM m² 1,093.94 48.55 53,110.79 60,993.15 60,993.15 15,887.99 18,245.98 - 0.00
2.2.5 CONCRETO ARMADO 20,778.84 23,862.70
2.2.5.1 ENCOFRADO Y DESENCOFRADO DE VIGUETAS m² 173.16 41.68 7,217.31 8,288.46 8,288.46 - 0.00 - 0.00
2.2.5.2 ACERO CORRUGADO f´y=4200 KG/CM2 GRADO 60 kg 920.86 7.64 7,035.37 8,079.51 8,079.51 - 0.00 - 0.00
2.2.5.3 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 17.32 371.80 6,439.58 7,395.30 7,395.30 - 0.00 - 0.00
2.2.5.4 CURADO DE CONCRETO m² 173.16 0.50 86.58 99.43 99.43 - 0.00 - 0.00
2.2.6 PISOS Y PAVIMENTOS 35,192.83 40,415.92
2.2.6.1 EMPEDRADO E=12.5CM m² 431.42 13.95 6,018.31 6,911.51 6,911.51 - 0.00 - 0.00
2.2.6.2 ENCOFRADO Y DESENCOFRADO m² 28.86 40.29 1,162.77 1,335.34 1,335.34 - 0.00 - 0.00
2.2.6.3 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 36.68 371.80 13,637.62 15,661.63 15,661.63 - 0.00 - 0.00
2.2.6.4 CURADO DE CONCRETO m² 460.28 0.50 230.14 264.30 264.30 - 0.00 - 0.00
2.2.6.5 ENCHAPADO DE PISOS 0.45X0.45M m² 259.00 54.61 14,143.99 16,243.15 16,243.15 - 0.00 - 0.00
2.2.7 REVOQUES, ENLUCIDOS Y MOLDURAS 60,343.63 69,299.44
2.2.7.1 TARRAJEO EN MUROS E=1.5 CM m² 2,465.42 18.94 46,695.05 53,625.23 53,625.23 - 0.00 - 0.00
2.2.7.2 DERRAMES A=0.15 M MORTERO 1:5 m 73.26 14.65 1,073.26 1,232.55 1,232.55 - 0.00 - 0.00
2.2.7.3 ENCHAPADO CON CERÁMICO 0.30X0.40 m² 364.08 34.54 12,575.32 14,441.67 14,441.67 - 0.00 - 0.00
2.2.8 ZOCALOS Y CONTRAZOCALOS 5,106.00 5,863.80
2.2.8.1 ZOCALO CERÁMICO m 255.30 20.00 5,106.00 5,863.80 5,863.80 - 0.00 - 0.00
2.2.9 COBERTURA TECHO 44,867.98 51,527.00
2.2.9.1 CORREA P/TECHO CON MADERA TRATADA m 1,398.60 23.41 32,741.23 37,600.47 37,600.47 - 0.00 - 0.00
2.2.9.2 COBERTURA CON PLANCHA DE CALAMINA m² 555.00 21.85 12,126.75 13,926.52 13,926.52 - 0.00 - 0.00
2.2.10 CARPINTERÍA EN MADERA 42,535.20 48,848.00
2.2.10.1 PUERTA DE MADERA TIPO PERSIANA und 74.00 574.80 42,535.20 48,848.00 48,848.00 - 0.00 - 0.00
2.2.11 CERRAJERÍA 2,535.98 2,912.35
2.2.11.1 CERRADURA TIPO POMO DE ACERO und 74.00 34.27 2,535.98 2,912.35 2,912.35 - 0.00 - 0.00
2.2.12 PINTURA 15,055.50 17,289.94
2.2.12.1 PINTURA LATEX EN MUROS m² 2,066.56 6.68 13,804.62 15,853.41 15,853.41 - 0.00 - 0.00
2.2.12.2 PINTURA LATEX EN DERRAMES m 73.26 1.22 89.38 102.65 102.65 - 0.00 - 0.00
2.2.12.3 PINTURA EN PUERTAS C/BARNIZ 2 MANOS m² 118.40 9.81 1,161.50 1,333.88 1,333.88 - 0.00 - 0.00
2.2.13 INSTALACIONES SANITARIAS 44,197.18 50,756.64
2.2.13.1 TRAZO, NIVELES Y REPLANTEO m² 694.12 1.62 1,124.47 1,291.36 1,291.36 - 0.00 - 0.00
2.2.13.2 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 297.18 21.37 6,350.74 7,293.28 7,293.28 - 0.00 - 0.00
2.2.13.3 PERFILADO Y COMPACTADO MANUAL m² 694.12 1.49 1,034.24 1,187.74 1,187.74 - 0.00 - 0.00
2.2.13.4 CAMA DE APOYO CON MATERIAL PROPIO SELECCIONADO E=0.10 m m² 694.12 3.38 2,346.13 2,694.33 2,694.33 - 0.00 - 0.00
2.2.13.5 TUBO PVC SAP C-10 DE1/2" m 688.20 5.95 4,094.79 4,702.51 4,702.51 - 0.00 - 0.00
2.2.13.6 TUBO PVC SAL DE 2" m 828.80 7.97 6,605.54 7,585.89 7,585.89 - 0.00 - 0.00
2.2.13.7 TUBO PVC SAL DE 4" m 499.50 15.56 7,772.22 8,925.72 8,925.72 - 0.00 - 0.00
