Está en la página 1de 25

MES SETIEMBRE OCTUBRE

FECHAS 9/15/2010 9/30/2010 10/1/2010


MES VALORIZADO PRIMER MES SEGUNDO MES
VALORIZACIONES
10 18
PROGRAMADAS
VALORIZACIONES
11 17
EJECUTADAS
CONDICION ADELANTADO
CANTIDAD 10.000% 0.000%
REPROGRAMACIÓN 11.00% 17.00%
OCTUBRE NOVIEMBRE DICIEMBRE ENERO
31/11/2010 11/1/2010 11/30/2010 12/1/2010 1/31/2010 1/1/2011
SEGUNDO MES TERCER MES CUARTO MES QUINTO MES
18 18 18 18
17 18 15 18.66
ATRASADO ATRASADO
0.000% 0.000% -16.667% -13.000%
17.00% 18.00% 15.00% 18.66%
ENERO FEBRERO MARZO
1/31/2011 2/1/2011 2/28/2011 3/1/2011 3/15/2011 TOTAL (%)
QUINTO MES SEXTO MES SEPTIMO MES
18 13 5 100
18.66 17.56 2.78 ----
ATRASADO --- --- ----
-13.000% 17.077% 0.000% ----
18.66% 17.56% 2.78% 1
Presupuesto 0801025 REHABILITACIÓN CAMINO VECINAL SANGAMA - INCAHUASI
Subpresupuesto 001 PRESUPUESTO BASE
Cliente M.T.C. - PROVIAS DESCENTRALIZADO
Lugar LAMBAYEQUE - FERREÑAFE - INCAHUASI

Item Descripción Und. Metrado Precio S/.

01 OBRAS PRELIMINARES
01.01 CAMPAMENTO PROVISIONAL glb 1.00 2,700.00
01.02 MOVILIZACION Y DESMOVILIZACIÓN glb 1.00 29,933.69
01.03 CARTEL DE OBRA und 1.00 1,050.73
01.04 TRAZO, NIVELACIÓN Y REPLANTEO km 43.72 622.32
02 MOVIMIENTO DE TIERRAS
02.01 EXCAVACIÓN EN MATERIAL SUELTO m3 25,070.45 3.58
02.02 EXCAVACIÓN EN MATERIALCOMPACTO m3 44,982.78 4.46
02.03 EXCAVACIÓN ROCA SUELTA m3 10,232.00 18.64
02.04 EXCAVACIÓN ROCA FIJA m3 675.65 21.56
02.05 RELLENO COMPACTADO CON MATERIAL PROPIO d < 120 m m3 9,871.52 5.14
02.06 RELLENO COMPACTADO CON MATERIAL PROPIO Dprom=3.67 km m3 32,081.23 5.14
02.07 TRANSPORTE DE MATERIAL PROPIO D=3.67 Km m3 9,871.52 4.77
02.08 TRANSPORTE DE MATERIAL EXCEDENTE D=10.768 km m3 39,008.14 11.44
03 PAVIMENTOS
03.01 PERFILADO Y COMPACTACIÓN DE LA SUBRASANTE m2 108,692.31 1.59
03.02 AFIRMADO m3 32,790.00 16.33
03.03 TRANSPORTE DE MATERIAL D=5.95 Km m3 32,790.00 6.72
04 OBRAS DE ARTE Y DRENAJE
04.01 CUNETAS
04.01.01 CUNETAS SIN REVESTIR m 43,720.00 1.35
04.02 ALCANTARILLAS
04.02.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 1,178.77 30.24
04.02.02 CONCRETO f'c=140 kg/cm2 m3 120.41 297.36
04.02.03 CONCRETO f'c=210 kg/cm2 m3 317.44 325.63
04.02.04 ENCOFRADO Y DESENCOFRADO m2 2,216.08 36.96
04.02.05 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO m3 306.47 23.79
04.02.06 ACERO FY=4200 KG/CM2 kg 24,507.06 4.13
04.03 BADENES
04.03.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 801.30 30.24
04.03.02 REFINE Y COMPACTACION DE TERRENO m2 100.16 11.61
04.03.03 ENCOFRADO Y DESENCOFRADO m2 381.80 36.96
04.03.04 EMBOQUILLADO DE PIEDRA m2 1,001.62 61.41
04.03.05 GAVIONES m3 358.50 168.00
04.04 MUROS DE SOSTENIMIENTO
04.04.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 1,092.75 30.24
04.04.02 CONCRETO f'c=210 kg/cm2 m3 338.05 325.63
04.04.03 ENCOFRADO Y DESENCOFRADO X 1,936.80 36.96
04.04.04 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO m3 567.80 23.79
04.04.05 ACERO FY=4200 KG/CM2 kg 18,783.60 4.13
05 SEÑALIZACIÓN
05.01 SEÑALES INFORMATIVAS und 4.00 349.92
05.02 SEÑALES PREVENTIVAS und 326.00 275.50
05.03 SEÑALES REGLAMENTARIAS und 4.00 275.50
05.04 HITO KILOMETRICO und 44.00 130.94
06 IMPACTO AMBIENTAL
06.01 PROGRAMA DE PREVENCIÓN, CONTROL Y MITIGACIÓN
06.01.01 REACONDICIONAMIENTO AREA OCUPADA POR PATIO DE MAQUINAS Y EQUIPOS m2 2,000.00 4.16
06.01.02 REHABILITACIÓN DE CANTERAS m2 12,000.00 6.76
06.01.03 CONSTRUCCIÓN DE DEPOSITO DE MATERIALES EXCEDENTES m2 14,000.00 6.02
06.02 PROGRAMA DE SEÑALIZACIÓN
06.02.01 SEÑALES DE TRABAJO PROVISIONALES und 6.00 219.70
06.02.02 SEÑALES INFORMATIVAS DEFINITIVAS und 20.00 349.92
06.03 PROGRAMA DE CAPACITACIÓN Y MONITOREO AMBIENTAL
06.03.01 PROGRAMA DE EDUCACIÓN Y MONITOREO AMBIENTAL und 1.00 600.00
06.04 PLAN DE MEDIDAS DE CONTROL DE ACCIDENTES O CONTINGENCIAS
06.04.01 PROGRAMA DE CONTINGENCIAS und 1.00 700.00
06.05 MANEJO DE RESIDUOS SÓLIDOS Y PELIGROSOS
06.05.01 CONTENEDOR DE RESIDUOS SÓLIDOS und 4.00 340.53
06.05.02 DISPOCICIÓN FINAL DE RESIDUOS PELIGROSOS glb 1.00 350.00
COSTO DIRECTO
GASTOS GENERALES FIJOS (0.56% Costo Directo)
GASTOS GENERALES VARIABLES (7.76% Costo Directo)
UTILIDAD 8%
SUB TOTAL
I.G.V. (18% SUB TOTAL)
TOTAL PRESUPUESTO
CRONOGRAMA PROGRAMADO

