GESTION DE LA CONSTRUCCION
EDT
ERB
Tabla Nª1: Valores y avances esperados
ITEM PRECIO MES 1 MES 2 MES 3 MES 4 AVANCE
Nave 1 $ 100,000.00 1
Nave 2 $ 100,000.00 1
Nave 3 $ 100,000.00 1
Nave 4 $ 100,000.00 1
TOTALES $ 400,000.00 1 2 3 4 4
B.A.C. = $ 400,000.00
A.C. = $ 280,000.00
% AVANCE TOTAL = 62.50%
% AVANCE PLANEADO = 75.00%
E.V. = $ 250,000.00
490+ ( 6 )∗330+820
=438.33 dias ,lo mas proximo es 490 dias
6
10 HORAS 1%
X HORAS 100%
X= 1000 HORAS
X= 50 SEMANAS
EV =50 %=600
P V =5 5 %=6 6 0
EV
CPI= =0.7
AC
BAC=1200 horas
600
0.7=
AC
AC=857.14 HORAS
E AC=857.14 horas+ 600horas =1457.14 horas