2.2.13.8 RELLENO Y COMPACTADO MANUAL CON MATERIAL PROPIO EN m³ 263.00 14.54 3,824.02 4,391.56 4,391.56 - 0.00 - 0.00
2.2.13.9 CAPAS DE E=0.20M
ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 34.19 17.81 608.92 699.29 699.29 - 0.00 - 0.00
2.2.13.10 ENCOFRADO Y DESENCOFRADO m² 149.67 40.29 6,030.20 6,925.16 6,925.16 - 0.00 - 0.00
2.2.13.11 ACERO CORRUGADO f´y=4200 KG/CM2 GRADO 60 kg 278.43 7.64 2,127.21 2,442.92 2,442.92 - 0.00 - 0.00
2.2.13.12 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 5.94 371.80 2,208.49 2,536.26 2,536.26 - 0.00 - 0.00
2.2.13.13 CURADO DE CONCRETO m² 140.42 0.50 70.21 80.63 80.63 - 0.00 - 0.00
2.2.14 APARATOS Y ACCESORIOS SANITARIOS 82,584.00 94,840.59
2.2.14.1 SUMINISTRO E INSTALACIÓN DE SANITARIO und 74.00 403.32 29,845.68 34,275.18 34,275.18 - 0.00 - 0.00
2.2.14.2 SUMINISTRO E INSTALACIÓN DE LAVATORIO und 74.00 200.95 14,870.30 17,077.25 17,077.25 - 0.00 - 0.00
2.2.14.3 SALIDA DE DUCHA TIPO ROCIADOR und 74.00 60.27 4,459.98 5,121.90 5,121.90 - 0.00 - 0.00
2.2.14.4 LLAVE PARA DUCHA und 74.00 59.73 4,420.02 5,076.01 5,076.01 - 0.00 - 0.00
2.2.14.5 LLAVE PARA LAVATORIO und 74.00 38.92 2,880.08 3,307.52 3,307.52 - 0.00 - 0.00
2.2.14.6 CODO F°G° DE 1/2" und 222.00 4.88 1,083.36 1,244.15 1,244.15 - 0.00 - 0.00
2.2.14.7 CODO PVC SAP 1/2" und 74.00 4.04 298.96 343.33 343.33 - 0.00 - 0.00
CRONOGRAMA DE EJECUCION DE OBRA EJECUTADO VS PROGRAMADO MES DE ABRIL 2022
PROYECTO: "AMPLIACION Y MEJORAMIENTO DEL SANEAMIENTO BASICO INTEGRAL DEL SECTOR DE PIÑALPATA DEL DISTRITO DE MARANURA - PROVINCIA DE LA CONVENCION - DEPARTAMENTO DE CUSCO"
PRESUPUESTO MODIFICADO PARA F 12
PRESUPUESTO DATOS AVALORIACION
ITEM DESCRIPCION PARCIAL + GG ACTUAL
CO+GG % MONTO
UND METRADO PRECIO S/. PARCIAL S/.
2.2.14.8 TEE PVC SAP DE 1/2" und 148.00 6.01 889.48 1,021.49 1,021.49 - 0.00 - 0.00
2.2.14.9 MANGUERA DE ABASTOS DE 1/2" und 148.00 29.17 4,317.16 4,957.89 4,957.89 - 0.00 - 0.00
2.2.14.10 VÁLVULA GLOBO DE 1/2" INCL. ACCESORIOS und 148.00 25.95 3,840.60 4,410.60 4,410.60 - 0.00 - 0.00
2.2.14.11 SUMIDERO DE BRONCE DE 2" und 148.00 16.15 2,390.20 2,744.94 2,744.94 - 0.00 - 0.00
2.2.14.12 REGISTRO ROSACADO DE 4" und 74.00 1.51 111.74 128.32 128.32 - 0.00 - 0.00
2.2.14.13 KIT DE TRAMPA PVC PARA LAVATORIO 2" und 74.00 26.57 1,966.18 2,257.99 2,257.99 - 0.00 - 0.00
2.2.14.14 CODO PVC SAL 4" und 148.00 15.83 2,342.84 2,690.55 2,690.55 - 0.00 - 0.00
2.2.14.15 CODO PVC SAL 2" und 740.00 8.07 5,971.80 6,858.10 6,858.10 - 0.00 - 0.00
2.2.14.16 YEE PVC SAL DE 2" und 74.00 7.14 528.36 606.78 606.78 - 0.00 - 0.00
2.2.14.17 TEE PVC SAL DE 4" C/R 2" und 74.00 12.85 950.90 1,092.03 1,092.03 - 0.00 - 0.00
2.2.14.18 TEE PVC SAL 2" und 74.00 9.51 703.74 808.18 808.18 - 0.00 - 0.00
2.2.14.19 SOMBRERO DE VENTILACIÓN DE 2" und 74.00 9.63 712.62 818.38 818.38 - 0.00 - 0.00
2.3 PILETAS DOMICILIARIAS 58,723.04 67,438.34
2.3.1 ESTRUCTURA DE PILETA 42,524.35 48,835.54
2.3.1.1 TRAZO, NIVELES Y REPLANTEO EN CONEXIONES DOMICILIARIAS m² 146.52 1.23 180.22 206.97 206.97 - 0.00 - 0.00
2.3.1.2 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 29.30 21.37 626.14 719.07 719.07 - 0.00 - 0.00
2.3.1.3 PERFILADO Y COMPACTADO MANUAL m² 146.52 1.49 218.31 250.71 250.71 - 0.00 - 0.00
