Está en la página 1de 1

1.7.1.

METRADOS DIARIOS Y ACUMULADO DEL MES


PRESUPUESTO (S/)
AVANCE AVANCE AVANCE
ITEM PARTIDAS ACUMULADO L M M J V S D L M M J V S D L M M J V S D L M M J V S D MENSUAL ACUMULADO
METRADO EXP.
UNIDAD ANTERIOR ACTUAL ACTUAL
TEC. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
01 OBRAS PROVISIONALES
01.01 ALMACEN DE OBRA M2 17.28 17.28 0.00 17.28
01.02 IMPLEMENTACION DE SS.HH. DE PERSONAL GLB 1.00 1.00 0.00 1.00
01.03 OBRAS DE DESVIO DE CANAL M 25.00 25.00 0.00 25.00
01.04 CAMINOS Y ACCESOS M 80.00 80.00 0.00 80.00
02 TRABAJOS PRELIMINARES
02.01 FLETE TERRESTRE AREQUIPA LA CAPILLA VJE 2.00 2.00 0.00 2.00
02.02 MOVILIDAD PARA PERSONAL ENCARGADO DIA 85.00 68.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 17.00 85.00
02.03 FLETE RURAL KG 41,909.36 41,909.36 0.00 41,909.36
02.04 IMPLEMENTOS DE SEGURIDAD DE PERSONAL GLB 15.00 15.00 0.00 15.00
03 CONSTRUCCION DE CANAL DE CONRETO
03.01 OBRAS PRELIMINARES
03.01.01 LIMPIEZA Y DESBROCE M2 5.60 5.60 0.00 5.60
03.01.02 TRAZO, NIVEL Y REPLANTEO EN CANALES M 8.00 8.00 0.00 8.00
03.02 MOVIMIENTO DE TIERRAS
03.02.01 EXCAVACION PARA CANAL DE CONCRETO M3 3.20 3.20 0.00 3.20
03.02.02 REFINE Y NIVELACION DE ZANJAS M2 8.00 8.00 0.00 8.00
03.02.03 RELLENO Y COMPACTACION CON MATERIAL PROPIO M3 1.60 1.60 0.00 1.60
03.02.04 ELEMINACION DE MATERIAL EXCEDENTE MANUAL M3 2.40 2.40 0.00 2.40
03.03 CANAL
03.03.01 CONCRETO FC=175KG/CM2 M3 2.10 2.10 0.00 2.10
03.03.02 ENCOFRADO Y DESENCOFRADO NORMAL DE CANALES M2 22.00 22.00 0.00 22.00
03.03.03 ENLUCIDO DE ESTRUCTURAS M2 8.00 8.00 0.00 8.00
04 PASE AEREO
04.01 OBRAS PRELIMINARES
04.01.01 TRAZO, NIVEL Y REPLANTEO M2 80.00 80.00 0.00 80.00

04.02 MOVIMINETO DE TIERRAS

04.02.01 EXCAVACION DE CIMENTACION P/ESTRUCTURAS M3 116.60 116.60 0.00 116.60


04.02.02 RELLENO Y COMPACTACION CON MATERIAL PROPIO M3 6.00 6.00 0.00 6.00
04.02.03 ELIMINACION DE MATERIAL EXCEDENTE MANUAL M3 139.75 139.75 0.00 139.75
04.03 OBRAS DE CONCRETO SIMPLE
04.03.01 CONCRETO F'C=140 KG/CM2 + 30% P.G. M3 76.95 76.95 0.00 76.95
04.03.02 ENCOFRADO Y DESENCOFRADO EN CAMARAS DE ANCLAJE M2 153.88 153.88 0.00 153.88
04.04 OBRAS DE CONCRETO ARMADO

04.04.01 ZAPATAS

04.04.01.01 SOLADO FC=100KG/CM2 e=10cm M2 0.90 0.90 0.00 0.90


04.04.01.02 CONCRETO ZAPATAS fc=210 KG/CM2 M3 27.00 27.00 0.00 27.00
04.04.01.03 ACERO DE REFUERZO fy=4200 KG/CM2 KG 244.61 244.61 0.00 244.61
04.04.02 COLUMNAS
04.04.02.01 CONCRETO COLUMNAS fc=210 KG/CM2 M3 6.54 6.54 0.00 6.54
04.04.02.02 ENCOFRADO Y DESENCOFRADO DE COLUMNAS M2 21.10 21.10 0.00 21.10
04.04.02.03 ACERO DE REFUERZO fy=4200 KG/CM2 KG 825.60 825.60 0.00 825.60
04.04.03 SUPERESTRUCTURA
04.04.03.01 VIGUETAS DE MADERA TORNILLO 4"X4" M 46.80 46.80 0.00 46.80

