SEMI SOTANO
Nivel -3.65 1.25 area 65.43 3.85 314.88
Nivel -2.45 1.25 area 61.43 2.45 188.13
ZAPATAS
Z-1 1.25 1.22 2.10 0.70 2.24
1.25 1.28 2.10 0.70 2.35
Z-2 1.25 5.10 0.90 0.70 4.02
1.25 1.30 0.90 0.70 1.02
Z-3 1.25 area 11.90 0.70 10.41
1.25 area 5.54 0.70 4.85
Z-4 1.25 2.40 2.00 0.70 4.20
Z-5 1.25 area 8.97 0.70 7.85
1.25 area 2.75 0.70 2.41
Z-6 1.25 2.50 2.40 0.80 6.00
Z-7 1.25 3.17 2.35 0.80 7.45
Z-8 1.25 2.50 1.25 0.70 2.73
Z-9 1.25 area 4.69 0.80 4.69
CIMIENTOS
TRANSVERSAL
EJE A , TRAMO 3-4 4.10 0.60 1.20 2.95
EJE A , TRAMO 4-5 4.25 0.80 1.20 4.08
EJE A , TRAMO 5-6 4.10 1.20 1.95 9.59
01.04.02 ZAPATAS
01.04.02.01 CONCRETO PARA ZAPATA ( 210Kg/cm2 ) M3 47.35
VC-1 (.30x.60 )
EJE D, TRAMO 5-6 1.00 4.79 0.30 0.60 0.86
V.C CORTE X1
EJE E , TRAMO 3-4 5.00 0.25 0.50 0.63
EJE E , TRAMO 4-5 4.00 0.25 0.50 0.50
EJE E , TRAMO 5-6 1.65 0.25 0.50 0.21
EJE E , TRAMO 5-6 2.43 0.25 0.50 0.30
01.04.04 COLUMNAS
01.04.04.01 COLUMNAS DE CONCRETO ( 210Kg/cm2 ) M3 37.06
01.04.05 VIGAS
01.04.05.01 CONCRETO DE VIGAS ( 210Kg/cm2 ) M3 47.42
VS-1 (.25x.40 ) 1.00 2.30 0.25 0.40 0.23
VS-2 (.25x.40 ) 1.00 3.85 0.25 0.40 0.39
VT-1 (.25x.40 ) 8.00 4.80 0.25 0.40 3.84
VT-2 (.30x.40 ) 8.00 4.80 0.30 0.40 4.61
VT-3 (.30x.40 ) 8.00 5.00 0.30 0.40 4.80
VT-4 (.30x.40 ) 8.00 4.00 0.30 0.40 3.84
VT-5 (.30x.40 ) 8.00 1.65 0.30 0.40 1.58
VT-6 (.30x.40 ) 8.00 1.50 0.30 0.40 1.44
VT-7 (.25x.40 ) 7.00 3.80 0.25 0.40 2.66
VT-8 (.25x.40 ) 7.00 4.20 0.25 0.40 2.94
VT-9 (.25x.40 ) 7.00 3.85 0.25 0.40 2.70
VT-10 (.25x.40 ) 8.00 4.40 0.20 0.40 2.82
VT-11 (.45x.40 ) 8.00 7.20 0.45 0.40 10.37
8.00 1.45 0.45 0.40 2.09
V-901 (.20x.50 ) 1.00 4.80 0.20 0.50 0.48
V-902 (.20x.50 ) 1.00 5.00 0.20 0.50 0.50
V-903 (0.25x0.40) 1.00 3.80 0.25 0.40 0.38
V-904 (.25x.40 ) 1.00 4.20 0.25 0.40 0.42
V-905 (.25x.40 ) 1.00 3.85 0.25 0.40 0.39
V-1001 (.25x.40 ) 1.00 4.80 0.25 0.40 0.48
V-1002 (.25x.40 ) 1.00 4.80 0.25 0.40 0.48
V-1002 (.25x.40 ) 1.00 1.70 0.25 0.40 0.17
1º PISO
CORTE 1 1.00 4.80 0.25 0.20 0.24
CORTE 1 2.00 4.65 0.25 0.20 0.47
CORTE 2 1.00 1.60 0.25 0.20 0.08
CORTE 3 1.00 3.50 0.20 0.40 0.28
CORTE 3 1.00 1.55 0.20 0.40 0.12
CORTE 3 1.00 3.40 0.20 0.40 0.27
CORTE 4 1.00 1.60 0.25 0.40 0.16
CORTE 4 1.00 2.40 0.25 0.40 0.24
CORTE 5 1.00 1.70 0.15 0.20 0.05
CORTE 6 1.00 1.10 0.25 0.40 0.11
CORTE 8 2.00 1.93 0.20 0.20 0.15
CORTE 8 1.00 2.89 0.20 0.20 0.12
CORTE 8 1.00 2.74 0.20 0.20 0.11
2º AL 7º PISO
CORTE 1 6.00 1.00 4.80 0.25 0.20 1.44
CORTE 1 6.00 2.00 4.65 0.25 0.20 2.79
CORTE 2 6.00 1.00 1.60 0.25 0.20 0.48
