Documentos de Académico
Documentos de Profesional
Documentos de Cultura
RESIDENTE DE OBRA:
ING. ALCIDES QUISPE MUÑOZ.
SUPERVISOR DE OBRA:
ING. ROGER DAVID GUTIERREZ QUISPE
ANDAHUAYLAS - APURIMAC
PERU
2022
FORMATO FF - 01
FICHA DE IDENTIFICACION DEL PROYECTO
Nombre del Proyecto: IRRIGACION CHUMBAO - COMPONENTE OBRAS DE ASPERSION
Unidad Ejecutora GERENCIA SUB REGIONAL CHANKA - ANDAHUAYLAS
Residente de Obra ING. ALCIDES QUISPE MUÑOZ.
Supervisor de Obra ING. ROGER DAVID GUTIERREZ QUISPE
Asistente Administrativo BRIAN ESPINOZA ALARCON
I.- GENERALIDADES
1.1.1.- Ubicación
FUNCION : 10 Agropecuaria
PROGRAMA : 0042 Riego
SUB PROGRAMA : 050 Infraestructura de Riego
COMPONENTE : Riego por Aspersion
COD. SNIP : 4978
META : 0001
UNIDAD EJECUTORA : Gerencia Sub Regional Chanka
MOD. EJECUCION : Administracion Directa
EXPEDIENTE COSTO
EXPEDIENTE
COMPONENTE PIP VIABLE ACTUALIZAD INCREMENTA TOTAL
TÈCNICO
Prensa Pampahuasi 1,055,024.00 2,364,326.36 O - L 2,364,326.36
Presa Paccoccocha 9,406,177.00 18,226,894.48 - 18,226,894.48
Prensa Huachuaccocha 6,883,693.00 13,848,601.13 - 13,848,601.13
Obras de Gravedad 7,161,867.00 16,058,695.51 4,447,027.09 2,344,995.94 18,403,691.45
Obras de Aspersión 3,655,842.00 12,746,722.24 6,734,758.63 4,109,091.16 16,855,813.40
Sistema Talavera 1,139,990.00 2,304,039.34 - 2,304,039.34
Mitigación de Impactos Ambientales 415,818.00 412,323.62 - 412,323.62
Costo de Capacitación de Usuarios 1,567,700.00 1,567,700.00 - 1,567,700.00
Costos de Expediente Técnico 571,465.00 571,465.00 - 571,465.00
Gasto de Supervisiòn 1,465,130.00 3,454,803.30 328,728.08 139,620.14 3,594,423.44
Gastos Generales - 472,769.86 1,118,375.62 645,605.76 1,118,375.62
Liquidación - 190,000.00 194,022.10 4,022.10 194,022.10
Costo Total S/. 33,322,706.00 72,218,340.84 12,822,911.52 7,243.00 79,461,675.93
PROYECTO CHUMBAO NRO DE RESOLUCION FECHA SOLES/MESES/DIAS
EXPEDIENTE TEC. N° 036-2010-GRA-GSRCH-GSR 3/18/2010 33,322,706.00 Soles
EXP. TEC. REFORMULADO N° 251-2011-GRA-GSRCH-GSR 12/28/2011 37,865,877.20 Soles
DEJAR SINEFECTO 251-2011 Y PRESUPUESTO ACTUAL N° 212-2012-GRA-GSRCH-GSR 12/21/2012 58,417,700.45 Soles
AMPLAICION DE PLAZO DE EJECUCION N° 01 N° 233-2013-GRA-GSRCH-GSR 12/27/2013 6.00 meses
PRESUPUESTO ACTUALIZADO N° 086-2014-GRA-GSRCH-GSR 5/7/2014 60,245,440.04 Soles
DEJAR SINEFECTO 086-2014 Y PRESUPUESTO ACTUAL N° 129-2015-GRA-GSRCH-GSR 8/11/2015 62,229,154.00 Soles
ADICIONAL N° 01 , N° 02 N° 157A-2018-GRA-GSRCH-GSR 9/18/2018 5,048,048.40 Soles
EXPEDIENTE TECNI ADICONAL N° 04 N° 303-2019-GRA-GSRCH-GSR 11/13/2019 5,579,576.43 Soles
Por medio de la intervención del presente proyecto se pretende la implementación de la infraestructura de riego por
aspersión, el cual brindara un mejor servicio del abastecimiento de agua para riego en los sectores de Lliupapuquio,
Negropuquio, Paccpapata, Poltocsa y Puiso, infraestructura que estara conformada de la siguiente manera (A
continuación se describe las metas físicas del proyecto):
Metas Fisicas
Incremento de la producción agrícola y el rendimiento de los cultivos en los sectores de riego Lliupapuquio, Laguna-
Tahuantinsuyo, Paccpapata- Santa Rosa.
Construcción de infraestructura de Riego tecnificado por aspersión que permita el abastecimiento de agua para riego e incorporar
1038.0 Has bajo riego por aspersión.
Capacitación de 1200 beneficiarios en el uso y manejo eficiente de agua.
Incremento de la producción agrícola e instalación de cultivos rentables, dentro del ámbito de proyecto.
I.- GENERALIDADES
1.1.1.- Ubicación
FUNCION : 10 Agropecuaria
PROGRAMA : 0042 Riego
SUB PROGRAMA: 050 Infraestructura de Riego
COMPONENTE : Riego por Aspersion
COD. SNIP : 4978
META : 0001
UNIDAD EJECUT : Gerencia Sub Regional Chanka
MOD. EJECUCIO : Administracion Directa
(e) Actualización de costo del saldo que falta por ejecutar; el costo incremental S/. 7,243,335.09; la actualización del costo saldo POR ASPERSIÓN C.T. S/. 7,713,692.59
según RESOLUCIÓN SUB REGIONAL Nº 203-2022-GRA-GSRCH-GSR.
RESUMEN DE INFORMACION FISICA - FINANCIERA / PRIMERA ASIGNACION 2022 (S/.1,479,911.00) + SEGUNDA ASIGNACION 2022 (S/.999,986.00)
(*) Resumen De Información Física - Financiera / Primera Asignación 2022 (S/.1,479,911.00) + Segunda Asignación 2022 (S/.999,986.00) = S/. 2,479,897.00.
La primera y segunda asignación suman S/. 2,479,897.00, por esta razón el cronograma se amplió a 2 meses más, por lo tanto, los porcentajes anteriores, acumulados y
saldo sufrirán variaciones mas no el monto ejecutado.
SE CONTINUA CON LOS TRABAJOS DE INSTALACIÓN DE HIDRANTES, CÁMARA DE ROMPER PRESIONES, VÁLVULAS DE CONTROL Y VÁLVULAS DE
PURGAS EN EL SECTOR DE LLIUPAPUQUIO Y EN EL SECTOR PUISO SE CONCLUYÓ AL 100% EL SECTOR CC-2.
IV.- DOCUMENTACION
FOTO 01: Instalación de accesorios en sedimentador en la cámara de carga 6 en el sector de LLIUPAPUQUI margen Derecha.
FOTO 02: Instalación de compuerta en la cámara de carga 8 del sector de LLIUPAPUQUIO MARGEN Derecha.
FOTOS 3: Instalación de accesorios de los hidrantes de 2 salidas en el sector LLIUPAPUQUIO margen derecha.
FOTO 4: Prueba de funcionamiento en los hidrantes de 3 salidas en sector de LLIUPAPUQUIO margen Derecha.
FOTO 08: Verificación y funcionamiento final de las tomas laterales con aspersor en el sector de PUISO CC-2.
FOTO 09: El Gerente de la Sub Región Chanka Verifico el funcionamiento final de las tomas laterales con aspersor en el sector de PUISO CC-2.
FOTO 10: Verificación del funcionamiento caja de válvula de control de la cámara de carga en el sector de PUISO CC-2.
FORMATO FE-03
RESOLUCION SUB REGIONAL Nº 203-2022-GRA-GSRCH-GSR
VALORIZACIÓN No. 06 OCTUBRE DEL 2022
PROYECTO : "PROYECTO DE IRRIGACION CHUMBAO". FECHA : ANDAHUAYLAS ABRIL DEL 2022
COMPONENTE : OBRAS DE ASPERSION DISTRITO : ANDAHUAYLAS.
SUB META : OBRAS DE ASPERSION PROVINCIA : ANDAHUAYLAS.
FTE - FTO : RECURSOS ORDINARIOS - RECURSOS DETERMINADOS. DEPARTAMENTO : APURIMAC.
MODALIDAD : ADMINISTRACION DIRECTA.
PPTO. APROBAD: S/. 7,713,692.59
CUADRO DE AVANCES
PRESUPUESTO SALDO
PARTIDA DESCRIPCIÓN Und. ANTERIOR ACTUAL (OCTUBRE 2022) ACUMULADO
Metrado P.Unit. S/. Pres. Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
01 SECTOR TAHUANTINSUYO 738,487.08
01.01 OBRAS PRELIMINARES 1,730.51
01.01.01 CAMPAMENTO PROVICIONAL DE OBRA glb 1.00 1,307.91 1,307.91 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,307.91 100.00%
01.01.02 CARTEL DE OBRA (GIGANTOGRAFIA DE 3.60MX2.40M) glb 1.00 422.60 422.60 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 422.60 100.00%
01.02 TOMA DE CANAL 6,587.82
01.02.01.01 TRAZO Y REPLANTEO PRELIMINAR m 12.00 1.54 18.48 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 12.00 18.48 100.00%
01.02.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 0.12 56.99 6.84 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.12 6.84 100.00%
01.02.03.01 CONCRETO f'c=175 kg/cm2 m3 0.07 436.03 30.52 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.07 30.52 100.00%
01.02.04 SUMINISTRO E INSTALACION DE ACCESORIOS 6,490.70
01.02.04.01 COMPUERTA DE 1.00M X 1.50M CON VOLANTE und 5.00 1,298.14 6,490.70 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.00 6,490.70 100.00%
01.03 11,997.48
01.03.01 SUMINISTRO E INSTALCION DE ACCESORIOS 11,997.48
01.03.01.01 SUM. Y COLOCACION DE ACCESORIOS VALVULA EN DESARENADOR 6" und 4.00 2,999.37 11,997.48 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.00 11,997.48 100.00%
01.04.01.01 PINTURA DE EXTERIORES DE CAMARA DE CARGA m2 149.24 13.83 2,063.99 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 149.24 2,063.99 100.00%
01.06.01.01 TRAZO Y REPLANTEO PRELIMINAR m 1,036.20 1.54 1,595.75 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,036.20 1,595.75 100.00%
01.06.02 MOVIMIENTO DE TIERRAS 70,836.92
01.06.02.01 EXCAVACION DE ZANJA MANUAL EN TERRENO NORMAL m3 1,036.20 51.16 53,011.99 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,036.20 53,011.99 100.00%
01.06.02.02 RELLENO DE ZANJA CON MATERIAL SELECCIONADO m3 156.22 5.70 890.45 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 156.22 890.45 100.00%
01.06.02.03 RELLENO CON MATERIAL PROPIO m3 558.10 2.15 1,199.92 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 558.10 1,199.92 100.00%
01.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 1,538.08 10.23 15,734.56 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,538.08 15,734.56 100.00%
01.06.03.01 NSTALACION DE TUBERIA PVC SAP 63mm C-7.5 m 626.82 14.10 8,838.16 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 626.82 8,838.16 100.00%
01.06.03.02 INSTALACION DE TUBERIA PVC SAP 75mm C-7.5 m 973.03 18.53 18,030.25 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 973.03 18,030.25 100.00%
01.06.03.03 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 90mm C-7.5 m 2,174.76 24.50 53,281.62 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2,174.76 53,281.62 100.00%
01.06.03.04 INSTALACION DE TUBERIA PVC SAP 110mm C-7.5 m 1,276.46 35.82 45,722.80 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,276.46 45,722.80 100.00%
01.06.03.05 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 140mm C-5 m 300.46 54.08 16,248.88 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 300.46 16,248.88 100.00%
01.06.03.06 INSTALACION DE TUBERIA PVC SAP 140mm C-7.5 m 605.49 61.99 37,534.33 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 605.49 37,534.33 100.00%
01.06.03.07 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 90mm C-5 m 317.96 24.96 7,936.28 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 317.96 7,936.28 100.00%
01.06.03.08 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 50mm C-7.5 m 465.69 12.26 5,709.36 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 465.69 5,709.36 100.00%
01.06.03.09 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 160mm C-5 m 629.79 68.87 43,373.64 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 629.79 43,373.64 100.00%
01.06.03.10 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 160mm C-7.5 m 979.40 72.44 70,947.74 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 979.40 70,947.74 100.00%
01.06.05.01 SUM. Y COLOCACION DE ACCESORIOS (TAHUANTINSUYO) glb 1.00 35,675.40 35,675.40 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 35,675.40 100.00%
01.07.01.01 LIMPIEZA DE TERRENO Y DESBROCE m 29.16 0.30 8.75 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 29.16 8.75 100.00%
CUADRO DE AVANCES
PRESUPUESTO SALDO
PARTIDA DESCRIPCIÓN Und. ANTERIOR ACTUAL (OCTUBRE 2022) ACUMULADO
Metrado P.Unit. S/. Pres. Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
01.07.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 17.64 2.15 37.93 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 17.64 37.93 100.00%
01.07.02 MOVIMIENTO DE TIERRAS 662.69
01.07.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 14.11 37.64 531.10 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 14.11 531.10 100.00%
01.07.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 17.64 7.46 131.59 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 17.64 131.59 100.00%
01.07.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 131.04 38.50 5,045.04 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 131.04 5,045.04 100.00%
01.07.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 131.04 25.80 3,380.83 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 131.04 3,380.83 100.00%
01.07.05.01 TAPA METALICA 0.70x0.50 m und 17.00 150.00 2,550.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 17.00 2,550.00 100.00%
01.07.05.02 TAPA METALICA 0.60x0.50 m und 19.00 130.00 2,470.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 19.00 2,470.00 100.00%
01.07.05.03 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 90mm und 9.00 660.78 5,947.02 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 9.00 5,947.02 100.00%
01.07.05.04 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 110mm und 9.00 832.98 7,496.82 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 9.00 7,496.82 100.00%
01.07.05.05 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 140mm und 7.00 1,464.62 10,252.34 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.00 10,252.34 100.00%
01.07.05.06 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 160mm und 10.00 1,425.98 14,259.80 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 10.00 14,259.80 100.00%
01.07.05.07 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 75mm und 1.00 586.48 586.48 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 586.48 100.00%
01.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 18.90 1.53 28.92 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 18.90 28.92 100.00%
01.08.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 14.60 2.15 31.39 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 14.60 31.39 100.00%
01.08.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 15.20 7.46 113.39 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 15.20 113.39 100.00%
01.08.03 ENCOFRADO Y DESENCOFRADO 2,795.10
01.08.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 72.60 38.50 2,795.10 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 72.60 2,795.10 100.00%
01.08.04.01 CONCRETO f'c=175 kg/cm2 m3 13.32 436.03 5,807.92 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 13.32 5,807.92 100.00%
01.08.04.02 ACERO fy = 4200 Kg/cm2 GRADO 60 kg 257.67 7.35 1,893.87 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 257.67 1,893.87 100.00%
01.08.04.03 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 28.20 25.80 727.56 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 28.20 727.56 100.00%
01.08.04.04 TAPA METALICA DE 0.75x0.75m und 5.00 181.46 907.30 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.00 907.30 100.00%
01.09.01.01 LIMPIEZA DE TERRENO MANUAL m2 9.72 1.53 14.87 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 9.72 14.87 100.00%
01.09.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 5.88 2.15 12.64 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.88 12.64 100.00%
01.09.02 MOVIMIENTO DE TIERRAS 220.77
01.09.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 4.70 37.64 176.91 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.70 176.91 100.00%
01.09.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 5.88 7.46 43.86 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.88 43.86 100.00%
01.09.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 43.68 38.50 1,681.68 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 43.68 1,681.68 100.00%
01.09.04.01 CONCRETO FC=140 KG/CM2 m3 2.60 384.38 999.39 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.60 999.39 100.00%
01.09.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 43.68 25.80 1,126.94 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 43.68 1,126.94 100.00%
01.09.04.03 TAPA METALICA DE 0.50x0.50m und 12.00 207.03 2,484.36 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 12.00 2,484.36 100.00%
01.09.05.01 SUM. E INSTALACION DE ACCESORIOS EN CAMARA ROMPE PRESION 6" und 3.00 3,814.64 11,443.92 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 11,443.92 100.00%
01.09.05.02 SUM. E INSTALACION DE ACCESORIOS EN CAMARA ROMPE PRESION 4" und 6.00 1,940.64 11,643.84 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 6.00 11,643.84 100.00%
01.09.05.03 SUM. E INSTALACION DE ACCESORIOS EN CAMARA ROMPE PRESION 3" und 3.00 1,115.14 3,345.42 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 3,345.42 100.00%
01.10.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.76 1.53 17.99 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 11.76 17.99 100.00%
01.10.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 6.00 2.15 12.90 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 6.00 12.90 100.00%
01.10.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 6.00 7.46 44.76 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 6.00 44.76 100.00%
CUADRO DE AVANCES
PRESUPUESTO SALDO
PARTIDA DESCRIPCIÓN Und. ANTERIOR ACTUAL (OCTUBRE 2022) ACUMULADO
Metrado P.Unit. S/. Pres. Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
01.10.03 ENCOFRADO Y DESENCOFRADO 2,587.20
01.10.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 67.20 38.50 2,587.20 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 67.20 2,587.20 100.00%
01.10.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 67.20 25.80 1,733.76 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 67.20 1,733.76 100.00%
01.10.04.03 TAPA METALICA 0.70x0.50 m und 147.00 150.00 22,050.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 147.00 22,050.00 100.00%
01.10.05.02 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 2" und 49.00 1,080.60 52,949.40 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 49.00 52,949.40 100.00%
01.10.05.03 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 3" und 11.00 1,565.76 17,223.36 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 11.00 17,223.36 100.00%
01.10.05.04 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 1 1/2" und 14.00 277.10 3,879.40 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 14.00 3,879.40 100.00%
01.10.05.05 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 2" und 46.00 528.60 24,315.60 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 46.00 24,315.60 100.00%
01.10.05.06 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 3" und 11.00 1,235.76 13,593.36 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 11.00 13,593.36 100.00%
