ECOPETROL

Informe Taller Constructibilidad


INGENIERÍA DE DETALLE PARA LA
RECONFORMACIÓN E IMPERMEABILIZACIÓN DE
DIQUES Y SUS ÁREAS INTERNAS QUE SE
ENCUENTRAN EN TIERRA EN CPF-2

Document No ECP-UOR-19028-GOR-ID01-0-GEN-IF-002

25 Junio 2019

Carrera 11b #99-25 (WeWork), Piso 15

Bogotá
Colombia
T: +57 1 794 17 93
© Copyright 2019 WorleyParsons
www.worleyparsons.com
Disclaimer
This report has been prepared on behalf of and for the exclusive use of ECOPETROL, and is subject to
and issued in accordance with the agreement between ECOPETROL and WorleyParsons. WorleyParsons
accepts no liability or responsibility whatsoever for it in respect of any use of or reliance upon this report
by any third party. Copying this report without the permission of ECOPETROL or WorleyParsons is not
permitted.

PROJECT ECP-UOR-19028-GOR-ID01-0-GEN-IF-002 – Informe Taller Constructibilidad

WorleyParsons Customer
Rev Description Original Review Date Date
Approval Approval
A Emitido para Comentarios N/A
23-06-2019
del Cliente

FEC GGR JAAM


0 Aprobado para FEC Digitally signed
by German
Digitally signed
by JAIME
ALBERTO
25-06-2019
construcción Garavito AMAYA MUNOZ

FEC GGR JAAM

ECOPETROL
Informe Taller Constructibilidad ii
Contents
1. RESUMEN EJECUTIVO .......................................................................................................................................1
2. DESCRIPCIÓN DEL SISTEMA ..............................................................................................................................4
3. OBJETIVO DEL ESTUDIO ....................................................................................................................................9
4. ALCANCE DEL ESTUDIO / DOCUMENTOS SUMINISTRADOS ...........................................................................10
5. EQUIPO DEL TALLER DE CONSTRUCTIBILIDAD ................................................................................................12
6. METODOLOGÍA ...............................................................................................................................................13
6.1 TÉCNICA CONSTRUCTIBILIDAD ............................................................................................................13
7. PREMISAS Y/O CONSIDERACIONES ESPECIALES .............................................................................................14
8. RESULTADOS ...................................................................................................................................................15
8.1 Secciones del Taller de Constructibilidad ............................................................................................15
8.2 Hoja de Trabajo ...................................................................................................................................15
8.3 Acciones y Recomendaciones ..............................................................................................................15
Tabla 3. Lista de Recomendaciones Taller Constructibilidad ...................................................................................18
Appendix A. Lista de Asistencia ...............................................................................................................................19
Appendix B. Registro hojas de trabajo .....................................................................................................................20

Appendix
Appendix A. Lista de Asistencia
Appendix B. Registro hojas de trabajo

ECOPETROL
Informe Taller Constructibilidad iii
1. RESUMEN EJECUTIVO

Este documento contiene el informe final del estudio de revisión de la constructibilidad del proyecto
de reconformación e impermeabilización de diques y sus áreas internas que se encuentran en tierra en
CPF-2, cuya fase de ingeniería de detalle elabora Worley por encargo de Ecopetrol SA.
El alcance de la ingeniería de detalle incluye las facilidades asociadas a los diques de los tanques de
almacenamiento y proceso que se encuentran en tierra en el CPF2 del campo de producción Rubiales.
El objetivo del análisis ha sido la identificación de los hallazgos de interés en etapas tempranas del
proyecto que puedan afectar la calidad de este, generar sobrecostos o retrasos en la construcción de
las obras civiles necesarias para la operación de las áreas a intervenir.
El Taller de Constructibilidad fue realizado de acuerdo las mejores prácticas de la ingeniería en la
búsqueda de hacer el uso óptimo de los conocimientos de construcción en el diseño y la planeación de
una obra para cumplir con los tiempos y optimizando los presupuestos.
Un equipo multidisciplinario de profesionales de Worley y Ecopetrol S.A, bajo la coordinación de CST
Consultoría (CST en adelante), participaron en la sesión del taller de constructibilidad que tuvo lugar el
miércoles 12 de junio de 2019, en las instalaciones de Ecopetrol sede San Martín en Bogotá.
El equipo de trabajo revisó información contenida en Planos Arquitectónicos, Civiles y Estructurales, a
través de la presentación llevada a cabo por WP, para la instalación del alcance, posteriormente se
realizó una descripción general del planteamiento de las obras, con la intención de identificar posibles
hallazgos que afecten los objetivos del proyecto o generen problemas en la etapa constructiva.
En el taller se analizaron aspectos generales y de logística, relacionados con el proyecto y el sitio de su
implantación; los hallazgos y recomendaciones planteadas se refieren a situaciones de orden legal
(permisos ambientales, certificación de canteras, etc.), climático (inviernos y veranos) y
socioeconómico (movilizaciones sociales). Finalmente se analizaron dificultades relacionadas con el
componente de la ingeniería involucrada en el proyecto (ingeniería civil).
Para la revisión de las actividades, se determinaron cuatro (4) secciones asociadas a Preliminares,
Movimiento de Tierras, Fundición de Concreto, Interferencias; de las cuales se definieron y
documentaron Veintitrés (23) recomendaciones a hallazgos identificados.
Un resumen de las recomendaciones generadas en el estudio se presenta a continuación, sin embargo,
la descripción detallada de las recomendaciones surgidas se incluye en la sección de resultados.

