CRONOGRAMA VALORIZADO

OBRA: "MEJORAMIENTO Y AMPLIACION DE LA IGLESIA DE SAN SANTIAGO APOSTOL DEL PUEBLO DE LLACTUM -DISTRITO DE AIJA-PROVINCIA DE AIJA-DEPARTAMENTO DE ANCASH"

Ejecuta:
Duración: 90 DIAS CALENDARIOS Fecha: Oct-21

PRECIO PARCIAL MES 01 MES 02 MES 03


Item Descripción UNIDAD METRADO
Parcial % Parcial % Parcial %
“MANTENIMIENTO DEL CEMENTERIO DE SAN MARCOS Y DE LOS ACCESOS
PRINCIPALES DEL BARRIO CANTA GALLO DEL DISTRITO DE SAN MARCOS - HUARI S/ 57,526.41 S/ 74,007.56 S/ 95,899.69
- ANCASH”
01 IGLESIA SAN SANTIAGO APOSTOL - LLACTUM 200,627.77 S/ 39,820.03 19.85% S/ 67,162.00 33.48% S/ 93,645.75 46.68%
01.01 OBRAS PROVISIONALES 2,328.25 S/ 2,328.25 100.00% 0.00% 0.00%
01.01.01 CARTEL DE IDENTIFICACION DE LA OBRA und 1.00 1,328.25 1,328.25 S/ 1,328.25 100.00% 0.00% 0.00%
01.01.02 MOVILIZACION DE MAQUINARIAS HERRAMIENTAS PARA LA OBRA glb 1.00 1,000.00 1,000.00 S/ 1,000.00 100.00% 0.00% 0.00%
01.02 SEGURIDAD Y SALUD 9,245.61 S/ 4,948.54 53.52% S/ 2,220.16 24.01% S/ 2,076.92 22.46%
01.02.01 ELABORACION,IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y glb 1.00 850.00 850.00 S/ 850.00 100.00% 0.00% 0.00%
01.02.02 EQUIPOS DE PROTECCION INDIVIDUAL glb 1.00 3,500.00 3,500.00 S/ 1,166.67 33.33% S/ 1,205.56 34.44% S/ 1,127.78 32.22%
01.02.03 EQUIPOS DE PROTECCION COLECTIVA. glb 1.00 750.00 750.00 S/ 750.00 100.00% 0.00% 0.00%
01.02.04 SEÑ ALIZACION TEMPORAL DE SEGURIDAD. glb 1.00 1,200.00 1,200.00 S/ 400.00 33.33% S/ 413.33 34.44% S/ 386.67 32.22%
01.02.05 CAPACITACION EN SEGURIDAD Y SALUD glb 1.00 1,200.00 1,200.00 S/ 1,200.00 100.00% 0.00% 0.00%
01.02.06 RECURSOS PARA RESPUESTA ANTE EMERGENCIA EN SST glb 1.00 1,745.61 1,745.61 S/ 581.87 33.33% S/ 601.27 34.44% S/ 562.47 32.22%
01.03 MITIGACION AMBIENTAL 2,500.00 S/ 833.33 33.33% S/ 861.11 34.44% S/ 805.56 32.22%
01.03.01 IMPACTO AMBIENTAL glb 1.00 2,500.00 2,500.00 S/ 833.33 33.33% S/ 861.11 34.44% S/ 805.56 32.22%
01.04 DEMOLICIONES 18,278.36 S/ 18,278.36 100.00% 0.00% 0.00%
01.04.01 DESMONTAJE DE COBERTURA m2 122.25 4.01 490.22 S/ 490.22 100.00% 0.00% 0.00%
01.04.02 DESMONTAJE DE PUERTAS m2 3.34 4.90 16.37 S/ 16.37 100.00% 0.00% 0.00%
01.04.03 DESMONTAJE DE TIJERALES und 6.00 36.42 218.52 S/ 218.52 100.00% 0.00% 0.00%