01.11.01.01 SUMINISTRO E INSTALACION DE LINEA PORTA ASPERSORES DE 01 LINEA und 1.00 1,157.73 1,157.73 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,157.73 100.00%
01.11.01.02 SUMINISTRO E INSTALACION DE LINEA PORTA ASPERSORES DE 02 LINEA und 1.00 2,762.23 2,762.23 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 2,762.23 100.00%
01.11.01.03 SUMINISTRO E INSTALACION DE LINEA PORTA ASPERSORES DE 03 LINEA und 3.00 4,812.23 14,436.69 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 14,436.69 100.00%
01.12 VALVULA DE PURGA 8,315.09
01.12.01.01 LIMPIEZA DE TERRENO MANUAL m2 9.80 1.53 14.99 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 9.80 14.99 100.00%
01.12.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 5.00 2.15 10.75 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.00 10.75 100.00%
01.12.02 MOVIMIENTO DE TIERRAS 150.22
01.12.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 3.00 37.64 112.92 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 112.92 100.00%
01.12.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 5.00 7.46 37.30 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.00 37.30 100.00%
01.12.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 38.40 38.50 1,478.40 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 38.40 1,478.40 100.00%
01.12.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 38.40 25.80 990.72 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 38.40 990.72 100.00%
01.12.04.03 TAPA METALICA 0.30x0.30 m und 20.00 126.05 2,521.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 20.00 2,521.00 100.00%
01.12.05.02 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE PURGA 1 1/2" und 3.00 132.45 397.35 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 397.35 100.00%
02.01.01.01 TRAZO Y REPLANTEO PRELIMINAR m 36.00 1.54 55.44 4.80 7.39 13.33% 7.20 11.09 20.00% 12.00 18.48 33.33% 24.00 36.96 66.67%
02.01.02.01 CORTE DE PAVIMENTO m 72.00 1.72 123.84 4.80 8.26 6.67% 7.20 12.38 10.00% 12.00 20.64 16.67% 60.00 103.20 83.33%
02.01.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 0.36 56.99 20.52 0.05 2.74 13.33% 0.07 3.99 19.44% 0.12 6.72 32.78% 0.24 13.79 67.22%
02.01.03 OBRAS DE CONCRETO SIMPLE 95.93
02.01.03.01 CONCRETO f'c=175 kg/cm2 m3 0.22 436.03 95.93 0.03 12.56 13.09% 0.04 17.44 18.18% 0.07 30.00 31.27% 0.15 65.93 68.73%
02.01.04.02 COMPUERTA DE 0.70M X 0.50M CON VOLANTE und 3.00 698.14 2,094.42 0.00 0.00 0.00% 3.00 2,094.42 100.00% 3.00 2,094.42 100.00% - - 0.00%
02.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 94.50 1.53 144.59 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 94.50 144.59 100.00%
02.02.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 60.00 2.15 129.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 60.00 129.00 100.00%
02.02.02.02 REFINE Y NIVELACION EN TERRENO ROCOSO m2 259.83 3.01 782.09 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 259.83 782.09 100.00%
CUADRO DE AVANCES
PRESUPUESTO SALDO
PARTIDA DESCRIPCIÓN Und. ANTERIOR ACTUAL (OCTUBRE 2022) ACUMULADO
Metrado P.Unit. S/. Pres. Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
02.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 673.98 10.23 6,894.82 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 673.98 6,894.82 100.00%
02.02.03 OBRAS DE CONCRETO SIMPLE 442.98
02.02.03.01 SOLADO PARA ZAPATAS DE 3" MEZCLA 1:12 CEMENTO-HORMIGON m2 0.80 97.77 78.22 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.80 78.22 100.00%
02.02.03.02 CONCRETO CICLOPEO FC=140KG/CM2 + 30 % PM. m3 1.19 306.52 364.76 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.19 364.76 100.00%
02.02.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 222.05 83.72 18,590.03 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 222.05 18,590.03 100.00%
02.02.04.02 CONCRETO FC=210 KG/CM2 m3 33.31 547.59 18,240.22 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 33.31 18,240.22 100.00%
02.02.04.03 ACERO ESTRUCTURAL Fy= 4200 KG/CM2 kg 956.20 7.57 7,238.43 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 956.20 7,238.43 100.00%
02.02.05.01 TARRAJEO CON IMPERMEABILIZANTE, MEZCLA 1:5, E=1.5cm m2 252.00 32.03 8,071.56 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 252.00 8,071.56 100.00%
02.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 32.40 1.53 49.57 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 32.40 49.57 100.00%
02.03.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 21.87 2.15 47.02 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 21.87 47.02 100.00%
02.03.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 38.88 7.46 290.04 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 38.88 290.04 100.00%
02.03.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 90.79 38.50 3,495.42 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 90.79 3,495.42 100.00%
02.03.04 OBRAS DE CONCRETO ARMADO 11,973.00
02.03.04.01 CONCRETO f'c=175 kg/cm2 m3 8.92 436.03 3,889.39 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.92 3,889.39 100.00%
02.03.04.02 CONCRETO f'c=175 kg/cm2 + 30% PM m3 3.28 421.66 1,383.04 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.28 1,383.04 100.00%
02.03.04.03 ACERO fy = 4200 Kg/cm2 GRADO 60 kg 400.17 7.35 2,941.25 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 400.17 2,941.25 100.00%
02.03.04.04 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 145.71 25.80 3,759.32 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 145.71 3,759.32 100.00%
02.03.05.01 SUM. E INSTALACION DE ACCESORIOS EN CAMARA DE CARGA und 3.00 1,584.45 4,753.35 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 4,753.35 100.00%
02.03.05.02 TAPA METALICA 0.50x0.50 m und 3.00 175.00 525.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 525.00 100.00%
02.03.06 PINTADO DE CAMARA DE CARGA 1,238.48
02.03.06.01 PINTURA DE EXTERIORES DE CAMARA DE CARGA m2 89.55 13.83 1,238.48 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 89.55 1,238.48 100.00%
02.04.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 5.63 0.92 5.18 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.63 5.18 100.00%
02.04.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 23.46 38.50 903.21 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 23.46 903.21 100.00%
02.04.04.02 ACERO fy = 4200 Kg/cm2 GRADO 60 kg 155.73 7.35 1,144.62 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 155.73 1,144.62 100.00%
02.04.04.03 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 14.04 25.80 362.23 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 14.04 362.23 100.00%
02.04.05.02 TAPA METALICA 0.80x0.70 m und 6.00 226.46 1,358.76 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 6.00 1,358.76 100.00%
02.05.01.01 TRAZO Y REPLANTEO PRELIMINAR m 17,922.91 1.54 27,601.28 5,313.50 8,182.79 29.65% 5,751.00 8,856.54 32.09% 11,064.50 17,039.33 61.73% 6,858.41 10,561.95 38.27%
02.05.02.01 CAMA DE APOYO PARA TIBERIA CON MATERIAL PROPIO ZARANDEADO m 23,941.84 1.87 44,771.24 5,913.53 11,058.30 24.70% 5,664.91 10,593.38 23.66% 11,578.44 21,651.68 48.36% 12,363.40 23,119.56 51.64%
02.05.02.02 RELLENO DE ZANJA CON MATERIAL SELECCIONADO m3 2,939.29 5.70 16,753.95 1,145.20 6,527.64 38.96% 1,132.98 6,458.00 38.55% 2,278.18 12,985.64 77.51% 661.11 3,768.32 22.49%
02.05.02.03 RELLENO CON MATERIAL PROPIO m3 3,874.55 2.15 8,330.28 978.08 2,102.87 25.24% 849.74 1,826.93 21.93% 1,827.82 3,929.81 47.17% 2,046.73 4,400.48 52.83%
CUADRO DE AVANCES
PRESUPUESTO SALDO
PARTIDA DESCRIPCIÓN Und. ANTERIOR ACTUAL (OCTUBRE 2022) ACUMULADO
Metrado P.Unit. S/. Pres. Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
02.05.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 276.65 10.23 2,830.13 17.30 176.98 6.25% 90.00 920.70 32.53% 107.30 1,097.68 38.79% 169.35 1,732.45 61.21%
02.05.03 SUMINISTRO E INSTALACION DE TUBERIAS 752,492.27
02.05.03.01 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 48 mm C-7.5 m 11,594.72 11.04 128,005.71 2,663.55 29,405.59 22.97% 2,505.00 27,655.20 21.60% 5,168.55 57,060.79 44.58% 6,426.17 70,944.92 55.42%
02.05.03.02 INSTALACION DE TUBERIA PVC SAP 160mm C-5 m 1,374.61 68.87 94,669.39 0.00 0.00 0.00% 600.00 41,322.00 43.65% 600.00 41,322.00 43.65% 774.61 53,347.39 56.35%
02.05.03.03 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 63 mm C-5 m 5,216.78 12.57 65,574.92 544.05 6,838.71 10.43% 0.00 0.00% 544.05 6,838.71 10.43% 4,672.73 58,736.22 89.57%
02.05.03.04 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 90mm C-5 m 1,329.37 24.96 33,181.08 181.47 4,529.49 13.65% 0.00 0.00% 181.47 4,529.49 13.65% 1,147.90 28,651.58 86.35%
02.05.03.05 INSTALACION DE TUBERIA PVC SAP 140mm C-7.5 m 234.30 61.99 14,524.26 234.30 14,524.26 100.00% 0.00 0.00% 234.30 14,524.26 100.00% - - 0.00%
02.05.03.06 INSTALACION DE TUBERIA PVC SAP 140mm C-10 m 2,467.58 64.28 158,616.04 0.00 0.00 0.00% 680.00 43,710.40 27.56% 680.00 43,710.40 27.56% 1,787.58 114,905.64 72.44%
02.05.03.07 INSTALACION DE TUBERIA PVC SAP 110mm C-5 m 649.26 33.68 21,867.08 264.14 8,896.24 40.68% 68.00 2,290.24 10.47% 332.14 11,186.48 51.16% 317.12 10,680.60 48.84%
02.05.03.08 INSTALACION DE TUBERIA PVC SAP 110mm C-7.5 m 53.37 35.82 1,911.71 116.00 4,155.12 217.35% 0.00 0.00% 53.37 1,911.71 100.00% - - 0.00%
02.05.03.09 INSTALACION DE TUBERIA PVC SAP 110mm C-10 m 1,635.28 41.33 67,586.12 0.00 0.00 0.00% 213.00 8,803.29 13.03% 213.00 8,803.29 13.03% 1,422.28 58,782.83 86.97%
02.05.03.10 INSTALACION DE TUBERIA PVC SAP 90mm C-10 m 2,296.28 24.96 57,315.15 234.00 5,840.64 10.19% 290.00 7,238.40 12.63% 524.00 13,079.04 22.82% 1,772.28 44,236.11 77.18%
02.05.03.11 INSTALACION DE TUBERIA PVC SAP 75mm C-5 m 1,130.87 16.70 18,885.53 50.12 837.00 4.43% 406.00 6,780.20 35.90% 456.12 7,617.20 40.33% 674.75 11,268.33 59.67%
02.05.03.12 INSTALACION DE TUBERIA PVC SAP 75mm C-7.5 m 468.91 18.53 8,688.90 162.40 3,009.27 34.63% 0.00 0.00% 162.40 3,009.27 34.63% 306.51 5,679.63 65.37%
02.05.03.13 INSTALACION DE TUBERIA PVC SAP 75mm C-10 m 1,227.15 22.51 27,623.15 0.00 0.00 0.00% 520.00 11,705.20 42.37% 520.00 11,705.20 42.37% 707.15 15,917.95 57.63%
02.05.03.14 INSTALACION DE TUBERIA PVC SAP 1 1/2" C-10 m 451.95 11.34 5,125.11 399.10 4,525.79 88.31% 34.80 394.63 7.70% 433.90 4,920.43 96.01% 18.05 204.69 3.99%
02.05.03.15 NSTALACION DE TUBERIA PVC SAP 63mm C-7.5 m 1,103.56 14.10 15,560.20 344.66 4,859.71 31.23% 300.00 4,230.00 27.18% 644.66 9,089.71 58.42% 458.90 6,470.49 41.58%
02.05.03.16 NSTALACION DE TUBERIA PVC SAP 63mm C-10 m 1,997.48 16.70 33,357.92 0.00 0.00 0.00% 1,060.00 17,702.00 53.07% 1,060.00 17,702.00 53.07% 937.48 15,655.92 46.93%
02.05.04.01 PRUEBA HIDRAULICA EN TUBERIA PVC m 56,919.68 1.12 63,750.04 16,117.08 18,051.13 28.32% 1,000.00 1,120.00 1.76% 17,117.08 19,171.13 30.07% 39,802.60 44,578.91 69.93%
02.05.05 SUMINISTRO E INSTALACION DE ACCESORIOS 63,045.60
02.05.05.01 SUM. Y COLOCACION DE ACCESORIOS glb 1.00 63,045.60 63,045.60 0.56 35,305.54 56.00% 0.10 6,304.56 10.00% 0.66 41,610.10 66.00% 0.34 21,435.50 34.00%
02.06.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 42.14 2.15 90.60 17.26 37.11 40.96% 6.48 13.93 15.38% 23.74 51.04 56.34% 18.40 39.56 43.66%
02.06.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 33.71 37.64 1,268.84 26.30 990.08 78.03% 5.83 219.52 17.30% 32.14 1,209.60 95.33% 1.57 59.25 4.67%
02.06.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 42.14 7.46 314.36 42.14 314.36 100.00% 0.00 0.00% 42.14 314.36 100.00% - - 0.00%
02.06.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 313.04 38.50 12,052.04 96.32 3,708.32 30.77% 40.86 1,573.11 13.05% 137.18 5,281.43 43.82% 175.86 6,770.61 56.18%
02.06.04 OBRAS DE CONCRETO SIMPLE 15,248.96
02.06.04.01 CONCRETO FC=140 KG/CM2 m3 18.66 384.38 7,172.53 11.92 4,582.19 63.89% 6.41 2,463.11 34.34% 18.33 7,045.30 98.23% 0.33 127.23 1.77%
02.06.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 313.04 25.80 8,076.43 108.92 2,810.14 34.79% 48.96 1,263.17 15.64% 157.88 4,073.30 50.43% 155.16 4,003.13 49.57%
02.06.05.02 TAPA METALICA 0.60x0.50 m und 18.00 130.00 2,340.00 15.00 1,950.00 83.33% 3.00 390.00 16.67% 18.00 2,340.00 100.00% - - 0.00%
02.06.05.03 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 90mm und 7.00 660.78 4,625.46 3.00 1,982.34 42.86% 4.00 2,643.12 57.14% 7.00 4,625.46 100.00% - - 0.00%
02.06.05.04 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 110mm und 11.00 832.98 9,162.78 7.00 5,830.86 63.64% 4.00 3,331.92 36.36% 11.00 9,162.78 100.00% - - 0.00%
02.06.05.05 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 140mm und 22.00 1,464.62 32,221.64 5.00 7,323.10 22.73% 3.00 4,393.86 13.64% 8.00 11,716.96 36.36% 14.00 20,504.68 63.64%
02.06.05.06 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 160mm und 39.00 1,425.98 55,613.22 3.00 4,277.94 7.69% 4.00 5,703.92 10.26% 7.00 9,981.86 17.95% 32.00 45,631.36 82.05%
02.06.05.07 SUM. Y COLOCACION DE ACCESORIOS DE VALVULA CONTROL 200mm und 7.00 1,897.98 13,285.86 1.00 1,897.98 14.29% 0.00 0.00% 1.00 1,897.98 14.29% 6.00 11,387.88 85.71%
02.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 86.94 1.53 133.02 7.56 11.57 8.70% 7.56 11.57 8.70% 15.12 23.13 17.39% 71.82 109.88 82.61%
02.07.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 67.16 2.15 144.39 5.84 12.56 8.70% 5.84 12.56 8.70% 11.68 25.11 17.39% 55.48 119.28 82.61%
02.07.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 49.31 37.64 1,856.03 4.29 161.40 8.70% 4.29 161.40 8.70% 8.58 322.80 17.39% 40.73 1,533.23 82.61%
02.07.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 69.92 7.46 521.60 6.08 45.36 8.70% 0.96 7.16 1.37% 7.04 52.52 10.07% 62.88 469.08 89.93%
02.07.03 ENCOFRADO Y DESENCOFRADO 12,857.46
02.07.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 333.96 38.50 12,857.46 29.04 1,118.04 8.70% 30.48 1,173.48 9.13% 59.52 2,291.52 17.82% 274.44 10,565.94 82.18%
02.07.04 OBRAS DE CONCRETO ARMADO 43,374.82
02.07.04.01 CONCRETO f'c=175 kg/cm2 m3 61.27 436.03 26,715.56 5.58 2,434.79 9.11% 6.22 2,713.85 10.16% 11.81 5,148.64 19.27% 49.46 21,566.92 80.73%
02.07.04.02 ACERO fy = 4200 Kg/cm2 GRADO 60 kg 1,185.26 7.35 8,711.66 103.07 757.54 8.70% 86.58 636.33 7.30% 189.64 1,393.87 16.00% 995.62 7,317.79 84.00%
02.07.04.03 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 146.28 25.80 3,774.02 12.72 328.18 8.70% 10.72 276.58 7.33% 23.44 604.75 16.02% 122.84 3,169.27 83.98%
CUADRO DE AVANCES
PRESUPUESTO SALDO
PARTIDA DESCRIPCIÓN Und. ANTERIOR ACTUAL (OCTUBRE 2022) ACUMULADO
Metrado P.Unit. S/. Pres. Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
02.07.04.04 TAPA METALICA DE 0.75x0.75m und 23.00 181.46 4,173.58 4.00 725.84 17.39% 18.00 3,266.28 78.26% 22.00 3,992.12 95.65% 1.00 181.46 4.35%
02.08 VALVULA DE CONTROL DE C.R.P. 169,546.27
02.08.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 34.79 2.15 74.80 8.82 18.96 25.35% 4.41 9.48 12.68% 13.23 28.44 38.03% 21.56 46.35 61.97%
02.08.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 27.83 37.64 1,047.52 7.06 265.59 25.35% 3.53 132.79 12.68% 10.58 398.38 38.03% 17.25 649.14 61.97%
02.08.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 34.79 7.46 259.53 8.82 65.80 25.35% 4.41 32.90 12.68% 13.23 98.70 38.03% 21.56 160.84 61.97%
02.08.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 258.44 38.50 9,949.94 81.72 3,146.22 31.62% 40.86 1,573.11 15.81% 122.58 4,719.33 47.43% 135.86 5,230.61 52.57%
02.08.05.02 SUM. E INSTALACION DE ACCESORIOS EN CAMARA ROMPE PRESION 4" und 29.00 1,940.64 56,278.56 3.00 5,821.92 10.34% 0.00 0.00 0.00% 3.00 5,821.92 10.34% 26.00 50,456.64 89.66%
02.08.05.03 SUM. E INSTALACION DE ACCESORIOS EN CAMARA ROMPE PRESION 3" und 16.00 1,115.14 17,842.24 4.00 4,460.56 25.00% 12.00 13,381.68 75.00% 16.00 17,842.24 100.00% - - 0.00%
02.08.05.04 SUM. E INSTALACION DE ACCESORIOS EN CAMARA ROMPE PRESION 2 1/2" und 3.00 1,049.14 3,147.42 2.00 2,098.28 66.67% 0.00 0.00 0.00% 2.00 2,098.28 66.67% 1.00 1,049.14 33.33%
02.08.05.05 SUM. E INSTALACION DE ACCESORIOS EN CAMARA ROMPE PRESION 2" und 11.00 915.14 10,066.54 6.00 5,490.84 54.55% 0.00 0.00 0.00% 6.00 5,490.84 54.55% 5.00 4,575.70 45.45%
02.08.05.06 TAPA METALICA 0.60x0.60 m und 71.00 175.00 12,425.00 18.00 3,150.00 25.35% 51.00 8,925.00 71.83% 69.00 12,075.00 97.18% 2.00 350.00 2.82%
02.09.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 125.25 2.15 269.29 32.80 70.52 26.19% 4.25 9.14 3.39% 37.05 79.66 29.58% 88.20 189.63 70.42%
02.09.02 MOVIMIENTO DE TIERRAS 4,705.90
02.09.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 100.20 37.64 3,771.53 21.40 805.50 21.36% 3.40 127.98 3.39% 24.80 933.47 24.75% 75.40 2,838.06 75.25%
02.09.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 125.25 7.46 934.37 26.75 199.56 21.36% 4.25 31.71 3.39% 31.00 231.26 24.75% 94.25 703.11 75.25%
02.09.04.01 CONCRETO FC=140 KG/CM2 m3 56.11 384.38 21,567.56 11.98 4,606.41 21.36% 1.90 731.86 3.39% 13.89 5,338.27 24.75% 42.22 16,229.29 75.25%
02.09.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 1,402.80 25.80 36,192.24 299.60 7,729.68 21.36% 47.60 1,228.08 3.39% 347.20 8,957.76 24.75% 1,055.60 27,234.48 75.25%
02.09.04.03 TAPA METALICA 0.70x0.50 m und 780.00 150.00 117,000.00 45.00 6,750.00 5.77% 190.00 28,500.00 24.36% 235.00 35,250.00 30.13% 545.00 81,750.00 69.87%
02.09.05.01 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 1 1/2" und 237.00 787.10 186,542.70 0.00 0.00 0.00% 77.00 60,606.70 32.49% 77.00 60,606.70 32.49% 160.00 125,936.00 67.51%