ECOPETROL
Informe Taller Constructibilidad 1
No. Acción
1 Evaluar la posibilidad de usar concreto de menor Resistencia.
2 Garantizar el replanteo de la obra acorde con lo establecido en ingeniería
3 Considerar el uso de una rejilla guía para ir verificando la sección una vez se va avanzando
la construcción.
4 Gestionar sitio de disposición de material sobrante de excavaciones, previo a actividades
de construcción.
5 Considerar ofrecer el material sobrante a otros proyectos.
6 Evaluar desde ingeniería la realineación del dique en el sector de interferencia.
7 Evaluar con proveedores disponibilidad de cantidad de material requerido y tiempos de
entrega.
8 Contemplar dentro el presupuesto contingencias relacionadas al riesgo de cierre de las
vías.
9 Solicitar al contratista adherirse al plan de contingencias de Campo Rubiales.
10 Solicitar al contratista Plan de construcción diferencial y procedimientos de la actividad
manual para las áreas no accesibles.
11 Considerar un vigía, constante capacitación y entrenamiento al personal que realiza el
trabajo manual.
12 Recomendar selección específica de cuadrilla para la realización de trabajo manual.
13 Asegurar que se realice las actividades de detección de elementos enterrados y liberación
de áreas.
14 Considerar la realización de un Plan Integrado de Trabajo con cada uno de los proyectos
paralelos.
15 Solicitar la definición de una estrategia para la emisión de permisos de trabajo y
seguimiento de las actividades en las áreas a cargo de la operación.
16 Definir Plan detallado de trabajo incluyendo demanda de personal con la anticipación
suficiente para realizar solicitud de suministro de recursos.
17 Generar la justificación para que se evalué la posibilidad de dar continuidad al contratista
de obras.
18 Considerar realizar zonificación de área una vez identificada tubería y bancos de ductos
enterrados y aplicar procedimientos de compactación manual.
19 Solicitud al contratista acompañamiento del proveedor tanto en el diseño de mezcla como
en la instalación del concreto, capacitación del personal para garantizar el uso adecuado
de la fibra.
20 Considerar el manejo de bomba de lanzado de concreto en áreas de acceso restringido de
maquinaria.
21 Garantizar la correcta compactación de la subrasante en la rampa de acceso.

ECOPETROL
Informe Taller Constructibilidad 2
No. Acción
22 Evaluar la inclusión de una junta tipo puente vehicular.
23 Evaluar la posibilidad de solicitar desde proceso de contratación trabajo nocturno.
Tabla 1 Resumen Recomendaciones

Debe resaltarse que las recomendaciones del Estudio fueron generadas principalmente cuando se
identificó un hallazgo de interés que pueda afectar el desarrollo de las actividades durante la
construcción o los objetivos del proyecto.
Adicionalmente es necesario resaltar que, pese a que las recomendaciones surgidas intentan generar
seguridad adecuada para los requerimientos del proyecto y contemplando la fase en la que se
encuentra la ingeniería (detalle), las partes responsables por el desarrollo del Plan de Acción final, no
debe restringir la planificación de las actividades y métodos presentados en el ejercicio si se consideran
apropiadas medidas adicionales.