2.3.1.4 ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 29.30 17.81 521.83 599.28 599.28 - 0.00 - 0.00
2.3.1.5 ENCOFRADO Y DESENCOFRADO m² 483.89 40.29 19,495.93 22,389.39 22,389.39 - 0.00 - 0.00
2.3.1.6 EMPEDRADO E=12.5CM m² 146.52 13.95 2,043.95 2,347.30 2,347.30 - 0.00 - 0.00
2.3.1.7 ACERO CORRUGADO f´y=4200 KG/CM2 GRADO 60 kg 700.97 7.64 5,355.41 6,150.23 6,150.23 - 0.00 - 0.00
2.3.1.8 CONCRETO F´C=175KG/CM2 +30% PM (MEZCLA MANUAL) m³ 18.20 303.15 5,517.33 6,336.18 6,336.18 - 0.00 - 0.00
2.3.1.9 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 22.27 371.80 8,279.99 9,508.85 9,508.85 - 0.00 - 0.00
2.3.1.10 CURADO DE CONCRETO m² 570.47 0.50 285.24 327.57 327.57 - 0.00 - 0.00
2.3.2 TUBERÍAS Y ACCESORIOS 16,198.69 18,602.80
2.3.2.1 SUMIDERO DE BRONCE DE 2" und 74.00 16.15 1,195.10 1,372.47 1,372.47 - 0.00 - 0.00
2.3.2.2 TUBO PVC SAL DE 2" m 222.00 7.97 1,769.34 2,031.93 2,031.93 - 0.00 - 0.00
2.3.2.3 TRAMPA PARA LAVATORIO und 74.00 32.64 2,415.36 2,773.83 2,773.83 - 0.00 - 0.00
2.3.2.4 CODO PVC SAL 2" und 148.00 8.07 1,194.36 1,371.62 1,371.62 - 0.00 - 0.00
2.3.2.5 CODO F°G° DE 1/2" und 74.00 4.88 361.12 414.72 414.72 - 0.00 - 0.00
2.3.2.6 CODO PVC SAP 1/2" und 74.00 4.04 298.96 343.33 343.33 - 0.00 - 0.00
2.3.2.7 TEE PVC SAP DE 1/2" und 74.00 6.01 444.74 510.75 510.75 - 0.00 - 0.00
2.3.2.8 GRIFO DE 1/2" INCL. ACCESORIOS und 74.00 42.17 3,120.58 3,583.72 3,583.72 - 0.00 - 0.00
2.3.2.9 VÁLVULA GLOBO DE 1/2" INCL. ACCESORIOS und 74.00 25.95 1,920.30 2,205.30 2,205.30 - 0.00 - 0.00
2.3.2.10 TUBO PVC SAP C-10 DE1/2" m 207.20 5.95 1,232.84 1,415.81 1,415.81 - 0.00 - 0.00
2.3.2.11 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 48.54 21.37 1,037.30 1,191.25 1,191.25 - 0.00 - 0.00
2.3.2.12 PERFILADO Y COMPACTADO MANUAL m² 121.36 1.49 180.83 207.67 207.67 - 0.00 - 0.00
2.3.2.13 CAMA DE APOYO CON MATERIAL PROPIO SELECCIONADO E=0.10 m m² 121.36 3.38 410.20 471.08 471.08 - 0.00 - 0.00
2.3.2.14 RELLENO Y COMPACTADO MANUAL CON MATERIAL PROPIO EN m³ 42.48 14.54 617.66 709.33 709.33 - 0.00 - 0.00
2.4 CAPAS
SISTEMADEDE
E=0.20M
TRATAMIENTO DE AGUAS RESIDUALES 252,501.57 289,976.24
2.4.1 BIODIGESTOR PREFABRICADO DE 600 L 165,197.23 189,714.74
2.4.1.1 ESTRUCTURA DE BIODIGESTOR 146,374.63 168,098.61
2.4.1.1.1 TRAZO, NIVELES Y REPLANTEO DE POZO SEPTICO m² 62.90 1.23 77.37 88.85 88.85 - 0.00 - 0.00
2.4.1.1.2 LIMPIEZA MANUAL DE TERRENO m² 62.90 1.34 84.29 96.80 96.80 - 0.00 - 0.00
2.4.1.1.3 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 113.22 21.37 2,419.51 2,778.60 2,778.60 - 0.00 - 0.00
2.4.1.1.4 PERFILADO Y COMPACTADO MANUAL m² 62.90 1.49 93.72 107.63 107.63 - 0.00 - 0.00
2.4.1.1.5 ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 113.22 17.81 2,016.45 2,315.72 2,315.72 - 0.00 - 0.00
2.4.1.1.6 BIODIGESTOR PREFABRICADO DE 600 L und 74.00 1,875.64 138,797.36 159,396.77 159,396.77 - 0.00 - 0.00
2.4.1.1.7 ACERO CORRUGADO f´y=4200 KG/CM2 GRADO 60 kg 55.50 7.64 424.02 486.95 486.95 - 0.00 - 0.00
2.4.1.1.8 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 1.04 371.80 386.67 444.06 444.06 - 0.00 - 0.00