Valorización # 01 Valorización # 02 Valorización # 03


Parcial S/. Set-10 Oct-10 Nov-10
Metrado % S/. Metrado % S/. Metrado %
60,892.25
2,700.00 1.00 100.00% 2,700.00
29,933.69 0.50 50.00% 14,966.85
1,050.73 1.00 100.00% 1,050.73
27,207.83 43.72 100.00% 27,207.83
1,204,644.30
89,752.21 7,521.14 30.00% 26,925.66 8,774.66 35.00% 31,413.27 8,774.66 35.00%
200,623.20 11,245.70 25.00% 50,155.80 28,429.12 63.20% 126,793.86 5,307.97 11.80%
190,724.48 2,660.32 26.00% 49,588.36 5,116.00 50.00% 95,362.24 1,841.76 18.00%
14,567.01 135.13 20.00% 2,913.40 337.83 50.00% 7,283.51 135.13 20.00%
50,739.61 2,467.88 25.00% 12,684.90 5,725.48 58.00% 29,428.97 691.01 7.00%
164,897.52 7,699.50 24.00% 39,575.40 18,607.11 58.00% 95,640.56 3,208.12 10.00%
47,087.15 1,974.30 20.00% 9,417.43 5,034.48 51.00% 24,014.45 1,678.16 17.00%
446,253.12 14,042.93 36.00% 160,651.12 17,163.58 44.00%
928,630.27
172,820.77 21,738.46 20.00%
535,460.70 4,918.50 15.00%
220,348.80 12,460.20 38.00%
891,287.83
59,022.00
59,022.00
365,230.51
35,646.00 235.75 20.00% 7,129.20 412.57 35.00% 12,476.10 229.86 19.50%
35,805.12 24.08 20.00%
103,367.99 32.70 10.30%
81,906.32 323.55 14.60%
7,290.92
101,214.16 3,480.00 14.20%
161,242.98
24,231.31 160.26 20.00% 4,846.26 641.04 80.00% 19,385.05
1,162.86 35.06 35.00% 407.00 50.08 50.00% 581.43 15.02 15.00%
14,111.33 114.54 30.00%
61,509.48 234.88 23.45%
60,228.00 99.81 27.84%
305,792.34
33,044.76
110,079.22
71,584.13
13,507.96
77,576.27
98,076.04
1,399.68
89,813.00
1,102.00
5,761.36
185,048.72
173,720.00
8,320.00
81,120.00
84,280.00 14,000.00 100.00% 84,280.00
8,316.60
1,318.20 6.00 100.00% 1,318.20
6,998.40 9.00 45.00% 3,149.28 11.00 55.00%
600.00
600.00 0.40 40.00% 240.00 40.00%
700.00
700.00 0.17 17.00% 119.00 0.20 20.00% 140.00 0.17 17.00%
1,712.12
1,362.12 4.00 100.00% 1,362.12
350.00
3,368,579.41 336,888.16 606,319.84
18,717.82 1,871.95 3,369.07
261,453.27 26,147.67 47,059.69
269,486.35 26,951.05 48,505.59
3,918,236.85 391,858.83 705,254.19
705,282.63 70,534.59 126,945.75
4,623,519.49 10.00% 462,393.42 18.00% 832,199.95 18.00%
Costo al 6/30/2010

Valorización # 03 Valorización # 04 Valorización # 05 Valorización # 06


Nov-10 Dec-10 Jan-11 Feb-11
S/. Metrado % S/. Metrado % S/. Metrado

31,413.27
23,673.54
34,330.41 613.92 6.00% 11,443.47
2,913.40 67.57 10.00% 1,456.70
3,551.77 987.15 10.00% 5,073.96
16,489.75 2,566.50 8.00% 13,191.80
8,004.82 1,184.58 12.00% 5,650.46
196,351.37 5,851.22 15.00% 66,937.97 1,950.41 5.00% 22,312.66

34,564.15 43,476.92 40.00% 69,128.31 27,825.23 25.60% 44,242.12 15,651.69


80,319.11 7,213.80 22.00% 117,801.35 9,837.00 30.00% 160,638.21 10,820.70
83,732.54 6,558.00 20.00% 44,069.76 9,686.17 29.54% 65,091.04 4,085.63

24,483.20 56.00% 33,052.32 19,236.80 44.00% 25,969.68

6,950.97 300.59 25.50% 9,089.73


7,161.02 27.69 23.00% 8,235.18 36.12 30.00% 10,741.54 32.51
10,646.90 79.36 25.00% 25,842.00 93.77 29.54% 30,534.90 111.61
11,958.32 586.15 26.45% 21,664.22 503.05 22.70% 18,592.73 803.33
56.24 18.35% 1,337.88 61.29
14,372.41 6,616.91 27.00% 27,327.82 7,254.09 29.60% 29,959.39 7,156.06

174.43
4,233.40 145.08 38.00% 5,362.31 122.18 32.00% 4,515.63
14,423.97 265.03 26.46% 16,275.41 265.03 26.46% 16,275.41 236.68
16,767.48 90.88 25.35% 15,267.80 91.96 25.65% 15,448.48 75.86

502.67 46.00% 15,200.59 441.47 40.40% 13,350.08 148.61


117.13 34.65% 38,142.45 123.15 36.43% 40,101.86 97.76
842.51 43.50% 31,139.10 725.33 37.45% 26,808.26 368.96
567.80 100.00% 13,507.96 0.00
5,991.97 31.90% 24,746.83 8,781.33 46.75% 36,266.91 4,010.30
1.39 34.64% 484.85 0.20
65.20 20.00% 17,962.60 19.56
0.92 23.00% 253.46 0.16
4.40 10.00% 576.14 2.20

754.60 37.73% 3,139.14 60.00


1,200.00 10.00% 8,112.00 306.00

3,849.12

240.00 0.20 20.00% 120.00

119.00 0.14 14.00% 98.00 0.10 10.00% 70.00 0.12

0.50
606,241.16 606,197.53 606,412.91
3,368.63 3,368.39 3,369.59
47,053.58 47,050.20 47,066.91
48,499.29 48,495.80 48,513.03
705,162.67 705,111.92 705,362.45
126,929.28 126,920.15 126,965.24
832,091.95 18.00% 832,032.07 18.00% 832,327.69
6/30/2010

Valorización # 06 Valorización # 07
Feb-11 Mar-11
% S/. Metrado % S/.