ECOPETROL
Informe Taller Constructibilidad 3
2. DESCRIPCIÓN DEL SISTEMA

Durante la construcción del CPF-2 no se completó la actividad de endurecemiento de los diques


perimetrales de contención de los Tanques de Almacenamiento: 300 TK-0303 Y 300 TK-0203 (100K), los
FWKOS: 3300-TK-0301, 2300-TK-201, 4300-TK-0401 y 5300-TK-0501 (71K), el Tanque de Relevo 300-TK-
002 (36K), los Tanques SKIM1400-K-0101, 2400-TK-0201, 3400-TK-0301 y 4400-TK-0401 (100K), y el
Tanque de Cabeza 2300-TK-0002(41K), dichos diques fueron conformados en suelo natural sin
protección, por lo que presentan deterioro, perdida de material y erosión, causada por los efectos
abrasivos del clima.

Figura 1 Tanque 300-TK-0301 CPF-2

El Campo Rubiales está localizado en el departamento del Meta, 167 km al oriente del municipio de
Puerto Gaitán, en un polígono cuyas coordenadas UTM son las siguientes: 905.400 N, 955.500 E y
920.400 N, 970.000 E, como se ilustra en la Figura 2.

ECOPETROL
Informe Taller Constructibilidad 4
Figura 2 Ubicación General

La ingeniería por desarrollar se requiere para la facilidad denominada CPF-2 del Campo Rubiales,
particularmente abarca las áreas aferentes a los tanques de almacenamiento y proceso de esta
facilidad, los cuales se describen y agrupan a continuación:

Figura 3 Distribución de las áreas a intervenir

ECOPETROL
Informe Taller Constructibilidad 5
El Área 1 está conformada por:

Tanque de Almacenamiento 300 TK-0303 (100 K)


Tanque de Almacenamiento 300 TK-0203 (100 K)
FWKO 3 300-TK-0301 (71 K)
FWKO 2 300-TK-0201 (71 K)
FWKO 4 300-TK-0401 (71 K)

Figura 4 Área 1

El área 2 está conformado por:

FWKO 4 300-TK-0401 (71 K)


Tanque de Relevo 300-TK-0002 (36 K)

ECOPETROL
Informe Taller Constructibilidad 6
Figura 5 Área 2

El área 3 está conformado por:

FWKO 5 300-TK-0501 (71 K)


Tanque SKIM 1 400-TK-0101 (100 K)
Tanque SKIM 2 400-TK-0201 (100 K)
Tanque SKIM 3 400-TK-0301 (100 K)
Tanque SKIM 4 400-TK-0401 (100 K)
Tanque de Cabeza 2 300-TK-0002 (41 K)

ECOPETROL
Informe Taller Constructibilidad 7
Figura 6 Área 3

Procesos Constructivo Obras Civiles CPF-2


1. Preliminares.
2. Movimientos de Tierra.
3. Fundicion de Concreto.
4. Interferencias.

ECOPETROL
Informe Taller Constructibilidad 8
3. OBJETIVO DEL ESTUDIO

El objetivo del estudio de revisión de constructibilidad es realizar mediante un ejercicio plural,


multidisciplinario y concertado, la identificación de eventuales situaciones que pueden afectar el logro
del alcance, cumplimiento, costo, seguridad, calidad y nivel de riesgo del proceso de construcción o
implantación del proyecto Ingeniería de detalle de reconformación e impermeabilización de diques y
sus áreas internas que se encuentran en tierra en CPF-2.

ECOPETROL
Informe Taller Constructibilidad 9
4. ALCANCE DEL ESTUDIO / DOCUMENTOS SUMINISTRADOS

El Proyecto ”INGENIERÍA DE DETALLE PARA LA RECONFORMACIÓN E IMPERMEABILIZACIÓN DE DIQUES


Y SUS ÁREAS INTERNAS QUE SE ENCUENTRAN EN TIERRA EN CPF-2”, a ser ejecutado por ECOPETROL
S.A, consiste en el planteamiento de alternativas para el endurecimiento de los pisos y corredores
vehiculares de los recintos de los tanques, verificación y validación de la ingeniería desarrollada para
los diques perimetrales de contención, diseño de las obras requeridas para la conformación e
impermeabilización de los muros internos para contención primarias y las áreas internas, para los
diques de los tanques que se encuentran en tierra en el CPF-2 del campo de producción Rubiales,
Operados por Ecopetrol S.A.
La información suministrada por WP para el desarrollo del estudio se muestra en la siguiente tabla.

