CALCULO DEL VAN Y LA TIR PARA UN

DATOS:

Inversion Inicial: S/ 250,000.00


Renovacion: 4
Retorno: S/ 150,000.00
Interes: 15%
Duracion: 12

PROYECTO Inversion inicial Mes 1 Mes 2 Mes 3 Mes 4


250000 -250000 150000 150000 150000 -100000

VAN = S/ 420,154.54
TIR = 50% Factible
PROYECTO DE INVER
S/ 1,400,000.00

S/ 1,200,000.00
0% S/ 1,300,000.00
S/ 1,000,000.00
5% S/ 873,812.13
10% S/ 601,300.41 S/ 800,000.00
15% S/ 420,154.54 S/ 600,000.00
20% S/ 295,319.24
25% S/ 206,368.31 S/ 400,000.00

30% S/ 141,007.06 S/ 200,000.00


35% S/ 91,608.89
S/ -
40% S/ 53,308.48 0% 10% 20% 30% 40% 50%
45% S/ 22,919.83 S/ -200,000.00
50% S/ -1,694.92
55% S/ -22,003.46
60% S/ -39,035.15
65% S/ -53,526.55
70% S/ -66,014.67
75% S/ -76,897.98
80% S/ -86,477.05
85% S/ -94,982.10
90% S/ -102,592.04
Y LA TIR PARA UN PROYECTO DE INVERSION

http://hebmerma.com/

Mes 5 Mes 6 Mes 7 Mes 8 Mes 9 Mes 10 Mes 11 Mes 12


150000 150000 150000 150000 150000 150000 150000 150000

PROYECTO DE INVERSION

10% 20% 30% 40% 50% 60% 70% 80% 90% 100%