02.09.05.02 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 2" und 154.00 1,080.60 166,412.40 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 154.00 166,412.40 100.00%
02.09.05.03 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 3" und 2.00 1,565.76 3,131.52 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 3,131.52 100.00%
02.09.05.04 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 1 1/2" und 253.00 277.10 70,106.30 222.00 61,516.20 87.75% 0.00 0.00% 222.00 61,516.20 87.75% 31.00 8,590.10 12.25%
02.09.05.05 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 2" und 193.00 528.60 102,019.80 0.00 0.00 0.00% 22.00 11,629.20 11.40% 22.00 11,629.20 11.40% 171.00 90,390.60 88.60%
02.09.05.06 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 3" und 2.00 1,235.76 2,471.52 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 2,471.52 100.00%
02.10.01.01 SUMINISTRO E INSTALACION DE LINEA PORTA ASPERSORES DE 01 LINEA und 5.00 1,157.73 5,788.65 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.00 5,788.65 100.00%
02.10.01.02 SUMINISTRO E INSTALACION DE LINEA PORTA ASPERSORES DE 02 LINEA und 5.00 2,762.23 13,811.15 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.00 13,811.15 100.00%
02.10.01.03 SUMINISTRO E INSTALACION DE LINEA PORTA ASPERSORES DE 03 LINEA und 5.00 4,812.23 24,061.15 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.00 24,061.15 100.00%
02.11.01.01 LIMPIEZA DE TERRENO MANUAL m2 33.81 1.53 51.73 15.19 23.24 44.93% 1.96 3.00 5.80% 17.15 26.24 50.72% 16.66 25.49 49.28%
02.11.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 17.25 2.15 37.09 7.75 16.66 44.93% 1.00 2.15 5.80% 8.75 18.81 50.72% 8.50 18.28 49.28%
02.11.02 MOVIMIENTO DE TIERRAS 518.26
02.11.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 10.35 37.64 389.57 4.65 175.03 44.93% 0.60 22.58 5.80% 5.25 197.61 50.72% 5.10 191.96 49.28%
02.11.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 17.25 7.46 128.69 7.75 57.82 44.93% 1.00 7.46 5.80% 8.75 65.28 50.72% 8.50 63.41 49.28%
02.11.04.03 TAPA METALICA 0.30x0.30 m und 69.00 126.05 8,697.45 9.00 1,134.45 13.04% 13.00 1,638.65 18.84% 22.00 2,773.10 31.88% 47.00 5,924.35 68.12%
02.11.05 SUMINISTRO E INSTALACION DE ACCESORIOS 8,173.05
02.11.05.01 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE PURGA 63mm und 69.00 118.45 8,173.05 48.00 5,685.60 69.57% 5.00 592.25 7.25% 53.00 6,277.85 76.81% 16.00 1,895.20 23.19%
02.12.01 FLETE TERRESTRE (LLIUPAPUQUIO) glb 1.00 12,241.51 12,241.51 0.60 7,344.91 60.00% 0.10 1,224.15 10.00% 0.70 8,569.06 70.00% 0.30 3,672.45 30.00%
03 SECTOR LASIMARCA 400,912.85
03.01.01 CAMPAMENTO PROVICIONAL DE OBRA glb 1.00 1,307.91 1,307.91 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,307.91 100.00%
03.01.02 CARTEL DE OBRA (GIGANTOGRAFIA DE 3.60MX2.40M) glb 1.00 422.60 422.60 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 422.60 100.00%
03.02 TOMA DE CANAL 2,636.11
03.02.01 OBRAS PRELIMINARES 7.39
03.02.01.01 TRAZO Y REPLANTEO PRELIMINAR m 4.80 1.54 7.39 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.80 7.39 100.00%
03.02.02 CORTE DE PAVIMENTO 19.36
03.02.02.01 CORTE DE PAVIMENTO m 9.60 1.72 16.51 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 9.60 16.51 100.00%
03.02.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 0.05 56.99 2.85 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.05 2.85 100.00%
03.02.04.01 COMPUERTA DE 1.00M X 1.50M CON VOLANTE und 2.00 1,298.14 2,596.28 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 2,596.28 100.00%
03.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 31.50 1.53 48.20 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 31.50 48.20 100.00%
03.03.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 20.00 2.15 43.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 20.00 43.00 100.00%
03.03.02.01 EXCAVACION MASIVA A MAQUINA EN TERRENO SEMIROCOSO/RETRO .5Y3 m3 54.15 20.97 1,135.53 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 54.15 1,135.53 100.00%
03.03.02.02 REFINE Y NIVELACION EN TERRENO ROCOSO m2 86.61 3.01 260.70 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 86.61 260.70 100.00%
03.03.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 74.89 10.23 766.12 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 74.89 766.12 100.00%
03.03.03.01 SOLADO PARA ZAPATAS DE 3" MEZCLA 1:12 CEMENTO-HORMIGON m2 0.27 97.77 26.40 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.27 26.40 100.00%
03.03.03.02 CONCRETO CICLOPEO FC=140KG/CM2 + 30 % PM. m3 0.40 306.52 122.61 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.40 122.61 100.00%
03.03.04 OBRAS DE CONCRETO ARMADO 14,687.99
03.03.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 74.02 83.72 6,196.95 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 74.02 6,196.95 100.00%
03.03.04.02 CONCRETO FC=210 KG/CM2 m3 11.10 547.59 6,078.25 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 11.10 6,078.25 100.00%
03.03.04.03 ACERO ESTRUCTURAL Fy= 4200 KG/CM2 kg 318.73 7.57 2,412.79 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 318.73 2,412.79 100.00%
03.03.05.01 TARRAJEO CON IMPERMEABILIZANTE, MEZCLA 1:5, E=1.5cm m2 84.00 32.03 2,690.52 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 84.00 2,690.52 100.00%
03.03.06.01 SUM. Y COLOCACION DE ACCESORIOS VALVULA EN DESARENADOR 6" und 1.00 2,999.37 2,999.37 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 2,999.37 100.00%
03.03.06.02 SUM. Y COLOCACION DE ACCESORIOS VALVULA EN DESARENADOR 8" und 2.00 3,272.21 6,544.42 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 6,544.42 100.00%
03.06.02.01 EXCAVACION DE ZANJA MANUAL EN TERRENO NORMAL m3 507.76 51.16 25,977.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 507.76 25,977.00 100.00%
03.06.02.02 REFINE Y NIVELACION DE FONDO DE ZANJA m 1,269.40 1.53 1,942.18 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,269.40 1,942.18 100.00%
03.06.02.03 CAMA DE APOYO PARA TIBERIA CON MATERIAL PROPIO ZARANDEADO m 1,321.48 1.87 2,471.17 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,321.48 2,471.17 100.00%
03.06.02.04 RELLENO DE ZANJA CON MATERIAL SELECCIONADO m3 397.99 5.70 2,268.54 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 397.99 2,268.54 100.00%
CUADRO DE AVANCES
PRESUPUESTO SALDO
PARTIDA DESCRIPCIÓN Und. ANTERIOR ACTUAL (OCTUBRE 2022) ACUMULADO
Metrado P.Unit. S/. Pres. Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
03.06.02.05 RELLENO CON MATERIAL PROPIO m3 557.68 2.15 1,199.01 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 557.68 1,199.01 100.00%
03.06.03 SUMINISTRO E INSTALACION DE TUBERIAS 165,985.98
03.06.03.01 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 63 mm C-5 m 209.27 12.57 2,630.52 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 209.27 2,630.52 100.00%
03.06.03.02 NSTALACION DE TUBERIA PVC SAP 63mm C-7.5 m 205.60 14.10 2,898.96 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 205.60 2,898.96 100.00%
03.06.03.03 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 90mm C-5 m 176.91 24.96 4,415.67 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 176.91 4,415.67 100.00%
03.06.03.04 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 90mm C-7.5 m 41.40 24.50 1,014.30 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 41.40 1,014.30 100.00%
03.06.03.05 INSTALACION DE TUBERIA PVC SAP 110mm C-7.5 m 36.34 35.82 1,301.70 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 36.34 1,301.70 100.00%
03.06.03.06 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 140mm C-5 m 288.84 54.08 15,620.47 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 288.84 15,620.47 100.00%
03.06.03.07 INSTALACION DE TUBERIA PVC SAP 200MM C-5 m 67.03 64.28 4,308.69 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 67.03 4,308.69 100.00%
03.06.03.08 INSTALACION DE TUBERIA PVC SAP 200MM C-7.5 m 23.14 79.58 1,841.48 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 23.14 1,841.48 100.00%
03.06.03.09 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 50mm C-7.5 m 205.60 12.26 2,520.66 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 205.60 2,520.66 100.00%
03.06.03.10 INSTALACION DE TUBERIA PVC SAP 110mm C-5 m 216.60 33.68 7,295.09 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 216.60 7,295.09 100.00%
03.06.03.11 INSTALACION DE TUBERIA PVC SAP 160mm C-5 m 132.00 68.87 9,090.84 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 132.00 9,090.84 100.00%
03.06.03.12 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 160mm C-7.5 m 408.00 72.44 29,555.52 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 408.00 29,555.52 100.00%
03.06.03.13 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 160 mm C-10 m 97.80 73.46 7,184.39 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 97.80 7,184.39 100.00%
03.06.03.14 INSTALACION DE TUBERIA PVC SAP 140mm C-10 m 147.00 64.28 9,449.16 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 147.00 9,449.16 100.00%
03.06.03.15 INSTALACION DE TUBERIA PVC SAP 110mm C-10 m 758.00 41.33 31,328.14 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 758.00 31,328.14 100.00%
03.06.03.16 INSTALACION DE TUBERIA PVC SAP 90mm C-10 m 506.70 24.96 12,647.23 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 506.70 12,647.23 100.00%
03.06.03.17 INSTALACION DE TUBERIA PVC SAP 75mm C-7.5 m 143.00 18.53 2,649.79 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 143.00 2,649.79 100.00%
03.06.03.18 INSTALACION DE TUBERIA PVC SAP 75mm C-10 m 396.60 22.51 8,927.47 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 396.60 8,927.47 100.00%
03.06.03.19 NSTALACION DE TUBERIA PVC SAP 63mm C-10 m 677.00 16.70 11,305.90 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 677.00 11,305.90 100.00%
03.07.01.01 LIMPIEZA DE TERRENO Y DESBROCE m 14.58 0.30 4.37 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 14.58 4.37 100.00%
03.07.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 8.82 2.15 18.96 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.82 18.96 100.00%
03.07.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 7.06 37.64 265.74 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.06 265.74 100.00%
03.07.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 8.82 7.46 65.80 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.82 65.80 100.00%
03.07.03 ENCOFRADO Y DESENCOFRADO 2,522.52
03.07.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 65.52 38.50 2,522.52 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 65.52 2,522.52 100.00%
03.07.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 65.52 25.80 1,690.42 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 65.52 1,690.42 100.00%
03.07.05.01 TAPA METALICA 0.70x0.50 m und 6.00 150.00 900.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 6.00 900.00 100.00%
03.07.05.02 TAPA METALICA 0.60x0.50 m und 1.00 130.00 130.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 130.00 100.00%
03.07.05.03 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 90mm und 4.00 660.78 2,643.12 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.00 2,643.12 100.00%
03.07.05.04 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 110mm und 9.00 832.98 7,496.82 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 9.00 7,496.82 100.00%
03.07.05.05 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 160mm und 4.00 1,425.98 5,703.92 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.00 5,703.92 100.00%
03.07.05.06 SUM. Y COLOCACION DE ACCESORIOS DE VALVULA CONTROL 200mm und 2.00 1,897.98 3,795.96 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 3,795.96 100.00%
03.08.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 32.12 2.15 69.06 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 32.12 69.06 100.00%
03.08.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 33.44 7.46 249.46 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 33.44 249.46 100.00%
03.08.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 159.72 38.50 6,149.22 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 159.72 6,149.22 100.00%
03.08.04 OBRAS DE CONCRETO ARMADO 18,542.73
03.08.04.01 CONCRETO f'c=175 kg/cm2 m3 29.30 436.03 12,775.68 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 29.30 12,775.68 100.00%
CUADRO DE AVANCES
PRESUPUESTO SALDO
PARTIDA DESCRIPCIÓN Und. ANTERIOR ACTUAL (OCTUBRE 2022) ACUMULADO
Metrado P.Unit. S/. Pres. Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
03.08.04.02 ACERO fy = 4200 Kg/cm2 GRADO 60 kg 566.86 7.35 4,166.42 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 566.86 4,166.42 100.00%
03.08.04.03 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 62.04 25.80 1,600.63 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 62.04 1,600.63 100.00%
03.08.05.02 SUM. E INSTALACION DE ACCESORIOS EN CAMARA ROMPE PRESION 4" und 2.00 1,940.64 3,881.28 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 3,881.28 100.00%
03.08.05.03 TAPA METALICA 0.60x0.60 m und 11.00 175.00 1,925.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 11.00 1,925.00 100.00%
03.09.01.01 LIMPIEZA DE TERRENO MANUAL m2 19.60 1.53 29.99 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 19.60 29.99 100.00%
03.09.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 10.00 2.15 21.50 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 10.00 21.50 100.00%
03.09.04.01 CONCRETO FC=140 KG/CM2 m3 4.48 384.38 1,722.02 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.48 1,722.02 100.00%
03.09.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 112.00 25.80 2,889.60 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 112.00 2,889.60 100.00%
03.09.04.03 TAPA METALICA 0.70x0.50 m und 40.00 150.00 6,000.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 40.00 6,000.00 100.00%
03.09.05.01 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 1 1/2" und 1.00 787.10 787.10 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 787.10 100.00%
03.09.05.02 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 2" und 12.00 1,080.60 12,967.20 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 12.00 12,967.20 100.00%
03.09.05.03 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 3" und 2.00 1,565.76 3,131.52 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 3,131.52 100.00%
03.09.05.04 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 1 1/2" und 1.00 277.10 277.10 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 277.10 100.00%
03.09.05.05 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 2" und 16.00 528.60 8,457.60 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 16.00 8,457.60 100.00%
03.09.05.06 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 3" und 8.00 1,235.76 9,886.08 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.00 9,886.08 100.00%
03.10.01.02 SUMINISTRO E INSTALACION DE LINEA PORTA ASPERSORES DE 02 LINEA und 1.00 2,762.23 2,762.23 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 2,762.23 100.00%
03.11.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 2.50 2.15 5.38 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.50 5.38 100.00%
03.11.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 2.50 7.46 18.65 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.50 18.65 100.00%
03.11.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 10.00 38.50 385.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 10.00 385.00 100.00%
03.11.04.01 CONCRETO FC=140 KG/CM2 m3 0.42 384.38 161.44 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.42 161.44 100.00%
03.11.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 10.00 25.80 258.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 10.00 258.00 100.00%
03.11.04.03 TAPA METALICA 0.30x0.30 m und 10.00 126.05 1,260.50 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 10.00 1,260.50 100.00%
03.11.05 SUMINISTRO E INSTALACION DE ACCESORIOS 1,184.50
03.11.05.01 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE PURGA 63mm und 10.00 118.45 1,184.50 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 10.00 1,184.50 100.00%
04.01.02 CARTEL DE OBRA (GIGANTOGRAFIA DE 3.60MX2.40M) glb 1.00 422.60 422.60 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 422.60 100.00%
04.02.04.01 COMPUERTA DE 1.00M X 1.50M CON VOLANTE und 4.00 1,298.14 5,192.56 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.00 5,192.56 100.00%
04.03.01.01 SUM. Y COLOCACION DE ACCESORIOS VALVULA EN DESARENADOR 6" und 3.00 2,999.37 8,998.11 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 8,998.11 100.00%
04.03.01.02 SUM. Y COLOCACION DE ACCESORIOS VALVULA EN DESARENADOR 8" und 1.00 3,272.21 3,272.21 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 3,272.21 100.00%
04.05.01.01 PINTURA DE EXTERIORES m2 14.40 13.83 199.15 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 14.40 199.15 100.00%
04.06.02.01 CAMA DE APOYO PARA TIBERIA CON MATERIAL PROPIO ZARANDEADO m 2,538.08 1.87 4,746.21 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2,538.08 4,746.21 100.00%
04.06.02.02 RELLENO DE ZANJA CON MATERIAL SELECCIONADO m3 488.74 5.70 2,785.82 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 488.74 2,785.82 100.00%
04.06.02.03 RELLENO CON MATERIAL PROPIO m3 410.09 2.15 881.69 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 410.09 881.69 100.00%
04.06.03.02 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 50mm C-7.5 m 363.02 12.26 4,450.63 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 363.02 4,450.63 100.00%
