DEDUCTIVO NRO. 01: ESTRUCTURAS PISOS 8, 9 Y 10 DISCONTI NUIDAD EN LA EJECUCIÓN DE OBRA. DR S/. 1,445,946.06 S/. 152,507.59 S/. 177,605.96
DEDUCTIVO NRO. 02: GIMNASIO SÓTANO 01 CAMBIO DE ACABADOS Y DE USO DEL ÁREA DR S/. 72,592.28 S/. 8,916.53
DEDUCTIVO NRO. 03: PISO 01 CAMBIO DE ACABADOS Y DE USO DEL ÁREA DR S/. 171,748.69 S/. 21,095.94
TOTALES S/. 1,690,287.03 S/. 152,507.59 S/. 207,618.43
PLAZO DE EJECUCIÓN
PORCENTAJE DE AVANCE FECHA DE
SUBTOTAL IGV TOTAL S/. EN OBRA PRESENTACION STATUS RO STATUS PRESENTACION
S/. 81,508.81
S/. 0.00 S/. 0.00 S/. 0.00 S/. 81,508.81 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO AGOSTO SEPTIEMBRE OCTUBRE
MONTOS / VALORIZACIONES - Y PLAZOS DE EJECUCION
ADICIONALES
NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO JUNIO TOTALES APROBADOS C.D.
592,019.87 592,019.87 592,019.87 S/. 1,776,059.61
S/. 81,508.81
S/. 0.00 S/. 0.00 S/. 592,019.87 S/. 592,019.87 S/. 592,019.87 S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,857,568.42