Está en la página 1de 3

2021

October
Line Actividades Duration Start Finish
15 16 17 18 19 20 21
1

6 INST. ELECTRICAS 96d 9/09/2021 4/01/2022


7 AREA 100 76d 10/09/2021 10/12/2021
8 CASA MATERNA 75d 11/09/2021 10/12/2021
9 CANALIZADO DE TUBERIA 75d 11/09/2021 10/12/2021

10 TBC 49d 10/09/2021 8/11/2021


11 CANALIZADO DE TUBERIA 36d 10/09/2021 22/10/2021

12 CABLEADO DE CIRCUITOS DERIVADOS 3d 20/10/2021 22/10/2021

13 PISO 5 44d 11/09/2021 3/11/2021


14 CANALIZADO DE TUBERIA 35d 11/09/2021 22/10/2021

15 CABLEADO DE CIRCUITOS DERIVADOS 2d 21/10/2021 22/10/2021

16 PISO 6 44d 24/09/2021 16/11/2021


17 CANALIZADO DE TUBERIA 32d 24/09/2021 2/11/2021
TENDIDO DE TUBERIA PVC 3/4" EN TABIQUERIA (TABIQUERIA
18 PISO 6)
18d 29/09/2021 20/10/2021
COLOCACION DE CAJAS DE PASE EN MUROS (TABIQUERIA
19 PISO 6)
14d 29/09/2021 15/10/2021

20 AREA 200 47d 10/09/2021 5/11/2021


21 PISO 3 44d 10/09/2021 2/11/2021
22 CANALIZADO DE TUBERIA 30d 17/09/2021 22/10/2021

23 CABLEADO DE CIRCUITOS DERIVADOS 2d 21/10/2021 22/10/2021


INSTALACION DE ACCESORIOS Y PLACAS EN
24 26d 1/10/2021 2/11/2021
GENERAL.
25 INSTALACION DE TABLEROS PRINCIPALES 22d 1/10/2021 27/10/2021

26 PISO 4 41d 17/09/2021 5/11/2021

18/10/2021 Planned by Asta PowerProject


2021
October
Line Actividades Duration Start Finish
15 16 17 18 19 20 21
1
27 BANDEJAS IIEE-TIC 33d 27/09/2021 5/11/2021

28 TENDIDO DE BANDEJA (FONDO DE TECHO PISO 4) 14d 4/10/2021 20/10/2021

29 CANALIZADO DE TUBERIA 37d 17/09/2021 30/10/2021


INSTALACION DE ACCESORIOS Y PLACAS EN
30 26d 4/10/2021 4/11/2021
GENERAL.
31 INSTALACION DE TABLEROS PRINCIPALES 20d 4/10/2021 27/10/2021

32 AREA 300 96d 9/09/2021 4/01/2022


33 PISO 1 62d 9/09/2021 22/11/2021
34 CANALIZADO DE TUBERIA 37d 9/09/2021 22/10/2021

35 CABLEADO DE CIRCUITOS DERIVADOS 2d 21/10/2021 22/10/2021

36 PISO 2 42d 20/09/2021 9/11/2021


37 CANALIZADO DE TUBERIA 42d 20/09/2021 9/11/2021

38 PISO 3 42d 20/09/2021 9/11/2021


39 CANALIZADO DE TUBERIA 37d 20/09/2021 3/11/2021

40 PISO 4 55d 1/10/2021 6/12/2021


41 CANALIZADO DE TUBERIA 37d 1/10/2021 15/11/2021

42 PISO 5 63d 9/10/2021 23/12/2021


43 CANALIZADO DE TUBERIA 31d 9/10/2021 15/11/2021

44 TRAZO DE RECORRIDO DE TUBERIA ( TABIQUERIA PISO 5) 11d 9/10/2021 21/10/2021


TENDIDO DE TUBERIA PVC 3/4" EN TABIQUERIA (TABIQUERIA
45 PISO 5)
11d 9/10/2021 21/10/2021
COLOCACION DE CAJAS DE PASE EN MUROS (TABIQUERIA
46 PISO 5)
11d 9/10/2021 21/10/2021

47 PISO 6 71d 9/10/2021 4/01/2022

18/10/2021 Planned by Asta PowerProject


2021
October
Line Actividades Duration Start Finish
15 16 17 18 19 20 21
1
48 CANALIZADO DE TUBERIA 31d 9/10/2021 15/11/2021

49 TRAZO DE RECORRIDO DE TUBERIA ( TABIQUERIA PISO 6) 11d 9/10/2021 21/10/2021


TENDIDO DE TUBERIA PVC 3/4" EN TABIQUERIA (TABIQUERIA
50 PISO 6)
11d 9/10/2021 21/10/2021
COLOCACION DE CAJAS DE PASE EN MUROS (TABIQUERIA
51 PISO 6)
11d 9/10/2021 21/10/2021

Actividades
Inst. Electricas

18/10/2021 Planned by Asta PowerProject

También podría gustarte