CORTE 3 6.00 1.00 3.50 0.20 0.40 1.68
CORTE 4 6.00 1.00 2.40 0.25 0.40 1.44
CORTE 5 6.00 1.00 1.70 0.15 0.20 0.31
CORTE 6 6.00 1.00 1.10 0.25 0.40 0.66
CORTE 6 6.00 1.00 1.60 0.25 0.40 0.96
8º PISO
CORTE 1 1.00 4.80 0.25 0.20 0.24
CORTE 1 2.00 4.65 0.25 0.20 0.47
CORTE 2 1.00 1.60 0.25 0.20 0.08
CORTE 3 1.00 3.50 0.20 0.40 0.28
CORTE 4 1.00 2.40 0.25 0.40 0.24
CORTE 5 1.00 1.70 0.15 0.20 0.05
CORTE 6 1.00 1.10 0.25 0.40 0.11
CORTE 6 1.00 1.60 0.25 0.40 0.16
9º PISO
CORTE 1 1.00 4.80 0.25 0.20 0.24
CORTE 1 1.00 4.00 0.25 0.20 0.20
CORTE 1 1.00 4.65 0.25 0.20 0.23
CORTE 2 1.00 1.60 0.25 0.20 0.08
CORTE 3 1.00 3.50 0.20 0.40 0.28
CORTE 4 1.00 2.40 0.25 0.40 0.24
CORTE 5 1.00 1.70 0.15 0.20 0.05
CORTE 6 1.00 1.10 0.25 0.40 0.11
CORTE 6 1.00 1.60 0.25 0.40 0.16
CORTE 10 1.00 5.00 0.40 0.20 0.40
CORTE 11 1.00 2.05 0.20 0.20 0.08
CORTE 11 1.00 2.40 0.20 0.20 0.10
METRADO RESIDENCIAL ALPAMAYO-ESTRUCTURA
PROYECTO : VIVIENDA DE INTERES SOCIAL
DISTRITO : ATE PROYECTISTA :
PROVINCIA : LIMA FECHA
DPTO. : LIMA
PART. N° DESCRIPCION UNID. N° Vec DIMENSIONES PARCIAL TOTAL
CANT.
LARGO ANCHO BASE ALTO
CORTE 12 1.00 4.65 0.35 0.20 0.33
CORTE 13 1.00 4.65 0.35 0.20 0.33
AZOTEA
CORTE 2 1.00 2.05 0.25 0.20 0.10
CORTE 2 1.00 1.60 0.25 0.20 0.08
CORTE 5 1.00 1.70 0.15 0.20 0.05
CORTE 5 2.00 1.20 0.15 0.20 0.07
CORTE 5 1.00 1.30 0.15 0.20 0.04
CORTE 6 1.00 1.10 0.25 0.40 0.11
CORTE 6 1.00 1.60 0.25 0.40 0.16
CORTE 7 1.00 3.10 0.20 0.20 0.12
CORTE 20 1.00 4.20 0.20 0.40 0.34
CORTE 20 1.00 5.49 0.20 0.40 0.44
CORTE 21 1.00 3.85 0.25 0.40 0.39
CORTE 21 1.00 0.95 0.25 0.40 0.10
CORTE 21 1.00 1.20 0.25 0.40 0.12
CORTE 21 1.00 1.49 0.25 0.40 0.15
TECHO ASCENSOR
CORTE 20 1.00 1.70 0.20 0.40 0.14
TECHO SEMISOTANO
4.55 5.20 0.20 4.73
2.70 4.55 0.20 2.46
1.70 1.10 0.20 0.37
2.30 1.55 0.20 0.71
0.30 1.60 0.20 0.10
1.70 1.60 0.20 0.54
3.85 5.00 0.20 3.85
2.40 1.30 0.20 0.62
01.04.08 SARDINEL
01.04.08.01 CONCRETO EN SARDINEL ( 210Kg/cm2 ) M3 1.39
9º PISO
CORTE 12 1.00 3.30 0.10 0.30 0.10
CORTE 13 1.00 3.30 0.15 0.30 0.15
CORTE 14 1.00 1.80 0.15 0.30 0.08
SARDINEL PARA JARDIN 1.00 33.61 0.10 0.30 1.01
CORTE 18 1.00 1.80 0.10 0.30 0.05
TRAMO 1
Base 10.00 1.20 1.88 22.56
Peldaños 10.00 6.00 1.20 0.18 12.96
Descanso 2.00 10.00 1.20 0.18 4.20
10.00 1.20 1.20 14.40
TRAMO 2
Base 10.00 1.20 1.90 22.80
Peldaños 10.00 6.00 1.20 0.18 12.96
Descanso 2.00 10.00 1.20 0.18 4.20
10.00 1.20 1.20 14.40
01.04.10 PLACAS
01.04.10.01 CONCRETO ( 210Kg/cm2 ) M3 270.37
SEMISOTANO
PLACAS PERIMETRICOS
EJE 1 TRAMO A-B-C-D 4.70 0.35 3.65 6.00