Fecha de
Código Descripción Rev.
emisión
PLANO DE MOVIMIENTO DE TIERRA ÁREA
ECP-UOR-19028-GOR-ID01-0-CIV-PL-
1 - PLANTA SECCIONES DE CORTE Y A 28/05/2019
005_1DE2-A.pdf
RELLENO
PLANO DE MOVIMIENTO DE TIERRA -
ECP-UOR-19028-GOR-ID01-0-CIV-PL-
ÁREA 1 - PLANTA SECCIONES DE CORTE Y A 28/05/2019
005_2DE2-A.pdf
RELLENO
PLANO DE MOVIMIENTO DE TIERRAS
ECP-UOR-19028-GOR-ID01-0-CIV-PL-
ÁREA 2 - PLANTA Y SECCIONES DE CORTE A 28/05/2019
006_1DE2-A.pdf
Y RELLENO
PLANO DE MOVIMIENTO DE TIERRAS
ECP-UOR-19028-GOR-ID01-0-CIV-PL-
ÁREA 2 - PLANTA Y SECCIONES DE CORTE A 28/05/2019
006_2DE2-A.pdf
Y RELLENO
ECP-UOR-19028-GOR-ID01-0-CIV-PL- PLANO DE VÍAS DE ACCESO ÁREA 1 -
A 28/05/2019
008_1DE2-A.pdf PLANTA Y PERFIL
ECP-UOR-19028-GOR-ID01-0-CIV-PL- PLANO DE VÍAS DE ACCESO ÁREA 1 -
A 28/05/2019
008_2DE2-A.pdf PLANTA Y PERFIL
ECP-UOR-19028-GOR-ID01-0-CIV-PL- PLANO DE VÍAS DE ACCESO ÁREA 2 -
A 28/05/2019
009_2DE2-A.pdf PLANTA Y PERFIL
ECP-UOR-19028-GOR-ID01-0-CIV-PL- PLANO DE REVESTIMIENTO EN
A 24/05/2019
014_1DE2-A.pdf CONCRETO PARA DIQUES
ECP-UOR-19028-GOR-ID01-0-CIV-PL- PLANO DE REVESTIMIENTO EN
A 24/05/2019
014_2DE2-A.pdf CONCRETO PARA DIQUES
ECP-UOR-19028-GOR-ID01-0-CIV-PL-
PLANO DE RED DE DRENAJES - ÁREA 1 A 17/05/2019
015_1DE1-A.pdf
ECP-UOR-19028-GOR-ID01-0-CIV-PL-
PLANO DE RED DE DRENAJES - ÁREA 2 A 17/05/2019
016_1DE1-A.pdf
ECP-UOR-19028-GOR-ID01-0-CIV-PL- PLANO GENERAL DE OBRAS CIVILES -
A 17/05/2019
017_1DE1-A.pdf ÁREA 3
ECP-UOR-19028-GOR-ID01-0-CIV-PL- PLANOS TÍPICOS DETALLES REDES DE
A 17/05/2019
018_1DE1-0.pdf DRENAJE

ECOPETROL
Informe Taller Constructibilidad 10
Fecha de
Código Descripción Rev.
emisión
ECP-UOR-19028-GOR-ID01-0-CIV-PL- PLANOS TÍPICOS DETALLES REDES DE
0 24/05/2019
018_1DE1-0_.pdf DRENAJE
IMPERMEABILIZACION DE AREAS
ECP-UOR-19028-GOR-ID01-0-CIV-PL-
INTERNAS A LOS DIQUES PARA A 29/05/2019
020-1DE3-A.pdf
ALTERNATIVA SELECCIONADA - AREA 1
IMPERMEABILIZACION DE AREAS
ECP-UOR-19028-GOR-ID01-0-CIV-PL-
INTERNAS A LOS DIQUES PARA A 29/05/2019
020-2DE3-A.pdf
ALTERNATIVA SELECCIONADA - AREA 2
IMPERMEABILIZACION DE AREAS
ECP-UOR-19028-GOR-ID01-0-CIV-PL-
INTERNAS A LOS DIQUES PARA A 29/05/2019
020-3DE3-A.pdf
ALTERNATIVA SELECCIONADA - AREA 3
ECP-UOR-19028-GOR-ID01-0-CIV-PL- PLANO DE DETALLE DE LA ESTRUCTURA
A 29/05/2019
021-1DE1-A.pdf DE PAVIMENTOS PARA VIAS DE ACCESO
ODS-053 Presentación Taller de Taller de Constructibilidad Equipo de
A 11/06/2019
Constructibilidad Ingeniería Worley
Tabla 2. Lista de Documentos Recibidos