04.06.03.03 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 90mm C-7.5 m 515.89 24.50 12,639.31 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 515.89 12,639.31 100.00%
04.06.03.04 INSTALACION DE TUBERIA PVC SAP 75mm C-5 m 156.71 16.70 2,617.06 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 156.71 2,617.06 100.00%
04.06.03.05 NSTALACION DE TUBERIA PVC SAP 63mm C-7.5 m 540.83 14.10 7,625.70 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 540.83 7,625.70 100.00%
04.06.03.06 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 90mm C-5 m 13.53 24.96 337.71 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 13.53 337.71 100.00%
04.06.03.07 INSTALACION DE TUBERIA PVC SAP 110mm C-5 m 41.92 33.68 1,411.87 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 41.92 1,411.87 100.00%
04.06.03.08 INSTALACION DE TUBERIA PVC SAP 75mm C-10 m 28.40 22.51 639.28 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 28.40 639.28 100.00%
04.06.03.09 INSTALACION DE TUBERIA PVC SAP 110mm C-7.5 m 715.27 35.82 25,620.97 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 715.27 25,620.97 100.00%
04.06.03.10 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 140mm C-5 m 83.15 54.08 4,496.75 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 83.15 4,496.75 100.00%
04.06.03.11 INSTALACION DE TUBERIA PVC SAP 160mm C-5 m 23.02 68.87 1,585.39 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 23.02 1,585.39 100.00%
04.06.03.12 INSTALACION DE TUBERIA PVC SAP 200MM C-7.5 m 478.31 79.58 38,063.91 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 478.31 38,063.91 100.00%
04.06.03.13 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 160mm C-7.5 m 821.00 72.44 59,473.24 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 821.00 59,473.24 100.00%
04.06.03.14 INSTALACION DE TUBERIA PVC SAP 140mm C-7.5 m 490.00 61.99 30,375.10 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 490.00 30,375.10 100.00%
04.06.03.15 INSTALACION DE TUBERIA PVC SAP 140mm C-10 m 125.00 64.28 8,035.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 125.00 8,035.00 100.00%
04.06.03.16 INSTALACION DE TUBERIA PVC SAP 110mm C-10 m 252.00 41.33 10,415.16 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 252.00 10,415.16 100.00%
04.06.03.17 INSTALACION DE TUBERIA PVC SAP 90mm C-10 m 451.00 24.96 11,256.96 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 451.00 11,256.96 100.00%
04.06.03.18 INSTALACION DE TUBERIA PVC SAP 75mm C-10 m 426.00 22.51 9,589.26 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 426.00 9,589.26 100.00%
04.06.03.19 NSTALACION DE TUBERIA PVC SAP 63mm C-10 m 258.41 16.70 4,315.45 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 258.41 4,315.45 100.00%
04.06.03.20 INSTALACION DE TUBERIA PVC SAP 1 1/2" C-10 m 57.90 11.34 656.59 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 57.90 656.59 100.00%
04.06.04.01 PRUEBA HIDRAULICA EN TUBERIA PVC m 7,615.51 1.12 8,529.37 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7,615.51 8,529.37 100.00%
04.06.05 SUMINISTRO E INSTALACION DE ACCESORIOS 8,102.54
04.06.05.01 SUM. Y COLOCACION DE ACCESORIOS (NEGROPUQUIO) glb 1.00 8,102.54 8,102.54 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 8,102.54 100.00%
04.07.01.01 LIMPIEZA DE TERRENO Y DESBROCE m 6.48 0.30 1.94 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 6.48 1.94 100.00%
04.07.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 3.92 2.15 8.43 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.92 8.43 100.00%
04.07.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 3.92 7.46 29.24 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.92 29.24 100.00%
CUADRO DE AVANCES
PRESUPUESTO SALDO
PARTIDA DESCRIPCIÓN Und. ANTERIOR ACTUAL (OCTUBRE 2022) ACUMULADO
Metrado P.Unit. S/. Pres. Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
04.07.03 ENCOFRADO Y DESENCOFRADO 1,121.12
04.07.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 29.12 38.50 1,121.12 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 29.12 1,121.12 100.00%
04.07.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 29.12 25.80 751.30 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 29.12 751.30 100.00%
04.07.05.01 TAPA METALICA 0.70x0.50 m und 14.00 150.00 2,100.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 14.00 2,100.00 100.00%
04.07.05.02 TAPA METALICA 0.60x0.50 m und 7.00 130.00 910.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.00 910.00 100.00%
04.07.05.03 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 90mm und 3.00 660.78 1,982.34 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 1,982.34 100.00%
04.07.05.04 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 110mm und 4.00 832.98 3,331.92 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.00 3,331.92 100.00%
04.07.05.05 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 140mm und 1.00 1,464.62 1,464.62 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,464.62 100.00%
04.07.05.06 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 160mm und 10.00 1,425.98 14,259.80 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 10.00 14,259.80 100.00%
04.07.05.07 SUM. Y COLOCACION DE ACCESORIOS DE VALVULA CONTROL 200mm und 3.00 1,897.98 5,693.94 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 5,693.94 100.00%
04.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 7.56 1.53 11.57 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.56 11.57 100.00%
04.08.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 5.84 2.15 12.56 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.84 12.56 100.00%
04.08.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 6.08 7.46 45.36 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 6.08 45.36 100.00%
04.08.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 29.04 38.50 1,118.04 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 29.04 1,118.04 100.00%
04.08.04 OBRAS DE CONCRETO ARMADO 3,377.26
04.08.04.01 CONCRETO f'c=175 kg/cm2 m3 5.33 436.03 2,324.04 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.33 2,324.04 100.00%
04.08.04.02 ACERO fy = 4200 Kg/cm2 GRADO 60 kg 103.70 7.35 762.20 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 103.70 762.20 100.00%
04.08.04.03 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 11.28 25.80 291.02 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 11.28 291.02 100.00%
04.08.05.01 SUM. E INSTALACION DE ACCESORIOS EN CAMARA ROMPE PRESION 4" und 2.00 1,940.64 3,881.28 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 3,881.28 100.00%
04.08.05.02 SUM. E INSTALACION DE ACCESORIOS EN CAMARA ROMPE PRESION 3" und 2.00 1,115.14 2,230.28 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 2,230.28 100.00%
04.08.05.03 TAPA METALICA 0.60x0.60 m und 2.00 175.00 350.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 350.00 100.00%
04.09.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 2.50 2.15 5.38 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.50 5.38 100.00%
04.09.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 2.50 7.46 18.65 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.50 18.65 100.00%
04.09.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 28.00 38.50 1,078.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 28.00 1,078.00 100.00%
04.09.04.01 CONCRETO FC=140 KG/CM2 m3 1.12 384.38 430.51 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.12 430.51 100.00%
04.09.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 28.00 25.80 722.40 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 28.00 722.40 100.00%
04.09.04.03 TAPA METALICA 0.70x0.50 m und 85.00 150.00 12,750.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 85.00 12,750.00 100.00%
04.09.05 SUMINISTRO E INSTALACION DE ACCESORIOS 56,055.00
04.09.05.01 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 1 1/2" und 26.00 787.10 20,464.60 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 26.00 20,464.60 100.00%
04.09.05.02 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 2" und 18.00 1,080.60 19,450.80 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 18.00 19,450.80 100.00%
04.09.05.03 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 1 1/2" und 22.00 277.10 6,096.20 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 22.00 6,096.20 100.00%
04.09.05.04 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 2" und 19.00 528.60 10,043.40 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 19.00 10,043.40 100.00%
04.10.01.01 SUMINISTRO E INSTALACION DE LINEA PORTA ASPERSORES DE 01 LINEA und 2.00 1,157.73 2,315.46 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 2,315.46 100.00%
04.10.01.02 SUMINISTRO E INSTALACION DE LINEA PORTA ASPERSORES DE 02 LINEA und 2.00 2,762.23 5,524.46 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 5,524.46 100.00%
04.11.01.01 LIMPIEZA DE TERRENO MANUAL m2 7.84 1.53 12.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.84 12.00 100.00%
CUADRO DE AVANCES
PRESUPUESTO SALDO
PARTIDA DESCRIPCIÓN Und. ANTERIOR ACTUAL (OCTUBRE 2022) ACUMULADO
Metrado P.Unit. S/. Pres. Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
04.11.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 4.00 2.15 8.60 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.00 8.60 100.00%
04.11.02 MOVIMIENTO DE TIERRAS 120.18
04.11.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 2.40 37.64 90.34 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.40 90.34 100.00%
04.11.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 4.00 7.46 29.84 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.00 29.84 100.00%
04.11.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 30.72 38.50 1,182.72 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 30.72 1,182.72 100.00%
04.11.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 30.72 25.80 792.58 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 30.72 792.58 100.00%
04.11.04.03 TAPA METALICA 0.30x0.30 m und 16.00 126.05 2,016.80 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 16.00 2,016.80 100.00%
04.12.01 FLETE TERRESTRE (NEGROPUQUIO) glb 1.00 4,349.02 4,349.02 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 4,349.02 100.00%
05 SECTOR PACPAPATA 565,631.91
05.01.01 CAMPAMENTO PROVICIONAL DE OBRA glb 1.00 1,307.91 1,307.91 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,307.91 100.00%
05.02.01.01 TRAZO Y REPLANTEO PRELIMINAR m 7.20 1.54 11.09 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.20 11.09 100.00%
05.02.02.01 CORTE DE PAVIMENTO m 14.40 1.72 24.77 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 14.40 24.77 100.00%
05.02.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 0.07 56.99 3.99 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.07 3.99 100.00%
05.02.04.01 COMPUERTA DE 1.00M X 1.50M CON VOLANTE und 3.00 1,298.14 3,894.42 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 3,894.42 100.00%
05.03.01.01 SUM. Y COLOCACION DE ACCESORIOS VALVULA EN DESARENADOR 6" und 2.00 2,999.37 5,998.74 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 5,998.74 100.00%
05.03.01.02 SUM. Y COLOCACION DE ACCESORIOS VALVULA EN DESARENADOR 8" und 1.00 3,272.21 3,272.21 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 3,272.21 100.00%
05.04.01.01 SUM. E INSTALACION DE ACCESORIOS EN CAMARA DE CARGA und 1.00 1,584.45 1,584.45 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,584.45 100.00%
05.04.01.02 TAPA METALICA 0.50x0.50 m und 3.00 175.00 525.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 525.00 100.00%
05.04.02 PINTADO DE CAMARA DE CARGA 1,238.48
05.04.02.01 PINTURA DE EXTERIORES DE CAMARA DE CARGA m2 89.55 13.83 1,238.48 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 89.55 1,238.48 100.00%
05.05.01.01 SUM. E INSTALACION DE ACCESORIOS EN CAJA DE VALVULA DE CC 6" und 2.00 1,012.98 2,025.96 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 2,025.96 100.00%
05.05.01.02 SUM. E INSTALACION DE ACCESORIOS EN CAJA DE VALVULA DE CC 8" und 1.00 1,506.98 1,506.98 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,506.98 100.00%
05.05.01.03 TAPA METALICA 0.80x0.70 m und 3.00 226.46 679.38 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 679.38 100.00%
05.06.02.01 REFINE Y NIVELACION DE FONDO DE ZANJA m 2,107.07 1.53 3,223.82 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2,107.07 3,223.82 100.00%
05.06.02.02 CAMA DE APOYO PARA TIBERIA CON MATERIAL PROPIO ZARANDEADO m 5,705.86 1.87 10,669.96 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5,705.86 10,669.96 100.00%
05.06.02.03 RELLENO DE ZANJA CON MATERIAL SELECCIONADO m3 377.31 5.70 2,150.67 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 377.31 2,150.67 100.00%
05.06.02.04 RELLENO CON MATERIAL PROPIO m3 359.50 2.15 772.93 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 359.50 772.93 100.00%
05.06.02.05 ELIMINACION DE MATERIAL EXCEDENTE m3 331.64 10.23 3,392.68 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 331.64 3,392.68 100.00%
05.06.03 SUMINISTRO E INSTALACION DE TUBERIAS 295,357.33
05.06.03.01 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 63 mm C-5 m 667.63 12.57 8,392.11 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 667.63 8,392.11 100.00%
CUADRO DE AVANCES
PRESUPUESTO SALDO
PARTIDA DESCRIPCIÓN Und. ANTERIOR ACTUAL (OCTUBRE 2022) ACUMULADO
Metrado P.Unit. S/. Pres. Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
05.06.03.02 NSTALACION DE TUBERIA PVC SAP 63mm C-7.5 m 52.31 14.10 737.57 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 52.31 737.57 100.00%
05.06.03.03 INSTALACION DE TUBERIA PVC SAP 75mm C-7.5 m 11.44 18.53 211.98 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 11.44 211.98 100.00%
05.06.03.04 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 50mm C-7.5 m 485.56 12.26 5,952.97 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 485.56 5,952.97 100.00%
05.06.03.05 INSTALACION DE TUBERIA PVC SAP 75mm C-5 m 176.55 16.70 2,948.39 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 176.55 2,948.39 100.00%
05.06.03.06 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 90mm C-5 m 483.93 24.96 12,078.89 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 483.93 12,078.89 100.00%
05.06.03.07 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 140mm C-5 m 5.58 54.08 301.77 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.58 301.77 100.00%
05.06.03.08 NSTALACION DE TUBERIA PVC SAP 63mm C-10 m 1,226.00 16.70 20,474.20 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,226.00 20,474.20 100.00%
05.06.03.09 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 160mm C-7.5 m 544.40 72.44 39,436.34 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 544.40 39,436.34 100.00%
05.06.03.10 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 160 mm C-10 m 1,028.80 73.46 75,575.65 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,028.80 75,575.65 100.00%
05.06.03.11 INSTALACION DE TUBERIA PVC SAP 140mm C-7.5 m 26.20 61.99 1,624.14 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 26.20 1,624.14 100.00%
05.06.03.12 INSTALACION DE TUBERIA PVC SAP 140mm C-10 m 156.00 64.28 10,027.68 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 156.00 10,027.68 100.00%
05.06.03.13 INSTALACION DE TUBERIA PVC SAP 110mm C-10 m 1,444.00 41.33 59,680.52 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,444.00 59,680.52 100.00%
05.06.03.14 INSTALACION DE TUBERIA PVC SAP 90mm C-10 m 1,308.00 24.96 32,647.68 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,308.00 32,647.68 100.00%
05.06.03.15 INSTALACION DE TUBERIA PVC SAP 75mm C-10 m 1,056.00 22.51 23,770.56 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,056.00 23,770.56 100.00%
05.06.03.16 INSTALACION DE TUBERIA PVC SAP 1 1/2" C-10 m 132.00 11.34 1,496.88 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 132.00 1,496.88 100.00%
05.06.04.01 PRUEBA HIDRAULICA EN TUBERIA PVC m 12,479.10 1.12 13,976.59 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 12,479.10 13,976.59 100.00%
05.07.01.01 LIMPIEZA DE TERRENO Y DESBROCE m 14.58 0.30 4.37 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 14.58 4.37 100.00%
05.07.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 8.82 2.15 18.96 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.82 18.96 100.00%
05.07.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 8.82 7.46 65.80 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.82 65.80 100.00%
05.07.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 65.52 38.50 2,522.52 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 65.52 2,522.52 100.00%
05.07.04 OBRAS DE CONCRETO SIMPLE 3,193.35
05.07.04.01 CONCRETO FC=140 KG/CM2 m3 3.91 384.38 1,502.93 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.91 1,502.93 100.00%
05.07.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 65.52 25.80 1,690.42 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 65.52 1,690.42 100.00%
05.07.05.02 TAPA METALICA 0.60x0.50 m und 8.00 130.00 1,040.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.00 1,040.00 100.00%
05.07.05.03 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 90mm und 1.00 660.78 660.78 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 660.78 100.00%
05.07.05.04 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 110mm und 2.00 832.98 1,665.96 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 1,665.96 100.00%
