RESUMEN DE METRADOS DE TRANSPORTE PAGADO

(AVANCE ACUMULADO AL MES DE JULIO - 2001)

PARTIDA :
06.00.00 TRANSPORTE

OBRA : CONSTRUCCION DE LA CARRETERA TACNA-TARATA-CANDARAVE-UMALSO


TRAMO : Km. 24+120 Km. 53+000
EJECUTA : MUNICIPALIDAD PROVINCIAL DE TACNA
SUPERVISA: CTAR - TACNA
arch.luisc
METRADO METRADO METRADO METRADO SALDO SALDO
ITEMS PARTIDAS UND. DE ACUMULADO ACUMULADO PRESENTE POR EN
PRESUPUESTO ACTUAL ANTERIOR VALORIZACION EJECUTAR (%)
06.01.00 Transporte de material D<=1 Km. m3xkm 110,312.10 52,381.50 52,381.50 0.00 57,930.60 52.52
06.02.00 Transporte de material D>=1 Km. m xkm
3
1,919,430.10 888,226.80 888,226.83 -0.03 1,031,203.30 53.72
06.03.00 Transporte de Mezcla Asfaltica D< 1 Km. m3xkm 11,976.66 6,377.53 3,048.63 3,328.90 5,599.13 46.75
06.04.00 Transporte de Mezcla Asfaltica D> 1 Km. m3xkm 208,393.83 111,160.38 53,137.59 58,022.79 97,233.45 46.66
06.05.00 Transporte de Roca m xkm
3
1,702.40 1,026.41 1,026.41 0.00 675.99 39.71

Nota : El Transporte de Roca, es una actividad que debe ser considerado, porque se refiere a una accion muy aparte del transpòrte interno
de la roca durante la ejecucion de la partida. No se debe entender que el transporte de roca este considerado dentro del la partida
enrocado para proteccion de explanaciones, es muy diferente.
RESUMEN DE METRADOS: TRANSPORTE PAGADO
(AVANCE ACUMULADO AL MES DE JUNIO - 2001)

PARTIDAS : TRANSPORTE PAGADO

OBRA : CONSTRUCCION DE LA CARRETERA TACNA-TARATA-CANDARAVE-UMALSO


TRAMO : Km. 24+120 Km. 53+000
EJECUTA : MUNICIPALIDAD PROVINCIAL DE TACNA
SUPERVISA : CTAR - TACNA
arch.luisc
METRADO METRADO METRADO DE METRADO METRADO
ITEMS PARTIDAS UND.
SUB BASE BASE CARPETA DE ROCA ACUM. ACTUAL
06.01.00 Transporte de material D<=1 Km. m3xkm 8,331.57 44,049.92 - - 52,381.50
06.02.00 Transporte de material D>=1 Km. m xkm
3
128,806.12 759,420.67 - - 888,226.80
06.03.00 Transporte de Mezcla Asfaltica D< 1 Km. m xkm
3
- - 6,377.53 - 6,377.53
06.04.00 Transporte de Mezcla Asfaltica D> 1 Km. m xkm
3
- - 111,160.38 - 111,160.38
06.05.00 Transporte de Roca m xkm
3
- - - 1,026.41 1,026.41

NOTA La partida 06.05.00 Transporte de Roca debe ser considerado en la valorizacion toda vez que es una actividad que se ha
realizado, y como toda actividad de Transporte debe ser valorizado en unidades de m3xkm. Pero sin embargo el Expediente
Tecnico manifiesta un transporte en m3., lo cual no es el correcto. Se esta valorizando el volumen de roca utilizado en el enrocado.
PLANILLA DE METRADOS
(AVANCE ACUMULADO AL MES DE JULIO - 2001)

06.00.00 TRANSPORTES
TRANSPORTE PAGADO DE MATERIAL DE BASE
06.01.00 TRANSPORTE DE MATERIAL D <= 1 Km.
06.02.00 TRANSPORTE DE MATERIAL D >= 1 Km.