ECOPETROL
Informe Taller Constructibilidad 11
5. EQUIPO DEL TALLER DE CONSTRUCTIBILIDAD

Un equipo multidisciplinario de profesionales de Worley y Ecopetrol, bajo la coordinación de CST,


participaron en la sesión del taller de constructibilidad que tuvo lugar el 12 de junio de 2019 en las
Instalaciones de ECOPETROL en el edificio San Martín en la ciudad de Bogotá
A continuación, los participantes del estudio realizado:

Nombre Empresa Cargo/Rol


Jaime A. Amaya Worley Coordinador de Proyectos
German Garavito Worley Ingeniero Civil
Rosana Cuellar Ecopetrol Proyectos Menores/ Madurado y calidad
Ronald Morales Ecopetrol Líder Proyectos
Luis Fernando Alcarcel Ecopetrol Proyectos Menores
Nelson Alvarez Ecopetrol Proyectos Menores/ Madurado y calidad
John Supez Ecopetrol Profesional VRE /Ingeniero Civil
Luis Fernando Conde CST Líder
Ingrid Padilla CST Asistente/ Ingeniera Química
Ingri Palomo CST Apoyo Técnico
Tabla 3. Asistencia Taller Constructibilidad

La lista de asistencia para la sesión está incluida en el Anexo 1.

ECOPETROL
Informe Taller Constructibilidad 12
6. METODOLOGÍA

La constructibilidad se define como ‘‘el óptimo uso del conocimiento sobre la construcción, experiencia
en planeación, ingeniería, compras y operaciones de campo, para llevar a cabo el objetivo global de un
proyecto’’.

6.1 TÉCNICA CONSTRUCTIBILIDAD


La constructibilidad, es una herramienta de control para lograr que la fase de construcción y montaje
del proyecto se logre exitosamente reduciendo al mínimo posibilidades de cambios y reclamaciones
luego de iniciada la fase de construcción. Implica revisar documentos del contrato e identificar posibles
conflictos que puedan ocurrir en la fase de construcción del proyecto.
El taller es un compromiso para el éxito y cubre:
La eliminación de barreras en la construcción del proyecto
Búsqueda de estrategias de cero accidentes durante la obra
Concientización al personal para adecuado manejo de materiales en la obra y mínimo impacto a
terceros de acuerdo con las normas
Disminución de reclamamos por errores, omisiones o discrepancias en información
La metodología se desarrolla en sinergia con las diferentes disciplinas de los participantes, aportando
ideas y juicios aplicados a la construcción y con aplicación de buenas prácticas y normas reconocidas,
se hace la discusión registrándose las acciones a seguir para hacer una efectiva construcción con
eficiencia y control de tiempo.
La participación de un equipo multidisciplinario y con amplia experiencia en implantación de proyectos
del sector petrolero fue de gran importancia para el éxito del estudio.
La información fue procesada de manera sistematizada en el software LEADER desarrollado por ABS
Consulting, cuyas hojas de reporte se adjuntan al presente documento.

ECOPETROL
Informe Taller Constructibilidad 13
7. PREMISAS Y/O CONSIDERACIONES ESPECIALES

Para el desarrollo del estudio se vio necesario tener en cuenta las siguientes Premisas y/o
consideraciones:

 La información analizada corresponde a la fase de Ingeniería de Detalle.


 La evaluación fue desarrollada por el equipo multidisciplinario de la sesión.
 Para el taller de constructibilidad se contemplaron todos los aspectos de interés para la
organización, enfocados en las especialidades de la etapa de la construcción y que puedan afectar
la etapa constructiva o los objetivos del proyecto.
 Se verificó durante la sesión con cada profesional de la especialidad las consideraciones
contempladas en la ingeniería de Detalle.
 Se generaron recomendaciones que prevengan los impactos generados por los hallazgos.

