HOJA RESUMEN DE PRESUPUESTO

OBRA : “CREACION DEL COMPLEJO RECREACIONAL EN EL BARRIO SANTA CRUZ


DEL DISTRITO DE ANTAUTA - PROVINCIA
DE MELGAR - DEPARTAMENTO DE PUNO”

UBICACIÓN : ANTAUTA - MELGAR- PUNO


PLAZO DE EJECUCIÓN : 18 MESES

ESTRUCTURAS S/. 1,375,930.45


ARQUITECTURA S/. 714,201.51
INSTALACIONES SANITARIAS S/. 57,764.18
INSTALACIONES ELECTRICAS S/. 67,594.95
ESTRUCTURA METALICAS Y COBERTURA S/. 565,793.53
LOSA MULTIUSOS S/. 130,407.58
IMPLENTACION DE EQUIPAMIENTO S/. 124,926.41
OBRAS COMPLEMENTARIAS S/. 67,293.86
MITIGACION DE IMPACTO AMBIENTAL S/. 10,841.10
FORTALECIMIENTO DE DEPORTE DE ALTO RENDIMIEN S/. 25,280.00

* COSTO DIRECTO 3,140,033.57


GASTOS GENERALES (6.94%) : 248,661.20
GASTOS DE SUPERVICION (1.82%) : 69,775.45
GASTOS DE LIQUIDACION (0.52%) : 16,287.86
GASTOS DE EXPEDIENTE TECNICO (0.77%) : 24,078.21
* COSTO INDIRECTO (10.05%) 358,802.72
* TOTAL PRESUPUESTO : 3,498,836.29
SON : TRES MILLONES CUATROCIENTOS CINCUENTA Y CINCO MIL DOSCIENTOS SETENTA Y DOS CON 15/100 SOLES
RESUMEN DEL PRESUPUESTO ANALÍTICO

Proyecto: CREACION DEL COMPLEJO RECREACIONAL EN EL BARRIO SANTA CRUZ DEL DISTRITO DE
ANTAUTA - MELGAR - PUNO

CUI. 2455394

Costo Directo S/ 3',295,663.37

COSTO DIRECTO 3,295,663.37


COSTO INDIRECTO 358,802.72
GASTOS GENERALES 7.55% 248,661.20
GASTOS DE SUPERVISIÓ N 2.12% 69,775.45
GASTOS DE LIQUIDACIÓ N 0.49% 16,287.86
GASTOS DE ELABORACIÓ N DE EXPEDIENTE TÉ CNICO 0.73% 24,078.21

TOTAL PRESUPUESTO 3,654,466.09


CUADRO DE PRESUPUESTO ANALITICO MODIFICADO
 

PROYECTO: CREACION DEL COMPLEJO RECREACIONAL EN EL BARRIO SANTA CRUZ DEL DISTRITO DE ANTAUTA - MELGAR -
PUNO
CUI 2455394

COSTO GASTOS GASTOS DE GASTOS DE GASTOS DE


CODIGO DESCRIPCION TOTAL
DIRECTO GENERALES SUPERVISION LIQUIDACION EXP. TECNICO

2.6 ADQUISICION DE ACTIVOS NO FINANCIEROS


2.6.2 CONSTRUCCION DE EDIFICIOS Y ESTRUCTURAS 3,295,663.37 248,661.20 69,775.45 16,287.86 24,078.21 3,654,466.09
2.6.2 3 OTRAS INSTALACIONES
2.6.2 3.99 OTRAS ESTRUCTURAS
2.6.2.3.99.3 COSTO DE CONSTRUCCION POR ADMINISTRACION DIRECTA - PERSONAL 960,871.65 98,100.00 1,058,971.65
2.6.2.3.99.4 COSTO DE CONSTRUCCION POR ADMINISTRACION DIRECTA - BIENES 2,298,362.29 10,611.20 2,308,973.49
2.6.2.3.99.5 COSTO DE CONSTRUCCION POR ADMINISTRACION DIRECTA - SERVICIOS 36,429.43 139,950.00 176,379.43
2.6.2.3.99.6 COSTO DE CONSTRUCCION POR ADMINISTRACION DIRECTA - OTROS 0.00
2.6.8.1.4.1 GASTOS POR LA CONTRATACIÓN DE PERSONAL (SUP Y LIQ) 0.00
2.6.8.1.4.2 GASTOS POR LA COMPRA DE BIENES (SUP Y LIQ) 2,275.45 2,024.26 4,299.71
2.6.8.1.4.3 GASTOS POR LA CONTRATACIÓN DE SERVICIOS (SUP Y LIQ) 67,500.00 14,263.60 81,763.60
2.6.8.1.3.1 ELABORACION DE EXPEDIENTES TECNICOS 24,078.21 24,078.21

TOTAL S/. 3,295,663.37 248,661.20 69,775.45 16,287.86 24,078.21 3,654,466.09


COSTO DIRECTO MODIFICADO
 

OBRA : “CREACION DEL COMPLEJO RECREACIONAL EN EL BARRIO SANTA CRUZ DEL DISTRITO DE ANTAUTA - PROVINCIA DE
MELGAR - DEPARTAMENTO DE PUNO”

COSTO DIRECTO = S/. 3,295,663.37


1.- PERSONAL S/. 960,871.65

Descripción UND CANTIDAD PRECIO PARCIAL Parcial (S/.)