05.07.05.05 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 140mm und 2.00 1,464.62 2,929.24 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 2,929.24 100.00%
05.07.05.06 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 160mm und 6.00 1,425.98 8,555.88 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 6.00 8,555.88 100.00%
05.07.05.07 SUM. Y COLOCACION DE ACCESORIOS DE VALVULA CONTROL 200mm und 2.00 1,897.98 3,795.96 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 3,795.96 100.00%
05.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.34 1.53 17.35 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 11.34 17.35 100.00%
05.08.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 8.76 2.15 18.83 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.76 18.83 100.00%
05.08.02 MOVIMIENTO DE TIERRAS 310.07
05.08.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 6.43 37.64 242.03 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 6.43 242.03 100.00%
05.08.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 9.12 7.46 68.04 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 9.12 68.04 100.00%
05.08.03 ENCOFRADO Y DESENCOFRADO 1,677.06
05.08.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 43.56 38.50 1,677.06 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 43.56 1,677.06 100.00%
05.08.04.02 ACERO fy = 4200 Kg/cm2 GRADO 60 kg 154.60 7.35 1,136.31 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 154.60 1,136.31 100.00%
05.08.04.03 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 16.92 25.80 436.54 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 16.92 436.54 100.00%
05.08.04.04 TAPA METALICA DE 0.75x0.75m und 1.00 181.46 181.46 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 181.46 100.00%
05.08.05 SUMINISTRO E INSTALACION DE ACCESORIOS EN C.R.P. 7,395.42
05.08.05.01 SUM. E INSTALACION DE ACCESORIOS EN CAMARA ROMPE PRESION 6" und 1.00 3,814.64 3,814.64 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 3,814.64 100.00%
CUADRO DE AVANCES
PRESUPUESTO SALDO
PARTIDA DESCRIPCIÓN Und. ANTERIOR ACTUAL (OCTUBRE 2022) ACUMULADO
Metrado P.Unit. S/. Pres. Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
05.08.05.02 SUM. E INSTALACION DE ACCESORIOS EN CAMARA ROMPE PRESION 4" und 1.00 1,940.64 1,940.64 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,940.64 100.00%
05.08.05.03 SUM. E INSTALACION DE ACCESORIOS EN CAMARA ROMPE PRESION 3" und 1.00 1,115.14 1,115.14 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,115.14 100.00%
05.08.05.04 TAPA METALICA 0.60x0.60 m und 3.00 175.00 525.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 525.00 100.00%
05.09 HIDRANTES 127,790.10
05.09.01.01 LIMPIEZA DE TERRENO MANUAL m2 2.94 1.53 4.50 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.94 4.50 100.00%
05.09.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 1.50 2.15 3.23 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.50 3.23 100.00%
05.09.02 MOVIMIENTO DE TIERRAS 56.36
05.09.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 1.20 37.64 45.17 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.20 45.17 100.00%
05.09.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 1.50 7.46 11.19 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.50 11.19 100.00%
05.09.04.01 CONCRETO FC=140 KG/CM2 m3 0.67 384.38 257.53 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.67 257.53 100.00%
05.09.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 16.80 25.80 433.44 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 16.80 433.44 100.00%
05.09.04.03 TAPA METALICA 0.70x0.50 m und 136.00 150.00 20,400.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 136.00 20,400.00 100.00%
05.09.05.01 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 1 1/2" und 32.00 787.10 25,187.20 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 32.00 25,187.20 100.00%
05.09.05.02 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 2" und 52.00 1,080.60 56,191.20 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 52.00 56,191.20 100.00%
05.09.05.03 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 3" und 1.00 1,565.76 1,565.76 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,565.76 100.00%
05.09.05.04 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 1 1/2" und 24.00 277.10 6,650.40 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 24.00 6,650.40 100.00%
05.09.05.05 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 2" und 24.00 528.60 12,686.40 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 24.00 12,686.40 100.00%
05.09.05.06 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 3" und 3.00 1,235.76 3,707.28 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 3,707.28 100.00%
05.10.01.01 SUMINISTRO E INSTALACION DE LINEA PORTA ASPERSORES DE 01 LINEA und 1.00 1,157.73 1,157.73 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,157.73 100.00%
05.10.01.02 SUMINISTRO E INSTALACION DE LINEA PORTA ASPERSORES DE 02 LINEA und 3.00 2,762.23 8,286.69 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 8,286.69 100.00%
05.11.01.01 LIMPIEZA DE TERRENO MANUAL m2 7.35 1.53 11.25 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.35 11.25 100.00%
05.11.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 3.75 2.15 8.06 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.75 8.06 100.00%
05.11.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 3.75 7.46 27.98 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.75 27.98 100.00%
05.11.04.01 CONCRETO FC=140 KG/CM2 m3 0.63 384.38 242.16 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.63 242.16 100.00%
05.11.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 15.00 25.80 387.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 15.00 387.00 100.00%
05.11.04.03 TAPA METALICA 0.30x0.30 m und 15.00 126.05 1,890.75 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 15.00 1,890.75 100.00%
05.11.05.01 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE PURGA 63mm und 15.00 118.45 1,776.75 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 15.00 1,776.75 100.00%
06.01.01.01 TRAZO Y REPLANTEO PRELIMINAR m 7.20 1.54 11.09 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.20 11.09 100.00%
06.01.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 0.07 56.99 3.99 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.07 3.99 100.00%
06.01.03.01 CONCRETO f'c=175 kg/cm2 m3 0.04 436.03 17.44 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.04 17.44 100.00%
06.01.04 SUMINISTRO E INSTALACION DE ACCESORIOS 3,894.42
06.01.04.01 COMPUERTA DE 1.00M X 1.50M CON VOLANTE und 3.00 1,298.14 3,894.42 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 3,894.42 100.00%
CUADRO DE AVANCES
PRESUPUESTO SALDO
PARTIDA DESCRIPCIÓN Und. ANTERIOR ACTUAL (OCTUBRE 2022) ACUMULADO
Metrado P.Unit. S/. Pres. Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
06.02 SEDIMENTADOR 8,998.11
06.02.01 SUMINISTRO E INSTALCION DE ACCESORIOS 8,998.11
06.02.01.01 SUM. Y COLOCACION DE ACCESORIOS VALVULA EN DESARENADOR 6" und 3.00 2,999.37 8,998.11 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 8,998.11 100.00%
06.03 CAMARA DE CARGA 1,238.48
06.03.01.01 PINTURA DE EXTERIORES DE CAMARA DE CARGA m2 89.55 13.83 1,238.48 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 89.55 1,238.48 100.00%
06.04.01.01 SUM. E INSTALACION DE ACCESORIOS EN CAJA DE VALVULA DE CC und 3.00 1,650.98 4,952.94 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 4,952.94 100.00%
06.04.01.02 TAPA METALICA 0.80x0.70 m und 6.00 226.46 1,358.76 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 6.00 1,358.76 100.00%
06.05.02.01 EXCAVACION DE ZANJA MANUAL EN TERRENO NORMAL m3 1,463.63 51.16 74,879.31 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,463.63 74,879.31 100.00%
06.05.02.02 REFINE Y NIVELACION DE FONDO DE ZANJA m 9,275.93 1.53 14,192.17 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 9,275.93 14,192.17 100.00%
06.05.02.03 CAMA DE APOYO PARA TIBERIA CON MATERIAL PROPIO ZARANDEADO m 9,275.93 1.87 17,345.99 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 9,275.93 17,345.99 100.00%
06.05.02.04 RELLENO DE ZANJA CON MATERIAL SELECCIONADO m3 1,218.96 5.70 6,948.07 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,218.96 6,948.07 100.00%
06.05.02.05 RELLENO CON MATERIAL PROPIO m3 2,247.96 2.15 4,833.11 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2,247.96 4,833.11 100.00%
06.05.03.02 NSTALACION DE TUBERIA PVC SAP 63mm C-7.5 m 568.94 14.10 8,022.05 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 568.94 8,022.05 100.00%
06.05.03.03 INSTALACION DE TUBERIA PVC SAP 75mm C-5 m 447.00 16.70 7,464.90 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 447.00 7,464.90 100.00%
06.05.03.04 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 50mm C-7.5 m 4,369.32 12.26 53,567.86 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4,369.32 53,567.86 100.00%
06.05.03.05 INSTALACION DE TUBERIA PVC SAP 75mm C-7.5 m 424.82 18.53 7,871.91 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 424.82 7,871.91 100.00%
06.05.03.06 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 90mm C-7.5 m 59.49 24.50 1,457.51 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 59.49 1,457.51 100.00%
06.05.03.07 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 140mm C-5 m 238.55 54.08 12,900.78 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 238.55 12,900.78 100.00%
06.05.03.08 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 90mm C-5 m 598.54 24.96 14,939.56 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 598.54 14,939.56 100.00%
06.05.03.09 INSTALACION DE TUBERIA PVC SAP 110mm C-5 m 437.12 33.68 14,722.20 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 437.12 14,722.20 100.00%
06.05.03.10 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 160mm C-5 m 393.48 68.87 27,098.97 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 393.48 27,098.97 100.00%
06.05.03.11 INSTALACION DE TUBERIA PVC SAP 110mm C-7.5 m 93.34 35.82 3,343.44 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 93.34 3,343.44 100.00%
06.05.03.12 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 160mm C-7.5 m 1,820.88 72.44 131,904.55 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,820.88 131,904.55 100.00%
06.05.03.13 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 160 mm C-10 m 154.00 73.46 11,312.84 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 154.00 11,312.84 100.00%
06.05.03.14 INSTALACION DE TUBERIA PVC SAP 110mm C-10 m 62.19 41.33 2,570.31 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 62.19 2,570.31 100.00%
06.05.03.15 INSTALACION DE TUBERIA PVC SAP 90mm C-10 m 382.00 24.96 9,534.72 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 382.00 9,534.72 100.00%
06.05.03.16 INSTALACION DE TUBERIA PVC SAP 75mm C-10 m 497.20 22.51 11,191.97 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 497.20 11,191.97 100.00%
06.05.03.17 NSTALACION DE TUBERIA PVC SAP 63mm C-10 m 250.60 16.70 4,185.02 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 250.60 4,185.02 100.00%
06.05.04.01 PRUEBA HIDRAULICA EN TUBERIA PVC m 13,544.25 1.12 15,169.56 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 13,544.25 15,169.56 100.00%
06.05.05.01 SUM. Y COLOCACION DE ACCESORIOS (POLTOCSA) glb 1.00 5,820.51 5,820.51 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 5,820.51 100.00%
06.06 CAJA DE VALVULA DE CONTROL 27,421.20
06.06.01.01 LIMPIEZA DE TERRENO Y DESBROCE m 17.01 0.30 5.10 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 17.01 5.10 100.00%
06.06.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 10.29 2.15 22.12 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 10.29 22.12 100.00%
06.06.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 8.23 37.64 309.78 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.23 309.78 100.00%
06.06.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 10.29 7.46 76.76 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 10.29 76.76 100.00%
06.06.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 76.44 38.50 2,942.94 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 76.44 2,942.94 100.00%
06.06.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 76.44 25.80 1,972.15 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 76.44 1,972.15 100.00%
CUADRO DE AVANCES
PRESUPUESTO SALDO
PARTIDA DESCRIPCIÓN Und. ANTERIOR ACTUAL (OCTUBRE 2022) ACUMULADO
Metrado P.Unit. S/. Pres. Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
06.06.05 SUMINISTRO E INSTALACION DE ACCESORIOS 20,339.58
06.06.05.01 TAPA METALICA 0.70x0.50 m und 3.00 150.00 450.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 450.00 100.00%
06.06.05.02 TAPA METALICA 0.60x0.50 m und 18.00 130.00 2,340.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 18.00 2,340.00 100.00%
06.06.05.03 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 90mm und 10.00 660.78 6,607.80 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 10.00 6,607.80 100.00%
06.06.05.04 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 110mm und 8.00 832.98 6,663.84 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.00 6,663.84 100.00%
06.06.05.05 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 160mm und 3.00 1,425.98 4,277.94 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 4,277.94 100.00%
06.07.01.01 SUM. E INSTALACION DE ACCESORIOS EN CAMARA ROMPE PRESION 6" und 2.00 3,814.64 7,629.28 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 7,629.28 100.00%
06.08.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 2.00 7.46 14.92 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 14.92 100.00%
06.08.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 22.40 38.50 862.40 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 22.40 862.40 100.00%
06.08.04 OBRAS DE CONCRETO SIMPLE 21,323.86
06.08.04.01 CONCRETO FC=140 KG/CM2 m3 0.90 384.38 345.94 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.90 345.94 100.00%
06.08.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 22.40 25.80 577.92 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 22.40 577.92 100.00%
06.08.04.03 TAPA METALICA 0.70x0.50 m und 136.00 150.00 20,400.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 136.00 20,400.00 100.00%
06.08.05 SUMINISTRO E INSTALACION DE ACCESORIOS 86,939.38
06.08.05.01 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 1 1/2" und 45.00 787.10 35,419.50 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 45.00 35,419.50 100.00%
06.08.05.02 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 2" und 13.00 1,080.60 14,047.80 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 13.00 14,047.80 100.00%
06.08.05.03 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 3" und 5.00 1,565.76 7,828.80 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.00 7,828.80 100.00%
06.08.05.04 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 1 1/2" und 44.00 277.10 12,192.40 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 44.00 12,192.40 100.00%
06.08.05.05 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 2" und 26.00 528.60 13,743.60 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 26.00 13,743.60 100.00%
06.08.05.06 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 3" und 3.00 1,235.76 3,707.28 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 3,707.28 100.00%
06.09.01.01 SUMINISTRO E INSTALACION DE LINEA PORTA ASPERSORES DE 01 LINEA und 1.00 1,157.73 1,157.73 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,157.73 100.00%
06.09.01.02 SUMINISTRO E INSTALACION DE LINEA PORTA ASPERSORES DE 02 LINEA und 2.00 2,762.23 5,524.46 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 5,524.46 100.00%
06.10.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 1.00 2.15 2.15 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 2.15 100.00%
06.10.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 0.60 37.64 22.58 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.60 22.58 100.00%
06.10.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 1.00 7.46 7.46 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 7.46 100.00%
06.10.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 7.68 38.50 295.68 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.68 295.68 100.00%
06.10.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 7.68 25.80 198.14 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.68 198.14 100.00%
06.10.04.03 TAPA METALICA 0.30x0.30 m und 3.00 126.05 378.15 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 378.15 100.00%
06.10.05 SUMINISTRO E INSTALACION DE ACCESORIOS 355.35
06.10.05.01 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE PURGA 63mm und 3.00 118.45 355.35 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 355.35 100.00%
07.01.01 CAMPAMENTO PROVICIONAL DE OBRA glb 1.00 1,307.91 1,307.91 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,307.91 100.00%
07.01.02 CARTEL DE OBRA (GIGANTOGRAFIA DE 3.60MX2.40M) glb 1.00 422.60 422.60 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 422.60 100.00%
07.02.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 0.05 56.99 2.85 0.00 0.00 0.00% 0.02 1.37 48.00% 0.02 1.37 48.00% 0.03 1.48 52.00%
07.02.03.01 CONCRETO f'c=175 kg/cm2 m3 0.03 436.03 13.08 0.00 0.00 0.00% 0.01 6.28 48.00% 0.01 6.28 48.00% 0.02 6.80 52.00%
