AREA 100

2021
October
Line Actividades Duration Start Finish 15 16 17 18 19 20 21 22
1

1 TBC 50d 30/09/2021 29/11/2021


2 REVOQUES Y REVESTIMIENTOS 18d 9/10/2021 29/10/2021

3 CASA MATERNA (CM) 72d 1/10/2021 28/12/2021


4 CIMIENTOS Y SOBRE CIM. 42d 1/10/2021 20/11/2021

5 ACERO 3d 14/10/2021 16/10/2021

6 CONCRETO EN CIMIENTO 1d 18/10/2021 18/10/2021

7 TRAZO 1d 19/10/2021 19/10/2021

8 ENCOFRADO 3d 20/10/2021 22/10/2021

9 MUROS Y TABIQUES DE ALBAÑILERIA 57d 1/10/2021 9/12/2021

10 CONCRETO EN COLUMNETAS PARA ALBAÑILERIA 2d 14/10/2021 15/10/2021

11 DESENCOFRADO DE COLUMNETAS PARA ALBAÑILERIA 2d 15/10/2021 16/10/2021 4d

12 REVOQUES Y REVESTIMIENTOS 60d 1/10/2021 13/12/2021

13 COLOCACION DE PUNTOS PARA TARRAJEO 12d 1/10/2021 15/10/2021

14 TARRAJEO PRIMARIO O FROTACHADO 12d 2/10/2021 16/10/2021

15 FALSO PISO 60d 4/10/2021 15/12/2021

16 Piso tecnico 46d 1/10/2021 25/11/2021


17 CIELORRASOS 46d 1/10/2021 25/11/2021

18 Piso 5 53d 1/10/2021 3/12/2021


19 MUROS Y TABIQUES DE ALBAÑILERIA 23d 1/10/2021 28/10/2021

20 ENCOFRADO DE COLUMNERAS Y VIGUETAS PARA ALBAÑILERIA 2d 14/10/2021 15/10/2021

21 CONCRETO EN COLUMNETAS Y VIGUETAS PARA ALBAÑILERIA 2d 15/10/2021 16/10/2021

15/10/2021 Planned by Asta PowerProject


AREA 100

2021
October
Line Actividades Duration Start Finish 15 16 17 18 19 20 21 22
1
DESENCOFRADO DE COLUMNETAS Y VIGUETAS PARA
22 ALBAÑILERIA
2d 16/10/2021 18/10/2021

23 2DO TRAMO DE ALBAÑILERIA HASTA 1.20 2d 18/10/2021 19/10/2021

24 ACERO EN VIGUETA PAR ALBAÑILERIA 2d 19/10/2021 20/10/2021

25 ENCOFRADO DE COLUMNETAS T VIGUETAS PARA ALBAÑILERIA 2d 20/10/2021 21/10/2021


CONCRETO EN COLUMNETAS Y VIGUETAS 2DO TRAMO PARA
26 ALBAÑILERIA
2d 21/10/2021 22/10/2021

27 REVOQUES Y REVESTIMIENTOS 27d 1/10/2021 3/11/2021

28 COLOCACION DE PUNTOS PARA TARRAJEO 11d 12/10/2021 23/10/2021

29 LIMPIEZA DE EFLORESCENCIA 11d 12/10/2021 23/10/2021

30 TARRAJEO PRIMARIO O FROTACHADO 11d 15/10/2021 27/10/2021

31 CONTRAPISOS 29d 15/10/2021 18/11/2021

32 LIMPIEZA DE REBABAS Y ESCARIFICADO PARA CONTRAPISO 12d 15/10/2021 28/10/2021

33 COLOCACION DE PUNTOS PARA CONTRAPISO 12d 16/10/2021 29/10/2021

34 HUMEDECIDO DE SUPERFICIE PARA CONTRAPISO 12d 21/10/2021 4/11/2021

35 Piso 6 59d 1/10/2021 11/12/2021


36 CIELORRASOS 23d 1/10/2021 28/10/2021

37 MUROS Y TABIQUES DE ALBAÑILERIA 27d 2/10/2021 4/11/2021

38 PERFORACION PARA COLUMNETAS 10d 5/10/2021 16/10/2021

39 ANCALJE DE MECHAS PARA COLUMNETAS 10d 6/10/2021 18/10/2021

40 ACERO EN COLUMNETAS Y VIGUETAS PARA ALBAÑILERIA 10d 7/10/2021 19/10/2021

41 1ER TRAMO DE AL BAÑILERIA HASTA 1.90 10d 9/10/2021 20/10/2021

42 ENCOFRADO DE COLUMNERAS Y VIGUETAS PARA ALBAÑILERIA 10d 11/10/2021 21/10/2021

15/10/2021 Planned by Asta PowerProject


AREA 100

2021
October
Line Actividades Duration Start Finish 15 16 17 18 19 20 21 22
1
43 CONCRETO EN COLUMNETAS Y VIGUETAS PARA ALBAÑILERIA 10d 12/10/2021 22/10/2021
DESENCOFRADO DE COLUMNETAS Y VIGUETAS PARA
44 ALBAÑILERIA
10d 13/10/2021 23/10/2021

45 2DO TRAMO DE ALBAÑILERIA HASTA 1.20 10d 14/10/2021 25/10/2021

46 ACERO EN VIGUETA PAR ALBAÑILERIA 10d 15/10/2021 26/10/2021

47 ENCOFRADO DE COLUMNETAS T VIGUETAS PARA ALBAÑILERIA 10d 16/10/2021 27/10/2021


CONCRETO EN COLUMNETAS Y VIGUETAS 2DO TRAMO PARA
48 ALBAÑILERIA
10d 18/10/2021 28/10/2021
DESENCOFRADO DE COLUMNETAS Y VIGUETAS SEGUNDO
49 TRAMO PARA ALBAÑILERIA
10d 19/10/2021 29/10/2021

50 3ER TRAMO DE ABAÑILERIA 10d 20/10/2021 30/10/2021

51 ENOFRADO DE COLUMNETAS PARA ALBAÑILERIA 10d 21/10/2021 2/11/2021

52 REVOQUES Y REVESTIMIENTOS 33d 4/10/2021 12/11/2021

Actividades
Cimientos y Sobre.Cim. Concreto Albañilería Encofrados Revoques y Revest.
Albañilería Acero Contrapisos

15/10/2021 Planned by Asta PowerProject