01.04.04 DEMOLICION DE MUROS DE ADOBE m 135.68 37.65 5,108.35 S/ 5,108.35 100.00% 0.00% 0.00%
01.04.05 DEMOLICION DE CIMIENTOS Y SOBRECIMIENTOS m3 36.07 28.43 1,025.47 S/ 1,025.47 100.00% 0.00% 0.00%
01.04.06 DEMOLICION DE PISOS Y FALSO PISOS m2 181.51 18.78 3,408.76 S/ 3,408.76 100.00% 0.00% 0.00%
01.04.07 DEMOLICION DE GRADERIAS. m2 24.85 19.14 475.63 S/ 475.63 100.00% 0.00% 0.00%
01.04.08 ACARREO DE MATERIAL EXCEDENTE DIST. PROM. 30 M. m3 124.98 23.47 2,933.28 S/ 2,933.28 100.00% 0.00% 0.00%
01.04.09 ELIMINACION DE MATERIAL EXCEDENTE m3 124.98 36.82 4,601.76 S/ 4,601.76 100.00% 0.00% 0.00%
01.05 TRABAJOS PRELIMINARES 767.93 S/ 767.93 100.00% 0.00% 0.00%
01.05.03 LIMPIEZA DE TERRENO MANUAL m2 139.37 2.01 280.13 S/ 280.13 100.00% 0.00% 0.00%
01.05.04 TRAZO Y REPLANTEO EN EDIFICACIONES m2 139.37 3.50 487.80 S/ 487.80 100.00% 0.00% 0.00%
01.06 MOVIMIENTO DE TIERRAS 4,876.46 S/ 3,017.15 61.87% S/ 1,859.31 38.13% 0.00%
01.06.01 EXCAVACION MANUAL EN CONGLOMERADO m3 74.00 32.10 2,375.40 S/ 2,375.40 100.00% 0.00% 0.00%
01.06.02 EXCAVACION MANUAL EN ROCA m3 3.84 47.95 184.13 S/ 184.13 100.00% 0.00% 0.00%
01.06.03 RELLENO CON MATERIAL PROPIO MANUAL m3 33.99 40.39 1,372.86 S/ 457.62 33.33% S/ 915.24 66.67% 0.00%
01.06.04 ELIMINACION DE MATERIAL EXCEDENTE C/ MAQUINARIA m3 54.82 12.86 704.99 0.00% S/ 704.99 100.00% 0.00%
01.06.05 AFIRMADO DE 2" EN INTERIORES, PATIOS Y VEREDAS m3 25.38 9.42 239.08 0.00% S/ 239.08 100.00% 0.00%
01.07 CONCRETO SIMPLE 18,121.89 S/ 9,646.47 53.23% S/ 8,475.42 46.77% 0.00%
01.07.01 CONCRETO 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS m3 25.90 339.52 8,793.57 S/ 8,793.57 100.00% 0.00% 0.00%
01.07.02 CONCRETO 1:8 +25% P.M PARA SOBRECIMIENTO m3 5.26 409.27 2,152.76 0.00% S/ 2,152.76 100.00% 0.00%
01.07.03 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMINETOS m2 70.14 24.32 1,705.80 S/ 852.90 50.00% S/ 852.90 50.00% 0.00%
01.07.04 CONCRETO EN FALSO PISO MEZCLA 1:8 C:H E=4'' m2 109.32 42.78 4,676.71 0.00% S/ 4,676.71 100.00% 0.00%
01.07.05 SOLADO PARA ZAPATAS 2'' MEZCLA C:H 1:12 m2 30.35 26.13 793.05 0.00% S/ 793.05 100.00% 0.00%
01.08 CONCRETO ARMADO 40,510.99 0.00% S/ 29,955.54 73.94% S/ 10,555.45 26.06%
01.08.01 ZAPATAS 9,682.28 0.00% S/ 9,682.28 100.00% 0.00%