PERSONAL 960,871.65
A.- PERSONAL
OPERADOR DE EQUIPO PESADO hh 86.63 12.45 1,078.54 1,078.54
TOPOGRAFO hh 200.25 12.40 2,483.14 2,483.14
TECNICO ENFERMERO hh 2,041.00 12.40 25,308.40 25,308.40
OPERARIO hh 30,478.92 12.40 377,938.64 377,938.64
OFICIAL hh 15,298.70 10.50 160,636.39 160,636.39
PEON hh 34,870.36 8.80 306,859.22 306,859.22
OPERARIO ESPECIALIZADO hh 3,699.50 12.40 45,873.83 45,873.83
OFICIAL ESPECIALIZADO hh 3,875.57 10.50 40,693.50 40,693.50

2. MATERIALES DE CONSTRUCCION S/. 2,298,362.29

Descripción Und Cantidad Precio Parcial

A.- MATERIALES DE CONSTRUCCION


CLAVOS PARA MADERA C/C 3" kg 1278.63 4.80 6,137.42
CLAVOS PARA MADERA C/C 4" kg 15.52 5.50 85.36
ALAMBRE NEGRO N°16 kg 3958.76 4.80 19,002.05
ALAMBRE NEGRO N°8 kg 1056.95 4.80 5,073.36
PERNO DE ANCLAJE A325 DE 3/4"x0.30 m. pza 288.00 30.00 8,640.00
FIERRO LISO DE 3/8" x 6 m. var 473.01 16.00 7,568.16
FIERRO LISO DE 1/2" x 6m. var 401.48 24.00 9,635.52
FIERRO LISO DE 1/2" x 6m. var 41.35 24.00 992.40
TIRAFONES Y ARANDELAS und 3176.50 4.00 12,706.00
ACERO DE REFUERZO FY=4200 GRADO 60 kg 83761.52 3.25 272,224.94
ARENA FINA m3 220.86 55.00 12,147.30
TIERRA CERNIDA m3 7.92 40.00 316.80
TIERRA DE CHACRA O VEGETAL m3 4.60 60.00 276.00
TIERRA DE CHACRA m3 12.02 25.00 300.50
PIEDRA CHANCADA DE 1/2" m3 767.70 50.00 38,385.00
PIEDRA CHANCADA DE 3/4" m3 0.12 50.00 6.00
PIEDRA GRANDE DE 8" m3 114.17 40.00 4,566.80
PIEDRA MEDIANA DE 3" m3 17.87 40.00 714.80
PIEDRA CHANCADA DE 3" m3 4.03 50.00 201.50
ARENA GRUESA m3 377.32 40.00 15,092.96
CONECTOR DE BRONCE PARA ELECTRODO DE 16MM Ø und 1.00 12.56 12.56
CABLE TW # 14 AWG 2.5 MM2 m 2.40 0.95 2.28
CABLE TW # 12 AWG - 4 MM2 m 4840.00 1.45 7,018.00
CABLE TW # 2 AWG - 35 MM2. m 10.00 22.00 220.00
CABLE TW N°14 AWG 2.5 MM2 m 1880.00 1.65 3,102.00
CABLE TW N°12 AWG 2.5 MM2 m 2790.00 1.55 4,324.50
CONDUCTOR DE COBRE ELECTROLITICO DE 07 HILOS m 70.00 7.66 536.20
INODORO TQUE. BAJO NORMAL BLANCO C/A. und 17.00 190.00 3,230.00
LAVATORIO 23"X17" P/GRIF.4" BLANCO C/A und 18.00 120.00 2,160.00
COSTO DIRECTO MODIFICADO
 

OBRA : “CREACION DEL COMPLEJO RECREACIONAL EN EL BARRIO SANTA CRUZ DEL DISTRITO DE ANTAUTA - PROVINCIA DE
MELGAR - DEPARTAMENTO DE PUNO”