2.4.1.1.9 CURADO DE CONCRETO m² 20.72 0.50 10.36 11.90 11.90 - 0.00 - 0.00
2.4.1.1.10 CAMA DE APOYO DE BIODIGESTOR m³ 12.58 126.87 1,596.02 1,832.89 1,832.89 - 0.00 - 0.00
2.4.1.1.11 RELLENO Y COMPACTADO MANUAL CON MATERIAL SELECCIONADO m³ 26.64 17.60 468.86 538.45 538.45 - 0.00 - 0.00
2.4.1.2 EN CAPASDEDELODOS
CAMARA E=0.20M 18,822.60 21,616.13
2.4.1.2.1 TRAZO, NIVELES Y REPLANTEO DE CAMARA DE LODOS m² 26.64 2.64 70.33 80.77 80.77 - 0.00 - 0.00
2.4.1.2.2 LIMPIEZA MANUAL DE TERRENO m² 26.64 1.34 35.70 41.00 41.00 - 0.00 - 0.00
2.4.1.2.3 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 15.98 21.37 341.49 392.17 392.17 - 0.00 - 0.00
2.4.1.2.4 PERFILADO Y COMPACTADO MANUAL m² 26.64 1.49 39.69 45.58 45.58 - 0.00 - 0.00
2.4.1.2.5 ELIMINACIÓN MANUAL DE MATERIAL EXCEDENTE m³ 15.98 17.81 284.60 326.84 326.84 - 0.00 - 0.00
2.4.1.2.6 ENCOFRADO Y DESENCOFRADO m² 267.14 40.29 10,763.07 12,360.46 12,360.46 - 0.00 - 0.00
2.4.1.2.7 ACERO CORRUGADO f´y=4200 KG/CM2 GRADO 60 kg 388.50 7.64 2,968.14 3,408.65 3,408.65 - 0.00 - 0.00
2.4.1.2.8 CONCRETO F´C=175KG/CM2 (MEZCLA MANUAL) m³ 11.21 371.80 4,167.88 4,786.45 4,786.45 - 0.00 - 0.00
2.4.1.2.9 CURADO DE CONCRETO m² 303.40 0.50 151.70 174.21 174.21 - 0.00 - 0.00
2.4.2 ZANJAS DE INFILTRACIÓN 87,304.34 100,261.49
2.4.2.1 TRAZO, NIVELES Y REPLANTEO DE ZANJAS DE INFILTRACIÓN m² 568.32 2.64 1,500.36 1,723.03 1,723.03 - 0.00 - 0.00
2.4.2.2 LIMPIEZA MANUAL DE TERRENO m² 568.32 1.34 761.55 874.57 874.57 - 0.00 - 0.00
2.4.2.3 EXCAVACIÓN MANUAL DE ZANJAS EN TERRENO NORMAL m³ 681.98 21.37 14,573.91 16,736.88 16,736.88 - 0.00 - 0.00
2.4.2.4 PERFILADO Y COMPACTADO MANUAL m² 568.32 1.49 846.80 972.48 972.48 - 0.00 - 0.00
2.4.2.5 CAMA DE APOYO E=0.15 PIEDRA CHANCADA m² 568.32 6.83 3,881.63 4,457.72 4,457.72 - 0.00 - 0.00
2.4.2.6 TUBO PVC SAL PESADO DE 4" m 310.80 29.10 9,044.28 10,386.57 10,386.57 - 0.00 - 0.00
2.4.2.7 TUBO CRIBADO PVC SAL PESADO DE 4" m 1,110.00 29.40 32,634.00 37,477.33 37,477.33 - 0.00 - 0.00
2.4.2.8 TEE DOBLE PVC SAL PESADO 4" und 74.00 32.67 2,417.58 2,776.38 2,776.38 - 0.00 - 0.00
2.4.2.9 CODO PVC SAL PESADO 4" und 296.00 5.34 1,580.64 1,815.23 1,815.23 - 0.00 - 0.00
2.4.2.10 TAPON PVC SAL 4" und 222.00 13.68 3,036.96 3,487.69 3,487.69 - 0.00 - 0.00
2.4.2.11 RELLENO CON MATERIAL PÉTREO m³ 310.80 38.00 11,810.40 13,563.22 13,563.22 - 0.00 - 0.00
2.4.2.12 RELLENO Y COMPACTADO MANUAL CON MATERIAL PROPIO EN m³ 358.75 14.54 5,216.23 5,990.39 5,990.39 - 0.00 - 0.00
3 CAPAS DE E=0.20M
COMPONENTE 3: ACCIONES DE PROMOCION, CAPACITACION EN 108,426.22 124,518.14
3.1 JASS, SEGURIDAD
DIAGNÓSTICO Y SALUD
COMUNITARIO 2,891.60 3,320.75
3.1.1 COSTO DIAGNOSTICO COMUNITARIO gbl 1.00 2,891.60 2,891.60 3,320.75 3,320.75 - 0.00 - 0.00
3.2 ACCIONES DE PROMOCIÓN 10,302.90 11,831.99
CRONOGRAMA DE EJECUCION DE OBRA EJECUTADO VS PROGRAMADO MES DE ABRIL 2022
PROYECTO: "AMPLIACION Y MEJORAMIENTO DEL SANEAMIENTO BASICO INTEGRAL DEL SECTOR DE PIÑALPATA DEL DISTRITO DE MARANURA - PROVINCIA DE LA CONVENCION - DEPARTAMENTO DE CUSCO"
PRESUPUESTO MODIFICADO PARA F 12
PRESUPUESTO DATOS AVALORIACION
ITEM DESCRIPCION PARCIAL + GG ACTUAL
CO+GG % MONTO
UND METRADO PRECIO S/. PARCIAL S/.