01.08.01.01 CONCRETO FC= 210KG/CM2 PARA ZAPATAS m3 15.18 445.20 6,758.14 0.00% S/ 6,758.14 100.00% 0.00%
01.08.01.02 ACERO fy=4200 kg/cm2 EN ZAPATAS kg 360.56 8.11 2,924.14 0.00% S/ 2,924.14 100.00% 0.00%
01.08.02 COLUMNAS 15,345.01 0.00% S/ 15,345.01 100.00% 0.00%
01.08.02.01 CONCRETO FC=210KG/CM2 PARA COLUMNAS m3 14.67 504.20 7,396.61 0.00% S/ 7,396.61 100.00% 0.00%
01.08.02.02 ENCOFRADO Y DESENCOFRADO DE COLUMNAS m2 41.35 56.81 2,349.09 0.00% S/ 2,349.09 100.00% 0.00%
01.08.02.03 ACERO fy=4200 kg/cm2 EN COLUMNAS kg 685.35 8.17 5,599.31 0.00% S/ 5,599.31 100.00% 0.00%
01.08.03 COLUMNETAS 3,731.27 0.00% S/ 3,027.85 81.15% S/ 703.42 18.85%
01.08.03.01 CONCRETO f'c=175 kg/cm2 PARA COLUMNETAS m3 1.58 445.20 703.42 0.00% 0.00% S/ 703.42 100.00%
01.08.03.02 ENCOFRADO Y DESENCOFRADO DE COLUMNETAS m2 1.58 62.54 98.81 0.00% S/ 98.81 100.00% 0.00%
01.08.03.03 ACERO fy=4200 kg/cm2 DE COLUMNETAS kg 357.20 8.20 2,929.04 0.00% S/ 2,929.04 100.00% 0.00%
01.08.04 VIGAS Y DINTELES 8,200.89 0.00% 0.00% S/ 8,200.89 100.00%
01.08.04.01 CONCRETO f'c=210 kg/cm2 PARA VIGAS m3 3.21 504.20 1,618.48 0.00% 0.00% S/ 1,618.48 100.00%
01.08.04.02 ENCOFRADO Y DESENCOFRADO DE VIGAS m2 27.31 74.05 2,022.31 0.00% 0.00% S/ 2,022.31 100.00%
01.08.04.03 ACERO fy=4200 kg/cm2 EN VIGAS kg 556.11 8.20 4,560.10 0.00% 0.00% S/ 4,560.10 100.00%
01.08.05 LOSAS ALIGERADAS 485.47 0.00% S/ 485.47 100.00% 0.00%
01.08.05.01 CONCRETO f'c=210 kg/cm2 EN LOSA ALIGERADA m3 0.17 479.82 81.57 0.00% S/ 81.57 100.00% 0.00%
01.08.05.02 ENCOFRADO Y DESENCOFRADO EN LOSA ALIGERADA m2 1.73 74.05 128.11 0.00% S/ 128.11 100.00% 0.00%
01.08.05.03 ACERO fy=4200 kg/cm2 EN LOSA ALIGERADA kg 27.65 8.14 225.07 0.00% S/ 225.07 100.00% 0.00%
01.08.05.04 LADRILLO DE TECHO und 14.41 3.52 50.72 0.00% S/ 50.72 100.00% 0.00%
01.08.06 VIGAS REMATE DE PARAPETO Y ALFEIZARES 3,066.07 0.00% S/ 1,414.93 46.15% S/ 1,651.14 53.85%
01.08.06.01 CONCRETO f'c=175 kg/cm2 PARA VIGA DE REMATE m3 0.77 468.18 360.50 0.00% 0.00% S/ 360.50 100.00%
01.08.06.02 ENCOFRADO Y DESENCOFRADO EN VIGA DE REMATE m2 10.24 56.95 583.17 0.00% 0.00% S/ 583.17 100.00%
01.08.06.03 ACERO fy=4200 kg/cm2 EN VIGA DE REMATE kg 259.78 8.17 2,122.40 0.00% S/ 1,414.93 66.67% S/ 707.47 33.33%