ECOPETROL
Informe Taller Constructibilidad 14
8. RESULTADOS

8.1 Secciones del Taller de Constructibilidad


Para el taller se propuso a su inicio cuatro (4) secciones o nodos de acuerdo con las especialidades, los
cuales se describen a continuación:
 Preliminares
 Movimientos de Tierra
 Fundición de Concreto
 Interferencias

8.2 Hoja de Trabajo


Las hojas de trabajo describen la información documentada durante la sesión o taller, la información
se establece en tablas donde pueden encontrarse:
 Actividad
 Hallazgos
 Recomendaciones
La totalidad de las hojas de trabajo pueden verse en Anexo 2 de este reporte.

8.3 Acciones y Recomendaciones


Con base en los resultados y el conocimiento que se obtiene a partir de la realización de este Estudio,
el equipo de trabajo generó un total de veintitrés (23) recomendaciones para su prevención o control.
Para los ejercicios donde se requiera un equipo multidisciplinario para la evaluación de diferentes
consideraciones es de vital importancia que se cuente con la disponibilidad y tiempo necesario para
desarrollar dichas actividades, de lo contrario los resultados pueden verse afectados.
Se requiere avance definido por parte de la ingeniería para el desarrollo de estas actividades con
equipos multidisciplinarios, al igual, es necesario que el personal asistente conozca con anticipación la
información a evaluarse durante el taller.
A continuación, presentamos la lista de las recomendaciones que fueron discutidas durante las sesiones
del estudio de Riesgos.

ECOPETROL
Informe Taller Constructibilidad 15
Escenario Sección Hallazgo Recomendación
Rec 4. Gestionar sitio de disposición de
material sobrante de excavaciones,
Manejo de sobrantes material de
1.1 Permisos ambientales previo a actividades de construcción
excavaciones.
Rec 5. Considerar ofrecer el material
sobrante a otros proyectos..
1.2 Permisos de trabajo No hay ningún hallazgo.
Rec 7. Evaluar con proveedores
Insuficiencia material fibra de
disponibilidad de cantidad de material
refuerzos para el concreto.
requerido y tiempos de entrega.
Interrupciones en la ruta de
Rec 8. Contemplar dentro el presupuesto
Disponibilidad y acarreo acarreo de material Bogotá -
1.3 contingencias relacionadas al riesgo de
de materiales Campo Rubiales (Cierre vía
cierre de las vías.
Villavicencio).
Bloqueos vía Puerto Gaitán - Rec 9. Solicitar al contratista adherirse al
Campo Rubiales por temas plan de contingencias de Campo
sociales. Rubiales.
Zonas de
1.4 almacenamiento y patio No hay ningún hallazgo.
de trabajo
Rec 16. Definir Plan detallado de trabajo
Disponibilidad de servicios de
incluyendo demanda de personal con la
catering y hospedaje para personal
anticipación suficiente para realizar
del proyecto.
solicitud de suministro de recursos.
1.5 Logística Impacto en tiempos por cambios
de contratista de obras asociados a Rec 17. Generar la justificación para que
movilización de contratista al se evalué la posibilidad de dar
campo e instalación de continuidad al contratista de obras.
campamentos y logística.
2.1 Localización y replanteo No hay ningún hallazgo.
Rec 10. Solicitar al contratista Plan de
Limitación en el desplazamiento de
construcción diferencial y
maquinaria pesada en áreas no
procedimientos de la actividad manual
accesibles de los tanques.
para las áreas no accesibles.
Rec 10. Solicitar al contratista Plan de
construcción diferencial y
procedimientos de la actividad manual
para las áreas no accesibles.
Posible afectación de facilidades
Rec 11. Considerar un vigía, constante
existentes superficiales durante el
capacitación y entrenamiento al
Excavaciones y desarrollo de trabajo manual.
2.2 personal que realiza el trabajo manual.
nivelación de terreno
Rec 12. Recomendar selección específica
de cuadrilla para la realización de trabajo
manual.
Rec 10. Solicitar al contratista Plan de
construcción diferencial y
procedimientos de la actividad manual
Exposición de personal a riesgos
para las áreas no accesibles.
locativos.
Rec 11. Considerar un vigía, constante
capacitación y entrenamiento al
personal que realiza el trabajo manual.