04.04.03.02 LARGUEROS DE MADERA TORNILLO 2"X3" M 132.00 132.00 0.00 132.00

04.04.03.03 TABLERO DE MADERA TORNILLO 1"X6" M 304.00 304.00 0.00 304.00


04.04.03.04 SUMINISTRO DE CABLE TIPO BOA DIAM. 1 1/4" M 130.00 130.00 0.00 130.00
04.04.03.05 PENDOLAS DE F° LISO DIAMETRO 5/8" M 87.76 87.76 0.00 87.76
04.04.03.06 SUMINISTRO DE CABLE TIPO BOA DIAM. 1/2" M 64.00 0.00 64.00 64.00 64.00
04.04.03.07 APOYO MOVIL SOBRE TORRE UND 4.00 0.00 4.00 4.00 4.00
04.04.03.08 ABRAZADERA ENTRE PENDOLA - CABLE UND 104.00 0.00 50.00 54.00 104.00 104.00

04.04.03.09 ABRAZADERA ENTRE PENDOLA - VIGA DE MADERA SEGÚN DISEÑO UND 104.00 0.00 50.00 54.00 104.00 104.00

04.04.03.10 ABRAZADERA PARA TUBERIA PVC DE 355 MM SEGÚN DISEÑO UND 26.00 0.00 26.00 26.00 26.00
04.04.03.11 BARANDA DE ESTRUCTURA METALICA M 60.00 0.00 60.00 60.00 60.00
04.04.03.12 ACCESORIOS VARIOS DE CAMARA DE ANCLAJE GLB 1.00 0.00 1.00 1.00 1.00
04.04.03.13 MONTAJE DE PASE AEREO M 30.00 0.00 20.00 10.00 30.00 30.00
04.04.04 SUMINISTRO E INSTALACIONES DE TUBERIA
04.04.04.01 SUMINISTRO Y COLOCACION DE TUBERIAS PVC S-20 O355MM M 35.00 0.00 10.00 25.00 35.00 35.00
04.04.05 PINTURAS DE ESTRUCTURAS DE CONCRETO
04.04.05.01 PINTURA DE TORRES C/LATEX C/BASE IMPRIMANTE M2 41.60 0.00 10.00 31.60 41.60 41.60
04.04.06 CAMARA DE INGRESO Y SALIDA
04.04.06.01 OBRAS PRELIMINARES
04.04.06.01.01 TRAZO, NIVEL Y REPLANTEO M2 5.06 0.00 5.06 5.06 5.06
04.04.06.02 MOVIMINETO DE TIERRAS
04.04.06.02.01 EXCAVACION MANUAL EN MATERIAL SUELTO M3 4.05 0.00 2.00 2.05 4.05 4.05
04.04.06.02.02 RELLENO Y COMPACTACION CON MATERIAL PROPIO M3 0.62 0.00 0.62 0.62 0.62
04.04.06.02.03 ELIMINACION DE MATERIAL EXCEDENTE MANUAL M3 4.29 0.00 4.29 4.29 4.29
04.04.06.03 OBRAS DE CONCRETO
04.04.06.03.01 SOLADO FC=100KG/CM2 e=10cm M2 2.42 0.00 2.42 2.42 2.42
04.04.06.03.02 CONCRETO FC=175KG/CM2 M3 1.28 0.00 1.28 1.28 1.28
04.04.06.03.03 ACERO DE REFUERZO fy=4200 KG/CM2 KG 50.74 0.00 20.00 30.74 50.74 50.74
04.04.06.03.04 ENCOFRADO Y DESENCOFRADO M2 12.72 0.00 12.72 12.72 12.72
04.04.06.03.05 ENLUCIDO DE ESTRUCTURAS M2 12.72 0.00 12.72 12.72 12.72
ACTIVIDADES PARA LA VIGILANCIA PREVENCION Y CONTROL DEL
05
COVID 19 EN EL TRABAJO
ELABORACION DE PLAN DE VIGILANCIA, PREVENCION Y CONTROL
05.01 GLB 1.00 1.00 0.00 1.00
DEL COVID 19
INSUMOS Y EQUIPOS PARA PREVENCION INDIVIDUAL Y COLECTIVA
05.02 GLB 1.00 1.00 0.00 1.00
CONTRA COVID 19

05.03 EVALUACION MEDICA DE PREVENCION Y DESCARTE DEL COVID 19 MES 1.00 1.00 0.00 1.00

También podría gustarte