EJE 2 TRAMO A-B-C-D 9.00 0.20 3.65 6.57
EJE 3 TRAMO A-B-C 3.45 0.25 3.65 3.15
EJE 3 TRAMO D-E 3.80 0.25 3.65 3.47
EJE 4 TRAMO D-E 4.70 0.25 3.65 4.29
EJE 5 TRAMO C-D 3.85 0.25 3.65 3.51
2º AL 7º PISO
P-1 6.00 5.10 0.25 2.50 19.13
P-2 6.00 2.30 0.25 2.50 8.63
6.00 1.70 0.25 2.50 6.38
6.00 2.30 0.25 2.50 8.63
P-3 6.00 4.25 0.25 2.50 15.94
6.00 5.10 0.25 2.50 19.13
6.00 2.90 0.25 2.50 10.88
6.00 1.60 0.25 2.50 6.00
P-4 6.00 1.50 0.25 2.50 5.63
P-5 6.00 2.40 0.25 2.50 9.00
8º PISO
P-1 5.10 0.25 2.50 3.19
P-2 2.30 0.25 2.50 1.44
1.70 0.25 2.50 1.06
2.30 0.25 2.50 1.44
P-3 4.25 0.25 2.50 2.66
5.10 0.25 2.50 3.19
2.90 0.25 2.50 1.81
1.60 0.25 2.50 1.00
P-4 1.50 0.25 2.50 0.94
P-5 2.40 0.25 2.50 1.50
9º PISO
P-1 5.10 0.25 2.50 3.19
P-2 2.30 0.25 2.50 1.44
1.70 0.25 2.50 1.06
2.30 0.25 2.50 1.44
P-3 4.25 0.25 2.50 2.66
5.10 0.25 2.50 3.19
2.90 0.25 2.50 1.81
1.60 0.25 2.50 1.00
P-4 1.50 0.25 2.50 0.94
P-5 2.40 0.25 2.50 1.50
AZOTEA
P-1 2.70 0.25 2.50 1.69
P-2 2.30 0.25 2.50 1.44
METRADO RESIDENCIAL ALPAMAYO-ESTRUCTURA
PROYECTO : VIVIENDA DE INTERES SOCIAL
DISTRITO : ATE PROYECTISTA :
PROVINCIA : LIMA FECHA
DPTO. : LIMA
PART. N° DESCRIPCION UNID. N° Vec DIMENSIONES PARCIAL TOTAL
CANT.
LARGO ANCHO BASE ALTO
1.70 0.25 2.50 1.06
2.30 0.25 2.50 1.44
P-3 4.25 0.25 2.50 2.66
5.10 0.25 2.50 3.19
2.90 0.25 2.50 1.81
1.60 0.25 2.50 1.00
TECHO
P-2 2.30 0.25 2.50 1.44
1.70 0.25 2.50 1.06
2.30 0.25 2.50 1.44
TANQUE ELEVADO
2.00 0.25 2.50 1.25
SEMISOTANO
PLACAS PERIMETRICOS
EJE 1 TRAMO A-B-C-D 2.00 4.70 3.65 34.31
EJE 2 TRAMO A-B-C-D 2.00 9.00 3.65 65.70
EJE 3 TRAMO A-B-C 2.00 3.45 3.65 25.19
EJE 3 TRAMO D-E 2.00 3.80 3.65 27.74
EJE 4 TRAMO D-E 2.00 4.70 3.65 34.31
EJE 5 TRAMO C-D 2.00 3.85 3.65 28.11
2º AL 7º PISO
P-1 2.00 6.00 5.10 2.50 153.00
2.00 6.00 5.10 0.25 15.30
P-2 2.00 6.00 2.30 2.50 69.00
2.00 6.00 2.30 0.25 6.90
P-2 2.00 6.00 1.70 2.50 51.00
2.00 6.00 1.70 0.25 5.10
P-2 2.00 6.00 2.30 2.50 69.00
2.00 6.00 2.30 0.25 6.90
P-3 2.00 6.00 4.25 2.50 127.50
2.00 6.00 4.25 0.25 12.75
P-3 2.00 6.00 5.10 2.50 153.00
2.00 6.00 5.10 0.25 15.30
P-3 2.00 6.00 2.90 2.50 87.00
2.00 6.00 2.90 0.25 8.70
P-3 2.00 6.00 1.60 2.50 48.00
2.00 6.00 1.60 0.25 4.80
P-4 2.00 6.00 1.50 2.50 45.00
2.00 6.00 1.50 0.25 4.50
P-5 2.00 6.00 2.40 2.50 72.00
2.00 6.00 2.40 0.25 7.20
8º PISO
P-1 2.00 5.10 2.50 25.50
METRADO RESIDENCIAL ALPAMAYO-ESTRUCTURA
PROYECTO : VIVIENDA DE INTERES SOCIAL
DISTRITO : ATE PROYECTISTA :
PROVINCIA : LIMA FECHA
DPTO. : LIMA
PART. N° DESCRIPCION UNID. N° Vec DIMENSIONES PARCIAL TOTAL
CANT.