arch.luisc
CENTRO DE DISTANCIA VOLUMEN
PROGRESIVA MATERIAL PARA SUB BASE
CANTERAS GRAVEDAD MEDIA TOTAL
DEL AL (Km) (km) (m3) (m3) (m3-Km)

Km. 23+540 34+000 35+000 34.50 3.98 2,491.78 2,491.78 9,917.29


Acc. 100 35+000 36+000 35.50 4.98 2,338.56 2,338.56 11,646.04
30.52
37.50
Km. 37+500 36+000 37+000 36.50 5.98 2,334.73 2,334.73 13,961.70
Acc. 300 44+240 44+780 44.55 7.20 1,166.50 1,166.50 8,398.78

TOTAL 8,331.57 43,923.81

CALCULO DEL TRANSPORTE DE MATERIAL PARA SUB BASE:

D=1 km. 43,923.81 = 5.27 km.


8,331.57

D<1 km. 43,923.82X1 = 8,331.57 m3xkm.


5.27

D>1 km. 43,923.91x15.46 = 128,806.12 m3xkm.


5.27
PLANILLA DE METRADOS
(AVANCE ACUMULADO AL MES DE JULIO - 2001)

06.00.00 TRANSPORTES :
TRANSPORTE PAGADO PARA MATERIAL DE BASE
06.01.00 TRANSPORTE DE MATERIAL D <= 1 Km.
06.02.00 TRANSPORTE DE MATERIAL D >= 1 Km.
arch.luisc
CENTRO DE DISTANCIA VOLUMEN
PROGRESIVA MATERIAL PARA BASE
CANTERAS GRAVEDAD MEDIA BASE
DEL AL (Km) (km) (m3) (m3) (m3-Km)
24+120 25+000 24.56 9.51 1,687.05 1,687.05 16,043.87
25+000 26+000 25.50 8.57 1,913.82 1,913.82 16,401.40
26+000 27+000 26.50 7.57 1,932.22 1,932.22 14,626.94
KM. 23+540 27+000 28+000 27.50 6.57 1,945.29 1,945.29 12,780.54
Acc. 100 m. 28+000 29+000 28.50 5.57 1,917.18 1,917.18 10,678.68
29+000 30+000 29.50 4.57 1,915.77 1,915.77 8,755.05
30+000 31+000 30.50 3.57 1,922.96 1,922.96 6,864.97
31+000 32+000 31.50 2.57 1,917.34 1,917.34 4,927.55
32+000 33+000 32.50 1.57 1,901.18 1,901.18 2,984.86
33+000 34+000 33.50 0.57 1,955.56 1,955.56 1,114.67
Cantera Ficticia 34+000 34+070 34.04 0.03
34.07 34+070 35+000 34.54 0.47 1,476.02 1,476.02 693.73
35+000 36+000 35.50 1.43 1,291.04 1,291.04 1,846.19
36+000 37+000 36.50 2.43 1,288.78 1,288.78 3,131.73
37+000 38+000 37.50 3.43 1,642.02 1,642.02 5,632.14
38+000 39+000 38.50 4.43 1,612.41 1,612.41 7,142.99
39+000 40+000 39.50 5.43 1,623.62 1,623.62 8,816.26
40+000 41+000 40.50 6.43 1,633.62 1,633.62 10,504.17
44.60 41+000 42+000 41.50 7.43 1,614.19 1,614.19 11,993.42
KM. 44+600 42+000 43+000 42.50 8.43 1,305.28 1,305.28 11,003.51
Acc. 200 m. 43+000 44+000 43.50 9.43 1,616.03 1,616.03 15,239.14
44+000 44+240 44.12 10.05 391.66 391.66 3,936.22
44+240 44+600 44.42 10.35 640.28 640.28 6,626.86
44+600 44+780 44.69 0.19
44+780 45+000 44.89 0.39 361.06 361.06 140.81
45+000 46+000 45.50 1.00 1,609.60 1,609.60 1,609.60
46+000 47+000 46.50 2.00 1,629.25 1,629.25 3,258.50
47+000 48+000 47.50 3.00 1,194.89 1,194.89 3,584.68
48+000 49+000 48.50 4.00 1,745.51 1,745.51 6,982.03
49+000 50+000 49.50 5.00 1,771.41 1,771.41 8,857.06
50+000 50+340 50.17 5.67 594.88 594.88 3,372.98
TOTAL 44,049.92 44,049.92 209,550.55