3.2.1 MATERIALES ACCIONES DE PROMOCIÓN 1,724.90 1,980.90
3.2.1.1 MATERIAL DE PROMOCIÓN ENTREGADO POR EL PROYECTO gbl 1.00 1,500.00 1,500.00 1,722.62 1,722.62 187.50 215.33 - 0.00
3.2.1.2 MATERIAL PARA TALLERES PROMOCIÓN (ANTES Y DURANTE) gbl 1.00 224.90 224.90 258.28 258.28 28.11 32.28 0.13 28.11
3.2.2 ACCIONES DE PROMOCIÓN EN EL ANTES 1,815.60 2,085.06
3.2.2.1 PAGO POR PROMOCIÓN EN EL ANTES mes 1.00 1,815.60 1,815.60 2,085.06 2,085.06 - 0.00 1.00 1,815.60
3.2.3 ACCIONES DE PROMOCIÓN EN EL DURANTE 1,815.60 2,085.06
3.2.3.1 PAGO POR PROMOCIÓN EN EL DURANTE mes 1.00 1,815.60 1,815.60 2,085.06 2,085.06 226.95 260.63 - 0.00
3.2.4 ACCIONES DE PROMOCIÓN Y EDUCACIÓN PARA LA HIGIENE EN EL 4,946.80 5,680.97
3.2.4.1 DESPUES
ACCIONES DE PROMOCIÓN Y SEGUIMIENTO A LA JASS (DESPUÉS) mes 2.00 1,815.60 3,631.20 4,170.12 4,170.12 - 0.00 - 0.00
3.2.4.2 MATERIAL PARA LA EJECUCIÓN DE LA PROMOCIÓN (DESPUÉS) gbl 1.00 22.00 22.00 25.27 25.27 - 0.00 - 0.00
3.2.4.3 CONCURSO COMUNIDAD SALUDABLE gbl 1.00 1,200.00 1,200.00 1,378.10 1,378.10 - 0.00 - 0.00
3.2.4.4 CAMPAÑAS DE SALUD E HIGIENE EN COMUNIDAD gbl 1.00 93.60 93.60 107.49 107.49 - 0.00 - 0.00
3.3 ACCIONES DE CAPACITACIÓN 6,491.40 7,454.81
3.3.1 MATERIALES ACCIONES DE CAPACITACIÓN 1,375.80 1,579.99
3.3.1.1 MATERIAL PARA TALLERES DE CAPACITACIÓN A JASS gbl 1.00 250.80 250.80 288.02 288.02 31.35 36.00 0.13 31.35
3.3.1.2 MATERIAL DE CAPACITACIÓN ENTREGADO POR EL PROYECTO gbl 1.00 1,125.00 1,125.00 1,291.97 1,291.97 140.63 161.50 0.13 140.63
3.3.2 ACCIONES DE CAPACITACIÓN 1,815.60 2,085.06
3.3.2.1 PAGO POR HONORARIOS TALLERES DE CAPACITACIÓN JASS gbl 1.00 1,815.60 1,815.60 2,085.06 2,085.06 226.95 260.63 0.13 226.95
3.3.3 ACCIONES DE CAPACITACIÓN EN EL DESPUES 3,300.00 3,789.76
3.3.3.1 CONCURSO DE JASS (DESPUÉS) gbl 1.00 3,300.00 3,300.00 3,789.76 3,789.76 - 0.00 - 0.00
3.4 SEGURIDAD, BIOSEGURIDAD Y SALUD 41,998.16 48,231.26
3.4.1 EQUIPOS DE PROTECCIÓN PERSONAL und 60.00 235.40 14,124.00 16,220.19 16,220.19 - 0.00 27.00 6,355.80
3.4.2 EQUIPO DE PROTECCIÓN COLECTIVA gbl 1.00 1,140.00 1,140.00 1,309.19 1,309.19 142.50 163.65 0.13 142.50
3.4.3 SEÑALIZACIÓN TEMPORAL DE SEGURIDAD Y BIOSEGURIDAD gbl 1.00 1,625.76 1,625.76 1,867.04 1,867.04 203.22 233.38 0.13 203.22
3.4.4 MONITOREO Y SENSIBILIZACIÓN DE SEGURIDAD Y BIOSEGURIDAD mes 8.00 3,000.00 24,000.00 27,561.93 27,561.93 3,000.00 3,445.24 1.00 3,000.00
3.4.5 SEGÚN PROTOCOLOS
RECURSOS CONTRA COVID
PARA RESPUESTAS 19
ANTE EMERGENCIAS EN SEGURIDAD gbl 1.00 294.10 294.10 337.75 337.75 36.76 42.22 - 0.00
3.4.6 Y SALUD DURANTE
IMPLEMENTOS EL TRABAJOSEGÚN PROTOCOLOS COVID 19
DE SEGURIDAD gbl 1.00 814.30 814.30 935.15 935.15 101.79 116.90 0.05 40.72
3.5 MITIGACIÓN DE IMPACTO AMBIENTAL 46,742.16 53,679.33
3.5.1 PLAN DE GESTIÓN AMBIENTAL gbl 1.00 46,742.16 46,742.16 53,679.33 53,679.33 - 0.00 1.00 46,742.16
1,712,672.600 125,315.09
COSTOS DIRECTOS S/. 1,491,337.80 1,712,672.60 250,630.20 #REF! 95,509.21
GASTOS GENERALES S/. 14.84% 221,334.80 #REF!
GASTOS DE SUPERVISIÓN S/. 3.94% 58,726.08 3,760.97
ELABORACIÓN DE EXPEDIENTE TÉCNICO S/. 1.58% 23,511.91 1,505.76
LIQUIDACIÓN DE OBRA S/. 0.98% 14,606.82

