Está en la página 1de 17

A) CUAL ES EL TIR DE CADA PROYECTO? RSPTA TIR DE A ES 20.

44%
RSPTA TIR DE B 18.84%
SE DEBE APECTAR EL PROYECTO A MAYOR TIR TENGO MAYPR POSIBILID

AÑO FCN(A) FCN(B)


0 -43000 -43000
1 23000 7000
2 17900 13800
3 12400 24000
4 9400 26000
TIR 20.44% 18.84%

B) SI EL RENDIMIENTO REQUERIDO = COK = 11%

AÑO FCN(A) FCN(B)


0 -43000 -43000
1 23000 7000 RSPTA EL VAN DE PROYECTO A ES 7507.61
2 17900 13800 RSPTA EL VAN DE PROYECTO A ES 9182.29
3 12400 24000 RSPTA SE ELEGIRIA EL PROYECTO B
4 9400 26000
COK 11% 11%
VAN S/ 7,507.61 S/ 9,182.29

C) EN QUE INTERVALO SE ESCOGE EL PROYECTO A Y EL PROYECTO B (GRAFICAMOS)

AÑO FCN(A) FCN(B) TASA VAN A VAN B FCN A- FCN B


0 -43000 -43000 1% S/ 18,388.11 S/ 25,738.43 S/ 0.00
1 23000 7000 20% S/ 306.33 -S/ 1,155.86 S/ 16,000.00
2 17900 13800 40% -S/ 10,472.93 -S/ 15,444.81 S/ 4,100.00
3 12400 24000 60% -S/ 17,171.14 -S/ 23,407.71 -S/ 11,600.00
4 9400 26000 80% -S/ 21,675.89 -S/ 28,259.87 -S/ 16,600.00
100% -S/ 24,887.50 -S/ 31,425.00 S/ 0.00
15.30%
TIR= LA TASA DE INTERSECC

RSPSTA EN EL PUNTO AMARILLO COINCIDE LA TASA Y EL VAN Y DA IGUAL INVERTIR EN A O EN B

C) CALCULAMOS EL PUNTO DE INDIFERENCIA


EN LA TASA DE 15.30% ES INDIFERENTE

METODO BUSCAR FUNCION OBJETIVO TIR


VAN A - VAN B

AÑO FCN(A) FCN(B) TASA VAN A VAN B DIFERENCIA


0 -43000 -43000 15.30% S/ 3,822.01 S/ 3,822.01 -S/ 0.00
1 23000 7000 20% S/ 306.33 -S/ 1,155.86
2 17900 13800 40% -S/ 10,472.93 -S/ 15,444.81
3 12400 24000 60% -S/ 17,171.14 -S/ 23,407.71
4 9400 26000 80% -S/ 21,675.89 -S/ 28,259.87
100% -S/ 24,887.50 -S/ 31,425.00

PREGUNTA DE EXAMEN ? A CUANTO ASCIENDE EL VAN DE A Y EL VAN DE B?


EL VAN DE A ASCIENDE A S/ 3,822.01
EL VAN DE B ASCIENTE A S/ 3,822.01
TENGO MAYPR POSIBILIDAD DE LA TASA

CTO A ES 7507.61
CTO A ES 9182.29

S/30,000.00

S/20,000.00

S/10,000.00

S/0.00
0% 20% 40% 60% 80%

(S/10,000.00)

(S/20,000.00)
S/10,000.00

S/0.00
0% 20% 40% 60% 80%

(S/10,000.00)

(S/20,000.00)

= LA TASA DE INTERSECCION DE AY B ES 15.30% (S/30,000.00)

R EN A O EN B (S/40,000.00)

VAN A VAN B

ACEPTO
A >0%,20.44%<

B >0%, 18.84%<

RECHAZO
A >20.44%, INFINITO+<
B >18.84%,INFITO+<
15.30% S/ 3,822.01 S/ 3,822.01 S/ 0.00
INDIFERENTE
A 20.44%
B 18.84%
40% 60% 80% 100% 120%
40% 60% 80% 100% 120%