URINARIO PICO BLANCO und 7.00 80.00 560.00


REGISTRO DE BRONCE DE 2" und 10.00 5.00 50.00
REGISTRO DE BRONCE DE 4" und 8.00 8.00 64.00
SUMIDERO CROMADO DE 2" und 19.00 5.00 95.00
CAUCHO SBR m2 673.20 75.00 50,490.00
DUCHAS CROMADAS CAB. GIRAT.,LLAVE MEZCL. pza 2.00 30.00 60.00
SISTEMA DE AUDIO INCL. ACCESORIOS E INSTALACION GLB 1.00 4,500.00 4,500.00
LAMPARA DE PARED MULTIUSOS GIRATORIA DE 350 GRADOS LED DE 2 und 4.00 38.00 152.00
SPOT LED PARA ADOSAR 12W COLOR NEGRO LUZ FRIA und 3.00 26.00 78.00
CRUCETA PARA CERAMICO DE PVC DE 3 MM pza 7.56 6.00 45.36
PARARRAYO PDC IONIFLASH MACH NG60 und 1.00 4,400.00 4,400.00
REFLECTOR MEDIANO pza 18.00 750.00 13,500.00
TABLERO ELECTRICO METAL - 8 CIRCUITOS und 5.00 250.00 1,250.00
TABLERO DE BASQUETBOL SEGUN DISEÑO GLB 2.00 15,000.00 30,000.00
TOMACORRIENTE DOBLE PLANO BAKELITA und 55.00 7.50 412.50
INTERRUPTOR TERMOMAGNETICO DE 2x30A und 12.00 55.00 660.00
INTERRUPTOR TERMOMAGNETICO 2 X 20A und 8.00 45.00 360.00
INTERRUPTOR TERMOMAGNETICO 2 X 50A und 2.00 65.00 130.00
INTERRUPTOR AUTOMATICO DE CAJA MOLDEADA TRIFASICO DE 125 A und 1.00 305.00 305.00
INTERRUPTOR TERMOMAGNETICO TRIFASICO DE 100 AMPERIOS und 1.00 380.00 380.00
INTERRUPTOR SIMPLE und 14.00 7.50 105.00
INTERRUPTOR DOBLE und 4.00 13.00 52.00
INTERRUPTOR TRIPLE und 3.00 18.00 54.00
CAJA OCTOGONAL GALV. LIVIANA 4"x4"x2 1/2 und 55.00 1.20 66.00
CAJA OCTOGONAL GALV. 4" X 2 1/8 " und 9.00 1.20 10.80
FLUORESCENTE CIRCULAR und 25.00 21.00 525.00
FLUORES. RECTO ISPE 1X40 W C/EQ + PANT und 6.00 50.00 300.00
LLAVE TERMOMAGNETICA 2 X 20 AMP pza 20.00 38.00 760.00
LLAVE TERMOMAGNETICA 2 X 50 AMP pza 1.00 98.00 98.00
LLAVE TERMOMAGNETICA 2 X 30 AMP pza 20.00 45.00 900.00
INTERRUPTOR MAGNETICO DE 50 AMPERIOS und 1.00 41.00 41.00
INTERRUPTOR DIFERENCIAL DE 32 AMPERIOS und 3.00 135.00 405.00
INTERRUPTOR DIFERENCIAL DE 20 AMPERIOS und 1.00 135.00 135.00
INTERRUPTOR TERMOMAGNETICO MONOFACICO DE 32 AMPERIOS und 5.00 145.00 725.00
INTERRUPTOR DIFERENCIAL MONOFACICO DE 40 AMPERIOS und 1.00 140.00 140.00
INTERRUPTOR TERMOMAGNETICO DE 2 X 16 AMPERIOS MONOFASICO und 5.00 41.00 205.00
TABLERO GENERAL DE DISTRIBUCION und 1.00 350.00 350.00
ASFALTO RC-250 gln 4.66 16.00 74.56
LADRILLO K.K. 18 HUECOS 9x12x24 CM und 14874.91 1.25 18,593.64
LADRILLO HUECO 30 X 25 X 15 CM und 454.82 3.60 1,637.35
CABLE DE COBRE TIPO NYY 3 X 10 MM2 m 65.00 22.00 1,430.00
CABLE NYY TRIFASICO 16MM m 25.00 41.00 1,025.00
CEMENTO PORTLAND TIPO I (42.5KG) BOL 13078.06 23.50 307,334.41
MAYOLICA DE COLOR m2 158.78 34.00 5,398.52
CERRADURA PARA PUERTA PRINCIPAL TRES GOLPES und 4.00 70.00 280.00
BISAGRA CAPUCHINA PLOMA 3 1/2" X 3 1/2" PAR 66.00 14.00 924.00
PIN DE ACERO A325 Ø 2" x 0.50M INC ACC. pza 36.00 50.00 1,800.00
CERRADURA PARA BAÑO TIPO CILINDRO und 20.00 48.00 960.00
PICAPORTE DE FIERRO und 52.00 5.00 260.00
CERRADURA PARA PUERTAEXTERIOR TRES GOLPES und 22.00 70.00 1,540.00
YESO EN BOLSAS DE 18 KG. BOL 16.85 9.00 151.65
TIZA kg 43.96 5.00 219.80
CINTA AISLANTE rll 29.97 3.50 104.90
COSTO DIRECTO MODIFICADO
 

OBRA : “CREACION DEL COMPLEJO RECREACIONAL EN EL BARRIO SANTA CRUZ DEL DISTRITO DE ANTAUTA - PROVINCIA DE
MELGAR - DEPARTAMENTO DE PUNO”