01.09 ESTRUCTURA DE MADERA Y COBERTURA 28,807.66 0.00% S/ 2,577.82 8.95% S/ 26,229.84 91.05%
01.09.01 TIJERAL und 4.00 1,503.73 6,014.92 0.00% S/ 2,577.82 42.86% S/ 3,437.10 57.14%
01.09.02 VIGUETAS DE MADERA TORNILLO 3" X 6" m 130.40 35.59 4,640.94 0.00% 0.00% S/ 4,640.94 100.00%
01.09.03 CORREAS DE MADERA TORNILLO 3''X4'' m 307.50 25.55 7,856.63 0.00% 0.00% S/ 7,856.63 100.00%
01.09.04 ENTRAMADO DE MADERA TORNILLO 2'' X 2'' m 184.50 12.24 2,258.28 0.00% 0.00% S/ 2,258.28 100.00%
01.09.05 COBERTURA DE TEJA ANDINA m2 121.81 55.63 6,776.29 0.00% 0.00% S/ 6,776.29 100.00%
01.09.06 CUMBRERA DE TEJA ANDINA m 23.70 53.19 1,260.60 0.00% 0.00% S/ 1,260.60 100.00%
01.10 MUROS Y TABIQUES DE ALBAÑ ILERIA 15,057.44 0.00% S/ 15,057.44 100.00% 0.00%
01.10.01 MURO DE LADRILLO ARCILLA 18 HUECOS DE CABEZA C/M 1:5X1.5CM m2 19.31 145.87 2,816.75 0.00% S/ 2,816.75 100.00% 0.00%
01.10.02 MURO DE LADRILLO ARCILLA 18 HUECOS DE SOGA C/M 1:4 X 1.5CM m2 134.50 83.88 11,281.86 0.00% S/ 11,281.86 100.00% 0.00%
01.10.03 ALAMBRE DE REFUERZO HORIZONTAL EN MUROS kg 45.00 8.07 363.15 0.00% S/ 363.15 100.00% 0.00%
01.10.04 JUNTA DE CONSTRUCCION CON TEKNOPORT DE 1" m 51.00 11.68 595.68 0.00% S/ 595.68 100.00% 0.00%
01.11 REVOQUES ENLUCIDOS Y MOLDURAS 4,439.93 0.00% 0.00% S/ 4,439.93 100.00%
01.11.01 TARRAJEO EN MUROS INTERIORES m2 134.50 22.13 2,976.49 0.00% 0.00% S/ 2,976.49 100.00%
01.11.02 TARRAJEO EN MUROS EXTERIORES m2 19.31 30.81 594.94 0.00% 0.00% S/ 594.94 100.00%
01.11.03 VESTIDURA DE DERRAMES m 45.00 19.30 868.50 0.00% 0.00% S/ 868.50 100.00%
01.12 CIELORASOS 12,921.55 0.00% 0.00% S/ 12,921.55 100.00%
01.12.01 CIELO RASO CON MEZCLA 1:5 m2 14.41 39.50 569.20 0.00% 0.00% S/ 569.20 100.00%
01.12.02 CIELO RASO CON FIBROCEMENTO DE 4 mm m2 121.81 99.11 12,072.59 0.00% 0.00% S/ 12,072.59 100.00%
01.12.03 ALERO DE CARRIZO ESTUCADO CON YESO m2 4.89 57.21 279.76 0.00% 0.00% S/ 279.76 100.00%
01.13 PISOS Y PAVIMENTOS 13,567.87 0.00% S/ 5,352.73 39.45% S/ 8,215.14 60.55%
01.13.01 CONTRAPISO DE 48 MM. MEZCLA 1:5 m2 181.51 29.49 5,352.73 0.00% S/ 5,352.73 100.00% 0.00%
01.13.02 PISO DE CERAMICA DE PIZARRA m2 181.51 45.26 8,215.14 0.00% 0.00% S/ 8,215.14 100.00%
01.14 CONTRAZOCALOS 920.83 0.00% 0.00% S/ 920.83 100.00%