LARGO ANCHO BASE ALTO
2.00 5.10 0.25 2.55
P-2 2.00 2.30 2.50 11.50
2.00 2.30 0.25 1.15
P-2 2.00 1.70 2.50 8.50
2.00 1.70 0.25 0.85
P-2 2.00 2.30 2.50 11.50
2.00 2.30 0.25 1.15
P-3 2.00 4.25 2.50 21.25
2.00 4.25 0.25 2.13
P-3 2.00 5.10 2.50 25.50
2.00 5.10 0.25 2.55
P-3 2.00 2.90 2.50 14.50
2.00 2.90 0.25 1.45
P-3 2.00 1.60 2.50 8.00
2.00 1.60 0.25 0.80
P-4 2.00 1.50 2.50 7.50
2.00 1.50 0.25 0.75
P-5 2.00 2.40 2.50 12.00
2.00 2.40 0.25 1.20
9º PISO
P-1 2.00 5.10 2.50 25.50
2.00 5.10 0.25 2.55
P-2 2.00 2.30 2.50 11.50
2.00 2.30 0.25 1.15
P-2 2.00 1.70 2.50 8.50
2.00 1.70 0.25 0.85
P-2 2.00 2.30 2.50 11.50
2.00 2.30 0.25 1.15
P-3 2.00 4.25 2.50 21.25
2.00 4.25 0.25 2.13
P-3 2.00 5.10 2.50 25.50
2.00 5.10 0.25 2.55
P-3 2.00 2.90 2.50 14.50
2.00 2.90 0.25 1.45
P-3 2.00 1.60 2.50 8.00
2.00 1.60 0.25 0.80
P-4 2.00 1.50 2.50 7.50
2.00 1.50 0.25 0.75
P-5 2.00 2.40 2.50 12.00
2.00 2.40 0.25 1.20
AZOTEA
P-1 2.00 2.70 2.50 13.50
2.00 2.70 0.25 1.35
P-2 2.00 2.30 2.50 11.50
2.00 2.30 0.25 1.15
P-2 2.00 1.70 2.50 8.50
2.00 1.70 0.25 0.85
P-2 2.00 2.30 2.50 11.50
2.00 2.30 0.25 1.15
P-3 2.00 4.25 2.50 21.25
2.00 4.25 0.25 2.13
P-3 2.00 5.10 2.50 25.50
2.00 5.10 0.25 2.55
P-3 2.00 2.90 2.50 14.50
2.00 2.90 0.25 1.45
METRADO RESIDENCIAL ALPAMAYO-ESTRUCTURA
PROYECTO : VIVIENDA DE INTERES SOCIAL
DISTRITO : ATE PROYECTISTA :
PROVINCIA : LIMA FECHA
DPTO. : LIMA
PART. N° DESCRIPCION UNID. N° Vec DIMENSIONES PARCIAL TOTAL
CANT.
LARGO ANCHO BASE ALTO
P-3 2.00 1.60 2.50 8.00
2.00 1.60 0.25 0.80
TECHO
P-2 2.00 2.30 2.50 11.50
2.00 2.30 0.25 1.15
P-2 2.00 1.70 2.50 8.50
2.00 1.70 0.25 0.85
P-2 2.00 2.30 2.50 11.50
2.00 2.30 0.25 1.15
TANQUE ELEVADO
2.00 2.00 2.50 10.00
2.00 2.00 0.25 1.00