CINTA TEFLON rll 2.00 1.00 2.00


GRAPAS CROSBY DE Ø 5/8" und 6.00 35.00 210.00
TEMPLADOR und 404.00 5.00 2,020.00
TEMPLADOR DE ACERO m 3.00 40.15 120.45
CINTA TEFLON und 170.95 1.00 170.95
OCRE kg 15.60 12.00 187.20
ELECTRODOS (SOLDADURA CELLOCORD 1/8") kg 674.90 12.00 8,098.80
ELECTRODOS (SOLDADURA CELLOCORD 3/16") kg 1369.51 10.00 13,695.10
ARCOS PARA FULBITO und 2.00 500.00 1,000.00
ACCESORIOS DIVERSOS PARA INSTALACION DE VIDRIOS und 645.83 5.00 3,229.15
IMPRIMANTE ACRILICO gln 43.09 30.00 1,292.70
YESO DE 28 Kg BOL 80.92 5.00 404.60
CABLE DE ACERO ALEACION ALUMINIO DE 16MM2 m 60.00 3.12 187.20
VARILLA DE COBRE DE 1/2" x 2.40m und 2.00 180.00 360.00
PEGAMEN.EPOX. POLIEPOX ENDUR.GEL CHEMA gln 165.00 79.00 13,035.00
PASTA MURAL gln 138.34 28.00 3,873.52
RODOPLAST PARA BORDE DE MAYOLICAS m 272.20 5.00 1,361.00
PORCELANA DE COLOR kg 30.24 6.00 181.44
PEGAMENTO PARA PVC AGUA FORDUIT gln 1.34 45.00 60.30
PEGAMENTO PARA LOSETAS Y CERAMICAS und 45.37 20.00 907.40
SILICONA und 0.08 10.00 0.80
PEGAMENTO PARA PVC AGUA 1 GLN gln 15.90 45.00 715.50
PEGAMENTO PLASTICO P/PVC gln 42.50 75.30 3,200.25
SOLDADURA CELLOCORD P 3/16" kg 10.21 7.50 76.58
CINTA AISLANTE NEGRO 3/4 X 18 METROS - 3M und 0.32 4.40 1.41
LETRAS EN ALTO RELIEVE SEGUN DISEÑO T-1 pza 43.00 500.00 21,500.00
LETRAS EN ALTO RELIEVE SEGUN DISEÑO T-2 pza 32.00 380.00 12,160.00
LOGO EN ALTO RELIEVE SEGUN DISEÑO pza 1.00 950.00 950.00
SIKAFLEX ADHESIVO ELASTOMERICO DE JUNTAS und 9.52 5.24 49.88
IMPRIMANTE gln 468.20 24.00 11,236.80
BALON DE BASQUET und 4.00 50.00 200.00
BALON DE VOLEY und 4.00 50.00 200.00
BALON DE FULBITO und 4.00 70.00 280.00
LIJA und 1396.38 2.00 2,792.76
CAJA PARA VALVULA DE 0.30x0.20 M INC. TAPA DE FºFº pza 2.00 20.00 40.00
FLETE TRANSPORTE LOCAL kg 23.03 0.15 3.45
HORMIGON m3 672.37 45.00 30,256.65
ENERGIA ELECTRICA GLB 1.00 3,500.00 3,500.00
AGUA GLB 1.00 1,000.00 1,000.00
TANQUE ELEVADO DE POLIETILENO DE 2000LT INC/ACCESORIOS und 2.00 870.00 1,740.00
TANQUE CISTERNA DE AGUA DE 1100 LITROS INC/ACCESORIOS und 1.00 700.00 700.00
TABLERO ELECTRONICO LED TIPO MARCADOR GLB 1.00 15,366.41 15,366.41
EMPALME A RED MATRIZ DESAGUE est 2.00 500.00 1,000.00
EMPALME A RED MATRIZ AGUA est 2.00 500.00 1,000.00
CARTEL DE OBRA INC.INSTALACION Y TRANSP GLB 1.00 1,000.00 1,000.00
MATERIALES ELECTRICOS 4 GLB 1.00 1,100.00 1,100.00
CERAMICO ANTIDESLIZANTE DE COLOR m2 167.28 32.00 5,352.96
MADERA NACIONAL P/ENCOFRADO-CARP p2 33931.49 9.30 315,562.86
MESA RECTANGULAR SEGUN DISEÑO pza 2.00 280.00 560.00
REGLA DE MADERA p2 133.09 3.00 399.27
REGLA DE ALUMINIO und 92.07 54.00 4,971.78
ARBOL ENANO PARA INTERIOR und 12.00 50.00 600.00
CERCO PERIMETRICO GLB 1.00 4,000.00 4,000.00
COSTO DIRECTO MODIFICADO
 

OBRA : “CREACION DEL COMPLEJO RECREACIONAL EN EL BARRIO SANTA CRUZ DEL DISTRITO DE ANTAUTA - PROVINCIA DE
MELGAR - DEPARTAMENTO DE PUNO”