0.50 50.00% 14,966.85

14.40% 24,886.19

33.00% 176,702.03

12.46% 27,455.46

27.00% 9,667.38

35.16% 36,344.19

36.25% 29,691.04

20.00% 1,458.18 188.94 61.65% 4,494.85

29.20% 29,554.53

23.63% 14,534.69

21.16% 12,744.24

13.60% 4,494.09

28.92% 31,834.91

19.05% 13,636.78

0.00%
21.35% 16,562.53
5.00% 69.98 2.41 60.36% 844.85

6.00% 5,388.78 241.24 74.00% 66,461.62

4.00% 44.08 2.92 73.00% 804.46

5.00% 288.07 37.40 85.00% 4,897.16

3.00% 249.60 1,185.40 59.27% 4,931.26

2.55% 2,068.56 10,494.00 87.45% 70,939.44

12.00% 84.00 0.10 10.00% 70.00

50.00% 175.00 50.00% 175.00


437,934.32 168,585.48
2,433.42 936.76
33,990.40 13,084.81
35,034.75 13,486.84
509,392.89 196,093.89
91,690.72 35,296.90

13.00% 601,083.61 5.00% 231,390.80 100.00%


CRONOGRAMA EJECUTADO - REPROGRAMACIÓN DE OBRA
Presupuesto 0801025 REHABILITACIÓN CAMINO VECINAL SANGAMA - INCAHUASI
Subpresupuesto 001 PRESUPUESTO BASE
Cliente M.T.C. - PROVIAS DESCENTRALIZADO Costo al
Lugar LAMBAYEQUE - FERREÑAFE - INCAHUASI