01.14.01 CONTRAZOCALO CEMENTO H=0.10M EN INTERIORES m 54.61 15.11 825.16 0.00% 0.00% S/ 825.16 100.00%
01.14.02 CONTRAZOCALO CEMENTO H=0.20M EN EXTERIORES m 7.15 13.38 95.67 0.00% 0.00% S/ 95.67 100.00%
01.15 CARPINTERIA DE MADERA 5,000.00 0.00% 0.00% S/ 5,000.00 100.00%
01.15.01 PUERTA APANELADA DE MADERA CEDRO glb 1.00 5,000.00 5,000.00 0.00% 0.00% S/ 5,000.00 100.00%
01.16 CERRAJERIA 13,522.73 0.00% 0.00% S/ 13,522.73 100.00%
01.16.01 VENTANA CIRCULAR glb 3.00 450.00 1,350.00 0.00% 0.00% S/ 1,350.00 100.00%
01.16.02 VENTANAS ALTAS glb 1.00 2,850.00 2,850.00 0.00% 0.00% S/ 2,850.00 100.00%
01.16.03 ESCALERA METALICA DE CARACOL glb 1.00 3,231.77 3,231.77 0.00% 0.00% S/ 3,231.77 100.00%
01.16.04 REJAS DE PROTECCION DE INGRESO m 10.57 576.25 6,090.96 0.00% 0.00% S/ 6,090.96 100.00%
01.17 VIDRIOS, CRISTALES Y SIMILARES 195.86 0.00% 0.00% S/ 195.86 100.00%
01.17.01 VIDRIOS INCOLORO SEMIDOBLE p2 41.32 4.74 195.86 0.00% 0.00% S/ 195.86 100.00%
01.18 PINTURA 1,741.22 0.00% 0.00% S/ 1,741.22 100.00%
01.18.01 PINTURA LATEX EN CIELO RASO m2 1.73 6.99 12.09 0.00% 0.00% S/ 12.09 100.00%
01.18.02 PINTURA LATEX EN MUROS INTERIORES m2 153.81 8.56 1,316.61 0.00% 0.00% S/ 1,316.61 100.00%
01.18.03 PINTURA LATEX EN MUROS EXTERIORES m2 19.31 9.11 175.91 0.00% 0.00% S/ 175.91 100.00%
01.18.04 PINTURA LATEX 2 MANOS EN ALERO DE YESO m2 4.89 10.30 50.37 0.00% 0.00% S/ 50.37 100.00%
01.18.05 PINTURA BARNIZ EN PUERTA m2 12.00 15.52 186.24 0.00% 0.00% S/ 186.24 100.00%
01.19 INSTALACIONES ELECTRICAS. 2,355.70 0.00% S/ 802.47 34.07% S/ 1,553.23 65.93%
01.19.01 SALIDA DE TECHO PARA CENTRO DE LUZ pto 1.00 141.27 141.27 0.00% S/ 141.27 100.00% 0.00%
01.19.02 SALIDA PARA TOMACORRIENTE DOBLE pto 8.00 82.65 661.20 0.00% S/ 661.20 100.00% 0.00%
01.19.03 TABLERO DE DISTRIBUCION und 2.00 301.64 603.28 0.00% 0.00% S/ 603.28 100.00%
01.19.04 POZO DE TIERRA und 1.00 949.95 949.95 0.00% 0.00% S/ 949.95 100.00%
01.20 ARTEFACTOS 798.48 0.00% 0.00% S/ 798.48 100.00%
01.20.01 ARTEFACTO FLUORESCENTE 2x40w und 8.00 77.22 617.76 0.00% 0.00% S/ 617.76 100.00%
01.20.02 ARTEFACTO FLUORESCENTE 2x30w und 2.00 90.36 180.72 0.00% 0.00% S/ 180.72 100.00%
01.21 CANALIZACIONES Y/O TUBERIAS 960.86 0.00% 0.00% S/ 960.86 100.00%