VAN A VAN B
AÑO F EFECTIVO
0 -34000
1 16000
2 18000
3 15000
COK 16%
TIR 20.97%

A) SE ACEPTA EL PROYECTO PORQUE LA TASA DE DESCUENTO ES MENOR AL 21% TIR

AÑO F EFECTIVO F EFECTIVO


0 -34000 -34000
1 16000 16000
2 18000 18000
3 15000 15000
COK 11% 30%
VAN S/ 5,991.49 -S/ 4,213.93

RSPTA
SI LA TASA ES DE 11% SE ACEPTA EL PROYECTO
SI LA TASA ES DE 30% SE RECHAZA EL PROYECTO

AÑO
0 -138000 -138000 -138000
1 28500 28500 28500
2 28500 28500 28500
3 28500 28500 28500
4 28500 28500 28500
5 28500 28500 28500
6 28500 28500 28500
7 28500 28500 28500
8 28500 28500 28500
9 28500 28500 28500
COK 8% 20%
VAN S/ 40,036.31 -S/ 23,117.45
TIR 14.59%

A) CON 8% SE ACEPTA ES UN BUEN PROYECTO


B) CON 20 % SE RECHAZA
C) LA TASA DE DESCUENTO DARIA LO MISMO CON UN TIR DE 14.59%

AÑO F EFECTIVO
0 -19500
1 9500
2 10300
3 8600
RSPTA TIR 21.81%

AÑO FEX FEY DIFERENCIA TASA


0 -15000 -15000 0 0
1 8150 7700 450 1%
2 5050 5150 -100 2%
3 6800 7250 -450 3%
TIR 16.57% 16.45% 11.73% 4%
TIRDE X E Y 5%
6%
7%
8%
9%
10%
11%
12%
13%
14%
15%
16%
17%
18%
19%
20%
21%
22%
23%
24%
25%

AÑO F EFECTIVO
0 -45000000
1 78000000
2 -14000000
COK 12%
VAN S/ 13,482,142.86
TIR 53%

A) SI SE DEBE ACEPTAR EL PROYECTO VAN MAYOR A 0


B) TIR ELEVCADO SE ACPETA EL PROYECTO
C) HAY UNA SOLA TIR
AÑO FEA FE B
0 -300000 -40000
1 20000 19000
2 50000 12000
3 50000 18000
4 39000 10500
COK 15% 15%
VAN -S/ 189,627.32 S/ 3,434.16
TIR -20.37% 19.50%

RSPTA SE ELJIGE DE ACUERDO AL VAN PROYECTO B


DE ACUERDO AL TIR PROYECTO B
MEJORES RESULTADOS PROYECTO B
S/6,000.00

X Y S/5,000.00

S/ 5,000.00 S/ 5,100.00 S/4,000.00


S/ 4,619.81 S/ 4,709.07
S/3,000.00
S/ 4,251.89 S/ 4,330.88
S/ 3,895.69 S/ 3,964.87 S/2,000.00

S/ 3,550.72 S/ 3,610.53 S/1,000.00


S/ 3,216.50 S/ 3,267.36
S/0.00
S/ 2,892.57 S/ 2,934.87 0 0.05 0.1 0.15 0.2 0.25 0.3
(S/1,000.00)

(S/2,000.00)

(S/3,000.00)
S/2,000.00

S/1,000.00

S/0.00
0 0.05 0.1 0.15 0.2 0.25 0.3
(S/1,000.00)
S/ 2,578.51 S/ 2,612.63
S/ 2,273.92 S/ 2,300.21 (S/2,000.00)
S/ 1,978.40 S/ 1,997.20 (S/3,000.00)
S/ 1,691.59 S/ 1,703.23
S/ 1,413.14 S/ 1,417.93 X Y

S/ 1,142.72 S/ 1,140.96
S/ 880.02 S/ 871.98
S/ 624.74 S/ 610.69
S/ 376.59 S/ 356.78
S/ 135.31 S/ 109.99
-S/ 99.37 -S/ 129.97
-S/ 327.70 -S/ 363.35
-S/ 549.90 -S/ 590.40
-S/ 766.20 -S/ 811.34
-S/ 976.82 -S/ 1,026.41
-S/ 1,181.96 -S/ 1,235.81
-S/ 1,381.81 -S/ 1,439.75
-S/ 1,576.57 -S/ 1,638.41
-S/ 1,766.40 -S/ 1,832.00
D
0.25 0.3
0.25 0.3