ECOPETROL
Informe Taller Constructibilidad 16
Rec 12. Recomendar selección específica
de cuadrilla para la realización de trabajo
manual.
Rec 10. Solicitar al contratista Plan de
construcción diferencial y
procedimientos de la actividad manual
para las áreas no accesibles.
Posible afectación a tuberías y
Rec 12. Recomendar selección específica
bancos de ductos enterrados en
de cuadrilla para la realización de trabajo
áreas de tránsito vehicular.
manual.
Rec 13. Asegurar que se realice las
actividades de detección de elementos
enterrados y liberación de áreas.
Rec 10. Solicitar al contratista Plan de
construcción diferencial y
procedimientos de la actividad manual
para las áreas no accesibles.
Posible afectación a tuberías y
Rec 12. Recomendar selección específica
bancos de ductos enterrados en
de cuadrilla para la realización de trabajo
áreas de trabajo manual.
manual.
Rec 13. Asegurar que se realice las
actividades de detección de elementos
enterrados y liberación de áreas.
Rec 18. Considerar realizar zonificación
Posible afectación de tuberías y de área una vez identificada tubería y
2.3 Rellenos banco de ductos enterrados por bancos de ductos enterrados y aplicar
compactación de materiales. procedimientos de compactación
manual.
Armado e Instalación de
3.1 No hay ningún hallazgo.
refuerzo en acero
Rec 19. Solicitud al contratista
acompañamiento del proveedor tanto
Utilización de las fibras Experiencia insuficiente en el uso en el diseño de mezcla como en la
3.2
de refuerzo en concreto de la tecnología. instalación del concreto, capacitación del
personal para garantizar el uso adecuado
de la fibra.
Mezcla de concreto
3.3 No hay ningún hallazgo.
(diferentes resistencias)
3.4 Ensayos de laboratorio No hay ningún hallazgo.
El diseño contempla el uso de Rec 1. Evaluar la posibilidad de usar
concreta resistencia 5000PSI. concreto de menor resistencia.
Dificultad para vaciado de concreto Rec 20. Considerar el manejo de bomba
en áreas con acceso restringido de de lanzado de concreto en áreas de
maquinaria. acceso restringido de maquinaria.
3.5 Fundición concreto
Rec 2. Garantizar el replanteo de la obra
Las dimensiones de las rejillas no acorde con lo establecido en ingeniería.
coinciden con el alojamiento en la Rec 3. Considerar el uso de una rejilla
sección de la cuneta de concreto. guía para ir verificando la sección una vez
se va avanzando la construcción.

ECOPETROL
Informe Taller Constructibilidad 17
Rec 14. Considerar la realización de un
Plan Integrado de Trabajo con cada uno
Actividades paralelas a la ejecución
de los proyectos paralelos.
de este proyecto (Mantenimiento
Rec 15. Solicitar la definición de una
4.1 Interferencias operativas tanque 0101, bypass skim tank
estrategia para la emisión de permisos
0101, interconexión de succión de
de trabajo y seguimiento de las
tanques Fwkos, entre otros).
actividades en las áreas a cargo de la
operación.
Rec 21. Garantizar la correcta
Posible desnivel consecuencia de
compactación de la subrasante en la
aplicación de concreto en la rampa
4.2 Interferencias físicas rampa de acceso.
de acceso norte contigua al box
Rec 22. Evaluar la inclusión de una junta
culvert (área 3).
tipo puente vehicular.
Superposición del Proyecto 4370 Rec 6. Evaluar desde ingeniería la
4.3 Proyectos futuros con obras proyectadas en la realineación del dique en el sector de
presente ingeniería para el área 3. interferencia.
Rec 23. Evaluar la posibilidad de solicitar
Posible afectación a ejecución de la
4.4 Clima desde proceso de contratación trabajo
obra por altos niveles de lluvia.
nocturno.
Tabla 3. Lista de Recomendaciones Taller Constructibilidad

Es importante mencionar que las recomendaciones antes relacionadas hacen referencia a eventos
específicos identificados en el mismo taller y que están relacionados por consideraciones generales de
la sesión como mejores prácticas.

ECOPETROL
Informe Taller Constructibilidad 18
Appendix A. Lista de Asistencia
Taller de Constructibilidad

ECOPETROL
Informe Taller Constructibilidad 19
ECOPETROL
Informe Taller Constructibilidad 20
Appendix B. Registro hojas de trabajo
Taller de Constructibilidad

ECOPETROL
Informe Taller Constructibilidad 20
ECOPETROL
Informe Taller Constructibilidad 21
ECOPETROL
Informe Taller Constructibilidad 22
ECOPETROL
Informe Taller Constructibilidad 23
ECOPETROL
Informe Taller Constructibilidad 24