N° de MEDIDAS
ITEM UND PARCIAL TOTAL
veces Largo Ancho Alto
07.00.00 BLOCK "G"
07.01.00 MOVIMIENTO DE TIERRAS
07.01.01 EXCAVACIÓN DE ZANJAS PARA ZAPATAS M3 63.84
Z-1 22.00 1.20 1.20 1.75 55.44
Z-7 4.00 1.50 1.20 1.75 8.40
Z-6 SE CONSIDERA EN BLOQUE F
CURADO M2 36.48
Z-1 22.00 1.20 1.20 31.68
Z-7 4.00 1.50 1.20 4.80
Z-6 SE CONSIDERA EN BLOQUE F
07.01.02 EXCAVACIÓN DE ZANJAS PARA CIMIENTOS M3 55.72
EJE "G" / EJE 1-4 (CC-1) 1.00 6.85 0.50 1.15 3.94
EJE "F" / EJE 1-4 (CC-1) 1.00 7.94 0.50 1.15 4.57
MURETE EJE "F" / EJE 1-4 (CC-1) 2.00 0.90 0.50 1.15 1.04
EJE "E" / EJE 1-4 (CC-1) 1.00 6.66 0.50 1.15 3.83
MURETE EJE "E" / EJE 1-4 (CC-1) 2.00 0.90 0.50 1.15 1.04
EJE "D" / EJE 1-4 (CC-1) 1.00 6.66 0.50 1.15 3.83
MURETE EJE "D" / EJE 1-4 (CC-1) 2.00 0.90 0.50 1.15 1.04
EJE "C" / EJE 1-4 (CC-1) 1.00 6.76 0.50 1.15 3.89
MURETE EJE "C" / EJE 1-4 (CC-1) 2.00 0.90 0.50 1.15 1.04
EJE "B" / EJE 1-4 (CC-1) 1.00 2.65 0.50 1.15 1.52
EJE "A" / EJE 1-5 (CC-1) 1.00 2.65 0.50 1.15 1.52
EJE "1" / EJE 1-5 (CC-1) 1.00 8.50 0.50 1.15 4.89
EJE "2" / EJE 1-5 (CC-1) 1.00 8.50 0.50 1.15 4.89
EJE "3" / EJE 1-5 (CC-1) 1.00 11.90 0.50 1.15 6.84
EJE "4" / EJE 1-5 (CC-1) 1.00 13.65 0.50 1.15 7.85
EJE "G" / EJE 3-4 (CC-1) 3.00 0.73 0.50 1.15 1.26
EJE "G" / EJE 3-4 (CC-1) 3.00 0.75 0.50 1.15 1.29
CIMENTACIÓN DE SARDINEL PARA DUCHAS 3.00 0.85 0.50 1.15 1.47
EJE "G" / EJE 1-4 (CC-1) 1.00 6.85 0.35 0.30 0.72
EJE "F" / EJE 1-4 (CC-1) 1.00 7.94 0.35 0.30 0.83
MURETE EJE "F" / EJE 1-4 (CC-1) 2.00 0.90 0.35 0.30 0.19
EJE "E" / EJE 1-4 (CC-1) 1.00 6.66 0.35 0.30 0.70
MURETE EJE "E" / EJE 1-4 (CC-1) 2.00 0.90 0.35 0.30 0.19
EJE "D" / EJE 1-4 (CC-1) 1.00 6.66 0.35 0.30 0.70
MURETE EJE "D" / EJE 1-4 (CC-1) 2.00 0.90 0.35 0.30 0.19
EJE "C" / EJE 1-4 (CC-1) 1.00 6.76 0.35 0.30 0.71
MURETE EJE "C" / EJE 1-4 (CC-1) 2.00 0.90 0.35 0.30 0.19
EJE "B" / EJE 1-4 (CC-1) 1.00 2.65 0.35 0.30 0.28
EJE "A" / EJE 1-5 (CC-1) 1.00 2.65 0.35 0.30 0.28
EJE "1" / EJE 1-5 (CC-1) 1.00 8.50 0.35 0.30 0.89
EJE "2" / EJE 1-5 (CC-1) 1.00 8.50 0.35 0.30 0.89