Valorización # 01 Valorización # 02 Valorización # 03 Valorización # 04


Item Descripción Und. Metrado Precio S/. Parcial S/. Set-10 Oct-10 Nov-10 Dec-10
Metrado % S/. Metrado % S/. Metrado % S/. Metrado % S/.
01 OBRAS PRELIMINARES 60,892.25
01.01 CAMPAMENTO PROVISIONAL glb 1.00 2,700.00 2,700.00 1.00 100.00% 2,700.00
01.02 MOVILIZACION Y DESMOVILIZACIÓN glb 1.00 29,933.69 29,933.69 0.50 50.00% 14,966.85
01.03 CARTEL DE OBRA und 1.00 1,050.73 1,050.73 1.00 100.00% 1,050.73
01.04 TRAZO, NIVELACIÓN Y REPLANTEO km 43.72 622.32 27,207.83 43.72 100.00% 27,207.83
02 MOVIMIENTO DE TIERRAS 1,204,644.30
02.01 EXCAVACIÓN EN MATERIAL SUELTO m3 25,070.45 3.58 89,752.21 10,028.18 40.00% 35,900.88 15,042.27 60.00% 53,851.33
02.02 EXCAVACIÓN EN MATERIALCOMPACTO m3 44,982.78 4.46 200,623.20 11,245.70 25.00% 50,155.80 28,429.12 63.20% 126,793.86 5,307.97 11.80% 23,673.54
02.03 EXCAVACIÓN ROCA SUELTA m3 10,232.00 18.64 190,724.48 2,660.32 26.00% 49,588.36 5,116.00 50.00% 95,362.24 1,841.76 18.00% 34,330.41 613.92 6.00% 11,443.47
02.04 EXCAVACIÓN ROCA FIJA m3 675.65 21.56 14,567.01 189.18 28.00% 4,078.76 270.26 40.00% 5,826.80 135.13 20.00% 2,913.40 81.08 12.00% 1,748.04
02.05 RELLENO COMPACTADO CON MATERIAL PROPIO d < 120 m m3 9,871.52 5.14 50,739.61 2,665.31 27.00% 13,699.69 5,725.48 58.00% 29,428.97 691.01 7.00% 3,551.77 789.72 8.00% 4,059.17
02.06 RELLENO COMPACTADO CON MATERIAL PROPIO Dprom=3.67 km m3 32,081.23 5.14 164,897.52 7,699.50 24.00% 39,575.40 18,607.11 58.00% 95,640.56 4,715.94 14.70% 24,239.94 1,058.68 3.30% 5,441.62
02.07 TRANSPORTE DE MATERIAL PROPIO D=3.67 Km m3 9,871.52 4.77 47,087.15 2,497.49 25.30% 11,913.05 5,034.48 51.00% 24,014.45 1,974.30 20.00% 9,417.43 365.25 3.70% 1,742.22
02.08 TRANSPORTE DE MATERIAL EXCEDENTE D=10.768 km m3 39,008.14 11.44 446,253.12 10,532.20 27.00% 120,488.34 19,113.99 49.00% 218,664.03 3,900.81 10.00% 44,625.31
03 PAVIMENTOS 928,630.27
03.01 PERFILADO Y COMPACTACIÓN DE LA SUBRASANTE m2 108,692.31 1.59 172,820.77 21,738.46 20.00% 34,564.15 17,390.77 16.00% 27,651.32
03.02 AFIRMADO m3 32,790.00 16.33 535,460.70 4,918.50 15.00% 80,319.11 5,246.40 16.00% 85,673.71
03.03 TRANSPORTE DE MATERIAL D=5.95 Km m3 32,790.00 6.72 220,348.80 12,460.20 38.00% 83,732.54 7,213.80 22.00% 48,476.74
04 OBRAS DE ARTE Y DRENAJE 891,287.83
04.01 CUNETAS 59,022.00
04.01.01 CUNETAS SIN REVESTIR m 43,720.00 1.35 59,022.00 30,604.00 70.00% 41,315.40
04.02 ALCANTARILLAS 365,230.51
04.02.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 1,178.77 30.24 35,646.00 412.57 35.00% 12,476.10 412.57 35.00% 12,476.10 229.86 19.50% 6,950.97 123.77 10.50% 3,742.83
04.02.02 CONCRETO f'c=140 kg/cm2 m3 120.41 297.36 35,805.12 24.08 20.00% 7,161.02 27.69 23.00% 8,235.18
04.02.03 CONCRETO f'c=210 kg/cm2 m3 317.44 325.63 103,367.99 32.70 10.30% 10,646.90 79.36 25.00% 25,842.00
04.02.04 ENCOFRADO Y DESENCOFRADO m2 2,216.08 36.96 81,906.32 323.55 14.60% 11,958.32 586.15 26.45% 21,664.22
04.02.05 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO m3 306.47 23.79 7,290.92
04.02.06 ACERO FY=4200 KG/CM2 kg 24,507.06 4.13 101,214.16 3,480.00 14.20% 14,372.41 6,616.91 27.00% 27,327.82
04.03 BADENES 161,242.98
04.03.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 801.30 30.24 24,231.31 641.04 80.00% 19,385.05 160.26 20.00% 4,846.26
04.03.02 REFINE Y COMPACTACION DE TERRENO m2 100.16 11.61 1,162.86 35.06 35.00% 407.00 50.08 50.00% 581.43 15.02 15.00% 174.43
04.03.03 ENCOFRADO Y DESENCOFRADO m2 381.80 36.96 14,111.33 114.54 30.00% 4,233.40 145.08 38.00% 5,362.31
04.03.04 EMBOQUILLADO DE PIEDRA m2 1,001.62 61.41 61,509.48 234.88 23.45% 14,423.97 265.03 26.46% 16,275.41
04.03.05 GAVIONES m3 358.50 168.00 60,228.00 99.81 27.84% 16,767.48 90.88 25.35% 15,267.80
04.04 MUROS DE SOSTENIMIENTO 305,792.34
04.04.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 1,092.75 30.24 33,044.76 502.67 46.00% 15,200.59
04.04.02 CONCRETO f'c=210 kg/cm2 m3 338.05 325.63 110,079.22 117.13 34.65% 38,142.45
04.04.03 ENCOFRADO Y DESENCOFRADO X 1,936.80 36.96 71,584.13 842.51 43.50% 31,139.10
04.04.04 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO m3 567.80 23.79 13,507.96
04.04.05 ACERO FY=4200 KG/CM2 kg 18,783.60 4.13 77,576.27 5,991.97 31.90% 24,746.83
05 SEÑALIZACIÓN 98,076.04
05.01 SEÑALES INFORMATIVAS und 4.00 349.92 1,399.68
05.02 SEÑALES PREVENTIVAS und 326.00 275.50 89,813.00
05.03 SEÑALES REGLAMENTARIAS und 4.00 275.50 1,102.00
05.04 HITO KILOMETRICO und 44.00 130.94 5,761.36
06 IMPACTO AMBIENTAL 185,048.72
06.01 PROGRAMA DE PREVENCIÓN, CONTROL Y MITIGACIÓN 173,720.00
06.01.01 REACONDICIONAMIENTO AREA OCUPADA POR PATIO DE MAQUINAS Y EQUIPOS m2 2,000.00 4.16 8,320.00
06.01.02 REHABILITACIÓN DE CANTERAS m2 12,000.00 6.76 81,120.00
06.01.03 CONSTRUCCIÓN DE DEPOSITO DE MATERIALES EXCEDENTES m2 14,000.00 6.02 84,280.00 14,000.00 100.00% 84,280.00
06.02 PROGRAMA DE SEÑALIZACIÓN 8,316.60
06.02.01 SEÑALES DE TRABAJO PROVISIONALES und 6.00 219.70 1,318.20 6.00 100.00% 1,318.20
06.02.02 SEÑALES INFORMATIVAS DEFINITIVAS und 20.00 349.92 6,998.40 9.00 45.00% 3,149.28 11.00 55.00% 3,849.12
06.03 PROGRAMA DE CAPACITACIÓN Y MONITOREO AMBIENTAL 600.00
06.03.01 PROGRAMA DE EDUCACIÓN Y MONITOREO AMBIENTAL und 1.00 600.00 600.00 0.40 40.00% 240.00 40.00% 240.00
06.04 PLAN DE MEDIDAS DE CONTROL DE ACCIDENTES O CONTINGENCIAS 700.00
06.04.01 PROGRAMA DE CONTINGENCIAS und 1.00 700.00 700.00 0.17 17.00% 119.00 0.20 20.00% 140.00 0.17 17.00% 119.00 0.14 14.00% 98.00
06.05 MANEJO DE RESIDUOS SÓLIDOS Y PELIGROSOS 1,712.12
06.05.01 CONTENEDOR DE RESIDUOS SÓLIDOS und 4.00 340.53 1,362.12 4.00 100.00% 1,362.12
06.05.02 DISPOCICIÓN FINAL DE RESIDUOS PELIGROSOS glb 1.00 350.00 350.00
COSTO DIRECTO 3,368,579.41 370,424.83 572,599.63 606,303.34 505,221.53
GASTOS GENERALES FIJOS (0.56% Costo Directo) 18,717.82 2,058.30 3,181.70 3,368.98 2,807.31
GASTOS GENERALES VARIABLES (7.76% Costo Directo) 261,453.27 28,750.63 44,442.49 47,058.41 39,212.92
UTILIDAD 8% 269,486.35 29,633.99 45,807.97 48,504.27 40,417.72
SUB TOTAL 3,918,236.85 430,867.75 666,031.79 705,235.00 587,659.48
I.G.V. (18% SUB TOTAL) 705,282.63 77,556.20 119,885.72 126,942.30 105,778.71
TOTAL PRESUPUESTO 4,623,519.49 11.00% 508,423.95 17.00% 785,917.51 18.00% 832,177.30 15.00% 693,438.19
MACIÓN DE OBRA

6/30/2010 6/30/2010

Valorización # 05 Valorización # 06 Valorización # 07


Jan-11 Feb-11 Mar-11
Metrado % S/. Metrado % S/. Metrado % S/.