01.21.01 TUBERIA PVC SEL 25 mm m 35.00 14.47 506.45 0.00% 0.00% S/ 506.45 100.00%
01.21.02 TUBERIA PVC SEL 35 mm m 27.00 16.83 454.41 0.00% 0.00% S/ 454.41 100.00%
01.22 SISTEMA DE EVACUACIÓ N PLUVIAL 3,181.64 0.00% 0.00% S/ 3,181.64 100.00%
01.22.01 CANALETA DE FIERRO GALVANIZADO m 37.00 74.65 2,762.05 0.00% 0.00% S/ 2,762.05 100.00%
01.22.02 TUBERIA PVC SAL Ø3'' P/DRENAJE m 9.00 10.79 97.11 0.00% 0.00% S/ 97.11 100.00%
01.22.03 CONCRETO PARA COLUMNETA DE PROTECCION m3 0.16 525.58 84.09 0.00% 0.00% S/ 84.09 100.00%
01.22.04 ENCOFRADO Y DESNCOFRADO DE COLUMNETA DE PROTECCION m2 3.20 56.62 181.18 0.00% 0.00% S/ 181.18 100.00%
01.22.05 REFUERZO DE COLUMNETA DE PROTECCION kg 7.70 7.43 57.21 0.00% 0.00% S/ 57.21 100.00%
01.23 VARIOS 526.51 0.00% 0.00% S/ 526.51 100.00%
01.23.01 RESANE Y PULIDO DE CAMPANA EXISTENTE glb 1.00 313.63 313.63 0.00% 0.00% S/ 313.63 100.00%
01.23.02 ACCESORIOS PARA CAMPANA glb 1.00 212.88 212.88 0.00% 0.00% S/ 212.88 100.00%
02 CONSTRUCCION DE ESCALERA DE ACCESO 1,014.42 0.00% S/ 110.63 10.91% S/ 903.79 89.09%
02.01 TRABAJOS PRELIMINARES 29.53 0.00% S/ 29.53 100.00% 0.00%
02.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.36 2.01 10.77 0.00% S/ 10.77 100.00% 0.00%
02.01.02 TRAZO Y REPLANTEO EN EDIFICACIONES m2 5.36 3.50 18.76 0.00% S/ 18.76 100.00% 0.00%
02.02 MOVIMIENTO DE TIERRAS 98.08 0.00% S/ 81.10 82.69% S/ 16.98 17.31%
02.02.01 EXCAVACION MANUAL EN CONGLOMERADO m3 1.13 32.10 36.27 0.00% S/ 36.27 100.00% 0.00%
02.02.02 EXCAVACION MANUAL EN ROCA m3 0.48 47.95 23.02 0.00% S/ 23.02 100.00% 0.00%
02.02.03 RELLENO CON MATERIAL PROPIO MANUAL m3 0.54 40.39 21.81 0.00% S/ 21.81 100.00% 0.00%
02.02.04 ELIMINACION DE MATERIAL EXCEDENTE C/ MAQUINARIA m3 1.32 12.86 16.98 0.00% 0.00% S/ 16.98 100.00%
02.03 CONCRETO SIMPLE 886.81 0.00% 0.00% S/ 886.81 100.00%
02.03.01 CONCRETO PARA GRADAS DE 1:8 C:H m3 1.34 359.69 481.98 0.00% 0.00% S/ 481.98 100.00%
02.03.02 ENCOFRADO Y DESENCOFRADO PARA GRADAS m2 7.15 56.62 404.83 0.00% 0.00% S/ 404.83 100.00%
03 PLAN DE PREVENCION Y CONTROL CONTRA EL COVID - 19 15,546.46 S/ 10,876.38 69.96% S/ 3,319.93 21.35% S/ 1,350.15 8.68%
03.01 IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE VIGILANCIA, glb 1.00 2,126.36 2,126.36 S/ 2,126.36 100.00% 0.00% 0.00%
