Está en la página 1de 2

DATOS

INVERSION 12,000,00 TASA DE DESCUENTO A 16.30%


TASA DE DESCEUENTO B 20.15%
TIPO DE INVERSION A;O 1 AO 2 AO 3 VAN
PRODUCTO
PROYECTO A -1200.00 1000.00 6500.00 20000.00 17179.77
PROYECTO B -1200.00 10000.00 4500.00 1000.00 10816.67

TASA DE VALOR ACTUAL NETO


DESCUENTO PROYECTO A PROYECTO B VAR Y T
0% 26300.00 14300.00
30,000
5% 22924.82 13269.28
10% 20107.29 12361.23 25,000
15% 17734.82 11555.81
20% 15721.30 10837.04 20,000

25% 14000.00 10192.00 15,000


30% 12518.71 9610.20
35% 11236.11 9082.99 10,000
40% 10119.24 8603.21
5,000
45% 9141.55 8164.88
50% 8281.48 7762.96 000
0% 5% 10% 15% 20% 25% 30%
60% 6846.88 7051.95
70% 5708.20 6442.99 VALOR ACTUAL NETO PROYEC
TIR

261%
777%

VAR Y TIR

5% 10% 15% 20% 25% 30% 35% 40% 45% 50% 60% 70%

VALOR ACTUAL NETO PROYECTO A PROYECTO B