07.02.04 SUMINISTRO E INSTALACION DE ACCESORIOS 2,596.28
07.02.04.01 COMPUERTA DE 1.00M X 1.50M CON VOLANTE und 2.00 1,298.14 2,596.28 0.00 0.00 0.00% 1.00 1,298.14 50.00% 1.00 1,298.14 50.00% 1.00 1,298.14 50.00%
07.03.02.02 REFINE Y NIVELACION EN TERRENO ROCOSO m2 173.22 3.01 521.39 173.22 521.39 100.00% 0.00 0.00% 173.22 521.39 100.00% - - 0.00%
07.03.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 299.55 10.23 3,064.40 90.34 924.18 30.16% 0.00 0.00% 90.34 924.18 30.16% 209.21 2,140.22 69.84%
07.03.03.01 SOLADO PARA ZAPATAS DE 3" MEZCLA 1:12 CEMENTO-HORMIGON m2 0.54 97.77 52.80 0.24 23.95 45.37% 0.00 0.00% 0.24 23.95 45.37% 0.30 28.84 54.63%
07.03.03.02 CONCRETO CICLOPEO FC=140KG/CM2 + 30 % PM. m3 0.79 306.52 242.15 0.40 121.08 50.00% 0.00 0.00% 0.40 121.08 50.00% 0.40 121.08 50.00%
07.03.04 OBRAS DE CONCRETO ARMADO 29,375.22
07.03.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 148.03 83.72 12,393.07 62.11 5,200.02 41.96% 0.00 0.00% 62.11 5,200.02 41.96% 85.92 7,193.05 58.04%
07.03.04.02 CONCRETO FC=210 KG/CM2 m3 22.20 547.59 12,156.50 9.32 5,101.79 41.97% 0.00 0.00% 9.32 5,101.79 41.97% 12.88 7,054.71 58.03%
07.03.04.03 ACERO ESTRUCTURAL Fy= 4200 KG/CM2 kg 637.47 7.57 4,825.65 318.73 2,412.79 50.00% 0.00 0.00% 318.73 2,412.79 50.00% 318.74 2,412.86 50.00%
07.03.05.01 TARRAJEO CON IMPERMEABILIZANTE, MEZCLA 1:5, E=1.5cm m2 168.00 32.03 5,381.04 67.66 2,167.02 40.27% 0.00 0.00% 67.66 2,167.02 40.27% 100.34 3,214.02 59.73%
07.04.01.01 SUM. E INSTALACION DE ACCESORIOS EN CAMARA DE CARGA und 1.00 1,584.45 1,584.45 1.00 1,584.45 100.00% 0.00 0.00% 1.00 1,584.45 100.00% - - 0.00%
07.04.01.02 TAPA METALICA 0.50x0.50 m und 2.00 175.00 350.00 1.00 175.00 50.00% 0.00 0.00% 1.00 175.00 50.00% 1.00 175.00 50.00%
07.04.02 PINTADO DE CAMARA DE CARGA 825.65
07.04.02.01 PINTURA DE EXTERIORES DE CAMARA DE CARGA m2 59.70 13.83 825.65 0.00 0.00 0.00% 29.85 412.83 50.00% 29.85 412.83 50.00% 29.85 412.83 50.00%
07.05 CAJA DE VALVULA DE CAMARA DE CARGA 3,854.46
07.05.01.01 SUM. E INSTALACION DE ACCESORIOS EN CAJA DE VALVULA DE CC und 2.00 1,650.98 3,301.96 1.00 1,650.98 50.00% 0.00 0.00% 1.00 1,650.98 50.00% 1.00 1,650.98 50.00%
07.05.01.02 TAPA METALICA 0.80x0.70 m und 2.00 226.46 452.92 1.00 226.46 50.00% 0.00 0.00% 1.00 226.46 50.00% 1.00 226.46 50.00%
07.05.02 PINTADO DE CAJA DE VALVULA 99.58
07.05.02.01 PINTURA DE EXTERIORES m2 7.20 13.83 99.58 0.00 0.00 0.00% 3.60 49.79 50.00% 3.60 49.79 50.00% 3.60 49.79 50.00%
07.06.01.02 TRAZO Y REPLANTEO PRELIMINAR m 1,815.37 1.54 2,795.67 1,759.52 2,709.66 96.92% 0.00 0.00% 1,759.52 2,709.66 96.92% 55.85 86.01 3.08%
07.06.02 MOVIMIENTO DE TIERRAS 113,859.56
07.06.02.01 EXCAVACION DE ZANJA MANUAL EN TERRENO NORMAL m3 1,707.84 51.16 87,373.09 1,291.26 66,060.86 75.61% 0.00 0.00% 1,291.26 66,060.86 75.61% 416.58 21,312.23 24.39%
07.06.02.02 REFINE Y NIVELACION DE FONDO DE ZANJA m 4,382.53 1.53 6,705.27 3,111.72 4,760.93 71.00% 0.00 0.00% 3,111.72 4,760.93 71.00% 1,270.81 1,944.34 29.00%
07.06.02.03 CAMA DE APOYO PARA TIBERIA CON MATERIAL PROPIO ZARANDEADO m 4,866.67 1.87 9,100.67 2,388.06 4,465.67 49.07% 0.00 0.00% 2,388.06 4,465.67 49.07% 2,478.61 4,635.00 50.93%
07.06.02.04 RELLENO DE ZANJA CON MATERIAL SELECCIONADO m3 795.51 5.70 4,534.41 494.12 2,816.48 62.11% 0.00 0.00% 494.12 2,816.48 62.11% 301.39 1,717.92 37.89%
07.06.02.05 RELLENO CON MATERIAL PROPIO m3 680.86 2.15 1,463.85 490.30 1,054.15 72.01% 0.00 0.00% 490.30 1,054.15 72.01% 190.56 409.70 27.99%
07.06.02.06 ELIMINACION DE MATERIAL EXCEDENTE m3 457.70 10.23 4,682.27 253.50 2,593.31 55.39% 0.00 0.00% 253.50 2,593.31 55.39% 204.20 2,088.97 44.61%
07.06.03.02 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 90mm C-5 m 185.70 24.96 4,635.07 75.00 1,872.00 40.39% 0.00 0.00% 75.00 1,872.00 40.39% 110.70 2,763.07 59.61%
CUADRO DE AVANCES
PRESUPUESTO SALDO
PARTIDA DESCRIPCIÓN Und. ANTERIOR ACTUAL (OCTUBRE 2022) ACUMULADO
Metrado P.Unit. S/. Pres. Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
07.06.03.03 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 50mm C-7.5 m 1,090.30 12.26 13,367.08 753.84 9,242.08 69.14% 0.00 0.00% 753.84 9,242.08 69.14% 336.46 4,125.00 30.86%
07.06.03.04 NSTALACION DE TUBERIA PVC SAP 63mm C-7.5 m 304.45 14.10 4,292.75 52.56 741.10 17.26% 0.00 0.00% 52.56 741.10 17.26% 251.89 3,551.65 82.74%
07.06.03.05 INSTALACION DE TUBERIA PVC SAP 160mm C-5 m 697.60 68.87 48,043.71 114.97 7,917.98 16.48% 0.00 0.00% 114.97 7,917.98 16.48% 582.63 40,125.73 83.52%
07.06.03.06 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 140mm C-5 m 121.10 54.08 6,549.09 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 121.10 6,549.09 100.00%
07.06.03.07 INSTALACION DE TUBERIA PVC SAP 110mm C-5 m 96.00 33.68 3,233.28 96.00 3,233.28 100.00% 0.00 0.00% 96.00 3,233.28 100.00% - - 0.00%
07.06.03.08 INSTALACION DE TUBERIA PVC SAP 110mm C-7.5 m 373.10 35.82 13,364.44 115.25 4,128.26 30.89% 0.00 0.00% 115.25 4,128.26 30.89% 257.85 9,236.19 69.11%
07.06.03.09 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 90mm C-7.5 m 623.40 24.50 15,273.30 81.90 2,006.55 13.14% 0.00 0.00% 81.90 2,006.55 13.14% 541.50 13,266.75 86.86%
07.06.03.10 INSTALACION DE TUBERIA PVC SAP 90mm C-10 m 152.90 24.96 3,816.38 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 152.90 3,816.38 100.00%
07.06.03.11 INSTALACION DE TUBERIA PVC SAP 75mm C-7.5 m 96.00 18.53 1,778.88 92.88 1,721.07 96.75% 0.00 0.00% 92.88 1,721.07 96.75% 3.12 57.81 3.25%
07.06.03.12 INSTALACION DE TUBERIA PVC SAP 75mm C-10 m 268.10 22.51 6,034.93 126.05 2,837.39 47.02% 0.00 0.00% 126.05 2,837.39 47.02% 142.05 3,197.55 52.98%
07.06.03.13 NSTALACION DE TUBERIA PVC SAP 63mm C-10 m 314.40 16.70 5,250.48 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 314.40 5,250.48 100.00%
07.06.03.14 INSTALACION DE TUBERIA PVC SAP 1 1/2" C-10 m 81.90 11.34 928.75 81.90 928.75 100.00% 0.00 0.00% 81.90 928.75 100.00% - - 0.00%
07.06.04 PRUEBA HIDRAULICA 5,450.66
07.06.04.01 PRUEBA HIDRAULICA EN TUBERIA PVC m 4,866.66 1.12 5,450.66 0.00 0.00 0.00% 2,400.00 2,688.00 49.32% 2,400.00 2,688.00 49.32% 2,466.66 2,762.66 50.68%
07.06.05 SUMINISTRO E INSTALACION DE ACCESORIOS 10,467.84
07.06.05.01 SUM. Y COLOCACION DE ACCESORIOS PVC DE 160MM glb 1.00 1,306.64 1,306.64 0.31 405.06 31.00% 0.00 0.00% 0.31 405.06 31.00% 0.69 901.58 69.00%
07.06.05.02 SUM. Y COLOCACION DE ACCESORIOS PVC DE 140MM glb 1.00 325.64 325.64 0.31 100.95 31.00% 0.00 0.00% 0.31 100.95 31.00% 0.69 224.69 69.00%
07.06.05.03 SUM. Y COLOCACION DE ACCESORIOS PVC DE 110MM glb 1.00 453.64 453.64 0.31 140.63 31.00% 0.00 0.00% 0.31 140.63 31.00% 0.69 313.01 69.00%
07.06.05.04 SUM. Y COLOCACION DE ACCESORIOS PVC DE 90MM glb 1.00 320.64 320.64 0.31 99.40 31.00% 0.00 0.00% 0.31 99.40 31.00% 0.69 221.24 69.00%
07.06.05.05 SUM. Y COLOCACION DE ACCESORIOS PVC DE 75MM glb 1.00 223.64 223.64 0.41 91.69 41.00% 0.00 0.00% 0.41 91.69 41.00% 0.59 131.95 59.00%
07.06.05.06 SUMINISTRO E INSTALACION DE ACCESORIOS DE TUBERIA DISTRIBUCION (PUISO) und 1.00 7,837.64 7,837.64 0.41 3,213.43 41.00% 0.00 0.00% 0.41 3,213.43 41.00% 0.59 4,624.21 59.00%
07.07.01.01 LIMPIEZA DE TERRENO Y DESBROCE m 8.91 0.30 2.67 4.86 1.46 54.55% 0.00 0.00% 4.86 1.46 54.55% 4.05 1.22 45.45%
07.07.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 5.39 2.15 11.59 2.94 6.32 54.55% 0.00 0.00% 2.94 6.32 54.55% 2.45 5.27 45.45%
07.07.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 4.31 37.64 162.23 2.35 88.53 54.57% 0.00 0.00% 2.35 88.53 54.57% 1.96 73.70 45.43%
07.07.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 5.39 7.46 40.21 2.94 21.93 54.55% 0.00 0.00% 2.94 21.93 54.55% 2.45 18.28 45.45%
07.07.03 ENCOFRADO Y DESENCOFRADO 1,541.54
07.07.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 40.04 38.50 1,541.54 21.84 840.84 54.55% 0.00 0.00% 21.84 840.84 54.55% 18.20 700.70 45.45%
07.07.04.01 CONCRETO FC=140 KG/CM2 m3 2.39 384.38 918.67 1.30 500.46 54.48% 0.00 0.00% 1.30 500.46 54.48% 1.09 418.21 45.52%
07.07.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 40.04 25.80 1,033.03 21.84 563.47 54.55% 0.00 0.00% 21.84 563.47 54.55% 18.20 469.56 45.45%
07.07.05.01 TAPA METALICA 0.70x0.50 m und 6.00 150.00 900.00 0.00 0.00 0.00% 3.00 450.00 50.00% 3.00 450.00 50.00% 3.00 450.00 50.00%
07.07.05.02 TAPA METALICA 0.60x0.50 m und 5.00 130.00 650.00 0.00 0.00 0.00% 3.00 390.00 60.00% 3.00 390.00 60.00% 2.00 260.00 40.00%
07.07.05.03 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 90mm und 2.00 660.78 1,321.56 0.00 0.00 0.00% 1.00 660.78 50.00% 1.00 660.78 50.00% 1.00 660.78 50.00%
07.07.05.04 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 110mm und 3.00 832.98 2,498.94 0.00 0.00 0.00% 2.00 1,665.96 66.67% 2.00 1,665.96 66.67% 1.00 832.98 33.33%
07.07.05.05 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 140mm und 1.00 1,464.62 1,464.62 0.00 0.00 0.00% 0.50 732.31 50.00% 0.50 732.31 50.00% 0.50 732.31 50.00%
07.07.05.06 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 160mm und 5.00 1,425.98 7,129.90 0.00 0.00 0.00% 3.00 4,277.94 60.00% 3.00 4,277.94 60.00% 2.00 2,851.96 40.00%
07.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 7.56 1.53 11.57 7.56 11.57 100.00% 0.00 0.00% 7.56 11.57 100.00% - - 0.00%
07.08.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 5.84 2.15 12.56 5.84 12.56 100.00% 0.00 0.00% 5.84 12.56 100.00% - - 0.00%
07.08.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 4.29 37.64 161.48 4.29 161.48 100.00% 0.00 0.00% 4.29 161.48 100.00% - - 0.00%
07.08.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 6.08 7.46 45.36 6.08 45.36 100.00% 0.00 0.00% 6.08 45.36 100.00% - - 0.00%
07.08.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 29.04 38.50 1,118.04 29.04 1,118.04 100.00% 0.00 0.00% 29.04 1,118.04 100.00% - - 0.00%
07.08.04 OBRAS DE CONCRETO ARMADO 3,372.62
07.08.04.01 CONCRETO f'c=175 kg/cm2 m3 5.33 436.03 2,324.04 5.33 2,324.04 100.00% 0.00 0.00% 5.33 2,324.04 100.00% - - 0.00%
07.08.04.02 ACERO fy = 4200 Kg/cm2 GRADO 60 kg 103.07 7.35 757.56 103.07 757.56 100.00% 0.00 0.00% 103.07 757.56 100.00% - - 0.00%
07.08.04.03 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 11.28 25.80 291.02 11.28 291.02 100.00% 0.00 0.00% 11.28 291.02 100.00% - - 0.00%
07.08.05 SUMINISTRO E INSTALACION DE ACCESORIOS EN C.R.P. 4,231.28
07.08.05.01 SUM. E INSTALACION DE ACCESORIOS EN CAMARA ROMPE PRESION 4" und 2.00 1,940.64 3,881.28 0.00 0.00 0.00% 2.00 3,881.28 100.00% 2.00 3,881.28 100.00% - - 0.00%
CUADRO DE AVANCES
PRESUPUESTO SALDO
PARTIDA DESCRIPCIÓN Und. ANTERIOR ACTUAL (OCTUBRE 2022) ACUMULADO
Metrado P.Unit. S/. Pres. Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
07.08.05.02 TAPA METALICA 0.60x0.60 m und 2.00 175.00 350.00 0.00 0.00 0.00% 2.00 350.00 100.00% 2.00 350.00 100.00% - - 0.00%
07.09 HIDRANTES 66,861.31
07.09.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 15.00 2.15 32.25 11.50 24.73 76.67% 0.00 0.00% 11.50 24.73 76.67% 3.50 7.53 23.33%
07.09.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 12.00 37.64 451.68 9.20 346.29 76.67% 0.00 0.00% 9.20 346.29 76.67% 2.80 105.39 23.33%
07.09.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 15.00 7.46 111.90 11.50 85.79 76.67% 0.00 0.00% 11.50 85.79 76.67% 3.50 26.11 23.33%
07.09.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 168.00 38.50 6,468.00 128.80 4,958.80 76.67% 0.00 0.00% 128.80 4,958.80 76.67% 39.20 1,509.20 23.33%
07.09.04.03 TAPA METALICA 0.70x0.50 m und 60.00 150.00 9,000.00 0.00 0.00 0.00% 42.00 6,300.00 70.00% 42.00 6,300.00 70.00% 18.00 2,700.00 30.00%
07.09.05 SUMINISTRO E INSTALACION DE ACCESORIOS 43,873.50
07.09.05.01 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 1 1/2" und 22.00 787.10 17,316.20 0.00 0.00 0.00% 18.00 14,167.80 81.82% 18.00 14,167.80 81.82% 4.00 3,148.40 18.18%
07.09.05.02 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 2" und 14.00 1,080.60 15,128.40 0.00 0.00 0.00% 8.00 8,644.80 57.14% 8.00 8,644.80 57.14% 6.00 6,483.60 42.86%
07.09.05.03 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 1 1/2" und 5.00 277.10 1,385.50 0.00 0.00 0.00% 3.00 831.30 60.00% 3.00 831.30 60.00% 2.00 554.20 40.00%
07.09.05.04 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 2" und 19.00 528.60 10,043.40 0.00 0.00 0.00% 12.00 6,343.20 63.16% 12.00 6,343.20 63.16% 7.00 3,700.20 36.84%
07.10.01.01 SUMINISTRO E INSTALACION DE LINEA PORTA ASPERSORES DE 02 LINEA und 2.00 2,762.23 5,524.46 0.00 0.00 0.00% 1.00 2,762.23 50.00% 1.00 2,762.23 50.00% 1.00 2,762.23 50.00%
07.11 VALVULA DE PURGA 2,001.70
07.11.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 1.50 2.15 3.23 1.00 2.15 66.67% 0.00 0.00% 1.00 2.15 66.67% 0.50 1.08 33.33%
07.11.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 0.90 37.64 33.88 0.60 22.58 66.67% 0.00 0.00% 0.60 22.58 66.67% 0.30 11.29 33.33%
07.11.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 1.50 7.46 11.19 1.00 7.46 66.67% 0.00 0.00% 1.00 7.46 66.67% 0.50 3.73 33.33%
07.11.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 6.00 38.50 231.00 4.00 154.00 66.67% 0.00 0.00% 4.00 154.00 66.67% 2.00 77.00 33.33%
07.11.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 6.00 25.80 154.80 4.00 103.20 66.67% 0.00 0.00% 4.00 103.20 66.67% 2.00 51.60 33.33%
07.11.04.03 TAPA METALICA 0.30x0.30 m und 6.00 126.05 756.30 0.00 0.00 0.00% 4.00 504.20 66.67% 4.00 504.20 66.67% 2.00 252.10 33.33%
07.11.05 SUMINISTRO E INSTALACION DE ACCESORIOS 710.70
07.11.05.01 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE PURGA 63mm und 6.00 118.45 710.70 0.00 0.00 0.00% 4.00 473.80 66.67% 4.00 473.80 66.67% 2.00 236.90 33.33%
07.12.01 FLETE TERRESTRE (PUISO) glb 1.00 1,913.26 1,913.26 0.50 956.63 50.00% 0.15 286.99 15.00% 0.65 1,243.62 65.00% 0.35 669.64 35.00%
08.01.01 CAMPAMENTO PROVICIONAL DE OBRA glb 1.00 1,307.91 1,307.91 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,307.91 100.00%
08.01.02 CARTEL DE OBRA (GIGANTOGRAFIA DE 3.60MX2.40M) glb 1.00 422.60 422.60 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 422.60 100.00%
08.02 TOMA DE CANAL 1,315.60
08.02.01.01 TRAZO Y REPLANTEO PRELIMINAR m 2.40 1.54 3.70 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.40 3.70 100.00%
08.02.02 CORTE DE PAVIMENTO 9.40
08.02.02.01 CORTE DE PAVIMENTO m 4.80 1.72 8.26 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.80 8.26 100.00%
08.02.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 0.02 56.99 1.14 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.02 1.14 100.00%
08.02.03 OBRAS DE CONCRETO SIMPLE 4.36
08.02.03.01 CONCRETO f'c=175 kg/cm2 m3 0.01 436.03 4.36 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.01 4.36 100.00%
08.02.04.01 COMPUERTA DE 1.00M X 1.50M CON VOLANTE und 1.00 1,298.14 1,298.14 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,298.14 100.00%
08.03 CAMARA DE CARGA 7,779.52
08.03.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 12.96 7.46 96.68 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 12.96 96.68 100.00%
08.03.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 30.26 38.50 1,165.01 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 30.26 1,165.01 100.00%
08.03.04 OBRAS DE CONCRETO ARMADO 3,988.15
08.03.04.01 CONCRETO f'c=175 kg/cm2 m3 2.97 436.03 1,295.01 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.97 1,295.01 100.00%
08.03.04.02 CONCRETO f'c=175 kg/cm2 + 30% PM m3 1.09 421.66 459.61 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.09 459.61 100.00%
08.03.04.03 ACERO fy = 4200 Kg/cm2 GRADO 60 kg 133.39 7.35 980.42 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 133.39 980.42 100.00%
08.03.04.04 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 48.57 25.80 1,253.11 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 48.57 1,253.11 100.00%
08.03.05 SUMINISTRO E INSTALACION DE ACCESORIOS EN CAMARA DE CARGA 1,759.45
08.03.05.01 SUM. E INSTALACION DE ACCESORIOS EN CAMARA DE CARGA und 1.00 1,584.45 1,584.45 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,584.45 100.00%
08.03.05.02 TAPA METALICA 0.50x0.50 m und 1.00 175.00 175.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 175.00 100.00%
08.03.06.01 PINTURA DE EXTERIORES DE CAMARA DE CARGA m2 29.85 13.83 412.83 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 29.85 412.83 100.00%
08.04.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 1.88 0.92 1.73 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.88 1.73 100.00%
08.04.02.01 PERFILADO DE LA SECCION DE LA ESTRUCTURA m2 1.88 1.53 2.88 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.88 2.88 100.00%
08.04.03 ENCOFRADO Y DESENCOFRADO 301.07
08.04.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 7.82 38.50 301.07 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.82 301.07 100.00%
08.04.04 OBRAS DE CONCRETO SIMPLE 872.91
08.04.04.01 CONCRETO f'c=175 kg/cm2 m3 0.85 436.03 370.63 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.85 370.63 100.00%
08.04.04.02 ACERO fy = 4200 Kg/cm2 GRADO 60 kg 51.91 7.35 381.54 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 51.91 381.54 100.00%
08.04.04.03 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 4.68 25.80 120.74 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.68 120.74 100.00%
08.04.05 SUMINISTRO E INSTALACION DE ACCESORIOS 1,877.44
08.04.05.01 SUM. E INSTALACION DE ACCESORIOS EN CAJA DE VALVULA DE CC und 1.00 1,650.98 1,650.98 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,650.98 100.00%
