PROYECTO : CONSTRUCCIÓN DE LA TROCHA CARROZABLE TRAMO : QUILAHUANI A HUANUARA, EN EL DISTRITO DE QUILAHUANI, PROV. DE CANDARAVE, DEP. TACNA, REGION TACNA
FECHA : SEPTIEMBRE 2011
LUGAR : DISTRITO DE QUILAHUANI, PROV. DE CANDARAVE, DEP. TACNA, REGION TACNA
CURVA "S"
3,500,000.00
3,000,000.00
2,500,000.00
ACUMULADO (S/.)
2,000,000.00
1,500,000.00
1,000,000.00
500,000.00
S10
G$M
Presupuesto
Obra CONSTRUCCIÓN DE LA TROCHA CARROZABLE TRAMO : QUILAHUANI A HUANUARA, EN EL DISTRITO DE QUILAHUANI, PROV. DE CA
Costo al
QUILAHUANI
Parcial Total
1,953.44
13,495.20
30,304.00
9,958.38
8,748.43
2,279.62
42,604.77
12,360.00 121,703.84
389,252.74
257,418.22
103,451.29
59,863.45
52,639.14 862,624.84
45,475.65 45,475.65
217,215.39
81,109.41
1,026,284.83
117,377.14 1,441,986.77
19,250.00 19,250.00
43,832.25 43,832.25
12,412.40
2,964.17 15,376.57
26,490.24
4,966.92
1,532.10
1,758.33 34,747.59
102,740.98
19,600.00 122,340.98
2,707,338.49
324,880.62
3,032,219.11
545,799.44
3,578,018.55
VALOR PLANEADO
Distribucion del Avance Programado % Parcial Mensual peso relativo al 3er valor planeado al
Indice Nombre de tarea Presupuesto Peso Relativo Duración Mes
MES 1 MES 2 MES 3 MES 4 MES 5 3er Mes
01.00.00 CONSTRUCCION DE LA TROCHA CARROZABLE TRAMO QUILAHUANI - 150 días
01.01.00 OBRAS PRELIMINARES
01.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 2.40M X 3.60 M. $ 1,953 0.07% 1 día 0.07% 0.07% $ 1,953.44
01.01.02 CAMPAMENTO PROVISIONAL DE LA OBRA $ 13,495 0.50% 4 días 0.50% 0.50% $ 13,495.20
01.01.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPO $ 30,304 1.12% 1 día 1.12% 1.12% $ 30,304.00
01.01.04 TRAZO Y REPLANTEO PARA CARRETERAS $ 9,958 0.37% 11 días 0.37% 0.37% $ 9,958.38
01.01.05 CONTROL TOPOGRAFICO EN OBRA $ 8,748 0.32% 9 días 0.32% 0.32% $ 8,748.43
01.01.06 LIMPIEZA DE GENERAL $ 2,280 0.08% 2 días 0.08% 0.08% $ 2,279.62
01.01.07 TRANSPORTE DE MATERIALES DE CONSTRUCCIÓN A OBRA $ 42,605 1.57% 15 días 1.57% 1.57% $ 42,604.77
01.01.08 PLAN DE SEGURIDAD EN EL TRABAJO $ 12,360 0.46% 1 día 0.46% 0.46% $ 12,360.00
02.00.00 MOVIMIENTO DE TIERRAS $0 0.00%
02.01.00 CORTE DE MATERIAL SUELTO C/MAQUINARIA $ 389,253 14.38% 45 días 3.59% 7.19% 3.59% 14.38% $ 389,252.74
02.02.00 CORTE ROCA SUELTA (PERF. Y DISP.) RENDIMIENTO=250 M3/DIA $ 257,418 9.51% 60 días 2.38% 4.75% 2.38% 9.51% $ 257,418.22
02.03.00 CORTE ROCA FIJA (PERF. Y DISP.) RENDIMIENTO=240 M3/DIA $ 103,451 3.82% 60 días 0.96% 1.91% 0.96% 3.82% $ 103,451.29
02.04.00 PERFILADO Y COMPACTACION DE SUBRASANTE $ 59,863 2.21% 15 días 0.55% 1.11% 0.55% 2.21% $ 59,863.45