EJE "3" / EJE 1-5 (CC-1) 1.00 11.90 0.35 0.30 1.25
EJE "4" / EJE 1-5 (CC-1) 1.00 13.65 0.35 0.30 1.43
EJE "G" / EJE 3-4 (CC-1) 3.00 0.73 0.35 0.30 0.23
EJE "G" / EJE 3-4 (CC-1) 3.00 0.75 0.35 0.30 0.24
CIMENTACIÓN DE SARDINEL PARA DUCHAS 3.00 0.85 0.35 0.30 0.27
07.01.04 ACARREO DE MATERIAL EXCEDENTE HASTA DIST.= M3 1.00 VOL= 119.56 1.20 143.48 98.95
30m
1.00 VOL= -44.53 -44.53
07.01.05 ELIMINACIÓN DE MATERIAL EXCEDENTE M3 1.00 VOL= 119.56 1.20 143.48 98.95
C/MAQUINARIA
1.00 VOL= -44.53 -44.53
EJE "G" / EJE 1-4 (CC-1) 1.00 9.70 0.50 0.70 3.40
EJE "F" / EJE 1-4 (CC-1) 1.00 9.43 0.50 0.70 3.30
EJE "E" / EJE 1-4 (CC-1) 1.00 8.20 0.50 0.70 2.87
EJE "D" / EJE 1-4 (CC-1) 1.00 8.20 0.50 0.70 2.87
EJE "C" / EJE 1-4 (CC-1) 1.00 8.35 0.50 0.70 2.92
EJE "B" / EJE 1-4 (CC-1) 1.00 3.45 0.50 0.70 1.21
EJE "A" / EJE 1-5 (CC-1) 1.00 3.45 0.50 0.70 1.21
EJE "1" / EJE 1-5 (CC-1) 1.00 12.80 0.50 0.70 4.48
EJE "2" / EJE 1-5 (CC-1) 1.00 12.80 0.50 0.70 4.48
EJE "3" / EJE 1-5 (CC-1) 1.00 16.35 0.50 0.70 5.72
EJE "4" / EJE 1-5 (CC-1) 1.00 16.35 0.50 0.70 5.72
EJE "G" / EJE 3-4 (CC-1) 3.00 1.25 0.50 0.70 1.31
EJE "G" / EJE 3-4 (CC-1) 3.00 0.25 0.50 0.70 0.26
07.03.01 ZAPATAS
07.03.01.01 CONCRETO F'C=210kg/cm2 C/CEMENTO TIPO V M3 18.24
Z-1 22.00 1.20 1.20 0.50 15.84
Z-7 4.00 1.50 1.20 0.50 2.40
EJE "G" / EJE 1-4 (CC-1) 1.00 8.58 0.15 0.65 0.84
EJE "F" / EJE 1-4 (CC-1) 1.00 9.46 0.15 0.65 0.92
EJE "E" / EJE 1-4 (CC-1) 1.00 8.26 0.15 0.65 0.81
EJE "D" / EJE 1-4 (CC-1) 1.00 8.26 0.15 0.65 0.81
EJE "C" / EJE 1-4 (CC-1) 1.00 8.36 0.15 0.65 0.82
EJE "B" / EJE 1-4 (CC-1) 1.00 3.60 0.15 0.65 0.35
MURETES DE CLOSET 8.00 0.65 0.15 0.65 0.51
EJE "1" / EJE 1-5 (CC-1) 1.00 12.80 0.15 0.65 1.25
EJE "2" / EJE 1-5 (CC-1) 1.00 9.60 0.15 0.65 0.94
EJE "3" / EJE 1-5 (CC-1) 1.00 12.45 0.15 0.65 1.21
EJE "4" / EJE 1-5 (CC-1) 1.00 16.96 0.15 0.65 1.65
EJE "G" / EJE 3-4 (CC-1) 3.00 1.2 0.15 0.65 0.35
EJE "G" / EJE 3-4 (CC-1) 3.00 0.20 0.15 0.65 0.06
SARDINEL 3.00 0.85 0.10 0.65 0.17