08.04.05.02 TAPA METALICA 0.80x0.70 m und 1.00 226.46 226.46 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 226.46 100.00%
08.05.01.02 TRAZO Y REPLANTEO PRELIMINAR m 2,292.00 1.54 3,529.68 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2,292.00 3,529.68 100.00%
08.05.02.01 EXCAVACION DE ZANJA MANUAL EN TERRENO NORMAL m3 916.80 51.16 46,903.49 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 916.80 46,903.49 100.00%
08.05.02.02 REFINE Y NIVELACION DE FONDO DE ZANJA m 2,292.00 1.53 3,506.76 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2,292.00 3,506.76 100.00%
08.05.02.03 CAMA DE APOYO PARA TIBERIA CON MATERIAL PROPIO ZARANDEADO m 2,292.00 1.87 4,286.04 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2,292.00 4,286.04 100.00%
08.05.02.04 RELLENO DE ZANJA CON MATERIAL SELECCIONADO m3 458.40 5.70 2,612.88 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 458.40 2,612.88 100.00%
08.05.02.05 RELLENO CON MATERIAL PROPIO m3 343.80 2.15 739.17 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 343.80 739.17 100.00%
08.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE m3 343.80 10.23 3,517.07 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 343.80 3,517.07 100.00%
08.05.03.01 INSTALACION DE TUBERIA PVC SAP 160mm C-5 m 41.80 68.87 2,878.77 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 41.80 2,878.77 100.00%
08.05.03.02 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 160mm C-7.5 m 457.70 72.44 33,155.79 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 457.70 33,155.79 100.00%
08.05.03.03 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 160 mm C-10 m 200.40 73.46 14,721.38 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 200.40 14,721.38 100.00%
08.05.03.04 INSTALACION DE TUBERIA PVC SAP 140mm C-10 m 190.40 64.28 12,238.91 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 190.40 12,238.91 100.00%
08.05.03.05 INSTALACION DE TUBERIA PVC SAP 110mm C-7.5 m 150.30 35.82 5,383.75 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 150.30 5,383.75 100.00%
08.05.03.06 INSTALACION DE TUBERIA PVC SAP 110mm C-10 m 296.60 41.33 12,258.48 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 296.60 12,258.48 100.00%
08.05.03.07 INSTALACION DE TUBERIA PVC SAP 90mm C-10 m 264.10 24.96 6,591.94 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 264.10 6,591.94 100.00%
08.05.03.08 INSTALACION DE TUBERIA PVC SAP 75mm C-10 m 275.10 22.51 6,192.50 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 275.10 6,192.50 100.00%
08.05.03.09 NSTALACION DE TUBERIA PVC SAP 63mm C-10 m 293.50 16.70 4,901.45 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 293.50 4,901.45 100.00%
08.05.03.10 INSTALACION DE TUBERIA PVC SAP 1 1/2" C-10 m 122.10 11.34 1,384.61 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 122.10 1,384.61 100.00%
CUADRO DE AVANCES
PRESUPUESTO SALDO
PARTIDA DESCRIPCIÓN Und. ANTERIOR ACTUAL (OCTUBRE 2022) ACUMULADO
Metrado P.Unit. S/. Pres. Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
08.05.04 SUMINISTRO E INSTALACION DE ACCESORIOS 2,630.20
08.05.04.01 SUM. Y COLOCACION DE ACCESORIOS PVC DE 160MM glb 1.00 1,306.64 1,306.64 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,306.64 100.00%
08.05.04.02 SUM. Y COLOCACION DE ACCESORIOS PVC DE 140MM glb 1.00 325.64 325.64 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 325.64 100.00%
08.05.04.03 SUM. Y COLOCACION DE ACCESORIOS PVC DE 110MM glb 1.00 453.64 453.64 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 453.64 100.00%
08.05.04.04 SUM. Y COLOCACION DE ACCESORIOS PVC DE 90MM glb 1.00 320.64 320.64 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 320.64 100.00%
08.05.04.05 SUM. Y COLOCACION DE ACCESORIOS PVC DE 75MM glb 1.00 223.64 223.64 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 223.64 100.00%
08.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 15.12 1.53 23.13 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 15.12 23.13 100.00%
08.06.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 11.68 2.15 25.11 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 11.68 25.11 100.00%
08.06.02 MOVIMIENTO DE TIERRAS 413.66
08.06.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 8.58 37.64 322.95 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.58 322.95 100.00%
08.06.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 12.16 7.46 90.71 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 12.16 90.71 100.00%
08.06.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 58.08 38.50 2,236.08 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 58.08 2,236.08 100.00%
08.06.04.02 ACERO fy = 4200 Kg/cm2 GRADO 60 kg 206.13 7.35 1,515.06 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 206.13 1,515.06 100.00%
08.06.04.03 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 22.56 25.80 582.05 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 22.56 582.05 100.00%
08.06.05.02 TAPA METALICA 0.60x0.60 m und 4.00 175.00 700.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.00 700.00 100.00%
08.07 VALVULA DE PURGA 2,904.22
08.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 0.43 1.53 0.66 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.43 0.66 100.00%
08.07.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 1.75 2.15 3.76 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.75 3.76 100.00%
08.07.02 MOVIMIENTO DE TIERRAS 52.58
08.07.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 1.05 37.64 39.52 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.05 39.52 100.00%
08.07.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 1.75 7.46 13.06 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.75 13.06 100.00%
08.07.04.01 CONCRETO FC=140 KG/CM2 m3 0.67 384.38 257.53 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.67 257.53 100.00%
08.07.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 13.44 25.80 346.75 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 13.44 346.75 100.00%
08.07.04.03 TAPA METALICA 0.30x0.30 m und 7.00 126.05 882.35 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.00 882.35 100.00%
08.07.05.01 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE PURGA 63mm und 6.00 118.45 710.70 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 6.00 710.70 100.00%
08.07.05.02 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE PURGA 1 1/2" und 1.00 132.45 132.45 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 132.45 100.00%
08.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 17.64 1.53 26.99 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 17.64 26.99 100.00%
08.08.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 9.00 2.15 19.35 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 9.00 19.35 100.00%
08.08.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 7.20 37.64 271.01 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.20 271.01 100.00%
08.08.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 9.00 7.46 67.14 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 9.00 67.14 100.00%
08.08.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 80.74 38.50 3,108.49 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 80.74 3,108.49 100.00%
08.08.04 OBRAS DE CONCRETO SIMPLE 9,029.56
08.08.04.01 CONCRETO FC=140 KG/CM2 m3 4.03 384.38 1,549.05 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.03 1,549.05 100.00%
08.08.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 80.64 25.80 2,080.51 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 80.64 2,080.51 100.00%
08.08.04.03 TAPA METALICA 0.70x0.50 m und 36.00 150.00 5,400.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 36.00 5,400.00 100.00%
08.08.05 SUMINISTRO E INSTALACION DE ACCESORIOS 43,873.50
08.08.05.01 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 1 1/2" und 22.00 787.10 17,316.20 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 22.00 17,316.20 100.00%
CUADRO DE AVANCES
PRESUPUESTO SALDO
PARTIDA DESCRIPCIÓN Und. ANTERIOR ACTUAL (OCTUBRE 2022) ACUMULADO
Metrado P.Unit. S/. Pres. Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
08.08.05.02 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 2" und 14.00 1,080.60 15,128.40 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 14.00 15,128.40 100.00%
08.08.05.03 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 1 1/2" und 5.00 277.10 1,385.50 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.00 1,385.50 100.00%
08.08.05.04 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 2" und 19.00 528.60 10,043.40 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 19.00 10,043.40 100.00%
08.09 CAJA DE VALVULA DE CONTROL 7,416.78
08.09.01.01 LIMPIEZA DE TERRENO Y DESBROCE m 1.21 0.30 0.36 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.21 0.36 100.00%
08.09.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 2.94 2.15 6.32 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.94 6.32 100.00%
08.09.02 MOVIMIENTO DE TIERRAS 110.38
08.09.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 2.35 37.64 88.45 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.35 88.45 100.00%
08.09.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 2.94 7.46 21.93 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.94 21.93 100.00%
08.09.04.01 CONCRETO FC=140 KG/CM2 m3 1.30 384.38 499.69 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.30 499.69 100.00%
08.09.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 21.84 25.80 563.47 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 21.84 563.47 100.00%
08.09.04.03 TAPA METALICA 0.50x0.50 m und 6.00 175.00 1,050.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 6.00 1,050.00 100.00%
08.09.05.01 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 90mm und 1.00 660.78 660.78 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 660.78 100.00%
08.09.05.02 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 110mm und 1.00 832.98 832.98 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 832.98 100.00%
08.09.05.03 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 160mm und 2.00 1,425.98 2,851.96 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 2,851.96 100.00%
09.01.01 LIMPIEZA DE TERRENO m2 390.00 1.23 479.70 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 390.00 479.70 100.00%
09.01.02 TRAZO Y REPLANTEO PRELIMINAR m 192.00 1.54 295.68 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 192.00 295.68 100.00%
09.02.01 ELIMINACION DE MATERIAL EXCEDENTE m3 5.74 56.99 327.12 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.74 327.12 100.00%
09.04.01 ALAMBRE DE PUA PARA CERCO PERIMETRICO m 12,350.00 26.17 323,199.50 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 12,350.00 323,199.50 100.00%
09.04.02 PUERTA DE ACCESO AL SEDIMENTADOR 1.00 x 1.80m und 34.00 190.00 6,460.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 34.00 6,460.00 100.00%
09.05.01 PINTURA DE ECERCO m2 1,132.20 8.71 9,861.46 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,132.20 9,861.46 100.00%
09.05.02 FLETE kg 6.00 55.50 333.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 6.00 333.00 100.00%
10.01 BIOSEGURIDAD PARA LA PREVENCION DEL COVID-19 glb 1.00 123,637.62 123,637.62 0.26 32,145.78 26.00% 0.03 3,709.13 3.00% 0.29 35,854.91 29.00% 0.71 87,782.71 71.00%
11.01 COSTOS POR ADMINISTRACIÓN DIRECTA-PERSONAL glb 1.00 30,253.50 30,253.50 0.64 19,362.24 64.00% 0.13 3,932.96 13.00% 0.77 23,295.20 77.00% 0.23 6,958.31 23.00%
11.02 EPPS - EQUIPOS DE PROTECCION PERSONAL glb 1.00 108,120.00 108,120.00 0.39 42,629.40 39.43% 0.10 10,812.00 10.00% 0.49 53,441.40 49.43% 0.51 54,678.60 50.57%
11.03 EQUIPOS DE PROTECCION COLECTIVA glb 1.00 12,268.00 12,268.00 0.50 6,134.00 50.00% 0.00 0.00% 0.50 6,134.00 50.00% 0.50 6,134.00 50.00%
11.04 SEÑALES Y LETREROS DE SEGURIDAD Y SALUD EN EL TRABAJO glb 1.00 2,850.00 2,850.00 0.50 1,425.00 50.00% 0.00 0.00% 0.50 1,425.00 50.00% 0.50 1,425.00 50.00%
11.05 INSUMOS DE PRIMEROS AUXILIOS glb 1.00 1,247.00 1,247.00 0.20 249.40 20.00% 0.10 124.70 10.00% 0.30 374.10 30.00% 0.70 872.90 70.00%
11.06 MOBILIARIO, EQUIPOS Y OTROS glb 1.00 25,985.00 25,985.00 0.18 4,677.30 18.00% 0.10 2,598.50 10.00% 0.28 7,275.80 28.00% 0.72 18,709.20 72.00%
12 CAPACITACION 149,080.39
12.01 CAPACITACION A USUARIOS EN RIEGO 149,080.39
12.01.01 CAPACITACIÓN SOCIAL glb 1.00 17,500.00 17,500.00 0.00 0.00 0.00% 0.20 3,500.00 20.00% 0.20 3,500.00 20.00% 0.80 14,000.00 80.00%
12.01.02 CAPACITACIÓN TÉCNICA glb 1.00 109,580.39 109,580.39 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 109,580.39 100.00%
12.01.03 ACTIVIDADES DE EMPODERAMIENTO glb 1.00 22,000.00 22,000.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 22,000.00 100.00%
13.01 MEDIDAS DE MITIGACION DE IMPACTO AMBIENTAL glb 1.00 10,000.00 10,000.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 10,000.00 100.00%
CUADRO DE AVANCES
PRESUPUESTO SALDO
PARTIDA DESCRIPCIÓN Und. ANTERIOR ACTUAL (OCTUBRE 2022) ACUMULADO
Metrado P.Unit. S/. Pres. Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
COSTO DIRECTO 6,734,758.63 641,914.79 9.53% 461,029.03 6.85% 1,100,700.41 16.34% 5,634,058.08 83.66%
COSTO TOTAL DEL PROYECTO 7,713,692.59 725,974.13 9.41% 521,401.22 6.76% 1,244,838.16 16.14% 6,371,843.23 82.60%
--------------------------------------- ---------------------------------------
ING. RESIDENTE DE OBRA ING. SUPERVISOR DE OBRA
Firma y Sello Firma y Sello
FORMATO FF-10
RESOLUCION SUB REGIONAL Nº 203-2022-GRA-GSRCH-GSR
METRADOS No. 06 OCTUBRE DEL 2022
PROYECTO : "PROYECTO DE IRRIGACION CHUMBAO". FECHA : ANDAHUAYLAS ABRIL DEL 2022
COMPONENTE : OBRAS DE ASPERSION DISTRITO : ANDAHUAYLAS.
SUB META : OBRAS DE ASPERSION PROVINCIA : ANDAHUAYLAS.
FTE - FTO : RECURSOS ORDINARIOS - RECURSOS DETERMINADOS. DEPARTAMENTO : APURIMAC.
MODALIDAD : ADMINISTRACION DIRECTA.
PPTO. APROBAD: S/. 7,713,692.59
DIMENSIONES
PARTIDA DESCRIPCIÓN Und. CANT. Nª DE VECES PARCIAL TOTAL
LARGO ANCHO ALTO
02 SECTOR LLIUPAPUQUIO
02.01 TOMA DE CANAL DE C.CN°07, C.C N°08C C N°01 (isquierda)
02.01.01 OBRAS PRELIMINARES
02.01.01.01 TRAZO Y REPLANTEO PRELIMINAR m 7.20
Margen Derecha
Canal Trapezoidal 3.00 1.00 2.40 7.20
02.01.02 CORTE DE PAVIMENTO
02.01.02.01 CORTE DE PAVIMENTO m 7.20
Margen Derecha
Canal Trapezoidal 3.00 1.00 2.40 7.20
02.01.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 0.07
Margen Derecha
Canal Trapezoidal 3.00 1.00 2.40 0.10 0.10 0.07
02.01.03 OBRAS DE CONCRETO SIMPLE
02.01.03.01 CONCRETO f'c=175 kg/cm2 m3 0.04
Margen Derecha
Canal Trapezoidal 3.00 2.00 2.40 0.03 0.10 0.04
02.01.04 SUMINISTRO E INSTALACION DE ACCESORIOS
02.01.04.02 COMPUERTA DE 0.70M X 0.50M CON VOLANTE und 3.00
Margen Derecha
Canal Trapezoidal 3.00 1.00 3.00
02.05 LINEA MATRIZ Y DE DISTRIBUCION
02.05.01 TRABAJOS PRELIMINARES
02.05.01.01 TRAZO Y REPLANTEO PRELIMINAR m 5,751.00
1.00 1.00 5,751.00 5,751.00
02.05.02 MOVIMIENTO DE TIERRAS
02.05.02.01 CAMA DE APOYO PARA TIBERIA CON MATERIAL PROPIO ZARANDEADO m 5,664.91
Margen Derecha 1.00 1.00 5,664.91 5,664.91
02.05.02.02 RELLENO DE ZANJA CON MATERIAL SELECCIONADO m3 1,132.98
Margen Derecha 1.00 5,664.91 0.50 0.40 1,132.98
02.05.02.03 RELLENO CON MATERIAL PROPIO m3 849.74
Margen Derecha 1.00 1.00 5,664.91 0.50 0.30 849.74
02.05.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 90.00
Margen Derecha 1.00 1.00 90.00 90.00
02.05.03 SUMINISTRO E INSTALACION DE TUBERIAS 2,505.00
02.05.03.01 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 48 mm C-7.5 m 1.00 1.00 2,505.00 2,505.00 -
-
02.05.03.02 INSTALACION DE TUBERIA PVC SAP 160mm C-5 m 600.00
1.00 1.00 600.00 600.00
02.05.03.03 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 63 mm C-5 m
02.05.03.04 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 90mm C-5 m
02.05.03.05 INSTALACION DE TUBERIA PVC SAP 140mm C-7.5 m
02.05.03.06 INSTALACION DE TUBERIA PVC SAP 140mm C-10 m 680.00
1.00 1.00 680.00 680.00
02.05.03.07 INSTALACION DE TUBERIA PVC SAP 110mm C-5 m 68.00
1.00 1.00 68.00 68.00
02.05.03.08 INSTALACION DE TUBERIA PVC SAP 110mm C-7.5 m
02.05.03.09 INSTALACION DE TUBERIA PVC SAP 110mm C-10 m 213.00
1.00 1.00 213.00 213.00
02.05.03.10 INSTALACION DE TUBERIA PVC SAP 90mm C-10 m 290.00
1.00 1.00 290.00 290.00
02.05.03.11 INSTALACION DE TUBERIA PVC SAP 75mm C-5 m 406.00
1.00 1.00 406.00 406.00
02.05.03.12 INSTALACION DE TUBERIA PVC SAP 75mm C-7.5 m
02.05.03.13 INSTALACION DE TUBERIA PVC SAP 75mm C-10 m 520.00
1.00 1.00 520.00 520.00
02.05.03.14 INSTALACION DE TUBERIA PVC SAP 1 1/2" C-10 m 34.80
1.00 1.00 34.80 34.80
02.05.03.15 NSTALACION DE TUBERIA PVC SAP 63mm C-7.5 m 300.00
1.00 1.00 300.00 300.00
02.05.03.16 NSTALACION DE TUBERIA PVC SAP 63mm C-10 m 1,060.00
1.00 1.00 1,060.00 1,060.00
02.05.04 PRUEBA HIDRAULICA
02.05.04.01 PRUEBA HIDRAULICA EN TUBERIA PVC m 1.00 1.00 1,000.00 1,000.00 1,000.00
02.05.05 SUMINISTRO E INSTALACION DE ACCESORIOS
02.05.05.01 SUM. Y COLOCACION DE ACCESORIOS glb 1.00 1.00 0.10 0.10 0.10
02.06 CAJA DE VALVULA DE CONTROL
02.06.01 TRABAJOS PRELIMINARES
02.06.01.01 LIMPIEZA DE TERRENO Y DESBROCE m 10.87
Margen Derecha 9.00 1.00 1.15 1.05 10.87
02.06.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 6.48
Margen Derecha 9.00 1.00 0.90 0.80 6.48
02.06.02 MOVIMIENTO DE TIERRAS
FORMATO FF-10
RESOLUCION SUB REGIONAL Nº 203-2022-GRA-GSRCH-GSR
METRADOS No. 06 OCTUBRE DEL 2022
PROYECTO : "PROYECTO DE IRRIGACION CHUMBAO". FECHA : ANDAHUAYLAS ABRIL DEL 2022
COMPONENTE : OBRAS DE ASPERSION DISTRITO : ANDAHUAYLAS.