02.05.00 CONFORMACION DE TERRAPLENES CON MATERIAL PROPIO $ 52,639 1.94% 15 días 0.49% 0.97% 0.49% 1.94% $ 52,639.14
03.00.00 PAVIMENTACION $0 0.00% 0.00% $ 0.00
03.01.00 MATERIAL AFIRMADO E=0.15 M $ 45,476 1.68% 5 días 0.42% 0.84% 0.42% 1.68% $ 45,475.65
04.00.00 TRANSPORTES $0 0.00%
04.01.00 TRANSPORTE DE MATERIAL AFIRMADO D<= 1.00 KM. $ 217,215 8.02% 70 días 2.01% 4.01% 2.01% 2.01% $ 54,303.85
04.02.00 TRANSPORTE DE MATERIAL AFIRMADO D>= 1.00 KM. $ 81,109 3.00% 70 días 0.75% 1.50% 0.75% 0.75% $ 20,277.35
04.03.00 TRANSPORTE DE MATERIAL EXEDENTE DE CORTE D <= 1.00 KM. $ 1,026,285 37.91% 70 días 9.48% 18.95% 9.48% 9.48% $ 256,571.21
04.04.00 TRANSPORTE DE MATERIAL EXEDENTE DE CORTE D>= 1.00 KM. $ 117,377 4.34% 70 días 1.73% 1.73% 0.87% 3.47% $ 93,901.71
05.00.00 OBRAS DE ARTE : CONSTRUCCION DE CUNETAS LONGITUDINALES SIN $0 0.00%
05.01.00 OBRAS PRELIMINARES $0 0.00% 14 días 0.00% $ 0.00
05.01.02 TRAZO NIVELACION Y REPLANTEO $ 19,250 0.71% 14 días 0.71% 0.71% $ 19,250.00
05.02.00 MOVIMIENTO DE TIERRAS $0 0.00% 0.00% $ 0.00
05.02.01 EXCAVACION CLASIFICADA P/CUNETA LONGITUDINAL $ 43,832 1.62% 25 días 1.62% 1.62% $ 43,832.25
05.03.00 TRANSPORTES $0 0.00% 0.00% $ 0.00
05.03.01 TRANSPORTE DE MATERIAL EXEDENTE DE EXCAVACION D <= 1.00 KM $ 12,412 0.46% 60 días 0.46% 0.46% $ 12,412.40
05.03.02 TRANSPORTE DE MATERIAL EXEDENTE DE EXCAVACION D>= 1.00 KM. $ 2,964 0.11% 60 días 0.11% 0.11% $ 2,964.17
10.00.00 SEÑALIZACION $0 0.00%
10.01.00 SEÑALES PREVENTIVAS $ 26,490 0.98% 30 días 0.98% 0.00% $ 0.00
10.02.00 SEÑALES REGLAMENTARIAS $ 4,967 0.18% 4 días 0.18% 0.00% $ 0.00
10.03.00 SEÑALES INFORMATIVAS $ 1,532 0.06% 1 día 0.06% 0.00% $ 0.00
10.04.00 POSTES KILOMETRICOS $ 1,758 0.06% 2 días 0.06% 0.00% $ 0.00
11.00.00 OBRAS DE MITIGACION AMBIENTAL $0 0.00%
11.01.00 CONFORMACION DE MATERIAL EN BOTADEROS $ 102,741 3.79% 32 días 3.79% 0.00% $ 0.00
11.02.00 RECOMPOSICIÓN DE CANTERAS $ 19,600 0.72% 15 días 0.72% 0.00% $ 0.00
$ 2,707,339 100% Parcial 13.59% 20.69% 22.35% 31.13% 12.23%
Valor Planeado $ 1,533,317
Acumulado 13.59% 34.28% 56.64% 87.77% 100.00%
VALOR GANADO
Costo
S/. 3,000,000.00
S/. 2,500,000.00
S/. 2,000,000.00
S/. 1,500,000.00
S/. 1,000,000.00
S/. 500,000.00
VALOR PLANEADO VALOR GANADO VALOR GANADO PROYECTADO VALOR REAL VALOR REAL PROYECTADO
S/. 0.00 Periodo de Control
S/. 0.00 S/. 367,978.96 S/. 928,188.89 S/. 1,533,317.28 S/. 2,376,186.10 S/. 2,707,338.51
PERIODO 0 1º MES 2º MES 3º MES 4º MES 5º MES
VALOR PLANEADO VALOR GANADO VALOR GANADO PROYECTADO VALOR REAL VALOR REAL PROYECTADO