07.03.03 COLUMNAS
07.03.03.01 CONCRETO F'C=210kg/cm2 C/CEMENTO TIPO V M3 8.17
C-1 16.00 0.25 0.25 4.45 4.45
C-1 12.00 0.25 0.25 4.15 3.11
CA-1 5.00 0.25 0.14 3.45 0.60
FRISOS
EJE A 1.00 5.53 0.35 1.94
EJE C 1.00 3.90 0.35 1.37
EJE G 1.00 9.70 0.35 3.40
EJE 1 1.00 12.80 0.30 3.84
EJE 2 1.00 5.35 0.30 1.61
EJE 4 1.00 18.15 0.30 5.45
FONDO DE VIGA
INTERIOR DE VIGA
EJE C ENTRE 3-4 MURETES DE CLOSET 2.00 0.65 0.10 2.20 0.29
EJE D ENTRE 3-4 MURETES DE CLOSET 2.00 0.65 0.10 2.20 0.29
EJE E ENTRE 3-4 MURETES DE CLOSET 2.00 0.65 0.10 2.20 0.29
EJE F ENTRE 3-4 MURETES DE CLOSET 2.00 0.65 0.10 2.20 0.29
En columnetas de Arriostre
En Primer nivel
ACERO LONGITUDINAL Y ESTRIBOS
En columnas
ACERO LONGITUDINAL Y ESTRIBOS
5 de 3
"Mejoramiento de Infraestructura de la Institucion Educativa Americo Garibaldi Ghersi, Distrito Pacocha, Provincia Ilo, Region Moquegua"
2.4+2.4+2.4+2.4+2.35+2.35
long. Emp. 1/2"=0.45
En viguetas entre ejes A-G, ENTRE EJE 3-4
21.04 1 9 1/2 " - - 189.36 - - - 189.36 189.36
20.74 0.89 1 9 3/8 " - 4.49 - - - - 8.01 4.49
0.15 0.15
1.44 1 9 3/8 " - 7.26 - - - - 12.96 7.26
0.74 2.03 2 9 3/8 " - 20.46 - - - - 36.54 20.46
0.15 1.29 2.38 2 9 3/8 " - 23.99 - - - - 42.84 23.99
0.15 2.35 2 9 3/8 " - 23.69 - - - - 42.30 23.69
2.40 4 9 3/8 " - 48.38 - - - - 86.40 48.38
2.03+2.03+2.38+2.38+2.35+2.35+2.4+2.4+2.4+2.4
long. Emp. 1/2"=0.45
En viguetas entre ejes A-G, ENTRE EJE 2-3
21.04 1 6 1/2 " - - 126.24 - - - 126.24 126.24
20.74 0.89 1 6 3/8 " - 2.99 - - - - 5.34 2.99
0.15 0.15 1.44 1 6 3/8 " - 4.84 - - - - 8.64 4.84
0.74 2.03 2 6 3/8 " - 13.64 - - - - 24.36 13.64
0.15 1.20 2 6 3/8 " - 8.06 - - - - 14.40 8.06
1.29
0.15 2.35 2 6 3/8 " - 15.79 - - - - 28.20 15.79
1.25 4 6 3/8 " - 16.80 - - - - 30.00 16.80
2.03+2.03+1.2+1.2+2.35+2.35+1.25+1.25+1.25+1.25
long. Emp. 1/2"=0.45
ACERO TRANSVERSAL (TEMPERATURA)
Entre ejes A-D y 1´-3
Entre ejes D-F´ y 1´-2
6 de 3
"Mejoramiento de Infraestructura de la Institucion Educativa Americo Garibaldi Ghersi, Distrito Pacocha, Provincia Ilo, Region Moquegua"