PREVENCION Y CONTROL DE COVID 19 EN EL TRABAJO
03.02 LIMPIEZA Y DESINFECCION EN LOS CENTROS DE TRABAJO glb 1.00 850.00 850.00 S/ 283.33 33.33% S/ 292.78 34.44% S/ 273.89 32.22%
03.03 EVALUACION DE LA CONDICION DE SALUD DEL TRABAJADOR PREVIO A LA INCORPO glb 1.00 3,825.00 3,825.00 S/ 2,550.00 66.67% S/ 1,275.00 33.33% 0.00%
03.04 LAVADO Y DESINFECCION DE MANOS OBLIGATORIO glb 1.00 925.50 925.50 S/ 308.50 33.33% S/ 318.78 34.44% S/ 298.22 32.22%
03.05 SENSIBILIZACION DE LA PREVENCION DEL CONTAGIO EN EL CENTRO DE TRABAJO glb 1.00 3,600.00 3,600.00 S/ 3,600.00 100.00% 0.00% 0.00%
03.06 MEDIDAS PREVENTIVAS DE APLICACION COLECTIVA glb 1.00 1,805.00 1,805.00 S/ 1,203.33 66.67% S/ 601.67 33.33% 0.00%
03.07 MEDIDAS DE PROTECCION PERSONAL glb 1.00 1,564.60 1,564.60 S/ 521.53 33.33% S/ 538.92 34.44% S/ 504.15 32.22%
03.08 VIGILANCIA DE LA SALUD DEL TRABAJADOR EN EL CONTEXTO DEL COVID 19 glb 1.00 850.00 850.00 S/ 283.33 33.33% S/ 292.78 34.44% S/ 273.89 32.22%
04 FLETE 10,245.00 S/ 6,830.00 66.67% S/ 3,415.00 33.33% 0.00%
04.01 FLETE -TERRESTRE glb 1.00 10,245.00 10,245.00 S/ 6,830.00 66.67% S/ 3,415.00 33.33% 0.00%
COSTO DIRECTO 227,433.65 57,526.41 74,007.56 95,899.69
GASTOS GENERALES 13.29% 30,224.00 7,644.77 9,834.98 12,744.25
UTILIDAD (8%) 18,194.69 4,602.11 5,920.60 7,671.98
=========== ============= ============= =============
PRESUPUESTO TOTAL DE EJECUCION DE OBRA 275,852.34 69,773.29 89,763.14 116,315.92
IMPUESTO GENERAL A LAS VENTAS (IGV) 49,653.42 12,559.19 16,157.37 20,936.87
=========== ============= ============= =============
325,505.76 82,332.49 105,920.51 137,252.78
PORCENTAJE DE AVANCE SEMANAL % 25.29% 32.54% 42.17%
AVANCE ACUMULADO 82,332.49 188,252.99 325,505.76
PORCENTAJE DE AVANCE ACUMULADO % 25.29% 57.83% 100.00%
CURVA "S"
OBRA: "MEJORAMIENTO Y AMPLIACION DE LA IGLESIA DE SAN SANTIAGO APOSTOL DEL PUEBLO DE LLACTUM -DISTRITO DE AIJA-
PROVINCIA DE AIJA-DEPARTAMENTO DE ANCASH"
Ejecuta:
Duracion: 90 DIAS CALENDARIOS

PROGRAMACIÓN
INICIO MES 01 MES 02 MES 03
0.00 82332.49 188252.99 325505.76

CURVA "S"
350,000.00
325505.76
300,000.00

250,000.00

200,000.00
188252.99

150,000.00

100,000.00
82332.49
50,000.00

0.00 0.00
INICIO MES 01 MES 02 MES 03