TOTAL VALORIZADO S/. 1,809,517.41 #REF! #REF!


FORMATO 12-B MES DE MAYO
MUNICIPALIDAD DISTRITAL DE MARANUERA OFICINA DE
UNIDAD EJECUTORA DE INVERSIONES: "SUB GERENCIA DE INFRAESTRUCTURA Y DESARROLLO TERRITORIAL" PROGRAMACION
“AÑO DEL FORTALECIMIENTO DE LA SOBERANIA NACIONAL ” MULTIANUAL DE
INVERSIONES (OPMI)
"AMPLIACION Y MEJORAMIENTO DEL SANEAMIENTO BASICO INTEGRAL DEL SECTOR DE PIÑALPATA DEL DISTRITO DE MARANURA - PROVINCIA DE LA CONVENCION - DEPARTAMENTO DE CUSCO"
MODELO DE VALORIZACION DE OBRA POR ACCIONES Y FACTOR PRODUCTIVO
FECHA DE INICIO DE OBRA 3/21/2022
RESIDENTE : ING. JORGE LUIS VALENCIA CORDOVA FECHA DE TERMINO PROGRAMADO 11/15/2022 OPMI
INSPECTOR : ING. EDGAR VIAMONTE CALLA FECHA DE TERMINO MODIFICADO
PRESUPUESTO DE OBRA-ACTUALIZADO 1,809,517.41
EJECUCION FISICA DE OBRA
PRESUPESTO VALORIZACION ANTERIOR VALORIZACION ACTUAL VALORIZACION ACUMULADO SALDO POR VALORIZAR
EJECUCION FINANCIERA
DESCRIPCION PROGRAMADO VALORIZACION % VALORIZACION % VALORIZACION % VALORIZACION % ACUMULADO
ITEM FORMATO 8A ANTERIOR
INFRAESTRUCTURA 1,546,698.83 57,426.36 3.71% 138,945.81 8.98% 111,719.90 12.70% 1,434,978.93 87.30%
1 ADECUADO SISTEMA DE ABASTECIMENTO DE AGUA 660,281.38 57,426.36 8.70% 54,293.54 8.22% 111,719.90 548,561.48
TRABAJOS PRELIMINARES INFRAESTRUCTURA 54,461.14 3,330 6.12% 6,170.45 11.33% 9,500.86 17.45% 44,960.28 82.55%
CAPTACIÓN SUPERFICIAL DE INSIENSUYOC INFRAESTRUCTURA 33,296.15 - 0.00% 0.00 0.00% 0.00 0.00% 33,296.15 100.00%
CAPTACIÓN DE LADERA HUERTO DEL EDEN INFRAESTRUCTURA 14,045.29 - 0.00% 0.00 0.00% 0.00 0.00% 14,045.29 100.00%
CAPTACIÓN SUPERFICIAL ROCOTOCHAYOC INFRAESTRUCTURA 28,957.64 - 0.00% 0.00 0.00% 0.00 0.00% 28,957.64 100.00%
DESARENADOR INFRAESTRUCTURA 14,428.71 - 0.00% 0.00 0.00% 0.00 0.00% 14,428.71 100.00%
 FILTRO LENTO DE ARENA-LINEA DE CONDUCCION INFRAESTRUCTURA 101,505.23 31,421 30.95% 15,217.94 14.99% 46,638.85 45.95% 54,866.38 54.05%
CÁMARA DE REUNIÓN-CÁMARA DE ROMPE PRESIÓN INFRAESTRUCTURA 28,512.61 - 0.00% 0.00 0.00% 0.00 0.00% 28,512.61 100.00%
RESERVORIOS INFRAESTRUCTURA 44,955.68 126 0.28% 0.00 0.00% 126.46 0.28% 44,829.22 99.72%
GASTOS GENERALES POR COVID - 19 INFRAESTRUCTURA 0.00 - 0.00% 0.00 0.00% 0.00 0.00% 0.00 100.00%
INVENTARIO FISICO COVID - 19 INFRAESTRUCTURA 0.00 - 0.00% 0.00 0.00% 0.00 0.00% 0.00 100.00%
TANQUE DE POLIETILENO-LINEA DE ADUCCIÓN-CAMARA DE DISTRIBUCIÓN INFRAESTRUCTURA 283,790.04 24,802 8.74% 32,905.15 11.59% 57,707.42 20.33% 226,082.62 79.67%
DE CAUDALES-CAMARA ROMPE PRESIÓN TIPO 7
PASE AEREO DE 5 M-10M -LUYCHO ALTO INFRAESTRUCTURA 34,515.87 - 0.00% 0.00 0.00% 0.00 0.00% 34,515.87 100.00%
PRUEBA HIDRAHULICA INFRAESTRUCTURA 21,813.02 - 0.00% 0.00 0.00% 0.00 0.00% 21,813.02 100.00%
2 ADECUADO SISTEMA DE ELIMINACION DE EXCRETAS 886,417.45 0.00 84,652.28 9.55% 84,652.28 801,765.17 563,074.82
TRABAJOS PRELIMARES Y LETRINAS INFRAESTRUCTURA 560,437.18 - 0.00% 84,652.28 15.10% 84,652.28 15.10% 475,784.90 84.90%
PILETAS DOMICILIARES INFRAESTRUCTURA 66,100.87 - 0.00% 0.00 0.00% 0.00 0.00% 66,100.87 100.00%
GASTOS GENERALES POR COVID - 19 INFRAESTRUCTURA 0.00 - 0.00% 0.00 0.00% 0.00 0.00% 0.00 100.00%
INVENTARIO FISICO COVID - 19 INFRAESTRUCTURA 0.00 - 0.00% 0.00 0.00% 0.00 0.00% 0.00 100.00%
SISTEMA DE TRATAMIENTO DE AGUAS RESIDUALES INFRAESTRUCTURA 259,879.40 - 0.00% 0.00 0.00% 0.00 0.00% 259,879.40 100.00%
3 ACCIONES DE PROMOCION Y CAPACITACION EN JASS 0.00 0.00
GASTOS GENERALES POR COVID - 19 INFRAESTRUCTURA 0.00 - 0.00% 0.00 0.00% 0.00 0.00% 0.00 100.00%
INVENTARIO FISICO COVID - 19 INFRAESTRUCTURA 0.00 - 0.00% 0.00 0.00% 0.00 0.00% 0.00 100.00%
EQUIPAMIENTO 20,658.48 0.00 0.00% 0.00 0.00% 0.00 0.00% 20,658.48 100.00%
1 ADECUADO SISTEMA DE ABASTECIMENTO DE AGUA 20,658.48 0.00 2.82 0.00 0.00% 0.00 0.00% 20,658.48 100.00%
TUBERÍA Y ACCESORIOS EQUIPAMIENTO 20,658.48 - 0.00% 0.00 0.00% 0.00 0.00% 20,658.48 100.00%
INTANGIBLE 145,315.29 67,442.93 46.41% 4,967.76 3.42% 72,410.69 49.83% 72,904.60 50.17%
1 ACCIONES DE PROMOCION Y CAPACITACION EN JASS 145,315.29 67442.93 1.22 4,967.76 3.42% 72,410.69 49.83% 72,904.60 50.17%
ACCIONES DE PROMOCION CAPACITACION JASS,SEGURIDAD Y SALUD INTANGIBLES 91,195.31 13,764 15.09% 4,967.76 0.00% 18,731.36 15.09% 72,463.95 84.91%
PLAN DE GESTION AMBIENTAL INTANGIBLES 54,119.98 53,679 99.19% 0.00 0.00% 53,679.33 99.19% 440.65 0.81%
TOTAL CD 1,712,672.60 127,122.97 7.42% 143,913.58 8.40% 271,036.54 15.83% 1,441,636.06 84.17%
FORMATO N° 12-B:-MES DE MAYO 2022
SEGUIMIENTO A LA EJECUCIÓN DE INVERSIONES
(La información registrada en este formato tiene carácter de Declaración Jurada - D.S. N° 284-2018-EF)