0.60
SUMATORIA TOTAL DE METRADOS 117.38
7 de 3
METRADOS
N° de MEDIDAS
ITEM UND PARCIAL TOTAL
veces Largo Ancho Alto
07.00.00 BLOCK "G"
07.01.00 ALBAÑILERIA
07.01.01 MURO DE SOGA LADRILLO KING -KONG CON M2 291.53
CEMENTO-ARENA
EJE B ENTRE 3 -4 1.00 3.60 2.75 9.90
EJE C ENTRE 1-2 1.00 3.90 2.75 10.73
EJE C ENTRE 3-4 1.00 4.45 2.75 12.24
EJE D ENTRE 1-2 1.00 4.40 2.75 12.10
EJE D ENTRE 3-4 1.00 3.60 2.75 9.90
EJE E ENTRE 1-2 1.00 3.90 2.75 10.73
EJE E ENTRE 3-4 1.00 4.36 2.75 11.99
EJE F ENTRE 1-2 1.00 4.66 2.75 12.82
EJE F ENTRE 3-4 1.00 4.55 2.75 12.51
EJE G ENTRE 1-2 1.00 8.56 2.75 23.54
EJE G ENTRE 2-3 1.00 2.20 2.75 6.05
EJE G P-3 -1.00 1.14 2.50 -2.85
EJE G ENTRE 3-4 1.00 3.60 2.75 9.90
TARRAJEO EXTERIOR
EJE G 1.00 10.70 3.30 35.31
P-3 EJE G EJE 2-3 -1.00 1.14 2.50 -2.85
EJE C 1.00 4.40 3.30 14.52
EJE B 1.00 3.95 3.30 13.04
EJE 1 1.00 14.05 3.30 46.37
V-1 EJE 1 EJE C-G -4.00 1.50 1.50 -9.00
COLUMNA EXTERIOR -1.00 1.20 2.70 -3.24
EJE 4 1.00 22.30 3.30 73.59
P-3 EJE 4 EJE A-B -2.00 1.14 2.50 -5.70
V-1 EJE 4 EJE B-F -4.00 1.50 1.50 -9.00
V-2 EJE 4 EJE F-G -1.00 2.00 0.50 -1.00
PARAPETO SUPERIOR 1.00 PER= 61.80 0.15 9.27
TARRAJEO INTERIOR
VIGAS
FRISOS
EJE A 1.00 5.53 0.35 1.94
EJE C 1.00 3.90 0.35 1.37
EJE G 1.00 9.70 0.35 3.40
EJE 1 1.00 12.80 0.30 3.84
EJE 2 1.00 5.35 0.30 1.61
EJE 4 1.00 18.15 0.30 5.45
INTERIOR DE VIGA
07.03.00 CIELORRASOS
07.03.01 CIELO RASO INCL. VIGAS EMPOTRADAS CON M2
140.89
CEMENTO - ARENA 1:5
04.07.00 COBERTURA
04.07.01 LADRILLO PASTELERO ASENTADO C/BARRO M2 171.36
Á REA BLOQUE "F" 1.00 AREA= 177.96 177.96
-4.00 AREA= 1.65 -6.60
07.06.00 CARPINTERIA DE MADERA
07.06.01 PUERTA DE TABLERO REBAJADO/ INC. M2 5.70
INSTALACION
P3 2 1.14 2.50 5.70
07.08.00 CERRAJERIA
07.08.01 CERRADURA EXTERIOR CHAPA 2 GOLPES FORTE PZA 2.00
O SIMILAR
P3 2 2.00
07.10.00 PINTURA
07.10.01 PINTURA LATEX EN MUROS , COLUMNAS Y VIGAS M2 644.75
(ALBERGUE)
PINTADO DE MURO INTERIOR C/LATEX C/BASE 562.30
IMPRIMANTE IDENT PARTIDA 07.02.02
INTERIOR DE VIGA