CALCULO DEL TRANSPORTE DE MATERIAL PARA BASE:

D=1 km. 209,550.55 = 4.76 km.


44,049.92
D<1 km. 209,550.55x1 = 44,049.92 m3xkm.
4.76
D>1 km. 209,550.55x17.24 = 759,420.67 m3xkm.
4.76
PLANILLA DE METRADOS: TRANSPORTE PAGADO DE MEZCLA ASFALTICA

arch.luisc
PLANTA DE AREA DE AREA TOTAL VOLUMEN
PROGRESIVA
ASFALTO DISTANCIA AREA SOBREANCHO (A) A*0.05*1.25
EN FRIO DEL AL (ml) (m2) (m2) (m2) (m3)
24+120 25+000 880 5,280.00 119.30 5,399.30 337.46
25+000 26+000 1000 6,000.00 119.08 6,119.08 382.44
26+000 27+000 1000 6,000.00 192.03 6,192.03 387.00
27+000 28+000 1000 6,000.00 276.44 6,276.44 392.28
28+000 29+000 1000 6,000.00 136.53 6,136.53 383.53
29+000 30+000 1000 6,000.00 153.03 6,153.03 384.56
30+000 31+000 1000 6,000.00 164.80 6,164.80 385.30
31+000 32+000 1000 6,000.00 136.68 6,136.68 383.54
32+000 33+000 960 5,760.00 433.92 6,193.92 387.12
33+000 34+000 1000 6,000.00 327.82 6,327.82 395.49
34+000 35+000 1000 6,000.00 465.17 6,465.17 404.07
35+000 36+000 1000 6,000.00 731.94 6,731.94 420.75
KM. 44+600 36+000 37+000 1000 6,000.00 716.86 6,716.86 419.80
Acc. 500 m. 37+000 38+000 1000 6,000.00 307.42 6,307.42 394.21
38+000 39+000 1000 6,000.00 112.06 6,112.06 382.00
39+000 40+000 1000 6,000.00 168.10 6,168.10 385.51
40+000 41+000 1000 6,000.00 212.46 6,212.46 388.28
41+000 42+000 970 5,820.00 359.44 6,179.44 386.22
42+000 43+000 920 5,520.00 247.88 5,767.88 360.49
43+000 44+000 1000 6,000.00 130.14 6,130.14 383.13
44+000 45+000 1000 6,000.00 122.61 6,122.61 382.66
45+000 46+000 1000 6,000.00 98.01 6,098.01 381.13
46+000 47+000 1000 6,000.00 196.26 6,196.26 387.27
47+000 48+000 720 4,320.00 250.47 4,418.01 276.13
48+000 49+000 1000 6,000.00 777.54 6,196.26 387.27
49+000 50+000 1000 6,000.00 907.07 6,250.47 390.65
50+000 50+340 340 2,040.00 271.41 2,817.54 176.10