0.50 50.00% 14,966.85

5,461.14 14.00% 62,475.44

21,738.46 20.00% 34,564.15 47,824.62 44.00% 76,041.14


9,837.00 30.00% 160,638.21 12,788.10 39.00% 208,829.67
9,686.17 29.54% 65,091.04 3,429.83 10.46% 23,048.48

13,116.00 30.00% 17,706.60

36.12 30.00% 10,741.54 32.51 27.00% 9,667.38


93.77 29.54% 30,534.90 111.61 35.16% 36,344.19
503.05 22.70% 18,592.73 803.33 36.25% 29,691.04
56.24 18.35% 1,337.88 250.23 81.65% 5,953.04
7,254.09 29.60% 29,959.39 7,156.06 29.20% 29,554.53

122.18 32.00% 4,515.63


265.03 26.46% 16,275.41 236.68 23.63% 14,534.69
91.96 25.65% 15,448.48 75.86 21.16% 12,744.24

441.47 40.40% 13,350.08 148.61 13.60% 4,494.09


123.15 36.43% 40,101.86 97.76 28.92% 31,834.91
725.33 37.45% 26,808.26 368.96 19.05% 13,636.78
567.80 100.00% 13,507.96 0.00 0.00%
8,781.33 46.75% 36,266.91 4,010.30 21.35% 16,562.53

1.39 34.64% 484.85 1.52 38.00% 531.88 1.09 27.36% 382.95


65.20 20.00% 17,962.60 195.60 60.00% 53,887.80 65.20 20.00% 17,962.60
0.92 23.00% 253.46 2.20 55.00% 606.10 0.88 22.00% 242.44
4.40 10.00% 576.14 22.00 50.00% 2,880.68 17.60 40.00% 2,304.54

754.60 37.73% 3,139.14 1,000.00 50.00% 4,160.00 245.40 12.27% 1,020.86


1,200.00 10.00% 8,112.00 2,400.00 20.00% 16,224.00 8,400.00 70.00% 56,784.00

0.20 20.00% 120.00

0.10 10.00% 70.00 0.12 12.00% 84.00 0.10 10.00% 70.00

1.00 100.00% 350.00


628,634.65 591,661.18 93,734.25
3,493.07 3,287.62 520.84
48,791.66 45,921.95 7,275.21
50,290.77 47,332.89 7,498.74
731,210.15 688,203.65 109,029.04
131,617.83 123,876.66 19,625.23
18.66% 862,827.98 17.56% 812,080.30 2.78% 128,654.27 100.00%
FORMULA POLINÓMICA

PLAZO DE EJECUCIÓN: 6 MESES


INICIO : 15 DE SETIEMBRE DEL 2010
ZONA GEOGRÁFICA: N°01
FECHA BASE DE PRESUPUESTO: 30 DE JUNIO DEL 2010

Incidencia Jun-10 Aug-10 Set-10 Oct-10 Nov-10


Simbolo IU Concepto Coef.
(%) Indice Base Incidencia Indice Incidencia Indice Incidencia Indice Incidencia Indice Incidencia
J 47 Mano de Obra inc. Leyes Sociales 0.192 100.00% 415.58 0.192 430.83 0.199 430.83 0.199 430.83 0.199 430.83 0.199
MAC 2 Acero de construcción Liso 0.113 37.17% 518.90 0.113 512.32 0.042 512.17 0.042 517.91 0.042 520.51 0.042
21 Cemento Portland Tipo I 22.12% 416.97 416.97 0.020 416.97 0.020 416.97 0.020 416.97 0.020
43 Madera Nacional para Enc. Y Carp. 40.71% 566.82 571.97 0.051 573.23 0.051 572.55 0.051 569.51 0.051
MQUI 49 Maquinaria y equipo importado 0.315 100.00% 243.50 0.315 240.59 0.311 239.56 0.310 239.47 0.310 240.48 0.311
MQN 48 Maquinaria y equipo Nacional 0.224 100.00% 334.06 0.224 332.05 0.223 330.41 0.222 330.88 0.222 331.7 0.222
I 39 Gastos generales y Utilidad 0.156 100.00% 352.39 0.156 354.62 0.157 354.51 0.157 354.01 0.157 354.04 0.157
Coeficiente de reajuste (k) 1.00 1.000 1.003 1.0005 1.0008 1.0027

Incidencia Jun-10 Dec-10 Jan-11 Feb-11 Mar-11


Simbolo IU Concepto Coef.
(%) Indice Base Incidencia Indice Incidencia Indice Incidencia Indice Incidencia Indice Incidencia
J 47 Mano de Obra inc. Leyes Sociales 0.192 100.00% 415.58 0.192 430.83 0.199 427.68 0.198 427.68 0.198 427.68 0.198
MAC 2 Acero de construcción Liso 0.113 37.17% 518.90 0.113 522.36 0.043 533.49 0.043 578.78 0.047 586.17 0.048
21 Cemento Portland Tipo I 22.12% 416.97 416.97 0.020 446.74 0.022 416.97 0.020 415.9 0.020
43 Madera Nacional para Enc. Y Carp. 40.71% 566.82 571.11 0.051 574.7 0.051 582.39 0.052 584.31 0.052
MQUI 49 Maquinaria y equipo importado 0.315 100.00% 243.50 0.315 240.97 0.312 238.94 0.309 238.57 0.309 240.07 0.311
MQN 48 Maquinaria y equipo Nacional 0.224 100.00% 334.06 0.224 332.35 0.223 331.54 0.222 331.31 0.222 332.16 0.223
I 39 Gastos generales y Utilidad 0.156 100.00% 352.39 0.156 354.67 0.157 356.05 0.158 357.41 0.158 359.92 0.159
Coeficiente de reajuste (k) 1.00 1.000 1.0043 1.0030 1.0059 1.0102

Incidencia Jun-10 Apr-11


Simbolo IU Concepto Coef.
(%) Indice Base Incidencia Indice Incidencia
J 47 Mano de Obra inc. Leyes Sociales 0.192 100.00% 415.58 0.192 427.68 0.198
MAC 2 Acero de construcción Liso 0.113 37.17% 518.90 0.113 591.89 0.048
21 Cemento Portland Tipo I 22.12% 416.97 415.9 0.020
43 Madera Nacional para Enc. Y Carp. 40.71% 566.82 579.69 0.052
MQUI 49 Maquinaria y equipo importado 0.315 100.00% 243.50 0.315 243.55 0.315
MQN 48 Maquinaria y equipo Nacional 0.224 100.00% 334.06 0.224 334.3 0.224
I 39 Gastos generales y Utilidad 0.156 100.00% 352.39 0.156 362.38 0.160
Coeficiente de reajuste (k) 1.00 1.000 1.0173
CALCULO DE REAJUSTES

Fórmula: R = V*(K-1)
Donde: R: Reajuste del componente en $. De la valorizacion Mensual.
V: Monto del Componente en $. De la valorización Mensual.
K: Coeficiente de reajuste obtenido por la aplicación de la Fórmula Polinómica.