ESTACA p2 31.37 3.00 94.11


ESTACA DE MADERA p2 282.29 3.00 846.87
ANDAMIO METALICO TIPO ACROW pza 14.39 380.00 5,468.20
SILLAS UNIPERSONALES SEGUN DISEÑO pza 12.00 95.00 1,140.00
ESTACA DE MADERA p2 2.50 2.80 7.00
ESTACION TOTAL INCLUYE ACCESORIOS und 0.95 18,000.00 17,100.00
PUERTA DE (2.50x 2.50) und 2.00 1,900.00 3,800.00
PUERTA DE (3.60x 2.50) und 4.00 1,400.00 5,600.00
PUERTA DE (2.00 x 0.60) und 5.00 800.00 4,000.00
PUERTA DE (2.60x 0.95) und 3.00 1,000.00 3,000.00
PUERTA DE (2.10x 0.95) und 2.00 900.00 1,800.00
PUERTA DE (1.00x 2.30) und 1.00 870.00 870.00
PUERTA DE (1.00x 2.60) und 1.00 900.00 900.00
LIMPIEZA PERMANENTE GLB 1.00 24,000.00 24,000.00
LIMPIEZA FINAL DE OBRA GLB 1.00 18,423.48 18,423.48
ELECTROBOMBA 1 HP ALTA PRESION 1" x 1" und 2.00 850.00 1,700.00
TRANSPORTE DE MATERIALES GLB 1.00 42,000.00 42,000.00
PLANCHA METALICA 1/32" 1.20 X 2.40 M pln 38.07 25.00 951.75
MELAMINE DE 15MM pln 53.62 455.00 24,397.10
CAJA DE DESAGUE DE 12"X24" und 5.00 10.00 50.00
TAPA C/MARCO FºFº DE DESAGUE 12" X 24" pza 5.00 10.00 50.00
TAPA C/MARCO FºFº DE DESAGUE 10" X 20" pza 2.00 10.00 20.00
MARCO DE ALUMINIO P/VENTANA SEGUN DISEÑO p2 2152.78 38.00 81,805.64
ANGULO 2"x2"x1/4" x6m. pza 201.73 205.00 41,354.65
ANGULO 3"x3"x1/2" x6m. pza 372.49 285.00 106,159.65
ANGULO 2"x2"x3/8" x6m. pza 388.99 50.00 19,449.50
PLATINA 2" X 3/16" X 6m pza 38.81 125.00 4,851.25
ESTRUCTURA METALICA PARA PARARRAYOS DE 30M. und 1.00 4,700.00 4,700.00
PUERTA METALICA ENRROLLABLE DE 1.80X2.50M und 6.00 1,900.00 11,400.00
GRASS NATURAL kg 0.60 20.00 12.00
THINER gln 107.71 25.00 2,692.75
PINTURA LATEX gln 53.16 70.00 3,721.20
PINTURA LATEX PARA EXTERIORES gln 130.35 75.00 9,776.25
PINTURA LATEX PARA INTERIORES gln 130.76 75.00 9,807.00
PINTURA ANTICORROSIVA gln 86.17 35.00 3,015.95
PINTURA ESMALTE SINTETICO gln 86.17 35.00 3,015.95
PINTURA DE POLIUTERANO gln 165.00 285.00 47,025.00
ARBUSTOS und 96.12 10.00 961.20
PLANCHA DE ACERO (1.22 x 2.40 m, e=1/2") - A36 pln 19.80 650.00 12,870.00
PLANCHA DE ACERO (1.22 x 2.40 m, e=5/8") - A36 pln 19.80 950.00 18,810.00
PLANCHA PARA COBERTURA 0.83 x 5.00 M pln 406.59 295.00 119,944.05
PLANCHA DE POLICARBONATO PLANA ALVEOLAR E=5 MM INC. ACC/CO m2 513.66 190.00 97,595.40
POSTE DE VOLEY / INCLUYE NET CON CASTILLO DE ARBITRAJE und 1.00 1,500.00 1,500.00
TUBO FO.GALV.ST.ISO-I 2" m 19.17 180.00 3,450.60
TUBO FO.GALV.ST.ISO-I 1" m 191.70 120.00 23,004.00
TUBO CUADRADO ELECTROSOLDADO DE 2"x2"x1.5 MM - 6.00 M. pza 75.07 100.00 7,507.00
TUBO FIERRO GALVANIZADO DE 1 1/2" m 9.30 42.00 390.60
TUBO FIERRO GALVANIZADO 2" m 17.05 47.00 801.35
MARCO Y TAPA FO. GO. P/MEDIDOR 1/2"-3/4" und 2.00 25.00 50.00
ESCALERA GATO TUB F.GVZDO.C/PARANTES DE 1" X PELDAÑOS DE 3/4", und 1.00 4,200.00 4,200.00
TUB. PVC SAP PRESION P/AGUA C-10 R. 1/2" m 206.25 2.50 515.63
TUB. PVC SAP PRESION P/AGUA C-10 R. 3/4" m 106.50 3.30 351.45
TUB. PVC SAP PRESION P/AGUA C-10 R. 1" m 5.25 3.70 19.43
COSTO DIRECTO MODIFICADO
 

OBRA : “CREACION DEL COMPLEJO RECREACIONAL EN EL BARRIO SANTA CRUZ DEL DISTRITO DE ANTAUTA - PROVINCIA DE
MELGAR - DEPARTAMENTO DE PUNO”

