PLAN DE REHABILITACION GL 255 - ZONA 01

DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE DIA NOCHE

Duracion
ITEM NIVEL LABOR DESCRIPCION DE ACTIVIDAD (guardias) 17-Feb 17-Feb 18-Feb 18-Feb 19-Feb 19-Feb 20-Feb 20-Feb 21-Feb 21-Feb 22-Feb 22-Feb 23-Feb 23-Feb 24-Feb 24-Feb 25-Feb 25-Feb 26-Feb 26-Feb 27-Feb 27-Feb 28-Feb 28-Feb % RESPONZABLES

255 GL 255 NE DESCARGA DE MALLA SOBRECARGADA 4 LUIS QUISPE / RONAL VELASQUEZ

255 GL 255 NE LIMPIEZA DE CARGA ZONA DE DESATE Y AREA PERTURBADA 3 LUIS QUISPE / RONAL VELASQUEZ

255 GL 255 NE SOSTENIMIENTO CON MALLA Y PERNO SPLIT SET 12 LUIS QUISPE / RONAL VELASQUEZ

GL 255 - NE
255 GL 255 NE LANZADO DE SHOTCRET 6 LUIS QUISPE / RONAL VELASQUEZ

255 GL 255 NE INSTALACION DE SERVICIOS (AGUA Y AIRE) 2 LUIS QUISPE / RONAL VELASQUEZ

255 GL 255 NE ADELANTAR INST. DE SERVICIOS ELECTRICOS 1 LUIS QUISPE / RONAL VELASQUEZ

255 GL 255 SW DESCARGA DE MALLA SOBRECARGADA 1 LUIS QUISPE / RONAL VELASQUEZ

255 GL 255 SW LIMPIEZA DE CARGA ZONA DE DESATE Y AREA PERTURBADA 1 LUIS QUISPE / RONAL VELASQUEZ

255 GL 255 SW INSTALACION DE SERVICIOS (AGUA Y AIRE) 3 LUIS QUISPE / RONAL VELASQUEZ

GL 255 -SW 255 GL 255 SW ADELANTAR INST. DE SERVICIOS ELECTRICOS 2 LUIS QUISPE / RONAL VELASQUEZ

255 GL 255 SW LANZADO DE SHOTCRET 4 LUIS QUISPE / RONAL VELASQUEZ

255 GL 255 SW SOSTENIMIENTO CON MALLA Y PERNO SPLIT SET 4 LUIS QUISPE / RONAL VELASQUEZ

Recursos Cantidad Cantidad Ubicación Responsable


TELEHANDER / ROBOT / CARMIX / BOLTER 1 UND ZONA 01 GABRIEL ULLOA
TUBERIA HDP DIAMETRO 4" 160 Metros ZONA 01 RICARDO GIMENEZ
ACCESORIOS T DE 4" 2 Metros ZONA 01 RICARDO GIMENEZ
REQUERIMIENTO
TABLERO CAJA PLOGA 1 UND ZONA 01 RICARDO GIMENEZ
ACCESORIOS BRIDAS DE 4" DE LA SERIE 905 6 UND ZONA 01 RICARDO GIMENEZ
CABLE ELECTRICO, 2 (0) . 70 Metros ZONA 01 RICARDO GIMENEZ