SUB META : OBRAS DE ASPERSION PROVINCIA : ANDAHUAYLAS.
FTE - FTO : RECURSOS ORDINARIOS - RECURSOS DETERMINADOS. DEPARTAMENTO : APURIMAC.
MODALIDAD : ADMINISTRACION DIRECTA.
PPTO. APROBAD: S/. 7,713,692.59
DIMENSIONES
PARTIDA DESCRIPCIÓN Und. CANT. Nª DE VECES PARCIAL TOTAL
LARGO ANCHO ALTO
02.06.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 5.83
Margen Derecha 9.00 1.00 0.90 0.80 0.90 5.83
02.06.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 0.72
Margen Derecha - 1.00 0.90 0.80 0.72
02.06.03 ENCOFRADO Y DESENCOFRADO 40.86
02.06.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2
Margen Derecha
muros exteriores 9.00 2.00 0.80 0.80 11.52
muros exteriores 9.00 2.00 0.90 0.80 12.96
muros interiores 9.00 2.00 0.60 0.70 7.56
muros interiores 9.00 2.00 0.70 0.70 8.82
02.06.04 OBRAS DE CONCRETO SIMPLE
02.06.04.01 CONCRETO FC=140 KG/CM2 m3 6.41
Margen Derecha
muros 9.00 2.00 0.80 0.10 0.60 0.86
muros 9.00 2.00 0.80 0.10 0.70 1.01
piso 9.00 1.00 0.80 0.70 0.90 4.54
02.06.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 48.96
Margen Derecha
INTERIOR 9.00 2.00 2.00 0.80 0.80 23.04
EXTERIOR 9.00 2.00 2.00 0.90 0.80 25.92
02.06.05 SUMINISTRO E INSTALACION DE ACCESORIOS
02.06.05.01 TAPA METALICA 0.70x0.50 m und 9.00
9.00 1.00 9.00
02.06.05.02 TAPA METALICA 0.60x0.50 m und 3.00
3.00 1.00 3.00
02.06.05.03 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 90mm und 4.00
4.00 1.00 4.00
02.06.05.04 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 110mm und 4.00
4.00 1.00 4.00
02.06.05.05 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 140mm und 3.00
3.00 1.00 3.00
02.06.05.06 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 160mm und 4.00
4.00 1.00 4.00
02.06.05.07 SUM. Y COLOCACION DE ACCESORIOS DE VALVULA CONTROL 200mm und -
- -
02.07 CAMARA ROMPE PRESION TIPO I
02.07.01 TRABAJOS PRELIMINARES
02.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 7.56
2.00 2.10 1.80 7.56
02.07.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 5.84
2.00 1.00 1.60 1.60 5.12
2.00 1.00 0.60 0.60 0.72
02.07.02 MOVIMIENTO DE TIERRAS
02.07.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 4.29
2.00 1.00 1.60 1.60 0.80 4.10
2.00 1.00 0.80 0.60 0.20 0.19
02.07.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 0.96
2.00 1.00 0.00 0.00 0.00
2.00 1.00 0.80 0.60 0.96
02.07.03 ENCOFRADO Y DESENCOFRADO
02.07.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 30.48
MUROS EXTERIOR 2.00 4.00 1.20 1.10 10.56
CAJA
MUROS EXTERIOR 2.00 1.00 2.80 0.50 2.80
CAJA
MURO 2.00 2.00 0.80 0.10 0.80
MURO 2.00 2.00 0.40 0.10 0.40 0.06
DIMENSIONES
PARTIDA DESCRIPCIÓN Und. CANT. Nª DE VECES PARCIAL TOTAL
LARGO ANCHO ALTO
N° de
Longitud de Peso en
Diametro piezas por total de kilos
Acero en muro lateral verticales pieza kilogramos
elemento
1.30
1.08
1.08
1.10
1.10
1.10
0.15
1.30
02.07.04.03 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 10.72
PARED INTERIOR 2.00 2.00 1.00 1.00 4.00
DIMENSIONES
PARTIDA DESCRIPCIÓN Und. CANT. Nª DE VECES PARCIAL TOTAL
LARGO ANCHO ALTO
02.08.05.02 SUM. E INSTALACION DE ACCESORIOS EN CAMARA ROMPE PRESION 4" und - -
1.00 -
02.08.05.03 SUM. E INSTALACION DE ACCESORIOS EN CAMARA ROMPE PRESION 3" und - 12.00
12.00 1.00 12.00
02.08.05.04 SUM. E INSTALACION DE ACCESORIOS EN CAMARA ROMPE PRESION 2 1/2" und - -
1.00 -
02.08.05.05 SUM. E INSTALACION DE ACCESORIOS EN CAMARA ROMPE PRESION 2" und - -
1.00 -
02.08.05.06 TAPA METALICA 0.60x0.60 m und 51.00
1 51.00 1.00 51.00
02.09 HIDRANTES
02.09.01 TRABAJOS PRELIMINARES
02.09.01.01 LIMPIEZA DE TERRENO MANUAL m2 8.33
Margen Derecha 17.00 1.00 0.70 0.70 8.33
02.09.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 4.25
Margen Derecha 17.00 1.00 0.50 0.50 4.25
02.09.02 MOVIMIENTO DE TIERRAS
02.09.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 3.40
Margen Derecha 17.00 1.00 0.50 0.50 0.80 3.40
02.09.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 4.25
Margen Derecha 17.00 1.00 0.50 0.50 4.25
02.09.03 ENCOFRADO Y DESENCOFRADO
02.09.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 47.60
Margen Derecha
INTERIOR 17.00 4.00 0.50 0.70 23.80
EXTERIOR 17.00 4.00 0.50 0.70 23.80
02.09.04 OBRAS DE CONCRETO SIMPLE
02.09.04.01 CONCRETO FC=140 KG/CM2 m3 1.90
Margen Derecha
PAREDES 17.00 2.00 0.50 0.10 0.70 1.19
17.00 2.00 0.30 0.10 0.70 0.71
02.09.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 47.60
Margen Derecha
INTERIOR 17.00 4.00 0.50 0.70 23.80
EXTERIOR 17.00 4.00 0.50 0.70 23.80
02.09.04.03 TAPA METALICA 0.70x0.50 m und 190.00
Margen Derecha 190.00 1.00 190.00
02.09.05 SUMINISTRO E INSTALACION DE ACCESORIOS
02.09.05.01 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 1 1/2" und
02.09.05.02 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 2" und º 22.00
22.00 1.00 22.00
02.09.05.03 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 3" und
02.09.05.04 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 1 1/2" und 77.00
77.00 1.00 77.00
02.09.05.05 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 2" und
02.09.05.06 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 3" und
02.10 LATERAL DE RIEGO
02.10.01 LINEA DE RIEGO MOVIL
02.10.01.01 SUMINISTRO E INSTALACION DE LINEA PORTA ASPERSORES DE 01 LINEA und
02.10.01.02 SUMINISTRO E INSTALACION DE LINEA PORTA ASPERSORES DE 02 LINEA und
02.10.01.03 SUMINISTRO E INSTALACION DE LINEA PORTA ASPERSORES DE 03 LINEA und
02.11 VALVULA DE PURGA
02.11.01 OBRAS PRELIMINARES
02.11.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.96
Margen Derecha 4.00 1.00 0.70 0.70 1.96
02.11.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 1.00
Margen Derecha 4.00 1.00 0.50 0.50 1.00
02.11.02 MOVIMIENTO DE TIERRAS
02.11.02.01 EXCAVACION MANUAL EN TERRENO SUELTO m3 0.60
Margen Derecha 4.00 1.00 0.50 0.50 0.60 0.60
02.11.02.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 1.00
Margen Derecha 4.00 1.00 0.50 0.50 1.00
02.11.03 ENCOFRADO Y DESENCOFRADO
02.11.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 7.68
Margen Derecha
INTERIOR 4.00 4.00 0.30 0.60 2.88
EXTERIOR 4.00 4.00 0.50 0.60 4.80
02.11.04 OBRAS DE CONCRETO ARMADO
02.11.04.01 CONCRETO FC=140 KG/CM2 m3 0.38
Margen Derecha
PAREDES 4.00 2.00 0.50 0.10 0.60 0.24
4.00 2.00 0.30 0.10 0.60 0.14
02.11.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 7.68
FORMATO FF-10
RESOLUCION SUB REGIONAL Nº 203-2022-GRA-GSRCH-GSR
METRADOS No. 06 OCTUBRE DEL 2022
PROYECTO : "PROYECTO DE IRRIGACION CHUMBAO". FECHA : ANDAHUAYLAS ABRIL DEL 2022
COMPONENTE : OBRAS DE ASPERSION DISTRITO : ANDAHUAYLAS.
SUB META : OBRAS DE ASPERSION PROVINCIA : ANDAHUAYLAS.
FTE - FTO : RECURSOS ORDINARIOS - RECURSOS DETERMINADOS. DEPARTAMENTO : APURIMAC.
MODALIDAD : ADMINISTRACION DIRECTA.
PPTO. APROBAD: S/. 7,713,692.59
DIMENSIONES
PARTIDA DESCRIPCIÓN Und. CANT. Nª DE VECES PARCIAL TOTAL
LARGO ANCHO ALTO
Margen Derecha
INTERIOR 4.00 4.00 0.30 0.60 2.88
EXTERIOR 4.00 4.00 0.50 0.60 4.80
07.06.03.01 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 63 mm C-5 m 1.00 1.00 17.52 -
07.06.03.02 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 90mm C-5 m -
07.06.03.03 INSTALACION DE TUBERIA DE PVC-UF/NTP ISO 1452 DN 50mm C-7.5 m 1.00 1.00 122.64 -
07.06.03.08 INSTALACION DE TUBERIA PVC SAP 110mm C-7.5 m 1.00 1.00 17.52 -
07.06.03.11 INSTALACION DE TUBERIA PVC SAP 75mm C-7.5 m 1.00 1.00 11.68 -
07.06.03.12 INSTALACION DE TUBERIA PVC SAP 75mm C-10 m 1.00 1.00 50.00 -
07.06.03.14 INSTALACION DE TUBERIA PVC SAP 1 1/2" C-10 m 1.00 1.00 1.90 -
DIMENSIONES
PARTIDA DESCRIPCIÓN Und. CANT. Nª DE VECES PARCIAL TOTAL
LARGO ANCHO ALTO
07.06.04.01 PRUEBA HIDRAULICA EN TUBERIA PVC m
07.06.05.05 SUM. Y COLOCACION DE ACCESORIOS PVC DE 75MM glb 1.00 1.00 0.10 -
07.06.05.06 SUMINISTRO E INSTALACION DE ACCESORIOS DE TUBERIA DISTRIBUCION (PUISO) und 1.00 1.00 0.10 -
07.07 CAJA DE VALVULA DE CONTROL
07.07.05.03 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 90mm und 1.00 1.00 1.00 1.00
07.07.05.04 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 110mm und 1.00 1.00 2.00 2.00
07.07.05.05 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 140mm und 1.00 1.00 0.50 0.50
07.07.05.06 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE CONTROL 160mm und 1.00 1.00 3.00 3.00
07.08.05.01 SUM. E INSTALACION DE ACCESORIOS EN CAMARA ROMPE PRESION 4" und 1.00 1.00 2.00 2.00 2.00
07.08.05.02 TAPA METALICA 0.60x0.60 m und 1.00 1.00 2.00 2.00 2.00
07.09 HIDRANTES - -
07.09.04.02 TARRAJEO EN MUROS EXTERIOR E INTERIOR C:A 1:5, e=1.5 cm. m2 1.00 1.00 90.00 90.00 90.00
07.09.04.03 TAPA METALICA 0.70x0.50 m und 1.00 1.00 42.00 42.00 42.00
07.09.05.01 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 1 1/2" und 1.00 1.00 18.00 18.00
07.09.05.02 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA CON VRP 2" und 1.00 1.00 8.00 8.00
07.09.05.03 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 1 1/2" und 1.00 1.00 3.00 3.00
07.09.05.04 SUMINISTRO E INSTALACION DE ACCESORIOS HIDRANTE PARA SIN VRP 2" und 1.00 1.00 12.00 12.00
1.00 1.00 -
07.11.04.03 TAPA METALICA 0.30x0.30 m und 1.00 1.00 4.00 4.00
07.11.05.01 SUM. Y COLOCACION DE ACCESORIOS VALVULA DE PURGA 63mm und 1.00 1.00 4.00 4.00
07.12 FLETE
10.01 BIOSEGURIDAD PARA LA PREVENCION DEL COVID-19 glb 1.00 0.03 0.03 0.03
11 SEGURIDAD Y SALUD OCUPACIONAL E IMPLEMENTACION
11.01 COSTOS POR ADMINISTRACIÓN DIRECTA-PERSONAL glb 1.00 0.13 0.13 0.13
11.02 EPPS - EQUIPOS DE PROTECCION PERSONAL glb 1.00 0.10 0.10 0.10
DIMENSIONES
PARTIDA DESCRIPCIÓN Und. CANT. Nª DE VECES PARCIAL TOTAL
LARGO ANCHO ALTO
11.05 INSUMOS DE PRIMEROS AUXILIOS glb 1.00 0.10 0.10 0.10
12 CAPACITACION
--------------------------------------- ---------------------------------------
ING. RESIDENTE DE OBRA ING. SUPERVISOR DE OBRA
Firma y Sello Firma y Sello
FORMATO …..
CRONOGRAMA DE EJECUCION DE OBRA
PROYECTO : "PROYECTO DE IRRIGACION CHUMBAO". PLAZO DE EJECUCION : 183 DIAS
COMPONENTE :OBRAS DE ASPERSION FECHA INICIO DE OBRA : 19-04-2022.
SUB META :OBRAS DE ASPERSION FECHA TERMINO DE OBRA : 19-10-2022.
FTE - FTO : RECURSOS ORDINARIOS - RECURSOS DETERMINADOS.
MODALIDAD : ADMINISTRACION DIRECTA. FECHA : ANDAHUAYLAS,
PPTO. APROBAD 7,713,692.59 DISTRITO : ANDAHUAYLAS.
PROVINCIA : ANDAHUAYLAS.
PPTO. ASIGNADO 2022 1,479,911.00 DEPARTAMENTO : APURIMAC.
*CRONOGRAMA SALDO
ABRIL.- 2022 MAYO.-2022 JUNIO.- 2022 JULIO.- 2022 AGOSTO.-2022 SEPTIEMBRE -.2022 OCTUBRE -.2022 (FIN
(INICIO 19 DE ABRIL) 19 DE OCTUBRE)
VALORIZACION VALORIZACION VALORIZACIO VALORIZACION VALORIZACION VALORIZACION VALORIZACION
MES -1 PORCENTAJE MES -2 PORCENTAJE N MES -3 PORCENTAJE MES -4 PORCENTAJE MES -5 PORCENTAJE MES -6 PORCENTAJE MES -7 PORCENTAJE
ITEM DESCRIPCIÓN UND MET PU PREST
ASPERSION 6,734,758.63 6,734,758.63 117,301.33 1.74% 192,422.71 2.86% 652,276.54 9.69% 754,183.67 11.20% 1,840,455.90 27.33% 2,061,893.40 30.62% 1,116,225.08 16.57%
6,734,758.63 COSTO DIRECTO 6,734,758.63 117,301.33 1.74% 192,422.71 2.86% 652,276.54 9.69% 754,183.67 11.20% 1,840,455.90 27.33% 2,061,893.40 30.62% 1,116,225.08 16.57%
- 0.00 GASTOS GENERALES 717,558.87 12,492.59 20,493.02 69,467.45 80,320.56 196,008.55 219,591.65 118,877.97
SUB TOTAL 7,452,317.50 129,793.92 212,915.73 721,743.99 834,504.23 2,036,464.45 2,281,485.05 1,235,103.06
Liquidación de Obra 97,011.05 97,011.05
GASTOS DE SUPERVISION 164,364.04 2,868.45 4,705.44 15,950.54 18,442.54 45,005.86 50,095.43 27,295.78
7,713,692.59 COSTO TOTAL 7,713,692.59 132,662.37 1.72% 217,621.17 2.82% 737,694.53 9.56% 852,946.77 11.06% 2,081,777.39 26.99% 2,331,580.48 30.23% 1,359,409.88 17.62%
*RESUMEN DE INFORMACION FISICA - FINANCIERA / PRIMERA ASIGNACION 2022 (S/.1,479,911.00) + SEGUNDA ASIGNACION 2022 (S/.999,986.00)
ABRIL.- 2022 MAYO.-2022 JULIO.- 2022 AGOSTO.- 2022 SEPTIEMBRE.- 2022 OCTUBRE.- 2022
(INICIO 19 DE ABRIL) (FIN 19 DE AGOSTO) (FIN 19 DE OCTUBRE)
VALORIZACION VALORIZACION VALORIZACIO VALORIZACION VALORIZACION VALORIZACION
MES -1 PORCENTAJE MES -2 PORCENTAJE N MES -4 PORCENTAJE MES -4 PORCENTAJE MES -4 PORCENTAJE MES -4 PORCENTAJE
ITEM DESCRIPCIÓN UND MET PU PREST
COSTO DIRECTO 1,702,949.50 1,702,949.50 11,285.92 0.66% 49,185.39 2.89% 455,407.31 26.74% 433,407.30 25.45% 333,407.30 19.58% 420,256.28 24.68%
GASTOS GENERALES 660,107.46 5,359.78 23,358.55 216,276.73 205,828.74 58,337.91 134,062.24
SUB TOTAL 2,363,056.96 16,645.70 72,543.94 671,684.04 639,236.04 391,745.21 554,318.52
GASTOS DE SUPERVISION 116,840.04 948.75 4,134.75 38,283.60 36,434.18 22,328.09 31,594.19
COSTO TOTAL 2,479,897.00 2,479,897.00 17,594.44 0.71% 76,678.69 3.09% 709,967.64 28.63% 675,670.22 27.25% 414,073.29 16.70% 585,912.71 23.63%