UNION UNIVERSAL PVC SAP DE 1/2" und 4.00 4.00 16.00


UNION UNIVERSAL PVC SAP DE 1" und 6.00 6.00 36.00
CODO DE 90°C/R PVC SAP P/AGUA DE 1/2" und 90.00 1.50 135.00
CODO DE 90°C/R PVC SAP P/AGUA DE 3/4" und 45.00 2.50 112.50
TUB. PVC SAP P/INST. ELECT. DE 1" m 10.00 7.50 75.00
CURVA PESADO PVC SAP P/INST. ELECT. 1" und 2.00 0.50 1.00
TUB. PVC SAL P/DESAGUE DE 2" m 76.00 3.50 266.00
TUB. PVC SAL P/DESAGUE DE 4" m 38.00 3.80 144.40
TEE PVC SAP ROSCADO 1/2" pza 45.00 1.50 67.50
TEE PVC SAP ROSCADO 3/4" pza 22.50 2.50 56.25
TEE PVC SAP ROSCADO 1" und 4.00 1.70 6.80
CODO DE 90 PVC SAL DE 2" und 57.00 3.00 171.00
RAMAL TEE DOBLE C/REDUC PVC SAL 4" A 2" und 19.00 7.50 142.50
TEE SANITARIA SIMPLE PVC SAL DE 4" und 8.00 6.00 48.00
TEE SANITARIA SIMP C/REDUC PVC SAL 4"A2" und 10.00 6.00 60.00
TUB. PVC SEL P/INST. ELECT. DE 5/8" x 3m und 594.00 3.50 2,079.00
CURVA LIVIANO PVC SEL P/INST. ELECT 3/4" und 65.01 0.50 32.51
CURVA LIVIANO PVC SEL P/INST. ELECT 1" und 8.35 1.20 10.02
NIPLE D/PLASTICO P/AGUA C/ROSCA 1/2"X 2" pza 4.00 2.50 10.00
NIPLE PVC SAP 1"X1" und 8.00 1.70 13.60
YEE PVC SAL 4" und 47.50 7.80 370.50
CODO PVC SAP 3/4"X90° und 16.00 1.70 27.20
TUBO PVC SAL 4" m 64.05 6.50 416.33
TUBO PVC SAL 6" m 18.90 8.00 151.20
TUBERIA PVC SEL 3/4" m 842.63 1.20 1,011.16
TUBO PVC SAL 2" m 58.40 3.00 175.20
TUBERIA PVC SAP C/R C-10 1"X5M m 7.77 12.00 93.24
TUBERIA PVC SAP 4" m 239.40 3.00 718.20
TUBERIA PVC SEL 1" m 157.50 2.10 330.75
TRAMPA PVC SAL 2" pza 19.00 6.50 123.50
CURVAS 90° PARA TUBERIA PVC DE 32MM Ø und 8.00 4.55 36.40
CODO PVC SEL 3/4" und 1430.00 1.00 1,430.00
TUBO PVC SEL (E/C) 3/4" X 3.00 M. pza 137.80 4.50 620.10
CURVAS PVC SEL 3/4" pza 6.00 0.60 3.60
VALVULA COMPUERTA DE BRONCE DE 1/2" und 2.00 19.50 39.00
VALVULA CHECK DE BRONCE DE 1/2" und 2.00 70.00 140.00
LLAVE DE PASO PVC 1/2" und 16.00 18.00 288.00
LLAVE DE PASO PVC 3/4" und 5.00 25.00 125.00
VALVULA ESFERICA DE 3/4" und 2.00 47.00 94.00
VIDRIO REFLEJANTE DE 8MM p2 2260.42 12.00 27,125.04
VIDRIO TRANSLUCIDO DE 8MM INCL. ACCESORIOS p2 1850.84 11.50 21,284.66
ESPEJO DE 50X60 und 4.00 68.50 274.00
CAJA DE DESAGUE SIN FONDO DE 12X24" und 5.00 10.00 50.00
MARCO Y TAPA DE PLANCHA ESTRIADA und 2.00 45.00 90.00
VESTUARIO GLB 1.00 3,500.00 3,500.00
PLAN PARA LA VIGILANCIA, PREVENCIÓN Y CONTROL DEL COVID – 19 GLB 1.00 30,989.70 30,989.70
DESAGUE PARA LA CONSTRUCCION GLB 1.00 1,000.00 1,000.00
HERRAMIENTAS MANUALES %MO 1.00 1,000.00 26,706.38
COSTO DIRECTO MODIFICADO
 

OBRA : “CREACION DEL COMPLEJO RECREACIONAL EN EL BARRIO SANTA CRUZ DEL DISTRITO DE ANTAUTA - PROVINCIA DE
MELGAR - DEPARTAMENTO DE PUNO”

3. SERVICIOS S/. 36,429.43

Descripción Und Cantidad Precio Parcial

A.- EQUIPOS DIVERSOS


MIRA TOPOGRAFICA HE 140.50 1.00 140.50
EQUIPO DE BOMBEO P/PRUEBAS EN TUB. GLB 2.00 150.00 300.00
COMPRESORA hm 28.77 7.50 215.78
COMPRESORA 250 P.C.M. hm 146.76 15.00 2,201.40
MARTILLO NEUMATICO 24 KG C/CINCEL-ACCS hm 293.52 25.00 7,338.00
RETROEXCAVADORA CON MARTILLO NEUMATICO hm 21.12 410.00 8,659.20
MOTOSOLDADORA DE 250 AMP. hm 1929.15 7.50 14,468.63
NIVEL HE 280.79 7.50 2,105.93
OFICINA GLB 1.00 1,000.00 1,000.00
GASTOS GENERALES MODIFICADO
 

OBRA : “CREACION DEL COMPLEJO RECREACIONAL EN EL BARRIO SANTA CRUZ DEL DISTRITO DE ANTAUTA - PROVINCIA DE
MELGAR - DEPARTAMENTO DE PUNO”

GASTOS GENERALES = S/. 248,661.20

2.1 DIRECCIÓN TÉCNICA Y ADMINISTRATIVA S/. 225,900.00


Descripción Cantidad Coef. de Part. N° de Meses Costo Mensual Parcial (S/.)
PERSONAL 225,900.00
A.- PERSONAL PROFESIONAL TECNICO
ING. RESIDENTE DE OBRA 1 1.00 18.00 3,500.00 63,000.00
ASISTENTE TECNICO I 1 1.00 18.00 1,800.00 32,400.00
ASISTENTE ADMINISTRATIVO 1 1.00 18.00 1,800.00 32,400.00
B.- PERSONAL ADMINISTRATIVO
MAESTRO DE OBRA 1 1.00 18.00 2,150.00 38,700.00
ALMACENERO 1 1.00 18.00 1,500.00 27,000.00
GUARDIAN 1 1.20 18.00 1,500.00 32,400.00

2.2 GASTOS DE SEGURIDAD, PRIMEROS AUXILIOS Y SALUD S/. 5,242.00


Descripción Und Cantidad Precio Parcial
A.- EQUIPO DE PROTECCIÓN Y SEGURIDAD AL PERSONAL
PERSONAL TECNICO
CASCOS DE PROTECCION P/ING. UNIDAD 10.00 36.00 360.00
CHALECOS DE SEGURIDAD UNIDAD 6.00 89.00 534.00
ZAPATOS DE ZEGURIDAD PAR 6.00 430.00 2,580.00
CASACAS DE SEGURIDAD UNIDAD 6.00 240.00 1,440.00
LENTES DE SEGURIDAD UNIDAD 6.00 38.00 228.00
B.- PRIMEROS AUXILIOS
BOTIQUIN DE PRIMEROS AUXILIOS GLB 1.00 100.00 100.00