Avance Mensual factor de reajuste R = reajuste r = 𝑽_𝒙 (𝒌−𝟏) Reajustes


Valoriz.
Periodo Programado Ejecutado mes siguiente a la Programado Ejecutado mes Reaj Reconocido
k r = 𝑽_𝒙 (𝒌−𝟏)
V Parcial Acumulado Parcial Acumulado val. parcial acumulado parcial acumulado acumulado
1 Sep-10 391,858.83 391,858.83 430,867.75 430,867.75 Oct-10 1.0008 332.07 332.07 365.13 365.13 365.13 365.13
2 Oct-10 705,254.19 1,097,113.02 666,031.79 1,096,899.54 Nov-10 1.0027 1,874.37 2,206.44 1,770.13 2,135.26 1,770.13 2,135.26
3 Nov-10 705,162.67 1,802,275.70 705,235.00 1,802,134.54 Dec-10 1.0043 3,031.95 5,238.40 3,032.26 5,167.52 3,032.26 5,167.52
4 Dec-10 705,111.92 2,507,387.62 587,659.48 2,389,794.02 Jan-11 1.0030 2,083.67 7,322.07 1,736.59 6,904.11 1,736.59 6,904.11
5 Jan-11 705,362.45 3,212,750.07 731,210.15 3,121,004.17 Feb-11 1.0059 4,129.67 11,451.74 4,281.00 11,185.11 4,281.00 11,185.11
6 Feb-11 509,392.89 3,722,142.96 688,203.65 3,809,207.81 Mar-11 1.0102 5,194.42 16,646.16 7,017.80 18,202.91 7,017.80 18,202.91
7 Mar-11 196,093.89 3,918,236.85 109,029.04 3,918,236.85 Apr-11 1.0173 3,387.88 20,034.04 1,883.68 20,086.59 1,831.13 20,034.04
3,918,236.85 20,034.04
DEDUCCION DEL REAJUSTE POR ADELANTO DIRECTO

Fórmula: D = A / C * v * (Kr / Ka - 1)

Donde: D: Deducción del reajuste generado por el adelanto directo


A: Monto del adelanto directo concedido al contratiste 14%
V: Monto de la Valorización mensual
C: Saldo del contrato por valorizar a la fecha de pago del adelanto directo
Kr: Coeficiente de reajuste de la valorizacion obtenido por la aplicación de la formula polinómica
Ka: Coeficiente de reajuste que corresponde al mes en que se cancelo el pago del adelanto directo.

A = 548,553.16 (Sep-10)

C = 3,918,236.85

Amortización Deducción del Reajuste


Ka (Sep - Mes siguiente a la
Nº VAL Periodo V A / C * V ($.) Kr D
10) Val.
1 Sep-10 430,867.75 60,321.49 1.0005 Oct-10 1.0008 23.16
2 Oct-10 666,031.79 93,244.45 1.0005 Nov-10 1.0027 204.52
3 Nov-10 705,235.00 98,732.90 1.0005 Dec-10 1.0043 378.59
4 Dec-10 587,659.48 82,272.33 1.0005 Jan-11 1.0030 204.91
5 Jan-11 731,210.15 102,369.42 1.0005 Feb-11 1.0059 551.65
6 Feb-11 688,203.65 96,348.51 1.0005 Mar-11 1.0102 937.41
7 Mar-11 109,029.04 15,264.07 1.0005 Apr-11 1.0173 256.52
Totales 548,553.16 2,556.77
DEDUCCIÓN DEL REAJUSTE POR ADELANTO DE MATERIALES

Formula: 𝑫 * 𝑨 * ( (𝑰𝒎𝒓 (en concordancia con D.S. Nº 011-79-VC y D.S. Nº 017-79-VC)


−𝑰𝒎𝒂)/𝑰𝒎𝒐 )

Donde: D : Deducción del reajuste generado por el adelanto de materiales Adelanto de Materiales: 3 6.00 % = 1,410,565.27
A : Monto deducido final hasta completar el total del adelanto otorgado.
Imr : Indice del precio del material a la fecha del reajuste.
Ima : Indice de precio del material a la fecha efectiva del adelanto.
Imo : Indice de precios del material a la fecha del presupuesto Base (Jun - 2010)

Adel mat deflatado


monto utilizado D deducción del
saldo adel mat Imr mes Ima a la fecha Imo a la fecha
Mes de Ima (fecha Imo (Jun monto bruto coeficiente en valorizacion a A monto deducido a la fecha del reajuste d =
Nº adelanto otorgado utilizable en siguiente a la del adelanto del Ppto Base
valorización adel) -10) a la fecha del Ppto ($.) (1) incidencia (2) la fecha del Ppto
valorización (4)
final mínimo (3,4) (5)
val
reajuste (6)
(7) a(Imr-Ima)/Imo
Base (3=1*2) Jun - 10 (8)
Base ($.) (9=5*(6-7)/8)

Amortización del adelanto Nº 01 para materiales

Iu 2 Aug-10
3 Nov-10 S/. 705,235.00 0.0420 S/. 29,619.76 S/. 531,012.49 S/. 29,619.76 Dec-10 522.36 S/. 512.32 S/. 518.90 S/. 573.10
4 Dec-10 S/. 587,659.48 0.0420 S/. 24,681.60 S/. 501,392.74 S/. 24,681.60 Jan-11 533.49 S/. 512.32 S/. 518.90 S/. 1,006.96
5 Jan-11 S/. 731,210.15 0.0420 S/. 30,710.71 S/. 476,711.13 S/. 30,710.71 Feb-11 578.78 S/. 512.32 S/. 518.90 S/. 3,933.39
6 Feb-11 S/. 688,203.65 0.0420 S/. 28,904.44 S/. 446,000.42 S/. 28,904.44 Mar-11 586.17 S/. 512.32 S/. 518.90 S/. 4,113.69
SUBTOTAL: S/. 524,278.90 S/. 512.32 S/. 518.90 S/. 531,012.49 S/. 9,627.13