I. DATOS GENERALES
Código único de inversiones 2350362 Código de la UP
Nombre de la inversión "AMPLIACION Y MEJORAMIENTO DEL SANEAMIENTO BASICO INTEGRAL DEL SECTOR DE PIÑALPATA DEL DISTRITO DE MARANURA - PROVINCIA DE LA CONVENCION - DEPARTAMENTO DE CUSCO"

Unidad Ejecutora de Inversiones SUB GERENCIA DE INFRAESTRUCTURA Y DESARROLLO TERRITORIAL Modalidad de ejecución ADM. DIRECTA

Costo actualizado 1,809,517.41 Estado1/ ACTIVO

II. EXPEDIENTE TÉCNICO (ET) / DOCUMENTO EQUIVALENTE (DE)


1. Procedimiento de selección
Actuaciones preparatorias Fecha de convocatoria Fecha de integración de bases Fecha de buena pro Fecha de suscripción de contrato/convenio
Programada Actualizada Programada Actualizada Final* Programada Actualizada Final* Programada Actualizada Final* Programada Actualizada Final*

2. Elaboración del Expediente Técnico 3. Elaboración del Documento Equivalente 2/


Fechas Programada Final Fechas Programada Final
Inicio Inicio
Culminación Culminación
Aprobación 7/9/2018 Aprobación

III. EJECUCIÓN FÍSICA


1. Procedimiento de selección
Actuaciones preparatorias Fecha de convocatoria Fecha de integración de bases Fecha de buena pro Fecha de suscripción de contrato/convenio
Item / Fechas
Programada Actualizada Programada Actualizada Final * Programada Actualizada Final * Programada Actualizada Final * Programada Actualizada Final *
Infraestructura
Equipamiento
Otros**
2. Fechas de ejecución física
Fecha Programada Actualizada Final
Inicio 3/21/2022 11/15/2022 Monto del Contrato
Culminación Monto actualizado del Contrato
3. AVANCE F[ISICO - METAS F[ISICAS (S/.)
Años anteriores ….. Año 2022 MONTO POR COMP.
Item
… ene feb mar abr may jun jul ago sep oct nov dic APROB TOTAL
Infraestructura 1,546,698.83
Avance físico programado … 50,956.38 86,623.35 132,459.73 196,805.07 216,424.01 332,649.63 136,665.65 375,800.94 18,314.07 1,546,698.83
Avance físico real … 17,438.92 42,241.13 138,945.81 198,625.87
Avance físico real acumulado … 17,438.92 59,680.05 198,625.87 275,744.84
Avance físico real acumulado % … 1.13% 3.86% 12.84% 17.83%
Equipamiento … 20,658.48
Avance físico programado … 680.60 1,156.98 1,769.20 2,628.63 2,890.67 4,443.03 1,825.37 5,019.38 244.62 20,658.48
Avance físico real … 0.00 0.00 0.00 0.00
Avance físico real acumulado … 0.00 0.00 0.00 0.00
Avance físico real acumulado % … 0.00% 0.00% 0.00% 0.00%
Intangibles 145,315.29
Avance físico programado … 4,787.45 8,138.43 12,444.84 18,490.21 20,333.45 31,253.06 12,840.00 35,307.21 1,720.64 145,315.29
Avance físico real … 0.00 67,442.93 4,967.76 72,410.69
Avance físico real acumulado … 0.00 67,442.93 72,410.69 139,853.62
Avance físico real acumulado % … 0.00% 46.41% 49.83% 96.24%

VALORIZADO ACUMULADO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17,438.92 109,684.06 143,913.58 0.00 0.00 0.00 0.00 0.00 0.00 1,712,672.60

Avance físico global (%) 15.83% Resumen de Valorización/Informe de avance (Adjuntar documento) Fotos (Adjuntar)
4. EJECUCIÓN FINANCIERA
Avance financiero de la inversión
Año … Año 2021
Avance ACUMULADO
2014 2015 2016 2017 2018 2019 2020 2021 … ene feb mar abr may jun jul ago sep oct nov dic TOTAL
Avance financiero programado … 42,842.74 343,581.55 196,512.85 300,914.31 127,679.95 330,039.40 156,314.25 104,740.05 104,740.05 50,605.70 1,757,970.85
Avance financiero actualizado 10,177.97 35,868.58 5,500.00 51,546.55 … 16,513.10 261,892.60 233,122.57 563,074.82
Avance final (Devengado/Girado) *** 10,177.97 35,868.58 5,500.00 51,546.55 … 16,513.10 261,892.60 233,122.57 563,074.82

5. ESTADO SITUACIONAL
Descripción: la obra se encuentra en ejecucion con inicio de obra en 21 de marzo del 2022

Problemática 3/

Documento de Paralización/Suspensión/Resolución/Otro (Adjuntar documento)

6. CULMINACIÓN
Fecha Programada Final
Culminación de la ejecución 11/15/2022
Recepción de la obra / activo
Nota:
Seleccionar de la lista de opciones el que corresponde:
1/
ET/DE en actuaciones preparatorias, ET/DE en procedimiento de selección, ET/DE en elaboración, Inversión en actuaciones preparatorias, Inversión en procedimiento de selección, Inversión en ejecución, Ejecución de saldo de inversión, Inversión culminada, o Recepción de la inversión.

2/
Especificaciones Técnicas, Términos de Referencia y/o Estudios Definitivos de Ingeniería.
3/
Modificaciones en calendario de procedimiento de selección, Atrasos y/o paralizaciones, Resolución de contrato, Resolución de Convenio, Falta de disponibilidad de terreno, Permisos y licencias, Otras autorizaciones, Interferencias, Arbitraje, Falta de recursos financieros, Supervisor/Inspector, Riesgo no identificado, Discrepancias (Valorización observada, etc.), Recepción observada u Otro.