2.3 GASTOS DE MATERIALES Y OTROS S/. 5,369.20


Descripción Und Cantidad Precio Parcial
A.- MATERIALES DE OFICINA (UTILES DE ESCRITORIO)
PAPEL BOND 75 G TAMAÑO A4 COLOR BLANCO EMPAQUE 20.00 14.00 280.00
CUADERNO CUADRICULADO TAMAÑO A4 X 100 HOJAS UNIDAD 10.00 8.00 80.00
CUADERNO CUADRICULADO TAMAÑO A4 X 100 HOJAS UNIDAD 48.00 0.60 28.80
ARCHIVADOR DE CARTON CON PALANCA LOMO ANCHO TAMAÑO A4 UNIDAD 30.00 10.00 300.00
VINIFAN TAMAÑO OFICIO UNIDAD 12.00 10.00 120.00
FOLDER A4 MANILA CON FASTENER UNIDAD 100.00 0.60 60.00
PLUMON RESALTADOR PUNTA FINA COLOR ANARANJADO UNIDAD 10.00 4.50 45.00
CORRECTOR LIQUIDO TIPO LAPICERO DOCENA 4.00 48.00 192.00
PAPEL LUSTRE 70cm X 50cm COLOR ANARANJADO UNIDAD 20.00 0.56 11.20
TONER DE IMPRESIÓN PARA HP COD. REF. 126A CE312A AMARILLO UNIDAD 1.00 300.00 300.00
PERFORADOR ARTESCO GRANDE UNIDAD 1.00 135.00 135.00
ENGRAPADOR DE METALMEDIANO UNIDAD 1.00 20.00 20.00
PAPEL BOND 75g TAMAÑO A4 COLOR CELESTE MILLAR 8.00 37.50 300.00
TONER DE IMPRESIÓN PARA HP COD. REF. 12A Q2612A NEGRO UNIDAD 1.00 300.00 300.00
PAPEL BOND PAQUETE 20.00 14.00 280.00
PAPEL BOND 75 g TAMAÑO A4 COLOR VERDE MILLAR 8.00 46.00 368.00
GASTOS GENERALES MODIFICADO
 

OBRA : “CREACION DEL COMPLEJO RECREACIONAL EN EL BARRIO SANTA CRUZ DEL DISTRITO DE ANTAUTA - PROVINCIA DE
MELGAR - DEPARTAMENTO DE PUNO”

BOLIGRAFO (LAPICERO) DE TINTA SECA PUNTA FINA COLOR AZUL, RO UNIDAD 50.00 3.00 150.00
ARCHIVADOR DE CARTON PLASTIFICADO CON PALANCA LOMO ANCHO UNIDAD 30.00 8.80 264.00
ARCHIVADOR DE CARTON PLASTIFICADO CON PALANCA LOMO DELGA UNIDAD 10.00 12.00 120.00
CINTA DE EMBALAJE UNIDAD 10.00 5.00 50.00
CORRECTOR LIQUIDO TIPO LAPICERO UNIDAD 15.00 2.50 37.50
PLUMON RESALTADOR PUNTA FINA COLOR AMARILLO UNIDAD 15.00 3.50 52.50
VINIFAN TAMAÑO OFICIO UNIDAD 12.00 9.60 115.20
PAPEL LUSTRE PLIEGO 60.00 0.50 30.00
TONER DE IMPRESIÓN PARA HP COD. REF. 12A Q2612A NEGRO UNIDAD 1.00 220.00 220.00
POST IT 2 X 2 MINICUBO NEON X 400H PAQUETE 5.00 8.50 42.50
MICAS PORTAPAPELES A4 (PQTE X 10 UNID) PAQUETE 20.00 10.00 200.00
GRAPAS 26/6 X 5000 CAJA 2.00 5.00 10.00
GOMA EN BARRA X 40 g APROX UNIDAD 5.00 5.50 27.50
LAPIZ DE CARBON N° 2B UNIDAD 15.00 1.00 15.00
CLIPS MARIPOSA CAJA 4.00 7.50 30.00
CLIPS JUMBO WINGO (CAX100) CAJA 3.00 5.00 15.00
FOLDER MANILA TAMAÑO OFICIO EMPAQUE X 25 4.00 12.50 50.00
CARTUCHO DE TINTA PARA IMPRESORA HP DESIGNGET T120 JUEGO 2.00 560.00 1,120.00

2.4 SERVICIOS S/. 12,150.00


Descripción Und Cantidad Precio Parcial
A.- SERVICIOS DE TERCEROS
LEGALIZACION DE CUADERNO DE OBRA UNIDAD 10.00 15.00 150.00
ALQUILER DE CAMIONETA MES 2.00 6,000.00 12,000.00
ANALISIS DE GASTOS DE SUPERVISION MODIFICADO
 

OBRA : “CREACION DEL COMPLEJO RECREACIONAL EN EL BARRIO SANTA CRUZ DEL DISTRITO DE ANTAUTA - PROVINCIA DE
MELGAR - DEPARTAMENTO DE PUNO”