Iu 21 Aug-10
3 Nov-10 S/. 705,235.00 0.0250 S/. 17,630.96 S/. 312,073.46 S/. 17,630.96 Dec-10 416.97 S/. 416.97 S/. 416.97 S/. 0.00
4 Dec-10 S/. 587,659.48 0.0250 S/. 14,691.56 S/. 294,442.50 S/. 14,691.56 Jan-11 446.74 S/. 416.97 S/. 416.97 S/. 1,048.92
5 Jan-11 S/. 731,210.15 0.0250 S/. 18,280.34 S/. 279,750.94 S/. 18,280.34 Feb-11 416.97 S/. 416.97 S/. 416.97 S/. 0.00
6 Feb-11 S/. 688,203.65 0.0250 S/. 17,205.17 S/. 261,470.60 S/. 17,205.17 Mar-11 415.9 S/. 416.97 S/. 416.97 S/. 44.15
7 Mar-11 S/. 109,029.04 0.0250 S/. 2,725.74 S/. 244,265.43 S/. 2,725.74 Apr-11 415.9 S/. 416.97 S/. 416.97 S/. 6.99
SUBTOTAL: S/. 312,073.46 S/. 416.97 S/. 416.97 S/. 312,073.46 S/. 997.77

Iu 43 Aug-10
2 Oct-10 S/. 666,031.79 0.0460 S/. 30,637.49 S/. 579,430.08 S/. 30,637.49 Nov-10 569.51 S/. 571.97 S/. 566.82 S/. 132.97
3 Nov-10 S/. 705,235.00 0.0460 S/. 32,440.84 S/. 548,792.59 S/. 32,440.84 Dec-10 571.11 S/. 571.97 S/. 566.82 S/. 49.22
4 Dec-10 S/. 587,659.48 0.0460 S/. 27,032.36 S/. 516,351.75 S/. 27,032.36 Jan-11 574.7 S/. 571.97 S/. 566.82 S/. 130.20
5 Jan-11 S/. 731,210.15 0.0460 S/. 33,635.70 S/. 489,319.39 S/. 33,635.70 Feb-11 582.39 S/. 571.97 S/. 566.82 S/. 618.33
6 Feb-11 S/. 688,203.65 0.0460 S/. 31,657.40 S/. 455,683.70 S/. 31,657.40 Mar-11 584.31 S/. 571.97 S/. 566.82 S/. 689.20
7 Mar-11 S/. 109,029.04 0.0460 S/. 5,015.34 S/. 424,026.30 S/. 5,015.34 Apr-11 579.69 S/. 571.97 S/. 566.82 S/. 68.31
SUBTOTAL: S/. 574,212.91 S/. 571.97 S/. 566.82 S/. 579,430.08 S/. 1,323.85

TOTAL: S/. 1,410,565.27 S/. 1,422,516.03 S/. 1,422,516.03 S/. 11,948.76


INTERESES POR MORA EN PAGO DE VALORIZACIONES

Concepto
Contrato Principal
PRESUPUESTO BASE CON FECHA AL 30 DE JUNIO DEL 2010

Item Descripción Und. Metrado Precio S/.

01 OBRAS PRELIMINARES
01.01 CAMPAMENTO PROVISIONAL glb 1.00 2,700.00
01.02 MOVILIZACION Y DESMOVILIZACIÓN glb 1.00 29,933.69
01.03 CARTEL DE OBRA und 1.00 1,050.73
01.04 TRAZO, NIVELACIÓN Y REPLANTEO km 43.72 622.32
02 MOVIMIENTO DE TIERRAS
02.01 EXCAVACIÓN EN MATERIAL SUELTO m3 25,070.45 3.58
02.02 EXCAVACIÓN EN MATERIALCOMPACTO m3 44,982.78 4.46
02.03 EXCAVACIÓN ROCA SUELTA m3 10,232.00 18.64
02.04 EXCAVACIÓN ROCA FIJA m3 675.65 21.56
02.05 RELLENO COMPACTADO CON MATERIAL PROPIO d < 120 m m3 9,871.52 5.14
02.06 RELLENO COMPACTADO CON MATERIAL PROPIO Dprom=3.67 km m3 32,081.23 5.14
02.07 TRANSPORTE DE MATERIAL PROPIO D=3.67 Km m3 9,871.52 4.77
02.08 TRANSPORTE DE MATERIAL EXCEDENTE D=10.768 km m3 39,008.14 11.44
03 PAVIMENTOS
03.01 PERFILADO Y COMPACTACIÓN DE LA SUBRASANTE m2 108,692.31 1.59
03.02 AFIRMADO m3 32,790.00 16.33
03.03 TRANSPORTE DE MATERIAL D=5.95 Km m3 32,790.00 6.72
04 OBRAS DE ARTE Y DRENAJE
04.01 CUNETAS
04.01.01 CUNETAS SIN REVESTIR m 43,720.00 1.35
04.02 ALCANTARILLAS
04.02.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 1,178.77 30.24
04.02.02 CONCRETO f'c=140 kg/cm2 m3 120.41 297.36
04.02.03 CONCRETO f'c=210 kg/cm2 m3 317.44 325.63
04.02.04 ENCOFRADO Y DESENCOFRADO m2 2,216.08 36.96
04.02.05 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO m3 306.47 23.79
04.02.06 ACERO FY=4200 KG/CM2 kg 24,507.06 4.13
04.03 BADENES
04.03.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 801.30 30.24
04.03.02 REFINE Y COMPACTACION DE TERRENO m2 100.16 11.61
04.03.03 ENCOFRADO Y DESENCOFRADO m2 381.80 36.96
04.03.04 EMBOQUILLADO DE PIEDRA m2 1,001.62 61.41
04.03.05 GAVIONES m3 358.50 168.00
04.04 MUROS DE SOSTENIMIENTO
04.04.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 1,092.75 30.24
04.04.02 CONCRETO f'c=210 kg/cm2 m3 338.05 325.63
04.04.03 ENCOFRADO Y DESENCOFRADO m2 1,936.80 36.96
04.04.04 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO m3 567.80 23.79
04.04.05 ACERO FY=4200 KG/CM2 kg 18,783.60 4.13
05 SEÑALIZACIÓN
05.01 SEÑALES INFORMATIVAS und 4.00 349.92
05.02 SEÑALES PREVENTIVAS und 326.00 275.50
05.03 SEÑALES REGLAMENTARIAS und 4.00 275.50
05.04 HITO KILOMETRICO und 44.00 130.94
06 IMPACTO AMBIENTAL
06.01 PROGRAMA DE PREVENCIÓN, CONTROL Y MITIGACIÓN
06.01.01 REACONDICIONAMIENTO AREA OCUPADA POR PATIO DE MAQUINAS Y EQUI m2 2,000.00 4.16
06.01.02 REHABILITACIÓN DE CANTERAS m2 12,000.00 6.76
06.01.03 CONSTRUCCIÓN DE DEPOSITO DE MATERIALES EXCEDENTES m2 14,000.00 6.02
06.02 PROGRAMA DE SEÑALIZACIÓN
06.02.01 SEÑALES DE TRABAJO PROVISIONALES und 6.00 219.70
06.02.02 SEÑALES INFORMATIVAS DEFINITIVAS und 20.00 349.92
06.03 PROGRAMA DE CAPACITACIÓN Y MONITOREO AMBIENTAL
06.03.01 PROGRAMA DE EDUCACIÓN Y MONITOREO AMBIENTAL und 1.00 600.00
06.04 PLAN DE MEDIDAS DE CONTROL DE ACCIDENTES O CONTINGENCIAS
06.04.01 PROGRAMA DE CONTINGENCIAS und 1.00 700.00
06.05 MANEJO DE RESIDUOS SÓLIDOS Y PELIGROSOS
06.05.01 CONTENEDOR DE RESIDUOS SÓLIDOS und 4.00 340.53
06.05.02 DISPOCICIÓN FINAL DE RESIDUOS PELIGROSOS glb 1.00 350.00
COSTO DIRECTO
GASTOS GENERALES FIJOS (0.56% Costo Directo)
GASTOS GENERALES VARIABLES (7.76% Costo Directo)
UTILIDAD 8%
SUB TOTAL
I.G.V. (18% SUB TOTAL)
TOTAL PRESUPUESTO
Parcial S/.