* Información será extraída del Sistema Electrónico de Contrataciones del Estado (SEACE) operado por el Organismo Supervisor de las Contrataciones del Estado (OSCE); excepto cuando la ejecución de proyectos de inversión se realiza mediante el mecanismo de Obras por Impuestos (OxI), Asociación Público Privado (APP).
En el caso la inversión se ejecute por Administración directa, la UEI no registrará información sobre el procedimiento de selección de la ejecución física.
* * Otros: Mobiliario, Intangibles, Vehículos, Terreno e Infraestructura natural.
*** Información será extraída del Portal de Transparencia Económica - Consulta Amigable de Ejecución del Gasto del Ministerio de Economía y Finanzas.
Las UEI registrarán información dependiendo del estado en que se encuentre la inversión.
Tamaño, volumen u
Unidad físicas otras unidades Costo a precio EXPEDIENTE
Descripción de productos/acciones Tipo de factor productivo representativas UEI FORMATO 8A
mercado TECNICO
U.M. Meta U.M. Meta
ADECUADO SISTEMA DE ABASTECIMENTO DE AGUA 604,071.80 680,939.86
Construccion de almacen :  TRABAJOS PRELIMINARES INFRAESTRUCTURA ESPACIOS 8 M2 300 54,461.14 UEIMDMRU1
FISICOS
Construccion de captacion de agua :  CAPTACIÓN SUPERFICIAL DE INSIENSUYOC INFRAESTRUCTURA ESPACIOS 37.86 M2 1.62 33,296.15 UEIMDMRU1
FISICOS
Construccion de captacion de agua :  CAPTACIÓN DE LADERA HUERTO DEL EDEN INFRAESTRUCTURA ESPACIOS 13.34 M2 1.62 14,045.29 UEIMDMRU1
FISICOS
Construccion de captacion de agua :  CAPTACIÓN SUPERFICIAL ROCOTOCHAYOC INFRAESTRUCTURA ESPACIOS 26.19 M2 1.62 28,957.64 UEIMDMRU1
FISICOS
Construccion de cerco perimetrico :  DESARENADOR INFRAESTRUCTURA ESPACIOS 8.67 M3 1.62 14,428.71 UEIMDMRU1
FISICOS
Construccion de línea de conducción :  FILTRO LENTO DE ARENA-LINEA DE CONDUCCION INFRAESTRUCTURA ESPACIOS 1201.16 M 1.62 101,505.23 UEIMDMRU1
FISICOS
Construccion de camara de control :  CÁMARA DE REUNIÓN-CÁMARA DE ROMPE PRESIÓN INFRAESTRUCTURA ESPACIOS 6.6 M2 1.62 28,512.61 UEIMDMRU1
FISICOS
Construccion de reservorio :  RESERVORIOS INFRAESTRUCTURA ESPACIOS 19.6 M2 1.62 44,955.68 UEIMDMRU1
FISICOS
Gastos generales por covid - 19 :  INFRAESTRUCTURA - UEIMDMRU1
Inventario físico covid - 19 :  INFRAESTRUCTURA - UEIMDMRU1
Construccion de línea de aducción :  TANQUE DE POLIETILENO-LINEA DE ADUCCIÓN-CAMARA DE INFRAESTRUCTURA ESPACIOS 2127.19 M2 2.61 283,790.04 UEIMDMRU1
DISTRIBUCIÓN DE CAUDALES-CAMARA ROMPE PRESIÓN TIPO 7 FISICOS
Construccion de sistema de transferencia de carga por tuberias :  TUBERÍA Y ACCESORIOS EQUIPAMIENTO KIT DE 61 M3 25.95 20,658.48 UEIMDMRU1
EQUIPAMIEN
Construccion de pase aereo :  ASE AEREO DE 5 M-10M -LUYCHO ALTO INFRAESTRUCTURA ESPACIOS 166.6 M2 5.71 34,515.87 UEIMDMRU1
TO
FISICOS
Construccion de equipo hidraulico :  PRUEBA HIDRAHULICA INFRAESTRUCTURA ESPACIOS 9623.46 M 1.5 21,813.02 UEIMDMRU1
FISICOS
ADECUADO SISTEMA DE ELIMINACION DE EXCRETAS 984,082.66 886,417.45
Construccion de letrina sanitaria :  TRABAJOS PRELIMARES Y LETRINAS INFRAESTRUCTURA ESPACIOS 615.62 M2 1.34 560,437.18 UEIMDMRU1
FISICOS
Construccion de pileta publica :  PILETAS DOMICILIARES INFRAESTRUCTURA ESPACIOS 146.52 M2 1.23 66,100.87 UEIMDMRU1
FISICOS
Gastos generales por covid - 19 :  INFRAESTRUCTURA - UEIMDMRU1
Inventario físico covid - 19 :  INFRAESTRUCTURA - UEIMDMRU1
Construccion de sistema de tratamiento de aguas residuales :  SISTEMA DE TRATAMIENTO DE AGUAS INFRAESTRUCTURA ESPACIOS 62.9 M2 1.23 259,879.40 UEIMDMRU1
RESIDUALES FISICOS
ACCIONES DE PROMOCION Y CAPACITACION EN JASS 124,518.14 145,315.29
Capacitacion de central de vigilancia y seguridad :  ACCIONES DE PROMOCION CAPACITACION INTANGIBLES NÚMERO DE 1 2891.6 91,195.31 UEIMDMRU1
JASS,SEGURIDAD Y SALUD CAPACITACI
ONES
Gastos generales por covid - 19 :  INFRAESTRUCTURA - UEIMDMRU1
Inventario físico covid - 19 :  INFRAESTRUCTURA - UEIMDMRU1
Capacitacion de documento de gestion :  PLAN DE GESTION AMBIENTAL INTANGIBLES N° DE 1 46742 54,119.98 UEIMDMRU1
DOCUMENT
SUBTOTAL:   S/. 1,712,672.60 1,712,672.60
OS
GESTION DEL PROYECTO:   S/. 0 UEIMDMRU1
EXPEDIENTE TÉCNICO:   S/. 23,511.91 UEIMDMRU1
EXPEDIENTE TECNICO COVID:   S/. 0 UEIMDMRU1
SUPERVISIÓN:   S/. 58,726.08 UEIMDMRU1
SUPERVISIÓN COVID:   S/. 0 UEIMDMRU1
LIQUIDACIÓN:   S/. 14,606.82 UEIMDMRU1
TOTAL:   S/. 1,809,517.41

CONTROL CONCURRENTE:   S/. 0

MONTO DE SOLUCIÓN DE CONTROVERSIAS:   S/. 0

COSTO TOTAL ACTUALIZADO:   S/. 1,809,517.41