GASTOS DE SUPERVISIÓN = S/. 69,775.45

1. GASTOS DE SUPERVISIÓN S/. 69,775.45

1.1 PERSONAL DE SUPERVISIÓN S/. 67,500.00


Descripción Cantidad Coef. de Part. N° de Meses Costo Mensual Parcial (S/.)
PERSONAL 63,000.00
A.- PERSONAL PROFESIONAL TECNICO
ING. SUPERVISOR DE OBRA 1.00 1.00 18.00 3,500.00 63,000.00
GASTOS VARIABLES Y OCASIONALES 4,500.00
A.- PERSONAL PROFESIONAL TECNICO
ING. SUPERVISOR DE OBRA 1 1.00 18.00 250.00 4,500.00

1.2 GASTOS DE SEGURIDAD, PRIMEROS AUXILIOS Y SALUD S/. 425.00


Descripción Und Cantidad Precio Parcial
A.- EQUIPO DE PROTECCIÓN Y SEGURIDAD AL PERSONAL
PERSONAL TECNICO
CASCOS DE PROTECCION P/ING. UNIDAD 1.00 35.00 35.00
CHALECOS DE SEGURIDAD UNIDAD 1.00 40.00 40.00
ZAPATOS DE ZEGURIDAD UNIDAD 1.00 350.00 350.00

1.3 GASTOS DE MATERIALES Y OTROS S/. 1,850.45


Descripción Und Cantidad Precio Parcial
A.- MATERIALES DE OFICINA (UTILES DE ESCRITORIO)
PAPEL BOND A-4 COLOR BLANCO 75 GR. MILLAR 1.50 25.00 37.50
CUADERNO CUADRICULADO DE 100 HJS T/OFICIO UNIDAD 2.00 4.50 9.00
FOLDER MANILA UNIDAD 10.00 0.50 5.00
SOBRE MANILA UNIDAD 10.00 0.50 5.00
RESALTADOR UNIDAD 1.00 2.50 2.50
CORRECTOR UNIDAD 1.00 2.00 2.00
LAPICEROS TINTA SECA (A/N) UNIDAD 3.00 0.50 1.50
LAPICEROS TINTA LIQUIDA (A/N) UNIDAD 3.00 2.00 6.00
IMPREVISTOS GLOBAL 1.00 1,781.95 1,781.95
ANÁLISIS DE GASTOS DE LIQUIDACÍON
 

OBRA : “CREACION DEL COMPLEJO RECREACIONAL EN EL BARRIO SANTA CRUZ DEL DISTRITO DE ANTAUTA - PROVINCIA DE
MELGAR - DEPARTAMENTO DE PUNO”

GASTOS DE LIQUIDACIÓN= S/. 16,287.86

1. GASTOS DE LIQUIDACIÓN S/. 16,287.86

1.1 GASTOS DE LIQUIDACIÓN S/. 14,263.60


Descripción Cantidad Coef. de Part. N° de Meses Costo Mensual Parcial (S/.)
PERSONAL 12,000.00
A.- PERSONAL PROFESIONAL TECNICO
INGENIERO LIQUIDADOR 1 1.00 2.00 3,500.00 7,000.00
CONTADOR PUBLICO 1 1.00 2.00 2,500.00 5,000.00
OBLICACIONES DEL EMPLEADOR 1,263.60
A.- PERSONAL PROFESIONAL TECNICO
INGENIERO LIQUIDADOR 1 1.00 2.00 368.55 737.10
CONTADOR PUBLICO 1 1.00 2.00 263.25 526.50
GASTOS VARIABLES Y OCASIONALES 1,000.00
A.- PERSONAL PROFESIONAL TECNICO
INGENIERO LIQUIDADOR 1 1.00 2.00 291.67 583.33
CONTADOR PUBLICO 1 1.00 2.00 208.33 416.67

1.2 GASTOS DE MATERIALES Y OTROS S/. 2,024.26


Descripción Und Cantidad Precio Parcial
A.- MATERIALES DE OFICINA (UTILES DE ESCRITORIO)
PAPEL BOND A-4 DE 75 GR. MILLAR 3.00 25.00 75.00
ARCHIVADORES DE PALANCA LOMO ANCHO UNIDAD 3.00 8.00 24.00
FOTOCOPIADO GLOBAL 1.00 600.00 600.00
PLOTEO DE PLANOS GLOBAL 1.00 800.00 800.00
IMPREVISTOS GLOBAL 1.00 525.26 525.26
ANÁLISIS DE EXPEDIENTE TÉCNICO
 

OBRA : “CREACION DEL COMPLEJO RECREACIONAL EN EL BARRIO SANTA CRUZ DEL DISTRITO DE ANTAUTA - PROVINCIA DE
MELGAR - DEPARTAMENTO DE PUNO”

1. GASTOS POR LA ELABORACIÓN DEL EXPEDIENTE TÉCNICO S/. 24,078.21

1.1 SERVICIOS DE TERCEROS S/. 23,300.00


Descripción Und Cantidad Precio Parcial
A.- PERSONAL PROFESIONAL TECNICO
PROYECTISTA RESPONSABLE MES 2.00 3,000.00 6,000.00
ARQUITECTO MES 2.00 2,700.00 5,400.00
ING. CIVIL MES 2.00 2,700.00 5,400.00
ING. ELECTRISISTA MES 0.50 2,500.00 1,250.00
TOPOGRAFO MES 0.50 2,000.00 1,000.00
ESTUDIOS DE SUELO GLB 1.00 2,000.00 2,000.00
CADISTA GLB 1.50 1,500.00 2,250.00

1.2 GASTOS DE MATERIALES Y OTROS S/. 778.21


Descripción Und Cantidad Precio Parcial
A.- MATERIALES DE OFICINA
IMPREVISTOS GLB 1.00 778.21 778.21