60,892.25
2,700.00
29,933.69
1,050.73
27,207.83
1,204,644.30
89,752.21
200,623.20
190,724.48
14,567.01
50,739.61
164,897.52
47,087.15
446,253.12
928,630.27
172,820.77
535,460.70
220,348.80
891,287.83
59,022.00
59,022.00
365,230.51
35,646.00
35,805.12
103,367.99
81,906.32
7,290.92
101,214.16
161,242.98
24,231.31
1,162.86
14,111.33
61,509.48
60,228.00
305,792.34
33,044.76
110,079.22
71,584.13
13,507.96
77,576.27
98,076.04
1,399.68
89,813.00
1,102.00
5,761.36
185,048.72
173,720.00
8,320.00
81,120.00
84,280.00
8,316.60
1,318.20
6,998.40
600.00
600.00
700.00
700.00
1,712.12
1,362.12
350.00
3,368,579.41
18,717.82
261,453.27
269,486.35
3,918,236.85
705,282.63
4,623,519.49
MES SETIEMBRE DE 2010 OCTUBRE DE 2010 NOVIEMBRE DE 2010 DICIEMBRE DE 2010 ENERO DE 2011 FEBRERO DE 2011
FECHAS 15 al 16 15 al 15 15 al 16 15 al 15 15 al 15 15 al 15 TOTAL (%)
MES VALORIZADO PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES
VALORIZACIONES
15 18 18 18 18 13 100
PROGRAMADAS
VALORIZACIONES
11 20 18 15 20 18 ----
EJECUTADAS
CONDICION ADELANTADO --- --- --- --- ----
CANTIDAD -26.7% -11.1% 11.1% -16.7% -5.6% 53.8% ----
REPROGRAMACIÓN 11 20 16.62 17.68 19.23 10.47 95
100
SETIEMBRE DE 2010 OCTUBRE DE 2010 NOVIEMBRE DE 2010 DICIEMBRE DE 2010 ENERO DE 2011 FEBRERO DE 2011
9/15/2010 9/30/2010 10/1/2010 31/11/2010 11/1/2010 11/30/2010 12/1/2010 1/31/2010 1/1/2011 1/31/2011 2/1/2011
PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES
11 % 17 % 18 % 15 % 18.66 % 17.56 %
CD S/. 3,368,579.41 S/. 370,543.74 S/. 572,658.50 S/. 606,344.29 S/. 505,286.91 S/. 628,576.92 S/. 591,522.54
GGF S/. 18,717.82 S/. 2,058.96 S/. 3,182.03 S/. 3,369.21 S/. 2,807.67 S/. 3,492.75 S/. 3,286.85
GGV S/. 261,453.27 S/. 28,759.86 S/. 44,447.06 S/. 47,061.59 S/. 39,217.99 S/. 48,787.18 S/. 45,911.19
UTILIDAD S/. 269,486.35 S/. 29,643.50 S/. 45,812.68 S/. 48,507.54 S/. 40,422.95 S/. 50,286.15 S/. 47,321.80
SUB TOTAL S/. 3,918,236.85 S/. 431,006.05 S/. 666,100.26 S/. 705,282.63 S/. 587,735.53 S/. 731,143.00 S/. 688,042.39

VAL. 1 VAL. 2 VAL. 3 VAL. 4 VAL. 5 VAL. 6


MONTO S/. 431,006.05 S/. 666,100.26 S/. 705,282.63 S/. 587,735.53 S/. 731,143.00 S/. 688,042.39

ADELANTO DIRECTO 19% S/. 744,465.00

ADELANTO MATERIALES 39% |=0.39*C14= S/. 1,528,112.37


FEBRERO DE 2011 MARZO DE 2011
2/28/2011 3/1/2011 3/15/2011
SEXTO MES SÉTIMO MES
17.56 % 2.78 %
S/. 591,522.54 S/. 93,646.51
S/. 3,286.85 S/. 520.36
S/. 45,911.19 S/. 7,268.40
S/. 47,321.80 S/. 7,491.72
S/. 688,042.39 S/. 108,926.98

VAL. 7 TOTAL
S/. 108,926.98 S/. 3,918,236.85