TOTAL 161,990.26 10,124.39


PLANILLA DE METRADOS
TRANSPORTE PAGADO DE MEZCLA ASFALTICA EN FRIO
OBRA : Construcción de la Carretera Tacna - Tarata - Candarave - Umalso
TRAMO : Km. 24+120 - Km. 50+340
EJECUTA : Municipalidad Provincial de Tacna (MPT)
SUPERVISA : Consejo Transitorio de Administración Regional (CTAR-TACNA)
arch.luisc
PLANTA DE DISTANCIA VOLUMEN
PROGRESIVA C.G. MATERIAL PARA CARPETA
ASFALTO MEDIA TOTAL
EN FRIO DEL AL (Km.) (m3) (m3) (m3)
24+120 25+000 24.56 9.80 337.46 337.46
25+000 26+000 25.50 8.86 382.44 382.44
26+000 27+000 26.50 7.86 387.00 387.00
27+000 28+000 27.50 6.86 392.28 392.28
28+000 29+000 28.50 5.86 383.53 383.53
29+000 30+000 29.50 4.86 384.56 384.56
30+000 31+000 30.50 3.86 385.30 385.30
31+000 32+000 31.50 2.86 383.54 383.54
32+000 33+000 32.50 1.86 387.12 387.12
33+000 34+000 33.50 0.86 395.49 395.49
34+000 35+000 34.50 0.14 404.07 404.07
35+000 36+000 35.50 1.14 420.75 420.75
36+000 37+000 36.50 2.14 419.80 419.80
37+000 38+000 37.50 3.14 394.21 394.21
KM. 44+600
Acc. 500 m. 38+000 39+000 38.50 4.14 382.00 382.00
39+000 40+000 39.50 5.14 385.51 385.51
40+000 41+000 40.50 6.14 388.28 388.28
41+000 42+000 41.50 7.14 386.22 386.22
42+000 43+000 42.50 8.14 360.49 360.49
43+000 44+000 43.50 9.14 383.13 383.13
44+000 44+600 44.30 9.94 382.66 382.66
44+600 45+000 44.80 0.45
45+000 46+000 45.50 1.15 381.13 381.13
46+000 47+000 46.50 2.15 387.27 387.27
47+000 48+000 47.50 3.15 276.13 276.13
48+000 49+000 48.50 4.15 387.27 387.27
49+000 50+000 49.50 5.15 390.65 390.65
50+000 50+340 50.17 5.82 176.10 176.10
TOTAL 10,124.39

DISTANCIA DE TRANSPORTE DE MATERIAL PARA CARPETA ASFALTICA EN FRIO

D=1 km. 48,590.79 = 4.80 km.


10,124.39

D<1 km. 48,590.79 x1 = 10,123.08 m3xkm.


4.80

D>1 km. 48,590.79 x17.4 = 176,445.31 m3xkm.


4.80
LANILLA DE METRADOS
AGADO DE MEZCLA ASFALTICA EN FRIO

MATERIAL PARA CARPETA

(m3-Km)
3,307.07
3,388.44
3,041.83
2,691.02
2,247.50
1,868.98
1,487.26
1,096.93
720.04
340.12
56.57
479.65
898.38
1,237.83
1,581.50
1,981.50
2,384.03
2,757.58
2,934.41
3,501.84
3,803.67
0.00
438.29
832.62
869.80
1,607.15
2,011.87
1,024.88
48,590.79
PLANILLA DE METRADOS
(AVANCE ACUMULADO AL MES DE JULIO - 2001)

06.00.00 TRANSPORTES
06.05.00 TRANSPORTE DE ROCAS
arch.luisc
CANTERA CENTRO DE DISTANCIA VOLUMEN
PROGRESIVA VOL. DE ROCAS
DE GRAVEDAD MEDIA TOTAL
ROCAS DEL AL (Km) (km) (m3) (m3)
39+400 39+438 39.42 6.32 225.72 225.72
Km. 43+700 49+706.8 49+780 49.72 6.32 59.41 59.41
Acc. 300 49+833.6 49+880 49.86 6.46 261.63 261.63
49+830 49+910.20 49.95 6.55 406.25 406.25
49+990 50+039.40 50.01 6.61 73.40 73.40
TOTAL 1,026.41 1,026.41